b pg concreting

Upload: rami1964

Post on 14-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 b Pg Concreting

    1/5

    View Publication

    You have asked to view a publication

    When you have finished viewing, click on in the toolbar above to return to this screen.

    Now choose one of the following options:

    Viewpublication

    chosen

    Return topublications

    list

    http://publications.pdf/http://publications.pdf/http://publications.pdf/http://publications.pdf/
  • 7/29/2019 b Pg Concreting

    2/5

    CONSTRUCTconcrete structures group

    www.bca.org.uk www.bre.co.uk www.construct.org.uk www.rcc-info.org.uk www.detr.gov.uk

    BEST PRACTICE GUIDES FOR IN-SITU CONCRETE FRAME BUILDINGS ...

    Concreting forimproved speedand efficiency

    Introduction

    The European Concrete BuildingProject is a joint initiative aimed at

    improving the performance of theconcrete frame industry.

    The principal partners in the worldsmost ambitious concrete researchprogramme are:

    British Cement Association

    Building Research Establishment Ltd

    Construct - the Concrete StructuresGroup

    Reinforced Concrete Council

    Department of the Environment,Transport and the Regions

    The programme involves theconstruction of a series of full-sizedconcrete structures in the LargeBuilding Test Facility at Cardington,where they are being subjected tocomprehensive testing of the buildingprocess and of their performance.

    With support from the DETR and theEngineering and Physical SciencesResearch Council, the first of thesebuildings, a seven-storey in-situ flatslab concrete frame, was completed

    in 1998. The results of investigationsinto all aspects of the concrete frameconstruction process are summarisedin this series of Best Practice Guides.

    These Guides are aimed at allthose involved in the process ofprocurement, design and constructionof in-situ concrete frames. Theyshould stimulate fundamental changein this process in order to yieldsignificant improvements in the cost,delivery time and the qualityof these structures.

    ... FROM THE EUROPEANCONCRETE BUILDING PROJECT

    1

    Figur e 1:Organisations and facilities involved in the concrete procurement process

    Designer/Specifier

    Contractor/Purchaser

    Supplier/Producer

    Concretesupply

    Concreteproduction plant

    SiteConcreting

    This Guide provides recommendations for improvingthe efficiency of the concreting process whilstmaintaining quality

    Key messagesAchieving optimum efficiency and quality of the concreting process on site requiresconsideration of:

    The concrete procurement process as a whole (Figure 1).

    Interactions between concreting and inter-related construction processes (Figure 2).

    The use of performance-based concrete specification.

    Best practiceWhen planning the concreting process, the following aspects should be considered:

    Specified properties of hardened and fresh concrete.

    Selection of the concrete supplier.

    The method of handling/transporting the concrete on site.

    Reinforcement densities and congestion of reinforcement.

    Appropriate compaction, curing and finishing methods.

    Pour sizes and construction joints.

    Use of special concretes and innovative methods.

    Implications of interactions with other construction activities that may share resources.

    The overall construction programme. Appropriate communication methods.

  • 7/29/2019 b Pg Concreting

    3/5

    2

    SpecificationConcrete specifications should be inaccordance with BS 5328: 1997,

    Concrete, Parts 1 and 2 as referencedby the National Structural ConcreteSpecification for Building Construction,

    (NSCS, Reference 1). The specification

    documents should be concise andcomplete as given in NSCS Part 2. This

    enables the supplier to immediatelyconsider the specification data without

    having to first interpret a new format.

    Specifications should be performance-

    based. They should state the requiredproperties of the hardened and freshconcrete, but should otherwise be free

    of unnecessary restrictions. This meansthat much of the responsibility forensuring that these qualities are achieved

    lies with the supplier. This is appropriate,

    since the concrete supplier is producingconcrete on a daily basis and thereforeis likely to have much greater expertiserelating to concrete production than any

    other party in the construction process.Under BS 5328, performance specifiedconcretes are categorised as either

    designed or designated mixes.

    The workability specified for the

    concrete must be appropriate for theintended placing method. The addition

    of water on site should be avoidedwherever possible and must not be seenas a substitute for specifying the correct

    workability in the first place.

    Where there are many separate concretesspecified within a project, it may be moreefficient to rationalise these by merging

    those with similar performancerequirements. This will result in reducedrisk of confusion and possibly economies

    of scale in batching.

    Concrete specification can be mademore efficient by using software tools,e.g. ConSpec (for more information see

    the Ready-mixed Concrete Bureauswebsite at www.rcb.org.uk).

