attachment c - expanded project cut sheets
TRANSCRIPT
Aune Street Extension (East) Scope The portion east of the parkway of the project to provide a two-lane extension of Aune Street to
connect 3rd Street and Bond Street. Includes 3rd Street and Miller Avenue Intersection improvements
and 3rd Street modification study and implementation.
To efficiently implement some of the smaller projects, some key route improvements along 3rd Street
have been combined with this project. These include:
Key Route R7-A Crosswalk: Create a safe crossing of 3rd Street between BNSF railroad and
Wilson Avenue using rectangular rapid flashing beacons and safety islands
Key Route R7-B Crosswalk: Create a safe crossing of 3rd Street between BNSF railroad and
Franklin Avenue using rectangular rapid flashing beacons and safety islands. (Same as key
intersection project)
Key Route R7-C 3rd Street Underpass: Near Term Enhancements to sidewalk.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 2/23 – 4/23
Procurement for design: 5/23 – 7/23
Design activities: 8/23 – 8/24*
Right-of-way activities: 3/24 – 11/24**
Procurement for construction: 11/24 – 1/25
Construction activities: 2/25 – 12/25
Project manager estimated commitment: 1 year @ 30% allocation, then 2 years @ 50%
allocation.
*Includes effort to select preferred alignment
**No guarantee on completion of right-of-way acquisition if portion of federal parcel is needed
for project.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 13 (ranked 1st)
• While the project scored highly in terms of prioritization, there are significant uncertainties with
regards to its alignment and right-of-way acquisition, accordingly project readiness is rated
relatively low.
• The project has been shifted to begin in FY 22-23 to allow time for defining the alignment, which
allows for other projects that have a higher likelihood of successful implementation in the near-
term.
Additional Information
Budget
Aune Street Extension (estimated allocation): $5,500,000 (GO Bond) *
Key Route R7-A: $215,000 (GO Bond)
Key Route R7-B: $215,000 (GO Bond)
Key Route R7-C: $210,000 (GO Bond)
Key Intersection (3rd/Clay allocation): $210,000 (GO Bond)
Total: $6,350,000**
*The $5.5M is the estimated need for this portion of $13M allocated to the Aune Street Extension
project as a whole. Figure will be updated once more information is gathered on the actual scope of
each project and a better estimate can be developed.
**Tax Incremental Financing is potentially available to this project – see Draft Capital Improvement Plan
Overview for more information.
Project Readiness The alignment of Aune between the Parkway and 3rd Street is undefined. The preferred alignment will
take some time to identify (4-6 months). A United States Forest Service parcel exists at the NW quadrant
of the 2nd Street and Miller Avenue intersection. The city may use eminent domain to minimize project
schedule uncertainty. Eminent domain, however, cannot be used on parcels owned by the federal
government. If the preferred alignment impacts the federal-owned parcel, no guarantees can be made
for a construction schedule.
Another option for the alignment of the Aune extension could tie into the northbound ramp terminal at
Colorado Avenue. The Colorado Avenue Interchange Improvements project is a project funded both by
the City’s GO Bond and by ODOT that will address congestion and safety at this ramp terminal. As of the
development of this document, no funding from the state has been identified in their Statewide
Transportation Improvements Program for the interchange improvement. As such, if this were the
preferred alignment, this project would either have to fully fund the Colorado Avenue Interchange
Improvements project, make an interim improvement, or wait until ODOT funding is available.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Aune Street
Extension (East) project. Those projects include Wilson Avenue Corridor, Aune Street Extension (West),
Midtown Crossings, and Colorado Avenue Interchange Improvements. Below is a discussion on each
conflicting project.
Wilson Corridor Improvements
The construction at the intersection of Third Street and Wilson Avenue will have impacts to East -West
connectivity resulting in a higher traffic load on the Reed Market, Franklin, and the streets connecting
2nd Street and 3rd Street between Wilson and the railroad (Yew Lane through Scott Street). The
improvements to Aune and 2nd Street, and Miller and 3rd Street as part of the Aune Street Extension
(East) will likely be in conflict with a potential detour route for the Wilson Avenue Corridor
Improvements project that will include Wilson Avenue, 2nd Street, and Colorado Avenue.
Aune Street Extension (West)
The construction of the Aune Street Extension (West) is likely to cause closures to Bond Street where
the Aune Extension ties in. The improvements to Aune and 2nd Street as part of the Aune Street
Extension (East) will likely be in conflict with a potential detour route that will include Wilson Avenue,
2nd Street, and Colorado Avenue.
Midtown Crossings
Depending on the selected alternative for the midtown crossings project, detour overlaps could occur
with the Aune Street Extension (East) project. A detour for the construction at 3rd Street and Miller
Avenue would utilize among other streets, Franklin Avenue, Bond Street, Wall Street, Colorado Avenue,
and Arizona Avenue. Should the selected alternative be a widening of the Franklin Avenue
undercrossing, this construction would conflict with those detours.
Colorado Avenue Interchange Improvements
As stated above, there is an option for the eastern alignment of Aune to tie into the northbound ramp
terminal at Colorado Avenue. If the alignment does not tie into the northbound ramp terminal, the Aune
Street Extension (East) project should avoid construction at the same time as the interchange
improvements to avoid overlapping detours and potential access issues.
Wilson Avenue Corridor Scope
Intersection improvements at 3rd Street and Wilson Avenue, 9th Street and Wilson Avenue, and 15th
Street and Wilson Avenue.
To efficiently implement some of the smaller projects, create a consistent corridor environment, and
minimize construction fatigue, the key route improvements along Wilson Avenue and 9th Street have
been combined with this project. These include:
Key Route R1-A SE 9th Street: Wilson Avenue to Reed Market Road Shared use path adjacent to
roadway: Close sidewalk gap and create low-stress bikeway.
Key Route R1-B SE 9th Street: Wilson Avenue to Glenwood Avenue Buffered bike lane: Re-stripe
roadway to include buffered bike lanes when roadway is repaved.
Key Route R12-A Wilson Ave: 2nd Street to SE 9th Street Shared use path adjacent to roadway:
Close sidewalk gap along Wilson Avenue and create a low-stress bikeway.
Key Route R12-B Wilson Avenue: 9th Street to 15th Street Shared use path adjacent to roadway:
Create a low-stress bikeway to connect near SE neighborhoods to Old Mill and Deschutes River
Trail.
Proposed Preliminary Project Schedule Project efforts prior to TBOC Authorization: 8/20 – 4/21
Procurement for design: 5/21 – 7/21
Design activities: 8/21 – 8/22
Right-of-way activities: 10/21 – 10/22
Procurement for construction: 10/21 – 1/22*
Construction activities: 1/22 – 6/23
Project manager estimated commitment: 2 years @ 50% allocation.
*Use of Construction Manager/General Contractor procurement method is anticipated. This
procurement method along with a phased implementation will allow for construction to begin
prior to completion of design on the entire corridor.
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 12.5 (ranked 2nd)
• Project scored highly in terms of prioritization.
• Project was underway prior to the passing of the GO Bond – this has allowed a rapid
acceleration of the procurement and design efforts; accordingly, project readiness is rated
extremely high.
• Staff presented project to TBOC as an opportunity to begin work while the remainder of the
projects are prioritized. TBOC voted unanimously to move forward with the project.
Additional Information
Budget
3rd Street and Wilson Avenue Intersection: $5,000,000 (GO Bond)
9th Street and Wilson Avenue Intersection: $4,500,000 (Transportation CIP)
15th Street and Wilson Avenue Intersection: $3,500,000 (GO Bond)
Key Route R1-A: $1,155,000 (GO Bond)
Key Route R1-B: $3,000 (GO Bond)
Key Route R12-A: $2,179,000 (GO Bond)
Key Route R12-B: $2,179,000 (GO Bond)
Associated Water Improvements: $350,000 (Water CIP)
Traffic Signal Improvements: $284,336.38 (Transportation Construction)
Total: $19,150,336.38
Project Readiness The Wilson Avenue Corridor project was well underway in the form of the Traffic Signal Improvements
project at the time of the vote for the GO Bond. Considering this, the project was well-primed to begin
design work at the time the TBOC prioritization efforts began. Since TBOC’s vote to move forward with
this project, design, right-of-way and utility coordination efforts have progressed. At this point, due to
the need for planning, procurement, right-of-way, utility coordination, public outreach, and design
efforts on all other projects, this is the only large GO Bond project that is feasible to begin construction
in 2022.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Wilson
Avenue Corridor project. Those projects include: Aune Street Extension (East), Aune Street Extension
(West), Reed Market Corridor, Bear Creek Road and 27th Street Improvements, and Colorado Avenue
Interchange Improvements. Below is a discussion on each conflicting project.
Aune Street Extension (East)
The construction at the intersection of 3rd Street and Wilson Avenue will have impacts to East-West
connectivity resulting in a higher traffic load on the Reed Market, Franklin, and the streets connecting
2nd Street and 3rd Street between Wilson and the railroad (Yew Lane through Scott Street). The
improvements to Aune and 2nd Street, and Miller and 3rd Street as part of the Aune Street Extension
(East) a likely detour route for the Wilson Avenue Corridor Improvements project that will include
Wilson Avenue, 2nd Street, and Colorado Avenue.
Aune Street Extension (West)
The construction of the Aune Street Extension (West) is likely to cause closures to Bond Street where
the Aune Extension ties in. The improvements to Wilson and 2nd Street as part of the Wilson Avenue
Corridor will likely be in conflict with a potential detour route that will include Wilson Avenue, 2nd Street,
and Colorado Avenue.
Reed Market Corridor
Construction activities for the Wilson Avenue Corridor project will cause full closures of Wilson Avenue
over the course of the project’s implementation. These closures will likely utilize Reed Market Road as
the main east-west detour in this part of town. The construction associated with the Reed Market
project will be in conflict with those detours.
Bear Creek Road and 27th Street Improvements
The construction of the Bear Creek Road and Pettigrew Road roundabout is likely to cause full closures
to this intersection. The improvements to Wilson Avenue and 15th Street as part of the Wilson Corridor
Improvements will likely be in conflict with a potential detour route that will include 15th Street, Reed
Market Road, and 27th Street.
Colorado Avenue Interchange Improvements
The construction of the Colorado Avenue Interchange Improvements likely to cause partial and full
closures to the northbound ramp terminal at Colorado Avenue. The improvements to Wilson Avenue
and 2nd Street as part of the Wilson Avenue Corridor will likely be in conflict with a potential detour
route that will include Bond Street, Colorado Avenue, and 2nd Street.
