ATSS Backlog Clearing Process (BCP) Customer WorkshopOctober 4, 2013
![Page 2: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/2.jpg)
Purpose
• Provide overview and details of the Backlog Clearing Process (BCP), including timelines and requirements
• Capture questions to include in posted documents
2
![Page 3: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/3.jpg)
Overview• Overview of the Backlog Clearing Process (BCP)• ATSS Completion Agreement (ACA) • Study Procedure• Third-party Impact Process • Make-Whole Payment (MWP)• Open Season Extension• One-Time Cost-Causer Exemption
3
![Page 4: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/4.jpg)
Definitions• Current Process
– The currently-effective aggregate study process• Backlog Clearing Process (BCP)
– The process to be implemented upon FERC acceptance of SPP’s filing in ER13-2164
– Requested effective date of October 12, 2013• New Process
– A new aggregate study process – still in development in SPP’s working groups – for future implementation with a date to be determined
– No tariff changes have yet been approved or filed
4
![Page 5: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/5.jpg)
Aggregate Study is an iterative process that continues until no customers withdraw.
Open Season
(4 months)
Open Season
(4 months)
Facilities Study
(60 days)
Facilities Study
(60 days)
Letter of Intent Response Period
(15 days)
Letter of Intent Response Period
(15 days)
Restudy Needed
?
Restudy Needed
?
Write Service
Agreement
Write Service
Agreement
YESYES
NONO
Current Aggregate Study Process
![Page 6: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/6.jpg)
Are New Completion
Requirements Met?
Are New Completion
Requirements Met?
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
Overview of the Backlog Clearing Process
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Facilities Study
Facilities Study
Accept all requests and Tender Service
Agreements
Accept all requests and Tender Service
Agreements
NO
YES
Collect Make-Whole Payments from
Customer, if required
Collect Make-Whole Payments from
Customer, if required
Customer Executes
ACA
Customer Executes
ACA
Customer Does Not
Execute ACA
Customer Does Not
Execute ACARequest
WithdrawnRequest
Withdrawn
Customer Confirms Service (and
Executes Service Agreement)
Customer Confirms Service (and
Executes Service Agreement)
Customer Does Not Confirm
Service
Customer Does Not Confirm
Service
StartStartNO
YES
Customer with 3rd
party impacts may
move to next study
Customer with 3rd
party impacts may
move to next study
Customer with 3rd Party impacts postpones action
Customer with 3rd Party impacts postpones action
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Did any customers withdraw?
Did any customers withdraw?
StopStop
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
![Page 7: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/7.jpg)
AGGREGATE STUDY COMPLETION AGREEMENT (ACA)
7
![Page 8: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/8.jpg)
ATSS Completion Agreement (ACA) and Process• ACA tendered only for studies that are first in queue and
after AFS-4
• ACA covers the request through the completion of the study
• Customer commits either to accept service offered within the ACA parameters or to pay a make-whole payment
• Baseline values are the values from the pre-ACA study iteration and customers can enter greater “acceptable” values
8
![Page 9: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/9.jpg)
ACA Contents
9
Additional components of ACA:•Agreement with Table 1 for OASIS requests •Appendix 1 – Study parameters•Appendix 2 – Mutually exclusive requests
![Page 10: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/10.jpg)
ACA – Table 1• ACA Table 1 will list all OASIS requests covered by
agreement:
• Any related GI study number should be included in the ‘GI Study Number’ column
10
![Page 11: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/11.jpg)
ACA – Appendix 1
13
Customer selects study option at top of Appendix 1.Remain: Items 1-5 must be completed.Sign and date at bottom.
![Page 12: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/12.jpg)
ACA – Appendix 1
14
Customer selects Expedited Service, Accepts ATC or Withdraws, then skip items 1-5 and sign and date at bottom.
![Page 13: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/13.jpg)
ACA – Appendix 1 – cont.
(1) Directly Assigned Upgrade Costs (DAUC)– Customer can specify a maximum amount, but no less
than its DAUC from the iteration prior to signing the ACA– If no maximum amount is provided in (1)(b), the value
from the most recently posted study will be utilized
15
![Page 14: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/14.jpg)
ACA – Appendix 1 – cont.(2) 3rd Party Upgrade Costs
– Customer can specify a maximum amount, but no less than its costs from the iteration prior to signing the ACA
– Customer can elect to either remain in the current study or move to the next highest priority study in queue if the 3rd party cost is non-zero or listed as indeterminate
– If no maximum amount is provided in (2)(b), the value from the most recently posted study will be utilized
– If no selection is made for (2)(c), the request will remain in study
16
![Page 15: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/15.jpg)
ACA – Appendix 1 – cont.