    Concrete supplyTo achieve the most efficient concreting,

    potential concrete suppliers must besupplied with the concrete specificationas well as additional information such

    as the proposed volumes, pour rates andplacing method. They may request further

    information or may make suggestions forimprovement (e.g. further rationalisation)before providing a quotation and mix

    design information.

    When selecting a concrete supplier, the

    primary issue other than cost is the abilityto supply at the required rate, particularly

    for large pours. The provision of a back-up supply should be considered by thepurchaser in case the primary plant fails.

    Figur e 2:Issues and interactions affecting optimisation of concreting process for in-situconcrete frames. Key influences are highlighted

    Table 1:Influence of pour size on aspects of slab construction for the ECBP in-situ frame

    Expertisefrom suppliers

    Architecturalrequirements(e.g finishes)

    Individualmix design

    Testingrequirements

    Construction jointsand detailing

    Methodof compaction

    Methodof curing

    Required

    finish

    Structural requirements(e.g. grade, durability,

    striking)

    Regulatoryframework

    Availabilityof materials

    Concrete

    specification

    Methodof placing

    Labour

    availability

    Optimisednumberof mixes

    Pour size

    Overall

    site constraints

    Requirements ofoverall construction

    programme and striking

    Geometry ofstructure

    Reinforcementfixing

    Access,on-site transport

    Formworkavailabilityand re-use

    Limits onconcrete delivery

    Single pour Two pours on Four pours onseparate days separate days

    Each pour achievable within a Just Yes, easily Yes, easilyworking day

    Supporting columns required to be All Over half Over a quartercomplete before slab pour

    Can proceed with next level of No Yes Yescolumns before slab completed

    Columns (above) poured at same No Possible Possibletime as slab (if same specification)

    Formwork required Full slab area Two-thirds of One-third of slab area slab area

    Construction joints None One Three

    Efficient use of pump hire Yes Less Much less

    Need for additional safety provisions None Some Considerable(e.g. edge protection)

    More even use made of site resources No Yes Yes (closer to a(plant, operatives, materials etc.) continuous manu-

    facturing process)

  • 7/29/2019 b Pg Concreting

    4/5

    3

    Handling, transporting andplacing concrete on siteAccess for the ready-mixed concretetruckshould be provided as close aspossible to the required location in thestructure. It may be possible todischarge concrete directly from the

    truck into foundations and columnbases, but for other components ameans of transporting the concrete fromthe truck discharge point to its requiredlocation in the frame will be required.

    The two methods of transportingconcrete that are most applicable tomulti-storey frame construction are:

    1. Pumping.A truck-mounted (oroccasionally static) concrete pump issited at ground level with its deliveryboom and/or hoses deployed so thatconcrete can be pumped directly to

    where it is required in the frame.The input hopper of the pump istopped-up from truck-mixers.

    2. By skip. A site crane hoists a skipfrom ground level (where it is filledwith concrete from a truck-mixer) tothe required location in the frame.

    A typical in-situ reinforced concreteflat-slab frame has two primary structuralcomponents: columns and slabs (withor without downstands). The volume ofthese components is significantly differentand they are best considered separately.

    For example, the European ConcreteBuilding Project frame at Cardingtonconsists of seven flat slabs each with20 columns. Each floor has a volumeof about 165 m3, whereas the columnsfor each floor have an overall volumeof only 9 m3.

    Slab concreting

    The volume of concrete required is amajor factor affecting the planning ofslab concreting operations. Daily pouringrates and hence slab concreting times canbe determined from considering the limits

    on the supply, handling on site, andplacing and finishing requirements. It maybe possible to pour an entire slab in oneday, but it could be more cost-effective tosplit the pour across two or more days.

    Pumping is an attractive method forplacing concrete in slabs, since arelatively high rate of almost continuousplacing is possible. The pump can belocated where two truck mixers candischarge simultaneously into itshopper, resulting in a zero changeovertime. Little or no use is made of site

    cranes, which are therefore available towork elsewhere on the site. Breaks inplacing are required only to connect ordisconnect pipework as the placingfront moves across the slab.

    However, using a skip for slab poursshould still be considered. This will makecontinuous use of a site crane, but if thecrane would otherwise be idle duringthe concreting operation it would be anefficient use of this resource. The rate ofplacing is likely to be significantly lessthan that possible by pumping since the

    placing is not continuous. This can bealleviated by using the largest capacityskip that can be hoisted by the crane orby using additional skips. As the framerises, the time taken to hoist the skip tothe slab will increase.