Midtown Crossings Scope The Midtown Crossing project includes a study to identify timing, feasibility, and needs for bicycle and
pedestrian improvements at the Greenwood Avenue undercrossing, Franklin Avenue undercrossing, and
Hawthorne Avenue crossing. The outcomes of the feasibility study will be presented to TBOC and Bend
City Council for direction on which crossing(s) to focus the limited funding on.
To efficiently implement some of the smaller projects, create a consistent corridor environment, and
minimize construction fatigue, several key route projects and key intersection projects have been
combined with this project. These include:
Key Route R2-A NW Franklin Avenue: Harriman Street to railroad undercrossing; Improve
transition at Hill Street: Project would manage the conflict between right turns and crosswalk to
sidewalk under railroad. Crosswalk: Create safe crossing of Franklin Avenue at Harriman Street.
Key Route R2-C Franklin Avenue: 1st Street to 5th Street; Buffered bike lane: Re-stripe roadway
to include buffered bike lane westbound; includes crosswalks at 2nd Street and 4th Street and
signal timing enhancements at 3rd Street.
Key intersection at 2nd Street and Franklin Avenue: Addresses bike and pedestrian safety and
improvement at key intersections identified in Transportation Safety Action Plan
Key intersection at 4th Street and Franklin Avenue: Addresses bike and pedestrian safety and
improvement at key intersections identified in Transportation Safety Action Plan
Key intersection at 2nd Street and Greenwood Avenue: Addresses bike and pedestrian safety and
improvement at key intersections identified in Transportation Safety Action Plan
There are several other synergy opportunities with projects funded through other City of Bend Capital
Improvement funds and other agencies.
An All Roads Transportation Safety (ARTS) project on Greenwood Avenue is currently underway. That
project’s scope is to identify potential multimodal enhancements for Greenwood Avenue from the
intersection at 3rd St (US20) west to Wall Street within the existing eighty-foot right of way and provide
a preliminary qualitative assessment of alternative configurations to support public conversations and
future refinements.
Another ARTS project is also currently underway along Franklin Avenue. That project’s scope is to install
corridor illumination on Franklin Avenue from Wall Street to 6th Street.
There are synergy opportunities with a Bicycle Greenways Phase IV project identified in the
transportation capital improvement plan. This project could be implemented together with the Midtown
Crossings project resulting in cost savings and more consistent corridors for bicycle users and
pedestrians.
There are potential synergies associated with water and stormwater projects identified in their
respective capital improvement plans as well as well as private development.
Proposed Preliminary Project Schedule Planning efforts prior to feasibility study: 8/21 – 10/21
Procurement for feasibility study: 11/21 – 1/22*
Feasibility study: 2/22 – 10/22
Procurement for design/permitting: 11/22 – 1/23
Design activities: 2/22 – 8/24
Right-of-way activities: 10/23 – 12/24
Permitting activities: 8/22 – 12/24
Procurement for construction: 1/25 – 3/25
Construction activities: 4/25 – 9/26
Project manager estimated commitment: 2 years @ 30% allocation, then 3 years at 60%
allocation.
*Funded with dollars received through the American Rescue Plan Act (ARPA)
Sequencing Notes and Reasons for Fiscal Year Funding • Franklin, Greenwood Priority score: 12 (ranked 3rd)
• Hawthorne Priority Score: 10.5 (ranked 8th)
• While the projects scored highly in terms of prioritization, there are significant uncertainties
with regards which midtown crossings project will ultimately receive funding. Additionally,
several years of railroad permitting would be required regardless of the preferred alternative,
accordingly project readiness is rated relatively low.
• The project is being started immediately using funding through the American Rescue Plan Act
(ARPA).
• Once TBOC and Council have given direction on the use of the midtown crossings project, the
funds for the projects that have less synergy with the larger crossing project may be separated
and implemented on their own or with other smaller projects.
Additional Information
Budget
Midtown Bicycle and Pedestrian Crossings: $12,000,000 (GO Bond)
Key Route R2-A: $176,000 (GO Bond)
Key Route R2-C: $164,000 (GO Bond)
Key Intersection (2nd/Greenwood allocation): $210,000 (GO Bond)
Key Intersection (2nd/Franklin allocation): $210,000 (GO Bond)
Key Intersection (4th/Franklin allocation): $210,000 (GO Bond)
Franklin ARTS Project: $355,047 (ARTS)
Greenwood ARTS Project: $700,000 (ARTS)
Bicycle Greenways: $1,000,000 (Transportation CIP)
Associated Water Improvements: $145,000 (Water CIP)
Associated Stormwater Improvements: $3,750,000 (Stormwater CIP)
Tax Increment Financing: $6,000,000 (TIF)*
Congressionally Directed Spending: $5,000,000 (Federal)**
American Rescue Plan Act: $2,000,000 (ARPA)
Total: $26,920,047
*Tax Incremental Financing is potentially available to this project – see Draft Capital Improvement Plan
Overview for more information.
**City staff was notified on October 20, 2021, that the Congressionally Directed Spending Request was
not selected by the Appropriations Committee. Staff will pursue other opportunities for additional
funding sources as they arise.
Project Readiness The allocation of the spending of the $12M under the midtown crossings project in the GO Bond
includes feasibility studies for all three crossings to determine the best allocation of the constrained
funding. The feasibility study effort will begin immediately with the funding received through ARPA. As
identified above, the duration for that study is anticipated to be 6 months – however, depending on the
level of public outreach efforts, the study’s timeframe could be prolonged.
Once the funding has been allocated to a certain crossing, the permitting processes with the State
Highway and Burlington Northern Santa Fe Railroad can begin. Based on recent experience, the
permitting efforts for the railroad are the critical path task and the expected duration is 2-3 years as
noted in the proposed preliminary project schedule above.
Depending on the crossing that is selected for improvement, there will be some key route and/or key
intersection projects that will lose some synergy with the overall crossing project. These smaller projects
could get separated from the larger project to be implemented under a different timetable. There is
potential to work with the construction projects identified in the Local Residential Safety Program to
implement these smaller projects together to reduce the costs and efficiencies lost through the
separation of the projects.
Construction Fatigue The effects of construction fatigue will be dependent upon the selected alternative. Greenwood Avenue
and Franklin Avenue undercrossings have more conflicts with other projects since they are already built
out and functioning corridors, however an alternative on Hawthorne Avenue could pose a challenge as
well.
Aune Street Extension (East)
Depending on the selected alternative for the Midtown Crossings project, detour overlaps could occur
with the Aune Street Extension (East) project. A detour for the construction at 3rd Street and Miller
Avenue would utilize Franklin Avenue, Bond Street, Wall Street, Colorado Avenue, and Arizona Avenue
among other streets. Should the selected alternative be a widening of the Franklin Avenue
undercrossing, this construction would conflict with those detours.
Olney Pedestrian and Bike Improvements
Depending on the selected alternative for the midtown crossings project, detour overlaps could occur
with the Olney Pedestrian and Bike Improvements project. A detour for the construction of the
undercrossing of the Parkway for Greenwood Avenue would utilize Wall Street, O3rd Street, Greenwood
Avenue, and Wall Street among other streets. Should the selected alternative be a modification or
widening of the Greenwood undercrossing, this construction would conflict with those detours.
Portland Avenue Improvements, 4th Street Intersection Improvements
While detour overlaps with the Portland Avenue Improvements project and the 4th Street Intersections
improvements projects are not anticipated with the construction of any of the Midtown Crossings
projects, there is the potential for construction fatigue to occur when detours from one project lead into
detours for other projects. These effects can be limited to an extent through careful planning and detour
design but should be considered while conducting the project sequencing.
Closure of Parkway Right-Outs
A project identified in the US 97 Parkway Plan Phase 2 would close several of the access to the parkway
that do not currently have acceleration lanes. That project would include the closure of the Hawthorne
Avenue right-on access to the Parkway. If the Hawthorne crossing project is selected as the preferred
alternative for the Midtown Crossings project, the Hawthorne Avenue eastbound at the parkway access
could be used as a landing for an overcrossing. This could be a benefit or a drawback depending on the
State’s timing of the closure of the right-on access. The benefit would allow for a convenient place to
land an overcrossing. The drawback would be that if that were the preferred landing for an
overcrossing, timing would have to align with ODOT’s project.
Reed Market Corridor Scope A phased project to leverage ODOT interchange improvement, construct a 2-lane roundabout at Reed
Market Road and 15th Street, and an overcrossing railroad at Reed Market Road.
This GO Bond project is anticipated to be implemented in conjunction with transportation projects from
the City’s Transportation Capital Improvement Plan. These projects include improvements to the
intersections of Reed Market Road and 3rd Street and Reed Market Road and Bond Street. The benefits
from combining these projects would include consistent planning-level assumptions, reduced
construction fatigue through the ability to capitalize upon traffic control coordination where possible,
and possible reduced overall project costs using fewer contracts and City personnel.
To efficiently implement some of the smaller projects, some key route improvements and other bike
and pedestrian safety improvements have been combined with this project. These include:
3rd canal crossing south of 3rd/Brosterhous – Construct pedestrian facilities on 3rd Street across
the canal bridge.
Key Route R1-D SE 15th Street: Reed Mkt Rd to 300’ south of King Hezekiah Shared use path
adjacent to roadway: Convert an existing curb-tight sidewalk to a separated shared use path.
Also combined with the project to construct an intersection improvement at Ferguson Road and 15th
Street.
Proposed Preliminary Project Schedule Refinement Study: 1/22 – 12/22*
(Phase 1) Ferguson Road and 15th Street Intersection, 3rd canal crossing south of 3rd/Brosterhous, Key
Route R1-D:
Planning efforts prior to design activities: 1/23 – 4/23
Procurement for design/permitting: 5/23 – 7/23
Design activities: 8/23 – 12/24
Right-of-way activities: 1/24 – 7/24
Permitting activities: 8/23 – 6/24
Procurement for construction: 1/25 – 3/25
Construction activities: 4/25 – 12/25
(Phase 2) ODOT interchange improvement, construct a 2-lane roundabout at Reed Market Road and 15th
Street, and an overcrossing railroad at Reed Market Road.
Procurement for design/permitting: 1/27 – 3/27
Design activities: 4/27 - 12/28
Right-of-way activities: 7/27 – 12/28
Permitting activities: 7/27 - 6/29
Procurement for construction: 1/29 – 3/29
Construction activities: 4/29 – 12/30
Project manager estimated commitment for Refinement Study: 1 years @ 15% allocation
Project manager estimated commitment for Phase 1: 2 years @ 50% allocation
Project manager estimated commitment for Phase 2: 4 years @ 60% allocation
*Planning level document coordinated with ODOT to assess transportation needs in the vicinity
of the interchange – includes public outreach effort.
