awarding extensions of time - - probyn · pdf filesee however fidic 1999 red book for...
TRANSCRIPT
![Page 1: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/1.jpg)
Awarding Extensions of Time Christopher Miers
23rd October 2013
![Page 2: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/2.jpg)
© 2013 - Probyn Miers Ltd
![Page 3: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/3.jpg)
© 2013 - Probyn Miers Ltd
“an extension of time provision confers benefits on both parties; in particular it enables a contractor to recover reasonable extensions of time whilst still maintaining the contractually agreed structure of a specified time for completion”
Steria v Sigma Wireless Communications [2007] EWHC 3454 (TCC) Similarly in Multiplex v Honeywell [2007] EWHC 447 (TCC)
![Page 4: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/4.jpg)
© 2013 - Probyn Miers Ltd
• Programmes
• Assessment of delay • Contract requirements
![Page 5: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/5.jpg)
© 2013 - Probyn Miers Ltd
We must start with the contract … • The prevention principle Where a party to a contract has, by any act or omission, prevented the other party from performing a particular obligation under the contract, they cannot insist upon the performance of that obligation by the other party. See for example Multiplex v Honeywell [2007] EWHC 447
![Page 6: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/6.jpg)
© 2013 - Probyn Miers Ltd
So express terms allow the Employer to adjust the completion date… • JCT and similar
• SBC 2011, 2.28 • DB 2011, 2.25 • IC 2011, 2.19 • MW 2011, 2.7
• NEC3, 63.3
![Page 7: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/7.jpg)
© 2013 - Probyn Miers Ltd
• SBC 2011, 2.28; DB 2011, 2.25 wording • a Relevant Event; and 1. “… completion of the Works or any Section 2. is likely to be delayed thereby 3. beyond the relevant Completion Date.” • ‘Prospective’ assessment… • with ‘Retrospective’ review 12 weeks after PC (SBC 2.28.5)
![Page 8: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/8.jpg)
© 2013 - Probyn Miers Ltd
• NEC 63.3 • a compensation event; and 1. “A delay is assessed as … the length of time that … 2. planned Completion is later than 3. Completion as shown on the Accepted Programme”
• ‘Prospective’ assessment… • no ‘Retrospective’ review
![Page 9: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/9.jpg)
© 2013 - Probyn Miers Ltd
• Delay to the completion date must
therefore be assessed by reference to
the progress of the works to the then
projected completion date.
Balfour Beatty v Chestermount Properties [1993] 62BLR1
![Page 10: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/10.jpg)
© 2013 - Probyn Miers Ltd
• Merely establishing delay
caused to a particular
work activity which does
not impact the completion
date of the works as a
whole, or theoretical
delay, will not suffice.
Adyard Abu Dhabi v SD Marine Services (2011)
![Page 11: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/11.jpg)
© 2013 - Probyn Miers Ltd
Giving / receiving notice
• Express terms • when it becomes reasonably apparent that the progress of
the works is being or is likely to be delayed • notice to be given forthwith • Condition precedent? LB Merton v Leach [1986] 32BLR51 see however FIDIC 1999 Red Book for example, and Steria v Sigma Wireless Communications [2007] EWHC 3454
![Page 12: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/12.jpg)
© 2013 - Probyn Miers Ltd
Giving / receiving notice • LB Merton v Leach [1986] 32BLR51
The giving of a notice (under JCT 63) was not a condition precedent before the architect was under a duty to consider any possible extension of time. However failure to give a notice on it becoming reasonably apparent that the progress of the work was delayed was a breach of contract and that breach could be taken into account by the architect providing an extension of time.
![Page 13: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/13.jpg)
© 2013 - Probyn Miers Ltd
Giving / receiving notice
• JCT SBC 2011, 2.27 • NEC3, 61
• Format for presentation of EOT claim?
• Next steps
Can the CA/PM ‘require’ the Contractor to submit more information?