    Both pump and skip placing will benefitfrom a planned progression across theslab. In general, pumping should bestarted in the corner most distant fromthe pump and worked backwardstoward it in a swathe of a convenientwidth, reducing the length of the

    pipeline as required. For skip placing,the swathes should be aligned in sucha way that the most frequent movementsof the crane are rotational.

    Column concretingIn contrast to slab concreting, that forcolumns may involve small volumes ofconcrete. For example, at each level ofthe in-situ frame at Cardington, the totalvolume of concrete for the columns was9 m3. There were 20 columns and sevensets of formwork available, so theconcrete was supplied and placed onthree separate days, each delivery being

    3 m3 (i.e. half a truckload).

    Overall speed of construction shouldbe balanced against other costs. Forexample, these columns could havebeen poured on two separate days if tensets of formwork had been available;in which case each concrete deliverywould have been 4.5 m3. One or twodays would possibly have been cut fromthe construction programme, butformwork costs would have increased.On the other hand, concrete costsmight have decreased due to fewer

    part-load surcharges.

    Pour sizes andconstruction jointsIdeally, each structural component ofa building would be cast monolithically,but this is often not practicable. TheNSCS, Part 1, Table 1 (Reference 1)suggests limits on pour sizes for wallsand slabs, although these can beexceeded by agreement. In general,a pour should be achievable within aworking day. Above ground level,

    a pour for the floor slabs of a typicalframe can be over 500 m2 in area andup to 30 m in any dimension (the ECBPin-situ frame was 30 m by 22.5 mor 675 m2). Construction joints areacceptable provided they do not

    compromise the performance of thestructure. Even when the use of aconstruction joint is not intended, thepossibility of an unexpected cessationof a pour should be planned for.

    The size and number of pours for eachfloor slab of a multi-storey frame affectsthe overall progression of construction,

    particularly the processes related toformwork and reinforcement. Forexample, each slab of the ECBP in-situframe was cast in a single day, but thismajor pour could have been split intotwo or four pours, each carried out onseparate days. To determine whichapproach is most efficient it is necessaryto consider the cost implications of thepoints of comparison listed in Table 1.

    CompactionAdequate compaction is essential to

    ensure that the concrete performssatisfactorily in the completed structure.Under-compacted concrete will havereduced strength and/or durability, andmay be of unacceptable appearance.Appropriate compaction equipmentmust therefore be available when it isrequired and concrete-placing personnelshould be trained to use it correctly

    The poker vibrator is likely to be mostappropriate compaction device forin-situ reinforced concrete frames.Beam vibrators or hand tamping can

    be used to compact and finish the topsurfaces of slabs, but a poker vibratorwill still be required to ensure thatadequate compaction is achieved throughthe full thickness and at the edges.

    FinishingThe finish required for a frame will bespecified within the overall specificationfor the structure. It will be at least

    Type A for formed finishes and U1 forunformed finishes (References 1 and 2).

    These will generally be adequate wherethe concrete surfaces are to be coveredby cladding or raised floors etc, as isoften the case for office buildings.If the concrete surface is to be visuallyexposed, or is to be directly fitted witha floor covering, then a higher qualityfinish may be required. This should bespecified in the NSCS, Part 2, Projectspecification.

    CuringCuring involves preventing the loss of

    moisture from the concrete after casting.This can best be achieved by protecting

    exposed surfaces.

    It may also be desirable, or even essential,to control the temperature of the concreteto ensure that cement hydration proceedsat an acceptable rate. In winter, the

  • 7/29/2019 b Pg Concreting

    5/5

    4

    ambient temperatures may be so lowthat it is necessary to take measures toensure that the concrete temperature ismaintained at a suitable level during theinitial stages of curing. The cast concretecan be insulatedagainst loss of heatgenerated by the hydration process; inaddition the concrete can be supplied at

    an elevated temperature.

    Special concretesReady-mixed concrete suppliers haveextensive databases that will allow themto rapidly produce a mix design to meetthe requirements of most in-situ frames.In some cases, however, some mixdesign development will be necessary.Examples include high strength andself-compacting concretes.

    High strength concreteHigh strength concrete is beingincreasingly used, particularly in highlystressed compression elements. Thecolumns on the lower three levels of theECBP frame were of grade C85 concrete,which permitted the same column sizeto be used economically over the fullheight of the structure. Polypropylenefibres were added to the high strengthconcrete columns at Cardington toreduce the potential for spalling in theevent of fire.

