b3_113_2012 (1).pdf

Upload: ahsan-mahmood

Post on 06-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 b3_113_2012 (1).pdf

    1/8

      1*[email protected]

    DESIGN CHALLENGES IN THE 765kV AIR INSULATED

    SUBSTATION

    I S Jha Oommen Chandy* R.K.Sarkar A.B.Singh

    Power Grid Corporation of India India Limited New Delhi, INDIA

    Summary

    POWERGRID commissioned its first 765/400/220kV Air Insulated Substation (AIS) in India at Seoniin 2007. The objective of Power Grid Corporation of India Ltd (POWERGRID) is to create a strong

    and vibrant National Grid in the country. Establishment of the ultimate National Grid is on fast trackand a number of projects are under implementation in this direction. For bulk power transmission

    across regions in the country, 765 kV and 1200kV transmission lines have been planned alongwith±600/±800kV DC transmission lines. In order to handle bulk power of the order of 6000MW, techno-economic design of 765kV substation by careful selection of switchgears and substation materials not

    only w.r.t reliability but also w.r.t electrical fields, corona,RIV, magnetic field and other aspects for itssmooth operation & maintenance assumes significance in this regard. This paper describes various

    challenges in the techno-economic design of UHV AIS substation and the improvements made basedon experience / feedback gained from Seoni substation

    Keyword

    765kV Air Insulated substation substation-Salient Design- Experience-Failure-Future challanges

    1.  Introduction

    There has been phenomenal expansion in the Power Sector since Indian Independence. Afterconstructing a large network of 400 kV transmission system some 25 years back, activities started inIndia for identification of next higher voltage level transmission system of 765kV for long-distance bulk power flow requirement in the future. The first 765kV Sipat-Seoni line was commissioned in2007 in western part of India and the first 765kV Seoni substation in India is in operation for morethan four years. More than 30 AIS substations of 765kV are in different stages of construction whichare targeted to be commissioned within next one and half years as shown in figure.1.

    21, rue d’Artois, F-75008 PARIS B3-113  CIGRE 2012 http : //www.cigre.org

  • 8/17/2019 b3_113_2012 (1).pdf

    2/8

      2*[email protected]

    Figure 1. 765kV Transmission Line network

    2.  Salient Design Considerations 

    2.1  Switching Scheme: A typical 765kV substation consist of 2 nos. 765kV Line bays alongwith 3nos. 765/400kV, 1500MVA Autotransformer (3 nos. of 500 MVA single phase unit with oneunit as a spare) bays, 2 nos.765kV , 240 MVAR Line Reactor ( 3 nos. of 80 MVAR single phaseunit)and 1 no. 765kV,240 MVAR Bus Reactor (3 nos. of 80 MVAR single phase unit ) bay.For

    765kV substation, breaker and half switching scheme has been selected as shown in Figure.2

    Figure 2. Single Line Diagram of 765kV substation

  • 8/17/2019 b3_113_2012 (1).pdf

    3/8

      3*[email protected]

    2.2 System Parameters

    Following major system parameters have been for 765kV substation as mentioned in table-I 

    Table-I : System Parameter for 765kV substation

    Description of Parameter 765kV system

    System operating vaoltage 765kV

    Maximum operating voltage of the system (rms) 800kV

    Lightning impulse withstand Voltage(1.2/50 micro sec) 2100kVp

    Switching impulse withstand voltage(250/2500 micro sec) 1550kVp

    One minute power frequency dry withstand voltage (rms) 830kV

    Corona Extinction Voltage (rms) 508kV

    Minimum creepage distance (25mm/kV) 20000 mm

    Based on the above system parameters following electrical clearances has been considered for765kV substation as mentioned in table-II.

    Table-II : Air-gap / Live-metal clearance

    Phase to Phase 7600mm (for conductor- conductor configuration)

    9400mm (for rod- conductor configuration)Phase to Earth 4900mm (for conductor-structure)

    6400mm (for rod-structure)

    Sectional Clearances 10300 mm

    In 765kV substation following spacing have been adopted considering above clearances andother design aspects like swing of conductors etc . as mentioned in table-III

    Table-III : Electrical spacing Phase to Phase Spacing 15 meters

    Phase to Earth Spacing 7.5 meters

    Sectional Clearances 10.3 meters

    2.3 Selection of Conductor

    A tubular bus of 120mm tube has been used for the first bus level to eliminate the tensions produced on the equipment terminal by short circuit induced pinch effect in a bundledconductor. For second and third level, Quad Bull All Aluminum Conductor (AAC) of size38.25 mm diameter with 450mm sub conductor spacing was selected based on Electric fieldand magnetic field consideration to restrict electric field of 10kV / meter and magnetic field of500 micro Tesla at 1.8 meter above ground level. For this purpose at some locations, whereall the three levels (i.e. equipment level, Bus level & line take off level) are crossing, theshield wire was provided at the height of equipment support structures as shown in Figure-3.