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 12 (ranked 3rd)
• While the project scored highly in terms of prioritization, there are significant planning efforts
and detour route upgrades needed prior to project construction
• Construction of the 15th Street and Reed Market Road Roundabout widening, 15th Street key
route and 15th and Ferguson intersection improvement in 2025 would allow for the Bear Creek
Road and 27th Street Improvements to occur without conflict
Additional Information
Budget Reed Market Road: $36,500,000 (GO Bond)
Reed Market Road and 3rd Street Intersection: $3,000,000 (Transportation CIP) *
Reed Market Road and Bond Street Intersection: $750,000 (Transportation CIP) *
Ferguson Road and 15th Street Intersection: $3,500,000 (GO Bond)
3rd canal crossing south of 3rd/Brosterhous: $980,000 (GO Bond)
Key Route R1-D: $1,185,000 (GO Bond)
Reed Market Interchange: $9,450,000 (ODOT)**
Total: $55,365,000
*Possible synergy projects to increase efficiency, create a consistent corridor environment, and/or
minimize construction fatigue. If delays to these improvements are unsatisfactory to the Transportation
CIP, these projects may be decoupled from the GO Bond projects.
**Funding has not been allocated in the State Transportation Improvements Program
Project Readiness Several planning efforts will be required to understand the project’s phasing options and its needs from
a corridor perspective. As the City’s only east-west major arterial in the southeast area of town, Reed
Market Road carries a large amount of daily traffic. Proper planning is required prior to the closure of
this road.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Reed
Market Corridor project. Those projects include Wilson Corridor Improvements, Aune Street Extension
(West), Powers, Parrell, Chase, Brosterhous Connection, Bear Creek Road and 27th Street
Improvements, and Colorado Capacity Improvements. Below is a discussion on each conflicting project.
Wilson Corridor Improvements
Construction activities for the Wilson Avenue Corridor project will cause full closures of Wilson Avenue
over the course of the project’s implementation. These closures will likely utilize Reed Market Road as
the main east-west detour in this part of town. The construction associated with the Reed Market
project will conflict with those detours.
Aune Street Extension (West)
The construction of the Aune Street Extension (West) is likely to cause closures to Bond Street where
the Aune Extension ties in. The improvements to Reed Market Road and Bond Street as part of the Reed
Market Corridor will conflict with a likely detour route that will include Bond Street, Reed Market Road,
Century Drive, and Colorado Avenue.
Powers, Parrell, Chase, Brosterhous Connection
The construction of the improvements to the Brosterhous Road and Chase Road intersection cause
closures to Brosterhous Road. The construction on Reed Market Road to construct the railroad
overcrossing, and the construction at the intersections of 15th Street and Reed Market Road and 3rd
Street and Reed Market Road as part of the Reed Market Corridor will conflict with a likely detour route
that will include American Lane, Brosterhous Road, and 3rd Street.
Bear Creek Road and 27th Street Improvements
Detours for the construction along Bear Creek Road and at the intersection of Bear Creek Road and
Pettigrew Road will utilize 15th Street, Reed Market Road, and 27th Street as a detour. The construction
at 15th and Reed Market conflicts with this construction.
Colorado Capacity Improvements
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the Reed Market Road and
Bond Street intersection will conflict with those detours.
Powers Road Interchange Improvements
The Powers Road Interchange Improvements project should be completed after the Reed Market Road
interchange work so as to avoid concurrent closures at the two adjacent Parkway
intersections/interchanges.
Project Separation During the Transportation Bond Oversight meeting on October 5th, 2021, an approach to accelerate the
implementation of the key route project, the project to construct pedestrian facilities on 3rd Street
across the canal, and intersection improvements at 15th Street and Ferguson Road was suggested. This is
a possibility and the approach would have some benefits and drawbacks as further discussed below.
Benefits of Separation
A separated implementation of this project could lead to a more rapid construction of some of the
smaller portions of the larger project. This more rapid implementation would result in a quicker
realization of the benefits of these projects. Care should still be taken to ensure that detour overlaps are
mitigated with the above-mentioned projects.
Drawbacks of Separation
By splitting up the project into several smaller projects, costs are anticipated to be significantly higher
than delivering the projects as one larger project due to economies of scale. Some examples where
projects costs were reduced by implementing them with larger projects include the Roosevelt
pedestrian crossing of 3rd Street and a traffic calming project on Harmon Boulevard. Construction costs
were reduced approximately 40% and 45% respectively for the projects when they were combined with
larger nearby projects. This effect is similar for the costs associated with the design efforts, and City staff
time allocated to the project. The result of an increase in project costs is likely a reduced total amount of
work being completed with the GO Bond, due to the fixed overall funding.
A disjointed implementation of the improvements under this project could also lead to increased
construction fatigue. As discussed in the previous paragraph, constructing projects in smaller increments
is a less efficient means of implementation. These inefficiencies would likely lead to longer closure
durations and a larger quantity of closures resulting in more detours and longer delays.
Reed Market Delay During the TBOC meeting on October 5th, 2021, an approach to delay the work for the Reed Market
Road railroad overcrossing, the Reed Market Interchange, and the Reed Market Road and 15th Street
roundabout widening was suggested. This is a possibility and the approach would have some benefits
and drawbacks as further discussed below.
Benefits
The suggestion to delay the Reed Market Road railroad overcrossing and Reed Market Road and 15th
Street roundabout widening would lead to more near-term city staff time available to dedicate to other
projects. Instead of the project manager commitment listed above (2 years @ 15% allocation then 70%
allocation for 4 years), the commitment would be lessened to an estimated commitment of 2.5 years at
50% commitment. This would open up some time for the project manager to take on another project or
assist with other GO Bond related tasks.
It should be noted that the approach would not, however, lead to a decreased amount of staff time
overall as further discussed in the Project Separation section above.
Drawbacks
This prioritization process is not only an effort to work towards a list of projects ordered by their
urgency and readiness, but should also be considering the scenario that the funding under the GO Bond
is insufficient to pay for all the projects identified. As was presented to the City of Bend Council on
January 8, 2020 – the results of the 1-minute survey were a convincing directive from the community for
the completion of improvements to Reed Market Road (See Attachment G).
This bond is the first of two similarly sized bonds identified in the Transportation System Plan (TSP) to
provide funding for transportation projects over the next 20 years. While not the sole sources of
revenue identified for transportation projects in the TSP, they do provide a majority of the funding (see
table 6-3 of the TSP for further discussion). A failure to complete the Reed Market Road railroad
overcrossing and widening of the Reed Market Road and 15th Street could have negative repercussions
on the successful passing of the second transportation bond.
Another drawback for pursuing a delay to these projects would be a potential delay to improvements to
the Reed Market Road interchange. Part of this project is a Refinement Study that would identify
improvements to the Interchange. Per the US97 Parkway Plan Phase 2 (Parkway Plan), this Refinement
Study would include an analysis of operational needs of all modes of transportation at and adjacent to
the interchange and make recommendations for improvements. The Parkway Plan also identifies the
Reed Market Road & US 97 Northbound Ramp Terminal as being one of the intersections with the
Parkway with the highest level of traffic stress for bicycles. The delay of the Reed Market Road project
would also delay any bicycle improvements to this ramp terminal.
Bear Creek Road and 27th Street Improvements Scope This project consists of three key routes projects combined with the project to construct a single lane
roundabout at the intersection of Pettigrew Road and Bear Creek Road.
The key route improvements along are more specifically defined as:
R2-D Bear Creek Safe Routes to School: Larkspur Trail to Coyner Trail Close sidewalk gap and
create a connection between Coyner and Larkspur Trail.
R2-E Bear Creek Road: Cessna Avenue to east Urban Growth Boundary; Shared use path
adjacent to roadway: Close sidewalk gap and create low-stress bikeway extending to 170 new
affordable housing units.
R8-A 27th Street: Highway 20 to Reed Market Road; Shared use path adjacent to road: Close
sidewalk gap along 27th Street and create a low-stress bikeway.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 10/23 – 12/23
Procurement for design: 1/24 – 3/24
Design activities: 4/24 – 9/25
Right-of-way activities: 8/24 – 7/25
Procurement for construction: 1/25 – 3/25
Construction activities: 4/25 – 11/26*
Project manager estimated commitment: 4 years @ 50% allocation.
*Phased construction could allow for a more rapid construction of some of the project elements
that have a higher level of project readiness (i.e., constructing one of the larger key route
projects in 2025 and the other in 2026)
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 11 (ranked 6th)
• The project scored relatively high in terms of prioritization
• The preferred alternative for the key routes along Bear Creek Road and 27th Street will have a
large effect on the readiness of the project overall due to right-of-way needs
• Early coordination with Bend-La Pine Schools is critical for the successful implementation of the
trail connection
• Improvements to Bear Creek Road are challenging as it requires detours on many other roads
identified in the GO Bond for improvements
Additional Information
Budget
Bear Creek Road and Pettigrew Road Intersection: $3,500,000 (GO Bond)
Key Route R2-D: $385,000 (GO Bond)
Key Route R2-E: $2,700,000 (GO Bond)
Key Route R8-A: $4,815,000 (GO Bond)
Total: $11,400,000
Project Readiness The readiness of this project is going to depend on the preferred alternative for the key routes along
Bear Creek Road and 27th Street. For example, an alternative that required significant right-of-way
acquisitions along each of the corridors would have far less project readiness than a project that
generally utilizes the existing public right-of-way.
Project readiness will also depend on the coordination with the Bend-La Pine Schools (BLPS) on the key
route project to connect the Coyner and Larkspur trail through their property. The trail connection, as
shown in the Transportation System Plan, is identified for placement on Bear Creek Elementary School
property. Early discussions to understand BLPS’s needs and concerns will be critical to implementing this
trail section in a timely manner.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Bear Creek
Road and 27th Street Improvements project. Those projects include: Wilson Corridor Improvements, Neff
Corridor improvements, Neff and Purcell, and Reed Market Corridor. Below is a discussion on each
conflicting project. Note that the construction for 27th Street is likely to have minimal traffic impacts due
to the availability of a wide existing right-of-way.
Wilson Corridor Improvements
Detours for the construction at 15th Street and Wilson Avenue will utilize Bear Creek Road, Pettigrew
Road, and Reed Market Road. The construction along Bear Creek Road and at the intersection of
Pettigrew Road and Bear Creek Road are in conflict with the 15th Street and Wilson Avenue detours.
Neff Corridor Improvements
Detours for the construction along Neff Road will utilize Greenwood Avenue as a detour as will detours
for the construction along Bear Creek Road and at the intersection of Bear Creek Road and Pettigrew
Road. This detour overlap will likely create an unsatisfactory condition along Greenwood Avenue,
especially for emergency vehicle access to the hospital.