(3) Deferred Start Date without redispatch– Customer can specify the latest acceptable start date– If date in (3)(b) is left blank, the Start Date from Most
Recently Posted Study will be the default date
17
![Page 16: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/16.jpg)
ACA – Appendix 1 – cont.
(4) Interim Redispatch, if it can provide an earlier Start Date
– Customer can specify if Interim Redispatch is acceptable– If no selection is made, then ‘No’ will be the default
18
![Page 17: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/17.jpg)
ACA – Appendix 1 – cont.
(5) Letter of Credit (if required)– Customer can specify a maximum amount– If no maximum amount is provided in (5)(b), the value
from the most recently posted study will be utilized
19
![Page 18: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/18.jpg)
ACA – Appendix 2
• Mutually-exclusive requests– Post AFS-4, customer must select only one (1) request to
remain in study. – Customer will withdraw any remaining requests
20
![Page 19: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/19.jpg)
BCP STUDY PROCEDURE
21
![Page 20: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/20.jpg)
Are New Completion
Requirements Met?
Are New Completion
Requirements Met?
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
BCP Study Procedure
Facilities Study
Facilities Study
Accept all requests and Tender Service
Agreements
Accept all requests and Tender Service
Agreements
NO
YES
NO
YES
3rd Party Process3rd Party Process
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Did any customers withdraw?
Did any customers withdraw?
• BCP Facilities Study begins once initial ACAs are returned
• Parameters evaluated from ACA Appendix 1 and 2
• Requests that don’t meet one of the parameters may be• Withdrawn• ACA Amended
• Requests that meet all parameters will remain in study
• Restudy, if needed
• If no requests are withdrawn, begin finalizing study• “Next Steps” emails• Accept all requests• Tender Service Agreements
• 3rd Party Process
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
![Page 21: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/21.jpg)
3RD PARTY IMPACTS
23
![Page 22: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/22.jpg)
3rd party impacts
• The customer with 3rd party impacts has three options prior to executing the ACA and entering into BCP– Option 1: Withdraw the
request
– Option 2: Move to next study
– Option 3: Continue in study subject to make-whole payment
24
![Page 23: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/23.jpg)
Are New Completion
Requirements Met?
Are New Completion
Requirements Met?
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
Request Withdrawn
Request Withdrawn
3rd Party Impacts – cont.
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Facilities Study
Facilities Study
Accept all requests and Tender Service
Agreements
Accept all requests and Tender Service
Agreements
NO
YES
Collect Make-Whole Payments from
Customer, if required
Collect Make-Whole Payments from
Customer, if required
Customer Executes
ACA
Customer Executes
ACA
Customer Does Not
Execute ACA
Customer Does Not
Execute ACA
Customer Confirms Service (and
Executes Service Agreement)
Customer Confirms Service (and
Executes Service Agreement)
Customer Does Not Confirm
Service
Customer Does Not Confirm
Service
StartStartNO
YES
Customer with 3rd
party impacts may move to next
study
Customer with 3rd
party impacts may move to next
study
Customer with 3rd Party impacts postpones action
Customer with 3rd Party impacts postpones action
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Did any customers withdraw?
Did any customers withdraw?
Issue NTCs, if required
Issue NTCs, if required
Project TrackingProject
Tracking
StopStop
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
Customers with unresolved 3rd party impacts may
choose to move to the next aggregate study prior to
execution of the ACA
![Page 24: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/24.jpg)
Are New Completion
Requirements Met?
Are New Completion
Requirements Met?
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
Request Withdrawn
Request Withdrawn
3rd Party Impacts – cont.
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Facilities Study
Facilities Study
Accept all requests and Tender Service
Agreements
Accept all requests and Tender Service
Agreements
NO
YES
Collect Make-Whole Payments from
Customer, if required
Collect Make-Whole Payments from
Customer, if required
Customer Executes
ACA
Customer Executes
ACA
Customer Does Not
Execute ACA
Customer Does Not
Execute ACA
Customer Confirms Service (and
Executes Service Agreement)
Customer Confirms Service (and
Executes Service Agreement)
Customer Does Not Confirm
Service
Customer Does Not Confirm
Service
StartStartNO
YES
Customer with 3rd
party impacts may move to next
study
Customer with 3rd
party impacts may move to next
study
Customer with 3rd Party impacts postpones action
Customer with 3rd Party impacts postpones action
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Did any customers withdraw?