    Figure 3. Shield Wire at the equipment support structure

    The cases studied and the values of electric field and magnetic field obtained for differentconfiguration to select conductor configuration is shown in Table –IV and Figure 4

    Shield wire

  • 8/17/2019 b3_113_2012 (1).pdf

    4/8

      4*[email protected]

    Table IV: Electrical and Magnetic field calculation

    Case

    Study No.

    Levels

    considered instudy

    Level 1

    at height

    of 14

    meters

    Tubular busbar

    diameter(mm)

    Levels 2 at height

    of 27 meter and

    Level 3 at height

    of 39 meter

    Quad Bull AACconductor with

     bundle spacing(mm)

    Support

    structurelevel shield

    wire atheight of8meters

    Maximum

    electricfield at

    height of1.8 meters(kV/m)

    Maximum

    magneticfield at

    height of1.8 meters(µT)

    120 450

    1 Level 1&3 × × - 9.6 57

    2 Level 1,2& 3 × × - 11.4 76.3

    3 Level 1,2, 3 &

    shield wire

    × × × 9.2 76.3

    Figure 4. Electrical field at height of 1.8 meters

    Apart from the selection criteria of normal current carrying capability, short circuit capability, bundle configuration etc., case studies have been carried out for corona extinction voltage to keepminimum corona extinction voltage of 508kV rms phase to ground and maximum voltage gradientof 21.1kVrms/cm. The result of maximum gradient for different case studies are indicated in table-V

    Table V: Case study for Voltage GradientStudyCase No.

    Maximum gradient per phase (kVrms/cm)

    Level 1

    (Tubular busbar of

    120mm diameter) 

    Level 2

    (Quad AAC Bull

    conductor of diameter38.25mm with450mm sub-conductorspacing)

    Level 3

    (Quad AAC Bull

    conductor of diameter38.25 mm with 450mmsub-conductor spacing)

    Shield Wire(diameter

    3.74mm)

    L1R L1B L1Y L2R L2B L2Y L3R L3B L3Y 1 2

    1 13.8 14.4 13.8 - - - - - - - -

    2 13.2 14.2 13.2 - - - 15.6 17.3 15.6 - -

    3 12.0 13.3 12.0 12.6 13.4 12.6 14.1 16.3 14.1 - -4 12.4 13.3 12.4 13.3 15.1 13.3 14.1 16.3 14.1 17.3 17.3

    0 10 20 30 400

    2000

    4000

    6000

    8000

    Distance from origin (m)

       E   l  e  c   t  r   i  c   F   i  e   l   d   M  a  g  n   i   t  u   d  e   (   V  o   l   t  s   /  m   )

  • 8/17/2019 b3_113_2012 (1).pdf

    5/8

      5*[email protected]

    2.4 Selection of levels

    Based on the results from table-IV and table-V following level have been selected for 765kVsubstation

    Level 1: Equipment level – 14.0 meterLevel 2: Bus level - 27 meterLevel 3: Line take off level - 39 meterShield wire - 45 meter

    Figure 5 : Different levels of substation

    2.5 Tower Configuration

    To economize the structurefoundations, Pie(π) type tower

    configuration for 765kV switchyardhas been considered with 30 meter

     beam witdh & phase to phase spacingof 15 meter .Further PolymerInsulator strings have been consideredto reduce the weight on structure.

    Figure6. Pie (π) type tower  

    3. Challenges faced in 765kV AIS substation

    3.1 Transformer and Reactors switching arrangement through Disconnectors Single phase transformers and Reactors have been used with the provision of spare unit oftransformer & reactors, The spare phase transformer and reactor has been arranged in such amanner that spare unit can be replaced with any of the units without physically shifting ofspare unit of transformer & reactor. In case of use of spare phase unit of transformer orreactor, phase opposition conditions arises across the disconnector points connected withauxiliary buses as shown in figure-7 Due to which minimum air clerances of 9400mm between isolator terminals are required. Since isolating distance between disconnector

    terminals of disconnector is less than 7200mm, additional disconnector in series has been

    Bus

    level(Quad

    Bull Cond.)