![Page 14: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/14.jpg)
© 2013 - Probyn Miers Ltd
Using best endeavours to mitigate delay
• SBC 2011, 2.28.6.1
• A “constant” obligation
• Contractor to do all that may reasonably be required to
proceed with the work
![Page 15: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/15.jpg)
© 2013 - Probyn Miers Ltd
Programmes
• Planned programme
• Updated programmes
• Finishing/Completion programmes
• As-built programme
![Page 16: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/16.jpg)
© 2013 - Probyn Miers Ltd
Programmes: Planned programme
• Requirements of the contract As soon as possible after execution of the contract
• Contact document or not • JCT forms • NEC, 31.2 acceptance / reasoned non-acceptance • Enhanced requirements of programme information by
particular conditions
![Page 17: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/17.jpg)
© 2013 - Probyn Miers Ltd
Programmes: Updated programmes JCT SBC 2011 2.9.2, within 14 days of EOT or pre-agreed adjustment NEC3, 32, within period of reply / intervals as contract data
![Page 18: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/18.jpg)
© 2013 - Probyn Miers Ltd
Programmes • Finishing/ Completion programmes
![Page 19: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/19.jpg)
© 2013 - Probyn Miers Ltd
Programmes • As-built programme
![Page 20: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/20.jpg)
© 2013 - Probyn Miers Ltd
Providing / obtaining the data • Keeping good records • Minutes of meetings • Contractor’s progress reports • Payment applications and certification • Other records of progress • Method statements • CoW reports • Resource schedules • Plant
![Page 21: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/21.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• John Barker v London Portman Hotels [1996] 83 BLR 31 “I recognise that the assessment of a fair and reasonable extension involves an exercise of judgment, but that judgment must be fairly and rationally based.”
1. A logical analysis in a methodical way - not impressionistic 2. Calculated assessment of the time which CA/PM thinks is
reasonable for various items individually and overall. 3. In accordance with the contract provisions. 4. Allowance which bears a logical and reasonable relation to
the delay caused.
![Page 22: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/22.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Cause, effect, responsibility • Float Ascon Contracting v Alfred McAlpine [1999] 66 Con LR 119 Royal Brompton Hospital v Hammond
• JCT / NEC - Contractor entitlement to complete early?
![Page 23: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/23.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Assessing the critical path • at the time of the relevant event • use ‘as-built’ information
• Working with/without Critical Path Analysis
![Page 24: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/24.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Working with Critical Path Analysis
• ICC Final Report on Construction Industry Arbitrations
(2001) - Chaired by HHJ Humphrey LLoyd QC and Dr Nael
Bunni
“… in projects where CPN techniques have already been used to manage the construction process and monitor its progress, CPN provides an excellent tool for establishing the causes and effects of delay…”
![Page 25: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/25.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Working with Critical Path Analysis
• City Inn v Shepherd Construction [2008] BLR 269
“… the pursuers went too far in suggesting that an expert could only give a meaningful opinion on the basis of an as-built critical path analysis… [with critical path analysis] any significant error in the information that is fed into the programme is liable to invalidate the entire analysis…”
![Page 26: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/26.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Working with Critical Path Analysis
• Great Eastern Hotels v John Laing Construction [2005] EWHC 181 TCC “… Laings also altered the logic link… by changing the finished relationship from seven weeks to four weeks Laing were enabled to under report the true delay…”
![Page 27: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/27.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay
• Working without Critical Path Analysis
• Walter Lilly v Mackay [2012] EWHC 1773 TCC
![Page 28: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/28.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay: without CPA
• Walter Lilly v Mackay [2012] EWHC 1773 TCC
• Logical analysis progressing month-by-month based on all
contemporaneous information
• To review what in each month was probably delaying overall
completion, and cross check by reference to what actually
happened
![Page 29: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/29.jpg)
© 2013 - Probyn Miers Ltd
Assessing the delay: without CPA
• and De Beers v Atos [2010] EWHC 3276 TCC
“… There has been no analysis of the critical delays to the
project, and so I must do my best to assess what delays
were in truth driving completion…”
![Page 30: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/30.jpg)
© 2013 - Probyn Miers Ltd
Calculating the extension due (whether using CPA or not):
1. Check programme construction logic and assess probable critical path at the time
2. Consider contractor’s options for mitigation – i.e. amending programme where reasonable
3. Focus on the overall effect on the Completion Date, not solely on the activity or activity sequence
![Page 31: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/31.jpg)
© 2013 - Probyn Miers Ltd
Calculating the extension due (whether using CPA or not):
4. ‘Dotting on’ net addition of time - Balfour Beatty v
Chestermount
5. Allow for consequential effects
6. Work in calendar days
7. Adhere to the contract
8. Remember that a final review will be undertaken (JCT)
![Page 32: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/32.jpg)
© 2013 - Probyn Miers Ltd
Concurrent delay
• What is concurrent delay?