Neff and Purcell
Detours for the construction at the Neff and Purcell intersection will utilize Greenwood Avenue as a
detour as will detours for the construction along Bear Creek Road and at the intersection of Bear Creek
Road and Pettigrew Road. This detour overlap will likely create an unsatisfactory condition along
Greenwood Avenue, especially for emergency vehicle access to the hospital.
Reed Market Corridor
Detours for the construction along Bear Creek Road and at the intersection of Bear Creek Road and
Pettigrew Road will utilize 15th Street, Reed Market Road, and 27th Street as a detour. The construction
at 15th and Reed Market is in conflict with this construction.
Neff Corridor Improvements Scope A combination of three key route projects defined as:
Key Route R3-A Norton Avenue: NE 6th Street to NE 12th Street; Neighborhood greenway:
Create a low-stress bikeway on NE Norton Avenue
Key Route R3-B Hillside Trail: Connects NE 12th Street to Neff Road; Hillside path: Close sidewalk
gap and create a switchback shared use path; includes school zone enhancements.
Key Route R3-C Neff Road: NE 12th Street to Big Sky; Park Shared use path adjacent to roadway:
Close sidewalk gaps and create a low-stress bikeway.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 7/23 – 9/23
Procurement for design: 10/23 – 12/23
Design activities: 1/24 – 12/24
Right-of-way activities: 3/24 – 12/24
Procurement for construction: 1/25 – 3/25
Construction activities: 4/25 – 3/26
Project manager estimated commitment: 2.5 years @ 40% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 11 (ranked 6th)
• The project scored relatively high in terms of prioritization
• Early coordination with Bend-La Pine Schools is critical for the successful implementation of the
trail connection
• Conflicts with the closures at Butler Market Road and Wells Acres Road prevent the construction
of these improvements in 2023.
• Construction occurring between early 2025 and early 2026 should avoid conflicts with the Bear
Creek Road and 27th Street Improvements
Additional Information
Budget Key Route R3-A: $196,000 (GO Bond)
Key Route R3-B: $241,000 (GO Bond)
Key Route R3-C: $3,634,000 (GO Bond)
Total: $4,071,000
Project Readiness The readiness of this project is going to depend on the preferred alternative for the improvements along
Neff Road. For example, an alternative that requires significant right-of-way acquisitions along the
corridor would have far less project readiness than a project that generally utilizes the existing public
right-of-way.
Project readiness will also depend on the coordination with the Bend-La Pine Schools (BLPS) on the key
route project to connect 12th Street to Neff Road through their property. The trail connection, as shown
in the Transportation System Plan, is identified for placement on Juniper Elementary School property.
Early discussions to understand BLPS’s needs and concerns will be critical to implementing this trail
section in a timely manner.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Neff
Corridor Improvements project. Those projects include: Neff and Purcell, Bear Creek Road and 27th
Street Improvements, 8th Street Intersections, and Butler Market Road and Boyd Acres Road
Improvements.
Neff and Purcell
The Neff and Purcell Intersection Improvements project is planned for construction during the 2022
calendar year. Due to the readiness of the Neff and Purcell project, there is little chance for the Neff
Corridor project to cause issues with detour overlaps during construction. Construction fatigue,
however, is not just limited to the presence of detour overlaps, in this case it can be associated with the
construction activities occurring under two separate projects during adjacent years. The scheduling of
this project has been preliminarily shown in calendar years 2025 and 2026 to allow for a break in
construction to occur between the two projects.
Bear Creek Road and 27th Street Improvements
Detours for the construction along Neff Road will utilize Greenwood Avenue as a detour as will detours
for the construction along Bear Creek Road and at the intersection of Bear Creek Road and Pettigrew
Road. This detour overlap will likely create an unsatisfactory condition along Greenwood Avenue,
especially for emergency vehicle access to the hospital.
8th Street Intersection Improvements
Detours for the construction along Neff Road will utilize 8th Street, Greenwood Avenue, Butler Market
Road, and 27th Street as detours. The construction at the intersections of 8th Street and Revere Avenue
and 8th Street and Penn Avenue are in conflict with the Neff Road detours.
Butler Market Road and Boyd Acres Road Improvements
Detours for the construction along Neff Road will utilize 8th Street, Greenwood Avenue, Butler Market
Road, and 27th Street as detours. The construction along Butler Market Road and at the intersection of
Butler Market Road and Wells Acres Road are in conflict with the Neff Road detours.
Olney Pedestrian and Bike Improvements Scope A combination of three pedestrian and bike focused projects defined as:
Olney protected bicycle lanes and parkway undercrossing: Provide protected bicycle lanes on
Olney Avenue at Parkway undercrossing.
Key intersection at 2nd and Olney: Addresses bike and pedestrian safety and improvement at key
intersections identified in Transportation Safety Action Plan
Key Route R3-E Olney Avenue: Wall Street to railroad; Shared use path adjacent to roadway:
close sidewalk gap over railroad and remove existing barrier to east-west bicycle connectivity
and create right-turn hook crash countermeasure.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 2/22 – 4/22
Procurement for design/permitting: 5/22 – 7/22
Design activities: 8/22 – 8/23
Right-of-way activities: 12/22 – 11/23*
Permitting activities: 12/22 – 11/23**
Procurement for construction: 12/23 – 2/24
Construction activities: 3/24 – 10/24
Project manager estimated commitment: 1 year @ 20% allocation then 1.5 years at 40%
allocation.
*Possibly unnecessary
**Large risk item depending on level of modification to the bridge structure
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 10.5 (ranked 8th)
• While the project scored somewhat highly in terms of prioritization, there are significant
uncertainties with the Central Interceptor sewer project that will impact Olney Avenue
throughout the limits of this project.
• Modifications to the parkway bridge structure may be required – could lead to longer permitting
durations.
• Project has been accelerated per the request of TBOC during the October 5, 2021 meeting.
Note that there are several risks with permitting and conflicting projects that may delay the
project’s construction.
Additional Information
Budget
Olney Protected Bicycle Lanes: $1,820,000 (GO Bond)
Key Intersection (2nd/Olney allocation): $210,000 (GO Bond)
Key Route R3-E: $421,000 (GO Bond)
Total: $2,451,000*
*Tax Incremental Financing is potentially available to this project – see Draft Capital Improvement Plan
Overview for more information.
Project Readiness
Central Interceptor
The Central Interceptor is a large sewer project that will impact Olney Avenue in the same location as
these GO Bond projects. The project is more specifically defined in the city’s Collection System Master
Plan (CSMP) as:
The Central Interceptor requires upsizing to accommodate buildout densities in a combination
of the West UGB expansion area, Shevlin UGB expansion area, Central Business District, KorPine
Site, OSU Cascades, and Century Drive area. Similar to the Drake Trunk, the interceptor
improvement is recommended between the mid- and long-term timeframes (10-years) to
accommodate phased development in 5 to 15-years.
The CSMP was most recently updated in 2014 and is planned for another update in 2023. There is a
chance that as part of the updates to the CSMP, the Central Interceptor project is eliminated in favor of
a different method of increasing sewer capacity in the above-mentioned areas.
The timing and prospects of the Central Interceptor project are important to understand when
contemplating the sequencing of this project. An effort to deliver the Olney Pedestrian and Bike
Improvements project completely separate from the Central Interceptor project risks increased overall
costs to the city and increasing construction fatigue.
Permitting
The crossing of the parkway and the railroad through this section of road will require some permitting .
Since the railroad crossing already exists, the permitting for the crossing modification should be able to
be completed relatively quickly. Depending on the selected cross-section of the improvements under
the parkway, there is a potential for impacts to the parkway bridge. The bridge modifications are not
anticipated to preclude any reasonable alternative but would require some additional time to ensure
that all stakeholders understand and approve of the work.
Early design
A strategy to complete the design early-on in the implementation of the GO Bond could be pursued with
this project. This strategy would allow for rapid project implementation either when more information is
known about the timing and prospects of the Central Interceptor project or if the Central Interceptor
project is eliminated with the update to the CSMP. Some limitations by utilizing this strategy would
include: less time for city project managers to dedicate to other projects with a higher level of readiness,
potential condition or policy changes that would supersede the project’s initial design, and private
development that would require design modifications leading to increased cost.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Olney
Pedestrian and Bike Improvements. Midtown Crossings, and Portland Avenue Corridor.
Midtown Crossings
Depending on the selected alternative for the midtown crossings project, detour overlaps could occur
with the Olney Pedestrian and Bike Improvements project. A detour for the construction of the
undercrossing of the Parkway for Greenwood Avenue would utilize Wall Street, O3rd Street, Greenwood
Avenue, and Wall Street among other streets. Should the selected alternative be a modification or
widening of the Greenwood undercrossing, this construction would conflict with those detours.
Portland Avenue Corridor
Detours for the construction on Portland Avenue will likely utilize College Way, Newport Avenue, and
Wall Street. The closures on Olney Avenue will also utilize Wall Street in this section as a detour. These
overlapping detours will likely lead to greater construction fatigue through additional congestion along
this stretch of roadway.
The Portland Avenue Corridor project is proposed for a combined implementation with the Awbrey
Butte Distribution Improvements project. The work included in that project that will impact Portland
Avenue is anticipated to occur in calendar year 2025. The same detour overlaps will need to be
considered under the scenario that the Portland Avenue Corridor is separated from the Awbrey Butte
Distribution Improvements and implemented later in the GO Bond schedule.
Aune Street Extension (West) Scope The portion west of the parkway of the project identified to provide a two-lane extension of Aune Road
to connect 3rd Street and Bond Street. Includes a Roundabout at the intersection of Bond Street and
Industrial Way.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 5/21 – 11/21
Design: 2026*
Construction: 2027*
*Needs for this corridor is going to depend on the timing of private development –
consideration for reprioritization of this project is very likely once more information is known.
Project manager estimated commitment: 2 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 10 (ranked 10th)
• The project scored somewhat highly in terms of prioritization
• The project is highly correlated with the private development in this area.
Additional Information
Budget Aune Street Extension (estimated allocation): $7,500,000 (GO Bond)
Project Readiness City staff is working with several landowners in the vicinity of this project to develop a refinement plan
for the western portion of the Aune Street extension and the options for tying Aune Street into Bond
Street. The timing and needs of the Aune Street Extension through the undeveloped properties in this
location is going to depend on the private development schedule.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Aune Street
Extension (West) project. Those projects include: Wilson Corridor Improvements, Aune Street Extension
(East), Colorado Avenue Interchange Improvements, and Colorado Avenue Capacity Improvements
project. Below is a discussion on each conflicting project.