    Take off

    level (Quad

     bull cond.)

    Equipmentlevel(120mmTube) 

  • 8/17/2019 b3_113_2012 (1).pdf

    6/8

      6*[email protected]

     provided to take care phase opposition condition. Therefore there is a need of designing765kV disconnectors meeting phase opposition requirement.

    Figure 7. Transformer switching through Isolator

    3.2  Compatibility of control switching devices of different makes

    Control switching has been used in 765kV Circuit Breaker for control switching oftransformer and Reactors as shown in figure 8. In case of installation of additionaltransformer bank and Reactor bank in future substation extension , control switching deviceof different make of circuit breaker may or may not be compatible with each other.Therefore there should be a common guideline for circuit Breaker manufacturers to design

    their control switching device compatible to each other.

    Figure 8. Control switching device of different make

  • 8/17/2019 b3_113_2012 (1).pdf

    7/8

      7*[email protected]

    4.0  Design challenges from operational experience of 765kV substation

    4.1 Failure of composite insulator In Seoni substation, 765kV polymer insulatorstrings had failed after commissioning of thesubstation. The cause and mitigation measurestaken w.r.t. the corona damage occurred in the765kV polymer insulator string in Seoni has beenan eye opener in the area of corona andelectomagnetic field control in UHV substations.Simulation studies for field distribution had beencarried out to address this problem. On analysisof voltage distribution it was observed thatcorona strike from the metal parts of tensionfitting and corona shield resulted in gradual wearand tear of composite insulator. All insulatorreplaced with providing additional corona ring at

    the bottom as shown in Figure-9(c).

    Figure 9(b) Corona observed on insulator Figure 9(c) Modified insulator with corona ring

    4.2 Failure of Circuit Breaker during type testing 

    Considering the voltage profile, the voltage factor for capacitive current switching duty of 765 kV CBwas specified as 1.4 (against the IEC requirement of 1.2. ). The circuit breaker was earlier type testedfor C2 duty with 1.2 voltage factor. But the same circuit breaker failed to pass the capacitive currentswitching duty C2 test when tested with a voltage factor of 1.4. The test was repeated with higher SF6gas pressure and precise alignment of contacts, still the CB failed to clear this duty. Finally the nozzle

    design was modified and the test was successfully completed.

    4.3  Observation of Corona on equipment After commissioning of the 765kV Seoni substation , Corona was observed on certain locations predominantly on T point section jumper of Disconnector switches and Corona bell (as shown inFigure 10. To overcome this problem corona bells and corona rings on Disconnector switches were

    modified. It is observed that corona ring of equipment should be designed based on the location ofequipment in the switchyard instead of adopting standard practice of providing Corona ring as a partof equipment.

    Figure 9(a) Insulator failure

    All insulator replaced with providing additional

    ring at the bottom

  • 8/17/2019 b3_113_2012 (1).pdf

    8/8

      8*[email protected]

    Figure 10 Corona problem on equipment terminal

    Figure 11 connecting strip of SAFigure 12 Rupture disc of CT

    4.4 Corona problem in 765kV Surge Arrestor During type testing of 765kV Surge Arrestor, Corona /RIV problem was observed. On analysis it wasfound that welding of strips connecting top ring & bottom ring from outside and sharp edge of thisstrip was causing Corona & RIV problem. With the shifting of connecting strip inside the rings, this

     problem was overcome as shown in Figure 11 above.

    4.5 Leakage of SF6 gas from 765kV Current Transformer After commissioning, SF6 gas leakage took place in few CTs due to the bursting of rupture disc . Afteranalysis it was concluded that rupture discs were damaged in transportation as shown in figure 12 and

    13. As a precautionary measure, all rupture disc were replaced with modified version of rupture disc.

    6. Bibliography i.  EPRI Transmission Line Reference Book - 200 kV and above.ii.  Hifreq software for electric and magnetic field calculation.

    iii.  POWERGRID Seoni site feedbackiv. POWERGRID Experience and Technical Specification 

    Corona

    observed

    strips

    Figure 13 Black spot inside the housinganalysis was found as a graphite particle caused by the rupture disc

    during bursting