Markos Mengesha, P.E. | Project No. R-002011-0089-3 | January 25, 2018

Avalon Place Neighborhood Reconstruction Project

PROJECT NUMBER R-002011-0089-3

PROJECT NAME Avalon Place Neighborhood Reconstruction Project

TYPE OF PROJECTDRAINAGE|COMPLETE STREET|MOBILITY|WATER WASTEWATER

Complete Street

BUDGET Approximately $25M

TIMELINE Scheduled Construction to Completion 2019 – 2022

COUNCIL DISTRICT Districts C & G

PROJECT CONTACT Wade Parks

CONTACT EMAIL [email protected]

2CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectGeneral Information

• Improve sanitary sewer, storm sewer, and

water systems

• Improve pavement condition

• Pedestrian/ bike safety and accessibility

3CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectIdentified Needs

Fairview St. Looking East at Hazard St.

Presenter
Presentation Notes
Existing sanitary sewer is connected to the Camp Logan trunk sewer, constructed in 1950’s. Project has 20,000+ linear feet of sanitary sewer needing replacement or rehabilitation. Sanitary sewer pipes to move from the back lots to the City of Houston right-of-way.

CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3 4

Avalon Place Neighborhood Reconstruction ProjectPlanned Updates

WASTEWATER WATER SIDEWALKS

ROADWAY TREESBIKE FACILITY

Presenter
Presentation Notes
In addition to sanitary sewer upgrades, street reconstruction and sidewalk reconfiguration is planned. Plans also include bike facilities along Fairview.

5CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectProposed Sidewalk PlanThe following sidewalk improvements are being planned as part of this project.

COUNCIL DISTRICT - G

COUNCIL DISTRICT - CNo UPGRADES, ADEQUATE CONDITION

PROPOSED SIDEWALK

NEW SIDEWALK (NO EXISTING SIDEWALK)

LIMITED PAVEMENT WORK (UNDERGROUND UTILITY WORK)

LEGEND

NEW SIDEWALK, TREE PROTECTION PRESERVATION

6

Avalon Place Neighborhood Reconstruction ProjectProposed Roadway Improvements

Presenter
Presentation Notes
In order to maintain the City’s design standards, some streets in this project area will be widened or narrowed. These adjustments may be necessary to accommodate sidewalks, traffic flow, bike facilities (along Fairview), and on-street parking.

7CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectExisting Road Section – Driscoll St. North of Fairview St.

50’ Existing Right- of way

8CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectProposed Road Section – Driscoll St. North of Fairview St.

Buffer (Varies)

Buffer (Varies)

50’ Existing Right-of-way

9CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectExisting Road Section – Fairview St. East of Huldy St.

75’ Existing Right- of way

10CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectProposed Road Section – Fairview St. East of Huldy St.

Buffer (Varies)

Buffer (Varies)

75’ Existing Right- of way

11CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectExisting Road Section – Huldy St. South of Fairview St.

70’ Existing Right-of-way

12CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectProposed Road Section – Huldy St. South of Fairview St.

70’ Existing Right-of-way

Buffer (Varies)

Buffer (Varies)

Option 1: Replace the broken length and width of thedriveway with plain reinforced cement concrete at nocost to the home owner.

Option 2: Grade the subgrade to proper slope andform the driveway to meet the new grades /slope. Youwould see the finished dirt with the proper slope.Homeowner will finish the driveway with their desiredfinish at their cost. (Driveway must be finished 2 weeksafter it’s been prepped by the City.)

13CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

Avalon Place Neighborhood Reconstruction ProjectDriveway Construction Options

CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3 14

Avalon Place Neighborhood Reconstruction ProjectTimeline

2012PLANNING

2018DESIGN

(IN PROGRESS)

2019SCHEDULED

CONSTRUCTION

2022ANTICIPATED COMPLETION

https://www.surveymonkey.com/r/Avalon_Place

Please use the survey to comment on the following:• Roadway Width• Sidewalk Updates• Fairview Mobility• Driveway Options

15CAPITAL PROJECTS | AVALON PLACE NEIGHBORHOOD RECONSTRUCTION PROJECT | NO. R-002011-0089-3

TAKE OUR AVALON PLACE SURVEY ONLINE!Survey available: Jan. 25 – Feb. 28, 2018