Wilson Corridor Improvements
The construction of the Aune West Extension is likely to cause closures to Bond Street where the Aune
Extension ties in. The improvements to Wilson and 2nd Street as part of the Wilson Avenue Corridor will
likely be in conflict with a potential detour route that will include Wilson Avenue, 2nd Street, and
Colorado Avenue.
Aune Street Extension (East)
The Aune West Extension is likely to cause closures to Bond Street where the Aune Extension ties in. The
improvements to Aune and 2nd Street as part of the Aune Street Extension (East) will likely be in conflict
with a potential detour route that will include Wilson Avenue, 2nd Street, and Colorado Avenue.
Colorado Avenue Interchange Improvements
The Aune Street Extension (West) is likely to cause closures to Bond Street where the Aune Extension
ties in. The improvements to the northbound Colorado Avenue interchange intersection will likely be in
conflict with a potential detour route that will include Wilson Avenue, 2nd Street, and Colorado Avenue.
Colorado Capacity Improvements
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the intersection of Bond
Street and Aune Street will likely be in conflict with those detours.
Reed Market Corridor
The construction of the Aune Street Extension (West) is likely to cause closures to Bond Street where
the Aune Extension ties in. The improvements to Reed Market Road and Bond Street as part of the Reed
Market Corridor will likely be in conflict with a potential detour route that will include Bond Street, Reed
Market Road, Century Drive, and Colorado Avenue.
Butler Market Road and Boyd Acres Road Improvements Scope A combination of two pedestrian and bike focused projects defined as:
Key Route R1-C NE Boyd Acres Road: Butler Market Road to Empire Avenue; Shared use path
adjacent to roadway: Close sidewalk gap and create low-stress bikeway.
Key Route R5-A Butler Market Road: Brinson Boulevard to NE 6th Street; Shared use path
adjacent to roadway: Close sidewalk gap along both sides of Butler Market Road and create low-
stress bikeway.
To efficiently implement these projects and to reduce construction fatigue, these projects are
recommended to be combined with the roundabout construction at the intersection of Butler Market
Road and Wells Acres Road (a project funded by the Transportation CIP).
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 11/21 – 2/22
Procurement for design/permitting: 3/22 – 5/22
Design activities: 6/22 – 3/23
Right-of-way activities: 9/22 – 6/23
Permitting activities: 6/22 – 3/23
Procurement for construction: 4/23 – 6/23
Construction activities: 7/23 – 11/24
Project manager estimated commitment: 3 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 10 (ranked 10th)
• The project scored somewhat highly in terms of prioritization
• The roundabout at the intersection of Butler Market Road and Wells Acres Road is anticipated
to begin construction in 2023.
• The alignment of the Central Interceptor project is anticipated to utilize Butler Market Road – see project readiness discussion for more information.
• Permitting for the Boyd Acres Road key route improvements rely on permitting through two canal districts. The need for this permitting effort could delay the improvements on Boyd Acres
Road
Additional Information
Budget Key route R1-C: $1,884,000 (GO Bond)
Key Route R5-A: $1,962,000 (GO Bond)
Butler Market Road and Wells Acres Road Roundabout: $3,000,000 (Transportation CIP)
Total: $6,846,000
Project Readiness
Synergy with Transportation CIP Project
The Butler Market Road and Wells Acres Road roundabout, funded through the Transportation Capital
Improvement Plan, is scheduled to be constructed in calendar year 2023. Two key route projects are
proposed to be combined with this project to capitalize upon cost savings gained through efficiencies of
scale and reduced construction fatigue through fewer overall corridor disruptions.
Central Interceptor
The Central Interceptor is a large sewer project that will impact Butler Market Road in the same location
as Key Route R5-A. The project is more specifically defined in the city’s Collection System Master Plan
(CSMP) as:
The Central Interceptor requires upsizing to accommodate buildout densities in a combination
of the West UGB expansion area, Shevlin UGB expansion area, Central Business District, KorPine
Site, OSU Cascades, and Century Drive area. Similar to the Drake Trunk, the interceptor
improvement is recommended between the mid- and long-term timeframes (10-years) to
accommodate phased development in 5 to 15-years.
The CSMP was most recently updated in 2014 and is planned for another update in 2023. There is a
chance that as part of the updates to the CSMP, the Central Interceptor project is eliminated in favor of
a different method of increasing sewer capacity in the above-mentioned areas.
In contrast to the Olney Pedestrian and Bike Improvements project, the work on Butler Market Road as
part of this project is not proposed to be delayed until a firmer schedule for the Central Interceptor can
be confirmed. There are two primary differences that allow for the separate treatments of these
projects: firstly, the two projects differ in that the rights-of-way have very different constraints; and
secondly, the location of the existing sewer infrastructure.
Butler Market Road is a much wider right-of-way, allowing for the sewer work to occur while not
impacting the key route improvements. Olney Avenue’s right-of-way is fairly narrow and constrained.
Further, given that the transportation system plan identifies a protected bike lane along this stretch, the
available area for construction and staging provides additional constraints for the project.
The existing sewer lines under Butler Market Road are generally located in the center of the roadway,
allowing for the sewer work to occur without impacting the pedestrian and bike improvements.
Permitting
The crossing of the canals for the Boyd Acres Road key route project will require some permitting. The
permitting process for different canals works in different ways depending on the permit-issuing agency.
This is a risk item that could delay the key route improvements to Boyd Acres Road.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Butler
Market Road and Boyd Acres Road Improvements project. Those projects include: Neff Corridor, Neff
and Purcell, and 8th Street Intersection Improvements. Below is a discussion on each conflicting project.
Neff Corridor
Detours for the construction along Neff Road will utilize 8th Street, Greenwood Avenue, Butler Market
Road, and 27th Street as detours. The construction along Butler Market Road and at the intersection of
Butler Market Road and Wells Acres Road are in conflict with the Neff Road detours.
Neff and Purcell
Detours for the construction at the intersection of Neff Road and Purcell Boulevard will utilize 8th Street,
Greenwood Avenue, Butler Market Road, and 27th Street as detours. The construction along Butler
Market Road and at the intersection of Butler Market Road and Wells Acres Road are in conflict with the
Neff Road detours.
8th Street Intersection Improvements
Detours for the full closure of Butler Market Road at Wells Acres will utilize 8th Street, Neff Road, and
27th Street. The construction at both the intersection at 8th Street and Revere Avenue and 8th Street and
Penn Avenue are in conflict with these detours.
Newport Corridor Improvements Scope The Newport Avenue Corridor Improvements an in-progress, multi-year, phased project along Newport
Avenue.
To efficiently implement some small key routes projects, two key route projects are proposed to be
combined with this project. These include:
NW 15th St: Lexington Ave to Milwaukie Ave Hillside path: Close sidewalk gap and create a
hillside switchback shared use path within the 15th St neighborhood greenway.
NW 14th St: Ogden Ave to Portland Ave Hillside path: Close sidewalk gap and create a hillside
switchback shared use path within 14th St right-of-way to connect route to Portland Ave.
Proposed Preliminary Project Schedule Design activities: 11/21 – 3/22*
Construction activities: 4/22 – 10/22
Project manager estimated commitment: 1 year at 100% (project manager time paid for through
stormwater fund).
*Due to the design being complete for the corridor, the relatively simple design needed, and the
ability to amend an existing design contract, the planning and procurement for design activities
are eliminated for this project.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 10 (ranked 10th)
• The project scored somewhat highly in terms of prioritization
• A coordinated effort with the Newport Corridor project could be swiftly implemented.
• A separate implementation If these two key routes projects would result in significantly higher
costs and possibly higher construction fatigue
Additional Information
Budget Newport Corridor Improvements: $26,123,700 (Other city CIPs)
Key Route R4-A: $110,000 (GO Bond)
Key Route R4-B: $110,000 (GO Bond)
Total: $26,343,700
Project Readiness These two hillside paths could be quickly amended into the existing contract to design Newport Avenue.
The existing Newport Avenue project is anticipated to be completed in late 2022, therefore an
amendment for design will need to happen quickly to capitalize on this synergy opportunity.
Construction Fatigue Since the Newport Avenue Corridor project is well underway, there aren’t many projects that would
have the ability to be implemented quickly enough to have an impact on construction fatigue.
Considerations should be given to allowing for a gap in construction activities between the end of this
project and the beginning of the Portland Avenue Corridor project.
Neff and Purcell (Purcell Extension) Scope The Neff and Purcell intersection improvements are a fully-designed project under the transportation
capital improvement plan to make safety and capacity improvements to the intersection at Neff Road
and Purcell Boulevard. There is an opportunity to combine this pre-existing project with the project to
extend Purcell Boulevard, specifically defined as:
Purcell Boulevard extension (from Full Moon Drive to Jackson Avenue) Two-lane complete street
extension to help north-south connectivity.
Proposed Preliminary Project Schedule Design activities: 5/19 – 12/21*
Procurement for construction: 1/22 – 3/22
Construction activities: 4/22 – 11/22
Project manager estimated commitment: 1 year @ 50% allocation project manager time paid for
through transportation fund).
*Due to the design being complete for the intersection, the relatively simple design needed, and
the ability to amend an existing design contract, the planning and procurement for design
activities are eliminated for this project.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 9.5 (ranked 13th)
• The project scored somewhat highly in terms of prioritization
• The Neff and Purcell intersection is fully designed and nearly ready for procurement for
construction to begin.
• The combined delivery of the Purcell extension with the Neff and Purcell intersection project
would save costs and minimize construction fatigue associated with the Neff and Purcell
intersection.
Additional Information
Budget Neff and Purcell Intersection: $6,168,000 (Other city CIPs)
Purcell Extension: $2,288,000 (GO Bond)
Total: $8,456,000
Project Readiness The Neff and Purcell Intersection project is fully designed and nearly ready to advertise for construction
bids. The Purcell Extension project requires some coordination with the owner of the land underlying
the extension (St. Charles Medical Center). This coordination is currently underway and the prospects of
combining these two projects is probable. The extension of Purcell Boulevard is a relatively simple
project as it mainly impacts an undeveloped parcel. The design process should be able to be completed
prior to construction advertisement in early 2022.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Neff and
Purcell project. Those projects include: 8th Street Intersection Improvements, Neff Road Corridor, Butler
Market Road and Boyd Acres Road Improvements, and Bear Creek Road and 27th Street Improvements.
Below is a discussion on each conflicting project.
8th Street Intersection Improvements
Detours for the full closure of Neff Road at Purcell Boulevard will utilize 8th Street, Butler Market Road,
Greenwood Avenue and 27th Street. The construction at both the intersection at 8th Street and Revere
Avenue and 8th Street and Penn Avenue are in conflict with these detours.
