AVANTech Incorporated
11.79%
19.79%
1.37%17.31%
49.66%
0.07% Government
Industrial
Municipal
Oil&Gas
Power
Remediation
Avantech Team:63 Employees
17 Engineers
5 Project Managers
3 Marketing and Sales
Avantech Water Treatment: Nuclear Water Treatment
Wastewater Treatment Recycling
Avantech Product Line: Water Treatment Services
100+ Standard Products
Nuclear Water Specialty Wastewater Specialty
Foundation For Excellence!
-
7/27/2019 avantech fukushima overview2013
3/43
AVANTech Incorporated
Foundation For Excellence!
Nuclear Quality:ASME NQA-1 Quality Program
Full time CWI, SN-TC-T1A Inspection
Professional Engineering:Chemical
Mechanical
Electrical
Professional Manufacturing:ASME Code Stamp
ASME/AWS Welding
UL Panels
-
7/27/2019 avantech fukushima overview2013
4/43
AVANTech Incorporated
Worldwide Expertise!
DOE Expertise:
International Expertise: Commercial Nuclear Expertise:
Power Generation:
-
7/27/2019 avantech fukushima overview2013
5/43
Water Treatment
Challenges at the
Fukushima-Daiichi
Nuclear Facility
AVANTech Incorporated
James L. BraunPresident and CEO
November - 2013
-
7/27/2019 avantech fukushima overview2013
6/43
Incident Fundamentals
EpicenterofThoku
EarthquakeFukushima
EurasianPlate NorthAmericanPlate PacificPlate PhilippinePlate
6
Tectonic Plates of Japan
1500Earthquakes
Annually
10%oftheworldsvolcanos
-
7/27/2019 avantech fukushima overview2013
7/43
Great East Japan Earthquakeo March 11, 2011
o Magnitude 9.0
o Power fails in northern Japan
o
Units 1, 2 & 3 shutdown automaticallyo Units 4, 5 & 6 already shutdown (defueled)
7
-
7/27/2019 avantech fukushima overview2013
8/43
Tsunami
Friday, March 11th at 14:46
No significant Rx
damage due to earth-
quake
Diesel generators start
(13 generators total)
Emergency core cooling
system initiate
Plant is stable
Tsunami Hits NPP at 15:41
50+ Fukushima NPP
Floods diesel generators
Station blackout- Only Battery Power
RemainsCooling Systems
All cooling systems fail
Steam from decay heat creates high pressure
8
-
7/27/2019 avantech fukushima overview2013
9/43
TsunamiTsunami
Wave Entering Turbine Building.
Automobile
9
-
7/27/2019 avantech fukushima overview2013
10/43
TsunamiTsunami
Flooding of Turbine Building
Automobile
10
-
7/27/2019 avantech fukushima overview2013
11/43
Accident ConditionsAccident Conditions
11
-
7/27/2019 avantech fukushima overview2013
12/43
Contributing Factor - TopographyContributing Factor - Topography
Avantech
Equipment
12Site Excavation Exacerbates the Problem
-
7/27/2019 avantech fukushima overview2013
13/43
Hydrogen ExplosionsHydrogen Explosions
Open Steam Relief Valves to Torus
Open Drywell Relief Valve
Zr + 2H20 1200CZrO2 + 2H2
Cooling Systems All cooling systems fail
Steam from decay heat creates high pressure
13
50psi
limit
Fuel
Pool
-
7/27/2019 avantech fukushima overview2013
14/43
Hydrogen Explosions
14
-
7/27/2019 avantech fukushima overview2013
15/43
Devastation from Explosion
Unit 4 Unit 3 Unit 2 Unit 115
-
7/27/2019 avantech fukushima overview2013
16/43
o Phase 1 - Cesium Removal SARRY System
o Phase 2 Multinuclide Removal
o Phase 3 - Strontium Removal
o Phase 4 - Groundwater Treatment
o Phase 5 - Car Wash
Fundamentals of the Emergency
16
-
7/27/2019 avantech fukushima overview2013
17/43
Fukushima Liquid Waste OverviewFukushima Liquid Waste Overview
17
Water Treatment Continues to Be a Challenge
-
7/27/2019 avantech fukushima overview2013
18/43
Phase 1 - The Technical Challenge
18
Removal of radioisotopes in a Seawater
Solution
Deliver it in less than 8 weeks
Start-up in less than 12 weeks
Ensure its safe! Dose Rates
Thermal
Operational Safety
Failure means Radioactive Wastewater
into the Pacific Ocean
-
7/27/2019 avantech fukushima overview2013
19/43
Phase 1: The AVANTech SolutionPhase 1: The AVANTech Solution
Crystalline Silicotitanate Polishing Ion Exchange
Distribution Coefficient (Kd) > 20,000
Needed to achieve complete activity
removal with a single pass
Axial
Cesium
Loading
CsLimitedto
200,000Ci
(7.5E+15Bq)