    Self-compacting concretesSelf-compacting concretesare nowbecoming available. They can be placed

    much more rapidly with savings inlabour and plant costs, which will offsetthe higher material cost. Their useresults in reduced noise on site andpermits placing of concrete incircumstances which would otherwisebe difficult or impossible with conven-tional concrete (e.g. highly congestedreinforcement, pumping from below,and greater lift heights up to 10 m).

    Use of such special concretes, whichis not currently routine, can affect theconstruction process. The supplier mayneed to develop and test an appropriate

    mix design. An extended lead-time willbe required for this and it will need tobe built into the overall constructionprogramme. Special arrangements mayalso be necessary if some of the mixconstituents are not routinely stored inhoppers at the ready-mixed plant.

    If the use of such special concretes isproposed, discussions with the suppliershould be held as early as possible.

    Early striking of formworkTo increase the speed of the constructionprocess and reduce formwork costs, itmay be desirable to strike formwork asrapidly as possible to make it availablefor early re-use. The NSCS states that itis the contractors responsibility toensure that the concrete has adequatestrength to support its own weight andany construction loads without sufferingshort- or long-term distress. This iscovered by a separate Guide in thisseries, Early striking for efficient flat slabconstruction. Concrete not required tocarry its own weight should still have acompressive strength of at least 5 N/mm2,to ensure that damage does not occurduring formwork stripping.

    Planning for interactionswith other site operationsConcreting is but one component of acomplex construction process. Manyparameters affect its efficiency andthese will vary between projects. Majorplanning decisions concerningconcreting operations cannot thereforebe taken without considering inter-actions with other processes on site.

    This needs to be done within thecontext of the specific project and withreference to the erection drawings,which may preclude some economicallyattractive options. Consideration mustalso be given to the effect of the various

    options on construction loadings andrequired concrete maturity.

    Figure 2 identifies the main issues andinteractions in relation to the concretingof an in-situ frame.

    CommunicationsCommunications are an important aspectof concreting, and indeed the wholeconstruction process. Everyone shouldbe aware of the need for informationflow to be concise, complete and timely.Clear specification is the key in this

    process (Reference 3). All parties musthave the information they require inorder to play their part in placing thespecified concrete in the correctlocation in the frame, in an appropriatemanner. Information technology anddocument layouts that are standardisedacross the industry should be usedmore widely.

    References

    1. CONSTRUCT, BCA, BRE and RCC

    National structural concrete specificationfor building construction (NSCS).

    Crowthorne, BCA, 2000. Ref 97.378.

    2. BSI. Structural use of concrete. Part 1:

    Code of practice for design and

    construction. London, BSI, 1997.

    BS 8110-1: 1997.

    3. COLIN GRAY. In situ concrete frames.

    The University of Reading, 1995.

    Best Practice Guides in this series

    Improving concrete frame construction

    Concreting for improved speed

    and efficiency

    Early age strength assessment ofconcrete on site

    Improving rebar information and supply

    Early striking for efficient flat slab

    construction

    Rationalisation of flat slab reinforcement

    Further Guides are planned

    Research partners for this Guide

    Imperial College

    RMC Readymix Limited

    Building Research Establishment Ltd

    BEST PRACTICE GUIDES FOR IN-SITU CONCRETE FRAME BUILDINGS

    This Best Practice Guide is basedon research report, Process efficientconcreting: improved speed and qualityby A. Pullen, J.B. Newman and P. Chana.BRE report published by CRC Ltd.(020 7505 6622).

    97.502First published 2000

    ISBN 0 7210 1553 0

    Price group A

    BCA, BRE Ltd, Construct, RCC, DETR

    Published by the British Cement Association

    on behalf of the project partners.British Cement AssociationCentury HouseTelford AvenueCrowthorne, Berkshire RG45 6YSwww.bca.org.uk

    For further copies of the Best Practice Guidesring the Concrete Bookshop on 01344 725704.

    All advice or information from the British CementAssociation is intended for those who will evaluate thesignificance and limitations of its contents and takeresponsibility for its use and application. No liability(including that for negligence) for any loss resulting fromsuch advice or information is accepted. Readers shouldnote that all BCA publications are subject to revision fromtime to time and should therefore ensure that they are inpossession of the latest version.

    Ready-mixed Concrete Bureau

    Century House, Telford Avenue

    Crowthorne, Berkshire RG45 6YS

    Tel: 01344 725732 Fax: 01344 774976

    www.rcb.org.uk

    e-mail: [email protected]