Neff Road Corridor
The Neff and Purcell Intersection Improvements project is planned for construction during the 2022
calendar year. Due to the readiness of the Neff and Purcell project, there is little chance for the Neff
Corridor project to cause issues with detour overlaps during construction. Construction fatigue,
however, is not just limited to the presence of detour overlaps, in this case it can be associated with the
construction activities occurring under two separate projects during adjacent years. The scheduling of
this project has been preliminarily shown in Calendar years 2025 and 2026 to allow for a break in
construction to occur between the two projects.
Butler Market Road and Boyd Acres Road Improvements
Detours for the construction at the intersection of Neff Road and Purcell Boulevard will utilize 8th Street,
Greenwood Avenue, Butler Market Road, and 27th Street as detours. The construction along Butler
Market Road and at the intersection of Butler Market Road and Wells Acres Road are in conflict with the
Neff Road detours.
Bear Creek Road and 27th Street Improvements
Detours for the construction at the Neff and Purcell intersection will utilize Greenwood Avenue as a
detour as will detours for the construction along Bear Creek Road and at the intersection of Bear Creek
Road and Pettigrew Road. This detour overlap will likely create an unsatisfactory condition along
Greenwood Avenue, especially for emergency vehicle access to the hospital.
4th Street Intersection Improvements Scope Intersection improvements at 4th Street and Revere Avenue and 4th Street and Olney Avenue – both
signals and roundabout improvements will be considered.
Proposed Preliminary Project Schedule Planning/Design: 2028
Construction: 2029
Project manager estimated commitment: 2 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 8.5 (ranked 14th)
• The project scored near the middle of the list of projects
• There are significant uncertainties with the Central Interceptor sewer project that will impact
the 4th Street and Revere Avenue intersection
Additional Information
Budget 4th Street and Revere Avenue Intersection: $3,500,000 (GO Bond)
4th Street and Olney Avenue Intersection: $3,500,000 (GO Bond)
Total: $7,000,000
Project Readiness The Central Interceptor is a large sewer project that will impact Olney Avenue in the same location as
this GO Bond project. The project is more specifically defined in the city’s Collection System Master Plan
(CSMP) as:
The Central Interceptor requires upsizing to accommodate buildout densities in a combination
of the West UGB expansion area, Shevlin UGB expansion area, Central Business District, KorPine
Site, OSU Cascades, and Century Drive area. Similar to the Drake Trunk, the interceptor
improvement is recommended between the mid- and long-term timeframes (10-years) to
accommodate phased development in 5 to 15-years.
The CSMP was most recently updated in 2014 and is planned for another update in 2023. There is a
chance that as part of the updates to the CSMP, the Central Interceptor project is eliminated in favor of
a different method of increasing sewer capacity in the above-mentioned areas.
The timing and prospects of the Central Interceptor project is important to understand when
contemplating the sequencing of this project. An effort to deliver the 4th Street Intersection
Improvements project completely separate from the Central Interceptor project risks increased overall
costs to the city and increasing construction fatigue.
Costs to the city could increase by implementing these projects separately – the location of the existing
sewer infrastructure along this corridor is coincidental with the existing pedestrian and bike facilities.
The Central Interceptor project would likely need to demolish and reconstruct some of the
improvements implemented with the GO Bond project.
Construction Fatigue The GO Bond has relatively few projects that have overlapping detours or overlapping closures with the
4th Street Intersection Improvements project. With that being said, care should be taken to avoid
overlapping construction with the 8th Street Intersection Improvements as construction at both the
intersection at 8th Street and Revere Avenue and 8th Street and Penn Avenue are in conflict with the
anticipated detours for the 4th Street Intersection Improvements.
While detour overlaps with the 4th Street Intersection Improvements project aren’t anticipated with the
construction of any of the Midtown Crossings projects, there is the potential for construction fatigue to
occur when detours from one project lead into detours for other projects. These effects can be limited
to an extent through careful planning and detour design, but should be considered while conducting the
project sequencing.
Improved Access to Transit Scope Leverages Cascade East Transit funding for capital projects like mobility hubs, shelters, and bus pull outs.
Proposed Preliminary Project Schedule First mobility hub: Q3 2025
Synergy opportunities: Ongoing
Other improvements: Undefined
Project manager estimated commitment: managed by CET, coordinated with other projects as
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 8.5 (ranked 14th)
• The project scored near the middle of the list of projects
• To allow for Cascades East Transit (CET) to construct the first mobility hub in by mid-2025, a
funding allocation from the GO Bond for capital improvements related to the mobility is going to
be required by mid-2024
• A small amount ($100,000) of funding has been allocated annually to allow for the construction
of synergy projects as they arise.
Additional Information
Budget Improved Access to Transit: $8,000,000 (GO Bond)
Project Readiness This project consists of improvements to bus route infrastructure (bus stops, shelters, bus pull outs,
etc.), especially as other GO Bond projects are implemented and funding that would assist CET in the
construction of the capital improvements related to the mobility hubs. To allow for some flexibility in
the construction of the synergy opportunities, $100,000 per year has been proposed to build these
improvements. CET is indicating that their first mobility will be constructed by mid-2025, this timing
would require a commitment of roughly $1,000,000 from the GO Bond in mid-2024.
Construction Fatigue Due to the uncertainties of the improvements associated with this project, construction fatigue cannot
be assessed.
8th Street Intersection Improvements Scope Intersection improvements at 8th Street and Revere Avenue and 8th Street and Olney Avenue – both
signals and roundabout improvements will be considered.
Proposed Preliminary Project Schedule Planning/Design: 2026
Construction: 2027
Project manager estimated commitment: 2 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 8.5 (ranked 14th)
• The project scored near the middle of the list of projects
• Some right-of-way has already been dedicated at 8th Street and Penn Avenue
• No major structures appear to be impacted with the 8th Street and Revere Avenue
improvements
Additional Information
Budget 8th Street and Revere Avenue Intersection: $3,500,000 (GO Bond)
8th Street and Penn Avenue Intersection: $3,500,000 (GO Bond)
Total: $7,000,000
Project Readiness There are few major hurdles to overcome to begin design and construction on this project. It appears
that the 8th Street and Penn Avenue intersection has had some right-of-way dedicated to allow for a
new roundabout. The 8th Street and Revere Avenue intersection has less available right-of-way, however
it does not appear that any major structures would be impacted by the improvements.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the 8th Street
Intersection Improvements project. Those projects include: Neff Corridor, Neff and Purcell, Butler
Market Road and Boyd Acres Road Improvements, and 4th Street Intersection Improvements. Below is a
discussion on each conflicting project.
Neff Corridor
Detours for the construction along Neff Road will utilize 8th Street, Greenwood Avenue, Butler Market
Road, and 27th Street as detours. The construction at the intersections of 8th Street and Revere Avenue
and 8th Street and Penn Avenue are in conflict with the Neff Road detours.
Neff and Purcell
Detours for the full closure of Neff Road at Purcell Boulevard will utilize 8th Street, Butler Market Road,
Greenwood Avenue and 27th Street. The construction at both the intersection at 8th Street and Revere
Avenue and 8th Street and Penn Avenue are in conflict with these detours.
Butler Market Road and Boyd Acres Road Improvements
Detours for the full closure of Butler Market Road at Wells Acres will utilize 8th Street, Neff Road, and
27th Street. The construction at both the intersection at 8th Street and Revere Avenue and 8th Street and
Penn Avenue are in conflict with these detours.
4th Street Intersection Improvements
Detours for the closures along 4th Street utilize 8th Street, Butler Market Road, 3rd Street and Greenwood
Avenue. The construction at both the intersection at 8th Street and Revere Avenue and 8th Street and
Penn Avenue are in conflict with these detours.
North Corridor Project Coordination Scope This project will realign one of the most congested portions of US 97 in the City of Bend and improve a
section of US 20. The US 97 Bend North Corridor project includes a realignment of US 97, improved
intersections, new ramps connections at critical locations to improve local and highway traffic, and
pedestrian and bicycle facilities.
US 97 is the main north-south highway through the central portion of Oregon connecting Oregon to
California and Washington. US 20 is a primary east-west highway in Oregon. In the Bend area, both
highways are primary routes that help local residents commute through town and is a connection to
area shopping, dining, businesses, schools and recreation. Central Oregon's population growth over the
last decade has increased traffic congestion and, in turn, reduced safety for motor vehicles, pedestrian
and bicyclists.
These improvements will do the following:
• Aid with congestion
• Support economic vitality
• Reduce traffic volume and speeds at high conflict locations
• Increase freight mobility
• Improve travel time reliability
The GO Bond-funded portion of this project is the US 20 southbound widening to two lanes from Cooley
to Empire. The concepts for the North Corridor project have evolved since the identification of the US20
widening project in the Transportation System Plan and the GO Bond and may no longer be relevant.
This funding may be reallocated to work that serves the same function as the US 20 widening project.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 2014 – 2021*
Procurement for design: 2021*
Design/Build activities: 2022 – 2024*
Project manager estimated commitment: 1 year @ 15% allocation (project manager time paid
for through transportation fund).
*Note that this is an ODOT-led design-build project
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 7.5 (ranked 17th)
• The project scored near the middle of the list of projects
• This is an ODOT-led project
Additional Information
Budget US-97/US-20 Bend North Corridor: $160,000,000* (ODOT)
US 20 Southbound Widening: $4,800,000 (GO Bond)
Total: $164,800,000
*Estimate
Project Readiness ODOT is currently working through the procurement of design-build services for this project. A design-
build team is anticipated for selection in 2022 with construction starting toward the end of the 2022
calendar year.
Construction Fatigue The GO Bond has relatively few projects identified for funding in the vicinity of the North Corridor
project. With that being said, care should be taken to avoid overlapping construction with the Empire
Avenue Interchange Improvements project, as the detours for the two projects could lead to confusion
among the traveling public.
Local Residential Street Safety Scope Provides funding for capital projects (infill sidewalk construction, lighting, safe routes to schools) to
improve safety projects in neighborhoods near schools and parks. Builds on city’s current Neighborhood
Street Safety Program (NSSP) success.
In Fall 2019, the City received more than 360 applications for projects all across Bend as part of the
NSSP. These projects were then reviewed and prioritized by the Neighborhood Associations (NAs) in
which they were located. Each NA submitted its top one or two projects for advancement to the
Neighborhood Leadership Alliance (NLA), which resulted in a list of 25 priority projects. Projects #1-6
and #8 have been completed (#7 is on hold for now), projects 9-11 are planned for implementation
during the 2022 construction year.