Engineered Zeolite Primary Ion Exchange
Distribution Coefficient (Kd) 2,000 in
seawater
Good Axial Cesium Distribution
19
Challenge 1 Activity Capture Challenge 2 Shielding
Integral Shielding
6 Pb Equiv.
Loaded Wt.:
23 mt (50,000 lb)
Safely Managing 200,000 Curies of Radioactive Material
Challenge 3 Heat Generation
855F
Centerline
Temperature
Profile
Centerline/ Core
Temperature
Passive Cooling
Contact Handled
Long Term Storage
-
7/27/2019 avantech fukushima overview2013
20/43
Phase 1 The AVANTech SolutionPhase 1 The AVANTech Solution
20Process Optimizes Media and Decontamination Factor
SARRY
Pipe Racks
SIXMs
Flexible Hoses
H2 Vents
Automatic Alignment
DP (kPad)
Throughput (m3)
Rad Loading (TBq)
Trending
-
7/27/2019 avantech fukushima overview2013
21/43
The Implementation Challenge
21
Rigors of Working at the Fukushima Site
Exclusion Zone - 20 to 30 km Around Fukushima Site
-
7/27/2019 avantech fukushima overview2013
22/43
Clean/ Regulated/ ContaminatedClean/ Regulated/ Contaminated
J-Village / National Soccer Center
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 22
-
7/27/2019 avantech fukushima overview2013
23/43
Site MobilizationSite Mobilization
J-Village (Dress Out Area)
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 23
-
7/27/2019 avantech fukushima overview2013
24/43
Site MobilizationSite Mobilization
J-Village (Dress Out Area)
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 24
-
7/27/2019 avantech fukushima overview2013
25/43
Site MobilizationSite Mobilization
J-Village (Dress Out Area)
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided.
Dosimetry
Tepco TLD
Toshiba TLD
D.A.D.
25
-
7/27/2019 avantech fukushima overview2013
26/43
Site MobilizationSite Mobilization
Transportation to Site
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 26
-
7/27/2019 avantech fukushima overview2013
27/43
Site MobilizationSite Mobilization
Exit from J-Village (From Regulated Area)
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 27
-
7/27/2019 avantech fukushima overview2013
28/43
Site MobilizationSite Mobilization
Contaminated Protective Clothing Storage
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 28
-
7/27/2019 avantech fukushima overview2013
29/43
Installation ChallengesInstallation Challenges
SIXMs Arriving at Fukushima Dock
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 29
Air Freight to Japan
Ship from Tokyo to Iwaki
Barge from Iwaki to Fukushima Site
Earthquake Damage Created Logistics Problems
-
7/27/2019 avantech fukushima overview2013
30/43
Equipment InstallationEquipment Installation
SARRY Pipe Racks
SIXMs
Post Filters
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. Thisdocument may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 30
Raised Walkway
Flexible Hoses
Dry Disconnects
Hydrogen Ventilation
Composite Autosamplers
Grab Samplers
Gamma Detectors
Remote Sampling
Mobile Equipment Aided Expedited Installation
-
7/27/2019 avantech fukushima overview2013
31/43
Equipment InstallationEquipment Installation
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. Thisdocument may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 31
Rx, Turbine and
Radwaste Building
24 million gallons of
Storage Capacity
Mobile Equipment Aided Expedited Installation
Submersible Transfer Pump Transfer HosesTurbine Building
-
7/27/2019 avantech fukushima overview2013
32/43
Simplified and Automated SolutionSimplified and Automated Solution
Automatic IX
Alignment
DP (kPad)
Throughput
(m3)
Rad Loading
(TBq)
Trending
2011 by AVANTech Inc. This document contains information that is confidential and proprietary. No rights to this document are granted herein, except as may be expressly provided in any signed written agreement. This
document may not be copied, modified, disclosed, or used other than in accordance with the terms and conditions of the agreement under which it is provided. 32
Automation Eliminates Exposure and Human Errors
-
7/27/2019 avantech fukushima overview2013
33/43
Phase 1: ResultsPhase 1: Results
Accumulated Water Volume Control
U2 T/B B1
WL [mm]
U3 T/B B1WL [mm]
33
SARRY Processed 80% of Water
Non-detectible CS-137 effluent
DF > 2 million
SARRY Generated 13% of Waste
Results by all Standards Exceeded Clients Expectations
-
7/27/2019 avantech fukushima overview2013
34/43
TEPCO Success!TEPCO Success!
34
Results by all Standards HaveExceeded Expectations
The Challenge: Lethal Levels of Cs-137:
Heat Generation:
Radiation Shielding:
Hydrogen Gas Gen:
The Product: Prefiltration
Ion Exchange
Automation
SamplingThe Result: < 10 week delivery
DF > 2,000,000
Cs Effluent Non-detectible
Waste Generation 10% Safe Operation
Additional Work: Groundwater Treatment
SARRY Replacement Vessels
Atrex
-
7/27/2019 avantech fukushima overview2013
35/43
Post Emergency Challenges
35
On-going Challenges
Phase 2 Brine Treatment
Phase 3 - Strontium Removal
Phase 4 - Groundwater Remediation
Phase 5 - Car Wash Wastewater
-
7/27/2019 avantech fukushima overview2013
36/43
Phase 3 Strontium RemovalPhase 3 Strontium Removal
Strontium Removal Focus Worker Exposure
Evaporator Maintenance
R/O Maintenance
Equipment Maintenance
Radionuclide Removal
Waste Generation
Technical Challenge High Salinity Water
Heat Dissipation
Radiation Exposure
Minimize Radwaste Generation
Optimize Material Handling
36
SARRY(AVANTech)
REVERSE
OSMOSISTURBINE BLDGS.