Did any customers withdraw?
Issue NTCs, if required
Issue NTCs, if required
Project TrackingProject
Tracking
StopStop
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
Customers with un-resolved 3rd party
impacts after study completion may
postpone the decision to confirm service
![Page 25: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/25.jpg)
27
3rd Party Impacts – Postponing Service
Agreement is not reached with
3rd party or time expires
Agreement is not reached with
3rd party or time expires
Request is Accepted and Service
Agreement is Tendered
Request is Accepted and Service
Agreement is Tendered
Make Whole Payment (MWP) is collected
from Customer
Make Whole Payment (MWP) is collected
from Customer
3rd Party clears Request
3rd Party clears Request
Customer Confirms Service (and
Executes Service Agreement)
Customer Confirms Service (and
Executes Service Agreement)
Request is Declined and Sponsored
Upgrade Agreement is Tendered
Request is Declined and Sponsored
Upgrade Agreement is Tendered
Customer with 3rd Party impacts
postpones action
Customer with 3rd Party impacts
postpones action
Timer Starts(1 year or
Service Start Date)
Timer Starts(1 year or
Service Start Date)
Applicable 3rd Party
Evaluation Process
Applicable 3rd Party
Evaluation Process
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
3rd Party Action
3rd Party Action
![Page 26: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/26.jpg)
Are New Completion
Requirements Met?
Are New Completion
Requirements Met?
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
ACA Completion Requirements1.Maximum directly-assigned upgrade cost2.Maximum 3rd party upgrade cost3.Latest acceptable deferred start date4.Accept interim redispatch5.Maximum Letter of Credit
Request Withdrawn
Request Withdrawn
3rd Party Impacts – cont.
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Post AFS-4 and Tender ATSS Completion
Agreement (ACA)
Facilities Study
Facilities Study
Accept all requests and Tender Service
Agreements
Accept all requests and Tender Service
Agreements
NO
YES
Collect Make-Whole Payments from
Customer, if required
Collect Make-Whole Payments from
Customer, if required
Customer Executes
ACA
Customer Executes
ACA
Customer Does Not
Execute ACA
Customer Does Not
Execute ACA
Customer Confirms Service (and
Executes Service Agreement)
Customer Confirms Service (and
Executes Service Agreement)
Customer Does Not Confirm
Service
Customer Does Not Confirm
Service
StartStartNO
YES
Customer with 3rd
party impacts may move to next
study
Customer with 3rd
party impacts may move to next
study
Customer with 3rd Party impacts postpones action
Customer with 3rd Party impacts postpones action
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Customers with requests that did not meet
parameters may withdraw or must execute ACA
amendment to remain
Did any customers withdraw?
Did any customers withdraw?
Issue NTCs, if required
Issue NTCs, if required
Project TrackingProject
Tracking
StopStop
Customer Action
Customer Action
SPP Staff Action
SPP Staff Action
Customers with 3rd party impacts that move forward by signing the ACA may be subject to a make-whole payment if service is not
confirmed.
![Page 27: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/27.jpg)
MAKE-WHOLE PAYMENT (MWP)
29
![Page 28: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/28.jpg)
Make-Whole Payment (MWP)• Customers that sign an ACA without executing a
Transmission Service Agreement (TSA) are obligated to pay for any shared upgrade costs in the form of a MWP
• Customers that pay a MWP will execute a Sponsored Upgrade agreement under Attachment J– Sponsored Upgrades are eligible to receive revenue
credits under Attachment Z2
30
![Page 29: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/29.jpg)
31
Re-Run Cost Allocation &
Prepare Sponsored Upgrade
Agreements
Re-Run Cost Allocation &
Prepare Sponsored Upgrade
Agreements
Notify Customer of MWP and
Tender Sponsored Upgrade
Agreements
Notify Customer of MWP and
Tender Sponsored Upgrade
Agreements
Settlement of Make Whole
Payment
Settlement of Make Whole
Payment
Incorporate into Creditable Upgrades Database
Incorporate into Creditable Upgrades Database
Make-Whole Payment (MWP) Process
![Page 30: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/30.jpg)
32
Maximum Potential MWP Example• Excerpt from Table 3 of study report showing Service
Upgrades allocated to a request
• The highlighted cells depict the potential MWP for each upgrade, based on the revenue requirements.