The program is planned to be implemented on an annual basis, delivering the projects based on the
priority developed in the NSSP. That initial project list is estimated to cost $2.5M of the $8M allocated to
this program under the GO Bond. A similar public process to identify and prioritize projects is anticipated
for the estimated $5.5M in unallocated funding.
Proposed Preliminary Project Schedule Design: Annually
Construction: Annually
Project manager estimated commitment: ongoing 40% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 7.5 (ranked 17th)
• The project scored near the middle of the list of projects
• This aim of this project is to build upon the NSSP – an annual project to make small neighborhood-level transportation improvements and therefore has had funding allocated to
make improvements on an annual basis
Additional Information
Budget Local Residential Street Safety Program: $8,000,000 (GO Bond)
Project Readiness The projects included in this program are fairly small, require right-of-way acquisition infrequently, and
rarely require in-depth permitting. An increase/decrease in each year’s project scope can happen fairly
swiftly.
Construction Fatigue In general, the projects implemented under this program are small in nature and the construction
impacts are minimal. Efforts will be made during construction to work with other current projects to
minimize construction fatigue.
Powers, Parrell, Chase, Brosterhous Connection Scope
Intersection improvements at Brosterhous Road and Chase Road, and at Powers Road, Parrell Road, and
Chase Road. These two projects would link Brosterhous Road to Parrell Road, provideing a new east-
west conection.
Proposed Preliminary Project Schedule Planning/Design: 2027
Construction: 2028
Project manager estimated commitment: 2 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 7.5 (ranked 17th)
• The project scored near the middle of the list of projects
Additional Information
Budget
Brosterhous Road and Chase Road Intersection: $5,000,000 (Transportation CIP)
Powers Road, Chase Road, and Parrell Road Intersection: $5,000,000 (GO Bond)
Total: $10,000,000
Project Readiness A State-owned parcel exists at the SE quadrant of the Powers Road, Parrell Road, and Chase Road
intersection. Generally, the City may use eminent domain to minimize project schedule uncertainty.
Eminent domain, however, cannot be used on parcels owned by the state government. Both the signal
and roundabout options are very likely to have an impact on this parcel, and therefore no guarantees
can be made for a construction schedule.
The connection from Brosterhous to Parrell that these two projects create would be a good additional
connection during the closures associated with the construction of the Reed Market Road railroad
overcrossing.
Construction Fatigue The construction of the improvements to the Brosterhous Road and Chase Road intersection cause
closures to Brosterhous Road. The construction on Reed Market Road to construct the railroad
overcrossing, and the construction at the intersections of 15th Street and Reed Market Road and 3rd
Street and Reed Market Road as part of the Reed Market Corridor will likely be in conflict with a
potential detour route that will include American Lane, Brosterhous Road and 3rd Street.
Colorado Avenue Interchange Improvements Scope Includes signal or roundabout at the Colorado / US 97 northbound ramp to leverage ODOT project and
improve traffic flow and safety.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 2026
Procurement for design: 2027
Project manager estimated commitment: 2 years @ 15% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 7 (ranked 20th)
• This project scored relatively poorly in terms of prioritization
• This is an ODOT-led project
Additional Information
Budget Colorado Avenue Interchange Improvements: $430,000 (GO Bond)
Colorado Avenue Interchange Improvements: $3,870,000 (ODOT)*
Total: $4,300,000
*Funding has not been allocated in the State Transportation Improvements Program
Project Readiness The Colorado Avenue Road Interchange Improvements project is a project funded both by the City and
by ODOT. As of the development of this document, no funding from the state has been identified in
their Statewide Transportation Improvements Program. As such, this project should be deferred until
ODOT funding is available.
An option for the extension of Aune Street east of the Parkway is to tie into the northbound ramp
terminal at Colorado Avenue. If this be the preferred alignment, then a reprioritization of this project
and the Aune Street Extension (East) project should be considered.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Colorado
Avenue Interchange Improvements project. Those projects include: Wilson Corridor Improvements,
Aune Street Extension (East), Aune Street Extension (West), and Reed Market Corridor. Below is a
discussion on each conflicting project.
Wilson Corridor Improvements
The construction of the Colorado Avenue Interchange Improvements likely to cause partial and full
closures to the northbound interchange intersection. The improvements to Wilson Avenue and 2nd
Street as part of the Wilson Avenue Corridor will likely be in conflict with a potential detour route that
will include Bond Street, Colorado Avenue, and 2nd Street.
Aune Street Extension (East)
As stated above, there is an option for the eastern alignment of Aune to tie into the Colorado
interchange. Should the alignment not tie into the interchange, the project should avoid construction at
the same time as the interchange improvements so as to avoid overlapping detours and potential access
issues.
Aune Street Extension (West)
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the intersection of Bond
Street and Aune Street will likely be in conflict with those detours.
Reed Market Corridor
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the Reed Market Road and
Bond Street intersection will be in conflict with those detours.
Empire Avenue Interchange Improvements Scope Empire Avenue widening to five lanes near US 97 interchange, widening at northbound off ramp, and
install traffic signal at southbound ramp.
Proposed Preliminary Project Schedule Design: 2027
Construction: 2028
Project manager estimated commitment: 2 years @ 15% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 7 (ranked 20th)
• This project scored relatively poorly in terms of prioritization
• This is an ODOT-led project
Additional Information
Budget Empire Avenue Interchange Improvements: $1,000,000 (GO Bond)
Empire Avenue Interchange Improvements: $9,000,000 (ODOT)*
Total: $10,000,000
*Funding has not been allocated in the State Transportation Improvements Program
Project Readiness The Empire Avenue Road Interchange Improvements project is a project funded both by the City and by
ODOT. As of the development of this document, no funding from the state has been identified in their
Statewide Transportation Improvements Program. As such, this project should be deferred until ODOT
funding is available.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Empire
Avenue Interchange Improvements project. Those projects include: The North Corridor Project, and the
Empire-OB Riley Intersection. Below is a discussion on each conflicting project.
North Corridor
Care should be taken to avoid overlapping construction with the Empire Avenue Interchange
Improvements project, as the detours for the two projects could lead to confusion among the traveling
public.
Empire – OB Riley Intersection
The construction of the 3rd Street and Empire Avenue intersection is likely to cause partial and full
closures to the east and west approached to the intersection. The improvements to OB Riley Road and
Empire Avenue will likely be in conflict with a potential detour route that will include OB Riley Road and
US 20.
Powers Road Interchange Improvements Scope The Transportation System Plan identifies this project initially as a project at Powers Road/US 97 for
preliminary engineering and ROW acquisition for interchange that may include interchange or
overcrossing, pending outcome of the Parkway Study. Since then, the Parkway Study has made
recommendations for the sequencing and scoping of this project. Per the Parkway Study:
This project is recommended after completion of the Murphy Road Tight Diamond Interchange
project (S6), which can partially address existing needs. The Badger Road RIRO project (C2e) is
required prior to the S6 project. Potential phasing would be to construct an overcrossing before
the interchange, but only after the Murphy Road Tight Diamond (S6) project is completed. Next
steps are to refine preliminary design and begin ROW acquisition in the short term, followed by
construction in the mid-term.
The Transportation System Plan further identified an interchange at Powers Road and US 97 to cost
approximately $20M, with the city contributing $2M.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 2028-2029
Procurement for design: 2030-2031
Project manager estimated commitment: 4 years @ 15% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 7 (ranked 20th)
• This project scored relatively poorly in terms of prioritization
• This is an ODOT-led project
Additional Information
Budget Powers/US97 Interchange: $2,650,000 (GO Bond)
Powers/US97 Interchange: $23,850,000 (ODOT)*
Total: $26,500,000
*Funding has not been allocated in the State Transportation Improvements Program
Project Readiness As noted in the US 97 Parkway Plan Phase 2, the Powers Road interchange could be a phased
implementation that would include an interim overcrossing at the interchange with the ultimate
solution being a full interchange. This phasing would require new Parkway connections at Murphy Road
to account for the reduced interim connections at Powers Road.
The Powers Road Interchange Improvements project is a project funded both by the City and by ODOT.
As of the development of this document, no funding from the state has been identified in their
Statewide Transportation Improvements Program. As such, this project should be deferred until ODOT
funding is available.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Powers
Road Interchange Improvements project. Those projects include: Murphy Parkway Ramps, the Powers,
Parrell, Chase, Brosterhous Connection, and the Reed Market Interchange. Below is a discussion on each
conflicting project.
Murphy Parkway Ramps
As noted above, the Murphy Parkway Ramps project should be completed prior to the Powers Road
Interchange Improvements project to allow for an interim Powers Road overcrossing to be built. The
interim solution would offload traffic that is currently using Powers Road onto the Murphy Road
interchange.
Reed Market Corridor
The Powers Road Interchange Improvements project should be completed after the Reed Market Road
interchange work so as to avoid concurrent closures at the two adjacent Parkway
intersections/interchanges.
Archie Briggs Improvements Scope The trail crossing portion of this project aims to design to improve pedestrian crossing at the Deschutes
River Trail Crossing of Archie Briggs Road.
To efficiently implement this project, an approach to combine the construction efforts with the project
to replace the Archie Briggs Road Bridge over the Deschutes River is proposed.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 7/22 – 8/22
Procurement for design: 9/22*
Design activities: 10/22 – 8/23
Right-of-way activities: 1/23 – 10/23**
Procurement for construction: 11/23 – 3/24***
Construction activities: 4/24 – 11/24
Project manager estimated commitment: 3 years @ 50% allocation.
*Design services procurement of less than $100,000 can be initiated more quickly than
otherwise would be possible.
**Possibly unnecessary
***Coordination with ODOT on bidding project for construction
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 6.5 (ranked 23rd)
• This project scored relatively poorly in terms of prioritization
Additional Information
Budget Deschutes River Trail Crossing of Archie Briggs Road: $500,000 (GO Bond)
Archie Briggs Road Bridge Replacement (design): $809,340 (ODOT and City CIP)
Archie Briggs Road Bridge Replacement (construction): $5,190,660 (Federal)*
Total: $6,500,000
*Federal funding is anticipated for the bridge replacement, but has not been allocated as of the writing
of this document
Project Readiness Alternatives that will be considered include over and undercrossing of Archie Briggs Road. The $500,000
in funding may be adequate to cover an over or undercrossing of the road, however there is a much
greater chance of success in implementing this project within budget if construction can be coordinated
with the bridge replacement project.
Construction Fatigue The GO Bond has relatively few projects identified for funding in the vicinity of the Deschutes River Trail
crossing of Archie Briggs Road. Coordination with the bridge replacement project will be critical to
maintain access and to avoid lengthy detours.
