F–7 STANDING COMMITTEES Finance and Asset Management Committee
F–7/206-18 6/7/18
Monthly Capital Report INFORMATION This item is being presented for information only. BACKGROUND This item is a standing monthly agenda item. Attachments 1. Active Capital Projects Summary as of June 18, 2018 2. Active Capital Projects Business Equity Scorecard as of June 18, 2018
Active Capital Projects Summary
as of June 18, 2018
Notes:
(1)
(2)
(3)
Project General Contractor buyout largely complete and business equity goals cannot be met with remaining spend
Project budget and funding will be reconciled during demo and site improvement phase
Forecasted permit review times from the City are longer than anticipated.
Project Name Financial Details Schedule Women & Minority
Business Equity* Project Health Trending
Budget Forecast Funding
Committed Target Forecast Committed Utilization Budget Funding Schedule Safety
Business Equity
NCH Phase IV(a): McCarty,
Madrona, & Willow Halls Kieran Timberlake/WG Clark $253.00 $252.76 $253.00 7/18 7/18 $70.68 33.7%
*
*
*
*
*
Life Sciences Building Perkins+Will/Skanska $171.45 $168.60 $171.56 7/18 7/18 $5.96 3.8%
*
*
*
*
(1)
SOM South Lake Union 3.2 Perkins+Will/Sellen $144.98 $141.31 $144.98 11/18 7/18 N/A N/A
*
*
*
*
N/A
UWMC ED East Extension Salus Architecture /Skanska $15.41 $15.41 $15.41 10/18 12/18 $1.19 9.7%
*
*
*
*
*
Bill and Melinda Gates Center
for CSE LMN Architects/Mortenson $105.50 $105.71 $105.50 12/18 12/18 $4.64 5.1%
*
*
*
*
(1)
New Burke Museum Olson Kundig/Skanska $79.70 $80.92 $79.70 7/19 7/19 $3.32 5.3%
(2)
*
*
*
(1)
Parrington Hall Renovation $20.00 $20.00 $20.00 1/20 1/20 TBD TBD
*
*
*
*
TBD
*
TBD
Population Health Facility Miller Hull Partnership/LCL $230.00 $230.00 $230.00 3/20 4/20 $0.88 2.4%
*
*
(3)
*
*
Kincaid Hall Psychology
Renovation 2017-2023 $30.00 $30.00 $30.00 6/20 6/20 TBD TBD
*
*
*
*
TBD
*
TBD
NWH Childbirth Center $25.00 $25.00 $25.00 9/20 9/20 TBD TBD
*
*
*
*
TBD
*
TBD
NCH Phase IV(b): Denny Field,
Haggett & Oak Halls Kieran Timberlake/WG Clark $86.20 $86.20 $86.20 7/21 7/21 $0.03 0.4%
*
*
*
*
TBD
*
Foster School Expansion $70.00 $70.00 $70.00 8/21 8/21 TBD TBD
*
*
*
*
TBD
*
TBD
Totals $1,231.24 $1,225.91 $1,231.35 $86.70 15.0%
$ All Dollars in Millions *Includes OMWBE certified and self-identified Women and Minority businesses
Targets Legend
Budget: Budget is equal to or greater than Forecast (1% Tolerance) Funding: Funding is equal to or greater than Forecast (1% Tolerance) Schedule: Forecast is equal to or sooner than Target (14 Day Tolerance) Safety: Total Recordable Incident Rate of 2.5 or lower Business Equity: On track for utilization of 10% or higher
Meeting Target
Not Meeting Target, Plan in Place
Not Meeting Target, No recovery Plan in Place
Arrow Up Improvement from Previous Month
Arrow Down Setback from Previous Month
ATTACHMENT 1F-7.1/207-18 7/12/18
Page 1 of 1
Business Equity Scorecardas of June 18, 2018
Project Total Commitments* Business Equity Commitments
Total Project Budget*
Committed Forecast Uncommitted OMWBE Businesses (State-Certified Only)
Women & Minority Businesses
(Certified and Self-Identified)
WBE, MBE, and SBE Businesses
(Certified and Self-Identified)
Project Name
(A) (B) (B-A) ((B-A)/B) (C) (C/A) Firms** (D) (D/A) Firms** (E) (E/A) Firms**
NCH Phase IV(a): McCarty, Madrona, & Willow Halls Kieran Timberlake/WG Clark
$223.29 $209.59 $223.54 $13.95 6.2% $5.55 2.6% 12 $70.68 33.7% 20 $75.27 35.9% 30
Life Sciences Building
Perkins+Will/Skanska $161.86 $156.89 $159.12 $2.23 1.4% $2.04 1.3% 16 $5.96 3.8% 29 $18.44 11.8% 62
UWMC ED East Extension
Salus Architecture /Skanska $13.38 $12.34 $13.38 $1.04 7.7% $1.18 9.6% 6 $1.19 9.7% 8 $1.33 10.8% 18
Bill and Melinda Gates Center for CSE LMN Architects/Mortenson
$93.11 $91.15 $97.20 $6.06 6.2% $1.49 1.6% 11 $4.64 5.1% 18 $20.67 22.7% 31
New Burke Museum Olson Kundig/Skanska
$70.32 $63.11 $71.47 $8.35 11.7% $1.19 1.9% 14 $3.32 5.3% 30 $8.08 12.8% 96
Population Health Facility Miller Hull Partnership/LCL
$199.00 $37.28 $199.30 $162.01 81.3% $0.72 1.9% 6 $0.88 2.4% 9 $2.16 5.8% 19
NCH Phase IV(b): Denny Field, Haggett & Oak Halls Kieran Timberlake/WG Clark
$74.89 $6.23 $74.89 $68.67 91.7% $0.02 0.3% 8 $0.03 0.4% 7 $0.79 12.7% 15
Totals $835.85 $576.59 $838.90 $262.31 31.3% $12.19 2.1% 39*** $86.70 15.0% 72*** $126.74 22.0% 178***
* Project Total Commitments and Budget include only costcodes that are business equity eligible. Those that are not (such as sales tax) are excluded.
** Firm total is a distinct count per Project
*** Bottom Line total is count of distinct firms across all projects
ATTACHMENT 2F-7.2/207-18 7/12/18
Page 1 of 1