awf cof eoi uganda

5
AWF Australia P.O. Box 12048 A'Beckett Street, Melbourne, VIC 8006 www.architectswithoutfrontiers.com.au AWF/ COTTON ON FOUNDATION PRO-BONO ARCHITECT EOI AND PROJECT DETAILS Table of Contents 1. Name .............................................................................................................................................................................2 2. Purpose ........................................................................................................................................................................2 3. EOI Lodgement ....................................................................................................................................................... 2 4. EOI Management .................................................................................................................................................. 2 5. EOI Dates ...................................................................................................................................................................2 6. EOI requirements ................................................................................................................................................... 3 7. EOI Evaluation criteria ........................................................................................................................................3 8. Project outline........................................................................................................................................................... 3 9. Project Deliverables..............................................................................................................................................4 10. Project Design ....................................................................................................................................................... 4 11. Project Infrastructure requirements ..........................................................................................................5 12. Project dates .......................................................................................................................................................... 5 13. Communication..................................................................................................................................................... 5 14. Further information .............................................................................................................................................5

Upload: architects-without-frontiers

Post on 19-Mar-2016

292 views

Category:

Documents


0 download

DESCRIPTION

Architects without Frontiers in partnership with the Cotton on Foundation would like to invite expressions of interest to provide pro-bono services for the design of a new HIV Centre in Mannya Village, Uganda.

TRANSCRIPT

Page 1: AWF COF EOI Uganda

AWF Australia P.O. Box 12048

A'Beckett Street, Melbourne, VIC 8006

www.architectswithoutfrontiers.com.au

AWF/ COTTON ON FOUNDATION

PRO-BONO ARCHITECT EOI AND PROJECT DETAILS

Table of Contents 1.  Name .............................................................................................................................................................................2 2.  Purpose ........................................................................................................................................................................2 3.  EOI Lodgement .......................................................................................................................................................2 4.  EOI Management ..................................................................................................................................................2 5.  EOI Dates ...................................................................................................................................................................2 6.  EOI requirements ...................................................................................................................................................3 7.  EOI Evaluation criteria ........................................................................................................................................3 8.  Project outline...........................................................................................................................................................3 9.  Project Deliverables..............................................................................................................................................4 10.  Project Design .......................................................................................................................................................4 11.  Project Infrastructure requirements..........................................................................................................5 12.  Project dates ..........................................................................................................................................................5 13.  Communication.....................................................................................................................................................5 14.  Further information .............................................................................................................................................5 

Page 2: AWF COF EOI Uganda

AWF Australia P.O. Box 12048

A'Beckett Street, Melbourne, VIC 8006

www.architectswithoutfrontiers.com.au

1. Name Mannya Village HIV Centre, UGANDA

2. Purpose To develop a modern, efficient and sustainable HIV Centre building for the community of Mannya, Uganda and surrounding areas.

3. EOI Lodgement Submissions must be emailed to [email protected] no later than 5pm Wednesday 19th December 2012.

4. EOI Management

AWF is the manager of the EOI process, working in association with the Cotton On Foundation (www.cottononfoundation.org). The assessment panel is composed of three AWF Board Members. Organiser Leeanne Marshall Adviser Esther Charlesworth Assessment panel Esther Charlesworth Architect, Founding Director AWF

Norman Day Architect and architectural writer

Andrew Mackenzie Architectural writer, publisher and consultant.

Leeanne Marshall

Architect, General Manager AWF

Philip Ward Architect

5. EOI Dates DATE ACTIVITY 14 December EOI open 19 December EOI close 21 December EOI selection and announcement 8 January Project briefing with selected architect

Page 3: AWF COF EOI Uganda

AWF Australia P.O. Box 12048

A'Beckett Street, Melbourne, VIC 8006

www.architectswithoutfrontiers.com.au

6. EOI requirements EOI should be no more than 7 x A4 pages in total supplied in softcopy only as pdf, emailed to the recipient identified above. EOI will need to clearly demonstrate that the team has the right mix of skills and the necessary experience. To establish a consistent basis of comparison, it is requested that the EOI be submitted in the following standard format:

• Covering letter • Overview of team including number of years in business, location, and names of

principals and directors committed to the EOI • Details of relevant experience, with social/healthcare projects

7. EOI Evaluation criteria EOI submissions will be evaluated against the following two criteria:

• Team constitution and key staff. • Past work and relevant experience.