Portland Avenue Corridor Improvements Scope Multi-modal transportation facility and safety improvements to help with pedestrian, bicycle, and
vehicular connectivity, including two intersection improvements.
This project is proposed to be combined with the Awbrey Butte Distribution Improvements project. This
is a phased, multi-year water infrastructure project that will have impacts to the same vicinity as the
Portland Avenue Corridor Improvements project.
Proposed Preliminary Project Schedule Planning efforts prior to design activities: 11/21 – 1/22
Procurement for design-build: 2/22 – 5/22*
Design activities: 7/24 – 2/25*
Right-of-way activities: 9/23 – 6/24
Construction activities: 3/25 – 9/25
Project manager estimated commitment to GO Bond: 1.5 years @ 10% allocation (project
manager committed to entire project at 70%).
*Note that the Awbrey Butte Distribution Improvements project will be delivered via a
progressive design-build procurement method. This will allow for the project to be delivered in
phases and in a more flexible manner.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 6.5 (ranked 23rd)
• This project scored relatively poorly in terms of prioritization
• Synergizing with the Awbrey Butte Distribution Improvements project would allow for more
work to be completed under the same budget through efficiencies of scale.
Additional Information
Budget Portland Avenue Corridor Improvements: $3,500,000 (GO Bond)
Awbrey Butte Distribution Improvements: $28,618,000 (Water CIP)
Total: $32,118,000
Project Readiness The Awbrey Butte Distribution Improvements project has identified that a progressive design-build
delivery method as the method of procurement. This delivery method allows for a more rapid delivery
where construction and design may overlap.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Portland
Avenue Corridor Improvements project. Those projects include: Midtown Crossings, Olney Pedestrian
and Bike Improvements, and Newport Corridor Improvements. Below is a discussion on each conflicting
project.
Midtown Crossings
While detour overlaps with the Midtown Crossings project aren’t anticipated with the construction of
any of the Portland Avenue Corridor Improvements project, there is the potential for construction
fatigue to occur when detours from one project lead into detours for other projects. These effects can
be limited to an extent through careful planning and detour design, but should be considered while
conducting the project sequencing.
Olney Pedestrian and Bike Improvements
Detours for the construction on Portland Avenue will likely utilize College Way, Newport Avenue, and
Wall Street. The closures on Olney Avenue will also utilize Wall Street in this section as a detour. These
overlapping detours will likely lead greater construction fatigue through additional congestion along this
stretch of roadway.
Newport Corridor Improvements
Since the Newport Avenue Corridor project is well underway, there aren’t many projects that would
have the ability to be implemented quickly enough to have an impact on construction fatigue.
Considerations should be given to allowing for a gap in construction activities between the end of this
project and the beginning of the Portland Avenue Corridor project.
Colorado Avenue Capacity Improvements Scope Includes incremental approach for Colorado Avenue widening, including right-of-way acquisition and
monitoring for if/when widening is appropriate, including intersection capacity and safety
improvements at Colorado Avenue/Simpson Avenue roundabout and Colorado Avenue/Industrial Way,
and complete streets upgrade.
Proposed Preliminary Project Schedule Study: 2026
Design: 2030
Construction: 2031
Project manager estimated commitment for study: 1 years @ 15% allocation
Project manager estimated commitment for design/construction: 2 years @ 50% allocation
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 6 (ranked 25th)
• This project scored relatively poorly in terms of prioritization
• Study is targeted for a 2026 timeframe to understand if the 2031 construction year is
appropriate
Additional Information
Budget Colorado Avenue Capacity Improvements: $7,000,000 (GO Bond)
Project Readiness The project includes a study to analyze if/when widening of the bridge is appropriate and propose
improvements to increase capacity and safety at either end of the bridge. The study will take some time
to complete and the bridge widening itself is not funded here – just the study and the intersection
improvements.
Construction Fatigue Several projects identified for funding within the GO Bond have conflicting detours with the Colorado
Avenue Capacity Improvements project. Those projects include: Reed Market Corridor, and Aune Street
Extension (West). Below is a discussion on each conflicting project.
Reed Market Corridor
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the Reed Market Road and
Bond Street intersection will be in conflict with those detours.
Aune Street Extension (West)
Construction activities for the Colorado Capacity Improvements project will cause full closures of
Colorado Avenue over the course of the project’s implementation. These closures will likely utilize Bond
Street, Reed Market Road and Century Drive as detours. The construction at the intersection of Bond
Street and Aune Street will likely be in conflict with those detours.
Butler Market Road Interchange Improvements Scope A project identified in the transportation System Plan that leverages ODOT project to construct frontage
road from US 97 southbound off-ramp to Division Street.
Proposed Preliminary Project Schedule Design: 2029
Construction: 2030
Project manager estimated commitment: 2 years @ 15% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 5 (ranked 26th)
• This project scored relatively poorly in terms of prioritization
• State funding for project is not yet identified
• Permitting with the canals could be onerous
• ODOT-led project
Additional Information
Budget
Butler Market interchange at US 20/US 97: $3,090,000 (GO Bond)
Butler Market interchange at US 20/US 97: $3,090,000 (ODOT)*
Total: $6,180,000
*Funding has not been allocated in the State Transportation Improvements Program
Project Readiness The Butler Market Road Interchange Improvements project is a project funded both by the City and by
ODOT. As of the development of this document, no funding from the state has been identified in their
Statewide Transportation Improvements Program. As such, this project should be deferred until ODOT
funding is available.
The identified location for the frontage road associated with this project would either require the
demolition of the existing hotel or construction to occur on land currently occupied by several
underground canals. A purchase of the hotel would likely exhaust all funding for this project (hotel
valuation: $8,529,130 per Deschutes County Property Information as of the writing of this document).
Coordination with the canals is anticipated to be very complicated – likely taking several years to work
out all necessary agreement.
Construction Fatigue Due to the uncertainties of the improvements associated with this project, construction fatigue cannot
be assessed.
Empire-OB Riley Intersection Scope A project to construct either a signal or a roundabout at the intersection of Empire Avenue and O.B.
Riley Road.
Proposed Preliminary Project Schedule Design: 2026
Construction: 2027
Project manager estimated commitment: 2 years @ 50% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 5 (ranked 26th)
• This project scored relatively poorly in terms of prioritization
• Right-of-way implications are cause for this project to rank relatively poorly in terms of
readiness
Additional Information
Budget Empire Avenue and O.B. Riley Road Intersection: $3,500,000 (GO Bond)
Project Readiness A State-owned parcel exists at the SE quadrant of the Empire Avenue and O.B. Riley Road intersection.
Generally, the City may use eminent domain to minimize project schedule uncertainty. Eminent domain,
however, cannot be used on parcels owned by the state government. Both the signal and roundabout
options are very likely to have an impact on this parcel, and therefore no guarantees can be made for a
construction schedule.
Construction Fatigue The GO Bond has relatively few projects identified for funding in the vicinity of the Empire-OB Riley
Intersection. With that being said, care should be taken to avoid overlapping construction with the
Empire Avenue Interchange Improvements project, as the detours for the two projects could lead to
confusion among the traveling public.
Murphy Parkway Ramps Project Scope
Construct northbound on ramp and southbound off ramp at Murphy Road improving traffic flow and
east/west connectivity at south end of town.
Proposed Preliminary Project Schedule Design: 2026
Construction: 2027
Project manager estimated commitment: 2 years @ 60% allocation.
Sequencing Notes and Reasons for Fiscal Year Funding
• Priority score: 4.5 (ranked 28th)
• This project scored relatively poorly in terms of prioritization
• Project may serve as a good detour and traffic offloading mechanism for the work on Reed
Market Road and at the Power Road and Reed Market Road interchanges
Additional Information
Budget Murphy Parky Ramps: $10,000,000 (GO Bond)
Congressionally Directed Spending: $5,000,000 (Federal)*
Total: $10,000,000**
*City staff was notified on October 20, 2021 that the Congressionally Directed Spending Request was
not selected by the Appropriations Committee. Staff will pursue other opportunities for additional
funding sources as they arise.
**Tax Incremental Financing is potentially available to this project – see Draft Capital Improvement Plan
Overview for more information.
Project Readiness In contrast to many of the other interchange projects, this project has been identified in the
Transportation System Plan as being fully-funded by the city. Since the project doesn’t need to wait until
the Statewide Transportation Improvements Program to allocate money to the project, the project
could be more rapidly implemented than the other Parkway-related projects.
Construction Fatigue Much of the work for this project can be completed without major traffic impacts, so no projects are
identified for conflicting detours. There is an opportunity, however, to accelerate this project to develop
better detour while the Reed Market Corridor project is under construction. With the closures to Reed
Market Road during the construction of the railroad overcrossing, access to the Parkway may be
challenging for those that live in the southeast area of town. The construction of the Murphy Parkway
Ramps would allow for better Parkway access for northbound traffic getting on the Parkway and
southbound traffic getting off the Parkway.
As noted in the US 97 Parkway Plan Phase 2, the Murphy Parkway Ramps project should be completed
prior to the Powers Road Interchange Improvements project to allow for an interim Powers Road
overcrossing to be built. The interim solution would offload traffic that is currently using Powers Road
onto the Murphy Road interchange.
Intelligent Transportation Systems Improvements Scope
Capital projects that support regional Intelligent Transportation System plan, for use of technology for
transportation and
traffic management systems to improve safety, efficiency, and sustainability of transportation networks.
Proposed Preliminary Project Schedule Project recommendation memo: 11/21 – 9/22
Memo presented to TBOC: 10/22
Improvement implementation: Ongoing
Sequencing Notes and Reasons for Fiscal Year Funding • Priority score: 2.5 (ranked 29th)
• This project scored relatively poorly in terms of prioritization
• Due to the unclear benefits and improvements associated with the project, the prioritization
scoring was difficult to assess
• As part of a larger traffic engineering contract, a memo will be developed to recommend
projects for funding allocation.
Additional Information
Budget
Intelligent Transportation Systems Improvements: $5,000,000 (GO Bond)
Project Readiness The improvements being funded through this project are not yet identified. A traffic engineering
contract has been entered into by the city that would, among other tasks, develop a memo to identify
and recommend improvements for funding under the Intelligent Transportation Systems Improvements
project. This memo will be presented to TBOC for their consideration in calendar year 2022.
The intent for spending money on such a low-scoring project early on in the implementation of the GO
Bond is to identify opportunities for synergy with other projects. This synergy could reduce construction
fatigue and minimize costs for GO Bond as a whole. Additionally, the identification of improvements
under this program could impact decisions on other projects through improvements made under this
project.
Construction Fatigue Due to the uncertainties of the improvements associated with this project, construction fatigue cannot
be assessed.