Welcome toAtwood Lake Park
Master Plan Update
Please hold questions until after the presentation is complete. MWCD Staff will be
available at the stations set up around the room.
Chief of Recreation‐Scott Barnhart Deputy Chief of Parks‐Joe McGlothlin Deputy Chief of Projects‐Tony Luther Park Manager‐ Aaron Stump Recreation & Park Planner‐
Eric Stechschulte
Introductions
Director of Administrative Services Barbara Bennett
Assistant Chief Engineer‐Mike Rekstis
Program Manager Consultant‐Ken Ricker, MS Consultants
2013 2014 2015 2016
Master Plan Timeline
• Woolpert completes overall conceptual master plan
• MWCD Board of Directors approves master plan in October
• Recreation Department prioritized projects
• Completed branding and design guidelines
• Utilities survey & inventory completed at each park
• MS Consultants contracted as MWCD Project Management Consultant
• Aerial topography surveys completed
• 6 Individual Park Designers contracted and began refining preliminary designs on each park
• Individual Park Designers complete preliminary designs for each park
• Individual Park Designers begin detailed design on campground projects
• First campground park projects will be bid out and construction to begin in late 2016
Project Prioritization Transitional Seasonal Camping Areas Infrastructure Stand Alone Projects
Atwood Lake ParkProject Phasing Strategy
Atwood Lake ParkApproved ProjectsFUNDING‐ $18,500,000 Dollars
Beach Seawall‐Complete 2015 Trail construction, Phase 1‐Complete
2016 Trail and Bridge ‐ Phase 2‐Complete 2016 Welcome Center‐Complete 2016 Amphitheater Trail Lighting‐ Complete
2016 New Transient RV Campground ‐ Area 20
(142 Lots)‐Scheduled 2017 Completion Sanitary Sewer ‐Main and Pump Station‐
Scheduled 2017 Completion Event Parking Improvements & New
Dump Station‐ Area 2 & 17‐Scheduled 2017 Completion
Event Parking Improvements‐ Leveling / Drainage 3A‐Scheduled 2017 Completion
New Electric Main‐Scheduled 2017 Completion
New Seasonal RV Campground ‐ Area 4 (28 Lots)‐Scheduled 2018 Completion
Seasonal RV Campground ‐ Area 8 (78 Lots)‐(Current Area A) Scheduled 2018 Completion
New Gas Main‐Scheduled 2018 Completion
Seasonal Camper TemporaryMoving Transition Plan
MWCD is committed to providing assistance by moving your camper, deck and dock to your temporary site, and then moving them back to your newly renovated area.
Seasonal Campers will be notified by letter this fall regarding their temporary move scheduled for the end of the 2017 camping season.
Seasonal Campers will receive a checklist that will address procedures for moving their camper, deck and dock.
Seasonal Campers relocated in the fall of 2017 will be moved back to their newly renovated area in Fall of 2018.
New Shower/Restroom Building in Map Area 4 and Area 20
Proposed Seasonal Camping Lot Layout
Atwood Lake ParkAmenity Pictures
Master Plan Budget
*Chart based on information from: http://www.macrotrends.net/1369/crude-oil-price-history-chart
Crude Oil Prices 2013-June 2016
The Master Plan is being funded through responsible stewardship of oil and gas resources.
In October of 2013 the MWCD Board of Directors approved the Master Plan.
$120 Million Dollars have been dedicated to Master Plan Projects over the next several years.
Atwood Lake Park Future ProjectsFUTURE PROJECTS AS FUNDING BECOMES AVAILABLE Seasonal Campground Renovation‐ Area 12 (84 Lots)
(Current Area F) Seasonal Campground Renovation‐ Area 9 (50 Lots)
(Current Areas B & C) Seasonal Campground Renovation‐ Area 10 (84 Lots)
(Current Areas D & E) Seasonal Campground Renovation‐ Area 16 (25 Lots)
(Current Area 4) Seasonal Campground Renovation‐ Area 13 (17
Lots)(Current Area 1) Activities Area (Splash Pad, Ropes Course, Putt‐putt,
Game Courts)‐ Area 5 Recreation Center, Parking & Turn Around‐Area 6 Beach Area‐Boardwalk, Gazebo, Trails, Sand Volleyball
– Area 7 Causeway Trail and Road Upgrade‐ Area 11 Seasonal Campground Renovation‐ Area 14 (44
Lots)(Current Areas 2 &3) Picnic Area Renovation‐Area 18 New Transient Campground ‐ Area 19 (52 Lots) Amphitheater Expansion & Redevelopment‐ Area 21 Boaters Beach Upgrades‐Area 22 Camper Activity Center Renovation‐Area 3 Cabin Area Renovations‐ Area 23 Primitive Campground & Roadway Development‐ Area
24 Lookout Improvements & New Zip Line‐ Area 25 New Group Campground‐ Area 26 New Cabins‐ Area 27 (10 Cabins) Maintenance Area Expansion‐ Area 30 Roadway & Trailhead‐ Area 31
2
MUSKINGUM WATERSHED CONSERVANCY DISTRICT | ATWOOD LAKE PARK PRELIMINARY DESIGN
Atwood Lake Park Overall Preliminary Plan