8. Project outline Architects without Frontiers (AWF), in Partnership with the Cotton On Foundation are inviting expressions of interest to provide pro-bono services for the design of a new HIV Centre in Mannya Village, Uganda. The village of Mannya in Uganda, Eastern Africa, lies a five hour drive from the Ugandan capital, Kampala. A decade ago the village consisted of little more than a small group of dwellings with a struggling primary school. Now, thanks to the hard work of all involved and the support of the Cotton On Foundation, it boasts a medical centre, secondary school, dormitories and a child sponsorship program. The Cotton On Foundation is now looking to add a new HIV centre to the village. The aim of the HIV centre building is to be the centrepiece of the village and demonstrate best practice health planning as well as innovative, sustainable design. The centre will include at a minimum: AREA DESCRIPTION APPROX

AREA (m2) 2 x Offices 8 1 x Laboratory 11 1 x Counselling room 11 1 x Conference hall (70 people) 70 1 x Reception/ Waiting area 24 4 x WC 5.5 Entrance porch/ Verandah 16 Circulation 25

The final brief will be decided on following consultation with the community, client and any other relevant stakeholders.

Page 4: AWF COF EOI Uganda

AWF Australia P.O. Box 12048

A'Beckett Street, Melbourne, VIC 8006

www.architectswithoutfrontiers.com.au

9. Project Deliverables The selected Architect will work with the local Ugandan Architect and Infrastructure Coordinator along with AWF to develop Schematic Designs for the centre. Once Schematic Designs are complete the project will be handed over to the local team for documentation and preparation of final construction drawings. The requirements for the pro bono architect are as follows: a. Site Visit 15th – 24th January 2013 The Architect will be required to travel to Uganda in January 2013 to meet with the client and visit the site. The Architect will also be required to accompany AWF and local Cotton On Foundation Staff to visit case study projects in Rwanda and Uganda. All travel and accommodation costs will be covered by the project client. b. Presentation of initial concept designs 11th February 2013 The selected Architect will present their initial ideas to a meeting of Cotton On Foundation specialists in Geelong in early 2013. The design deliverables for this concept design will include:

• Concept plans and elevations • Three dimensional Sketches of intended design

c. Design Development The selected Architect will develop the design based on feedback from the meeting and initial electronic feedback from the Cotton On Foundation Uganda team. d. Site Visit Uganda March 2013 The selected Architect and AWF may return to Uganda to present the developed design to the Cotton On Foundation Uganda team, revise any outstanding issues and handover to the local team for construction documentation The design deliverables for Design Development will include:

• Developed plans and elevations • Developed sketches/ 3ds of intended aesthetic • Indication of proposed materials

e. Comment on final construction package The selected Architect to provide feedback to the Cotton On Foundation Uganda team on the final package to ensure design intent has been retained and drawings are ready for construction.

10. Project Design Concepts will be developed by the selected Architect following consultation with AWF, the Client (the Cotton On Foundation), the local team and local stakeholders. The design should take into account the sustainable infrastructure principles used by AWF to guide the project which include:

1. Key stakeholder consultation 2. Adherence to the Mannya Masterplan 3. Consideration of gender issues

Page 5: AWF COF EOI Uganda

AWF Australia P.O. Box 12048

A'Beckett Street, Melbourne, VIC 8006

www.architectswithoutfrontiers.com.au

4. Water and sanitation considerations 5. Sustainable construction/ future maintenance strategy 6. Local training opportunities provided 7. Adherence to budget

The design will also:

• Employ best practice design principles for health buildings • Keep environmental systems in mind, with an emphasis in reducing operational

costs such as power and water (use of passive systems) • Consider the ongoing cost and maintenance of the building • Encourage, where possible, the use of local resources

11. Project Infrastructure requirements Any design will also need to consider:

• Power requirements of the facility • Water options for the facility (cost, maintenance, ease of construction) • Technology requirements • Sewerage treatment options

12. Project dates DATE ACTIVITY December 21st 2012 Acceptance of brief January 8th 2012 Briefing discussion with AWF January 15th – 24th 2013 Site Visit Uganda, case study tour Uganda/ Rwanda February 11th 2013 Presentation of concept design Early March 2013 Site Visit Uganda presentation of design to Cotton On

Foundation Uganda team 15 March 2013 Final developed designs handed over to Cotton On

Foundation Uganda team

13. Communication Open and clear communication is expected at all times between the Architect and AWF. Weekly updates with the AWF Project Coordinator will be required as a minimum. MOUs will be signed before work commences. Communication schedules with the Client will be negotiated with the Client.

14. Further information For any question or clarifications in relation to this EOI please contact: Leeanne Marshall [email protected]