PURE COOLINGWATER STORAGE
600 M3/D
GROUNDWATER
1000M3/D
400 -500M3/D
BRINESTORAGE
TANKS
Reject
1000M3/D
50% Rec.
500M3/D
STORAGETANKS
STORAGE OFSHIELDED IX
MODULES
Volumes as of
September 26, 2012
500 M3/D
RX
1ST
CESIUMAPPARATUS
RADWASTE
BLDGS
90,000 M3
(24 MGAL)
180,000 M3
(47.5 MGAL)
22,000 M3
(5.8 MGAL)
New Sr
Media
Areva/ KurionStandby Operation
120 Mgal treated
since June-2011
Creating a Safer Work Environmentand Minimizing Exposure
-
7/27/2019 avantech fukushima overview2013
37/43
Phase 3 Strontium RemovalPhase 3 Strontium Removal
Current Process
System Objectives Minimize On-site work
Utilize Existing Crane Passive operation
37
Design Inputs Sr-90 Concentration 1E+05 Bq/cm3
Cs-134 Concentration 7E+04 Bq/cm3
Cs-137 Concentration 1E+05 Bq/cm
3
IX Volume 1E+06 cm3
SARRY System Flow
Plug-n-Play Creates a Simplified Solution
Retrofit Results ASME Section IX Pressure Vessel
Operating Pressure 200 psig
Integrated into existing SARRY System
55 m3/hr flow rate per vessel
Thermal Results
Dose Profiling Operation 1st Quarter 2014
-
7/27/2019 avantech fukushima overview2013
38/43
Phase 4 Groundwater RemediationPhase 4 Groundwater Remediation
38
Groundwater Goals Rad Removal for Discharge
High TDS Influent
Minimize Waste Generation Minimize Consumables
Groundwater Problem Groundwater In-leakage
Increased Contaminated Water
Increased Waste Volumes Radionuclides getting to the Ocean
Lower Groundwater to Reduce In-Leakage
-
7/27/2019 avantech fukushima overview2013
39/43
Phase 4 Groundwater RemediationPhase 4 Groundwater Remediation
39
System Solution Gross Filtration
Fine Filtration
Ion Exchange
System Design Inputs 1,200 m3 per day (220 gpm)
Chemistry Cl- 800 ppm
Ca 23 ppm
Mg 61 ppm
COD 7 mg/l
Activity Cs-134: 5.12 Bq/ml
Cs-137 9.46 Bq/ml
I-131: 6.65E-02 Bq/ml
Co-60: 1.64E-02 Bq/ml
Sr-90: 3.56E-02 Bq/ml
Laboratory Scale Validation of Media
-
7/27/2019 avantech fukushima overview2013
40/43
Phase 4 Groundwater RemediationPhase 4 Groundwater Remediation
40
Operations
Plug-n-Play Installation
AutomatedMaterial Handling Similar
to SARRY
Anticipated ResultsNondetectible Effluent
Minimal Waste Generation
Start-up February 2014
Filtration
Ion Exchange
Controlling In-Leakage to Meet the Site Objectives
-
7/27/2019 avantech fukushima overview2013
41/43
Phase 5 Vehicle DecontaminationPhase 5 Vehicle Decontamination
41
Vehicle Challenge Clean Wastewater from
Decontamination of Vehicles
Radionuclide Removal
Minimize Waste Generation
Technical Challenge High Solids
Radiation Exposure
Material Handling Minimize Waste Generation
Item UnitInlet
(Waste Water)
Outlet
(Treated Water)
SS ppm 200
-
7/27/2019 avantech fukushima overview2013
42/43
Phase 5 Vehicle DecontaminationPhase 5 Vehicle Decontamination
42
Technical Solution Batch Process
Collection Tank
Clarification Chemical Treatment
Filtration
Solids Treatment
Design Characteristics 10 m3/day in hr
2.5 m3/hr
Automated Nondetectible Effluent
ATREX Arrangement
Clarification
Sample
Tanks Filtration
Chemical
Treatment
-
7/27/2019 avantech fukushima overview2013
43/43
Fukushima Water ChallengeFukushima Water Challenge
43
Phase 1 - Cesium Removal Avantechs SARRY System
Phase 2 Multinuclide Removal Phase 3 - Strontium Removal Avantechs SARRY Upgrade
Phase 4 - Groundwater Treatment Avantechs Treatment System
Phase 5 - Car Wash Avantechs Atrex System
Past Success has Created Future Opportunities