• The non-highlighted upgrades are non-shared upgrades and are not included in the MWP calculation.
Upgrade # Upgrade Name DUN EOCEarliest
Start DateRedispatch Available
Allocated E & C Cost Total E & C Cost
Total Revenue Requirements
1 GRAND ISLAND - SWEETWATER 345KV CKT 2 12/1/2013 6/1/2019 No $ 207,454 $ 96,288,750 $ 634,269
2 HYDRALIC JCT NORTH - MACARTHUR 69KV CKT 1 6/1/2018 6/1/2018 $ 1,745,900 $ 1,745,900 $ 5,150,283
3 HYDRALIC JCT NORTH - OAKLAWN 69KV CKT 1 6/1/2018 6/1/2018 $ 1,098,100 $ 1,098,100 $ 3,239,318
4 SMAN_W_3 115.00 - SOUTH MANHATTAN 115KV CKT 1 6/1/2015 6/1/2016 $ 78,476 $ 790,000 $ 285,837
5 ST JOHN - ST_JOHN 115KV CKT 1 MIDW 12/1/2013 6/1/2016 No $ 19,438 $ 450,000 $ 55,670
6 ST JOHN - ST_JOHN 115KV CKT 1 MKEC 12/1/2013 6/1/2016 No $ 24,298 $ 562,500 $ 117,718
Total: $ 3,173,666 $ 100,935,250 $ 9,483,093
Maximum Potential MWP:
$1,098,494
Maximum Potential MWP:
$1,098,494
![Page 31: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/31.jpg)
Non-Shared Upgrades
• Non-shared upgrades will not be included in the Make-Whole Payment for requests that are not confirmed
• Exception: – Non-shared upgrades that are allocated to a request
with a third-party impact that exercised the option to postpone action will be included in subsequent studies
– If service is granted to subsequent requests that rely on the non-shared upgrade, the original request will be assigned a MWP if the request is not confirmed
33
![Page 32: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/32.jpg)
OPEN SEASON EXTENSION
34
![Page 33: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/33.jpg)
Open Season Extension• Open season will remain open until either the
immediately prior study becomes the highest priority study or SPP Staff determines the Open Season needs to close– SPP will give at least 10 days’ notice before the open
season closes
– The Open Season will be open for no less than 4 months
• 2014-AG1 will be the first open season to be extended
35
![Page 34: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/34.jpg)
ONE-TIME COST-CAUSER EXEMPTION
36
![Page 35: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/35.jpg)
One-Time Cost-Causer Exemption
• Customers will have an opportunity to withdraw any pending aggregate study request without incurring an obligation to pay for subsequent restudies– Customers have 45 days after FERC acceptance
of the tariff language to exercise the option
• This is a one-time exemption
37
![Page 36: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/36.jpg)
WRAP-UP
38
![Page 37: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/37.jpg)
39
Implementation Timeline
• Filed Tariff Aug. 15, 2013
• FERC order expected by Oct. 14, 2013
• Letters of Intent due for 2011-AG3-AFS-10 on Oct. 12
• If FERC issues an order by COB October 14, 2013 and accepts the October 12, 2013 effective date, then:– 2011-AG3 will be subject to BCP if it did not complete
with AFS-10 (ACA will be tendered)
– If October 12th is not the effective date, 2011-AG3 will continue under the Current Process if it did not complete with AFS-10
![Page 38: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/38.jpg)
Posting of Documents on spp.org
40
![Page 39: ATSS Backlog Clearing Process (BCP) Customer Workshop October 4, 2013](https://reader036.vdocuments.site/reader036/viewer/2022062320/56649d0f5503460f949e5705/html5/thumbnails/39.jpg)
41
ATSS Contact InformationSteve Purdy, Manager [email protected] (501) 614-3371
Chris Jamieson, Lead Engineer [email protected] (501) 614-3231Eric Samson, Sr. Engineer [email protected] (501) 614-3375James Bailey, Engineer [email protected] (501) 688-8243David Duhart, Engineer [email protected] (501) 688-1705Terry Fang, Engineer [email protected] (501) 688-1709Charlton Hill, Engineer [email protected] (501) 688-1716Aaron Stewart, Engineer [email protected] (501) 482-2168
John O’Dell, Analyst [email protected] (501) 688-8285Sherri Maxey, Analyst [email protected] (501) 688-1648
General email: [email protected]