“a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency.” John Marrin QC
• Adyard Abu Dhabi v SD Marine Services (2011) approved
• Also SCL Delay and Disruption Protocol, 2002, ref Steria Ltd
v Sigma Wireless Communications Ltd (2008) BLR 79, TCC at 130-131
![Page 33: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/33.jpg)
© 2013 - Probyn Miers Ltd
Time in the event of concurrent delay
• Full award where one cause of delay is a Relevant Event • Walter Lilly v Mackay [2012] EWHC 1773 TTC
“…where a delay is caused by two or more effective causes, one of which entitles the Contractor to an extension of time as being a Relevant Event, the Contractor is entitled to a full extension of time.”
• Henry Boot Construction v Malmaison Hotel
• Apportionment (Scottish law) • City Inn v Shepherd Construction
![Page 34: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/34.jpg)
© 2013 - Probyn Miers Ltd
Making the Award
• In accordance with the contract
• SBC 2011, 2.28, time attributed to each relevant event
• NEC3, 32.1 – the effect of implemented compensation
events on the revised programme
• Observing the contract time frames
![Page 35: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/35.jpg)
© 2013 - Probyn Miers Ltd
Keeping a record of the Award
• Recording the methodology of assessment
• Recording the calculation
Review after Practical Completion- JCT
• 12 week review – SBC 2011, 2.28.5
![Page 36: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/36.jpg)
© 2013 - Probyn Miers Ltd
Later disputes
• Retrospective Critical Path Analysis
• ICC Final Report on Construction Industry Arbitrations, 2001, paras 42-44 re Critical Path Networks
• The Royal Brompton Hospital NHS Trust v Hammond and Others, (2000)
• Importance of contemporaneous documents
![Page 37: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/37.jpg)
© 2013 - Probyn Miers Ltd
What if the award is later found by the Court to be wrong?
“The duty of a professional man, generally stated, is not to be right, but to be careful… The fact that he is in the event proved to be wrong is not, in itself, any evidence that he has been negligent. His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.”
• Royal Brompton Hospital v Hammond [2000] -HHJ Seymour
![Page 38: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/38.jpg)
© 2013 - Probyn Miers Ltd
Guidance for professionals
• RIBA Good Practice Guide: Extensions of Time, by Gillian Birkby, Albert Ponte and Frances Alderson, 2008
• SCL Delay and Disruption Protocol, 2002
Authoritative legal reference books
• Keating on Construction Contracts, 9th Ed., August 2011
• Construction Law, Julian Bailey, April 2011
![Page 39: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/39.jpg)
© 2013 - Probyn Miers Ltd
Other sources of interest • SCL Paper 179, Concurrent Delay Revisited, John Marrin,
February 2013
• ICC Final Report on Construction Industry Arbitrations, 2001, paras 42-44 re Critical Path Networks
Source for full texts of judgments
• www.bailii.org
![Page 40: Awarding Extensions of Time - - Probyn · PDF filesee however FIDIC 1999 Red Book for example, ... • Format for presentation of EOT claim? ... [2012] EWHC 1773](https://reader034.vdocuments.site/reader034/viewer/2022051718/5a70854c7f8b9a98538c1539/html5/thumbnails/40.jpg)