atlas central solenoid - kekatlas.kek.jp/solenoid/2001/cern-20011205.pdf · atlas central solenoid...

47
1 Draft Draft Working List to be done at CERN for ATLAS Central Solenoid Originated, Dec. 4, 2001 Revised, Dec.5, 2001 Akira Yamamoto (KEK)

Upload: truongdat

Post on 10-Mar-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

1

DraftDraftWorking List to be done at CERN for

ATLAS Central Solenoid

Originated, Dec. 4, 2001

Revised, Dec.5, 2001

Akira Yamamoto (KEK)

2

General Working List

• Works in Bldg. 180:– CS system delivered and acceptance test made,

– Chimney and prox. cryogenics placed and pre-tested,

– CS assembled into LAr cryostat and General Test made,

• Works in Pit 1:– Chimney and prox. cryogenics installed

– LAr+CS installed into ATAS detector system,

– General test together with LAr calorimeter.

3

Plan at CERN

2001 9 Central Solenoid delivered,

10 ~ Chimney and proximity cryogenics assembly in 180,

2002 6 Test of chimney and proximity cryogenics,

2003 6 Installation of CS into LAr cryostat

10 General test of LAr system with Central Solenoid

2004 Installation of chimney and LAr/CS in the pit.

?? General test in the pit.

4

Works in Bldg. 180

• Delivery– Unloaded, placed, and acceptance check made,

• Proximity cryogenics test– Cryogenics hardware placement and connection,– PLC for cryogenics established,– Power supply ( 10 kA, ??V),– MCS and MSS,

• Installation of CS into LAr crostat– Co-work with CERN/ATLAS/LAr group

• General test of CS with Prox. Cryogenics– Test items to be determined.

• Preparation for movement– Disassembly of Chimney, CD and valve unit

5

General Guide Line forWork Responsibility at B180, CERN• KEK responsible for;

– Participate the chimney and Prox. Cryogenics test.• Including cooperative preparatin work with ECR group.

– Installation of SC bus line in LAr cryostat,• Including superconductor joints, cooling pipe connection as well as

signal wiring,

– Watching installation work of the IWV and CS into Lar cryostat inBldg-180,

• CERN/ATLAS/LAr group responsible for– Physical installation work of LAr/IWV and CS assembled

• CERN/ECR responsible for– Installation and connection of external cryogenics– Part of connections and layout of prox. Cryogenics

6

ATLAS CS assembled withLAr/IWV

7

CS Coil, LAr/IWV, and Supports

8

Chimney, Control Dewar,andValve Unit for ATLAS CS

Chimney

Control Dewar

Valve Unit

9

Layout Plan in B180

10

May/2002 Chimney Test Layo

11

Layout in B180 in 2003

12

Step 0:Assembly beam

13

Step 1:Solenoid arrival

14

Step 2a:Solenoid lifting (w/ Beam)

15

Step 3:Setting on Assembly beam

16

Step 4:Disassembling END C plate

17

Step 5:Installing into LAr cryostat

18

Step 6:Finish the installing

19

Step 7:Remove END A plate

20

ATLAS Central Solenoid

Z = 2650

Z = 3150R = 1150

R = 1234

Z = 3150

LAr Calorimeter

Coil

22

Summer/2003 Coil Test Layo

23

ATLAS-CS Integration with LAr

24

Work in Point-1

• Installation of CH and PC,

• Installation of CS pre-assembled with LAr,

• Installation of proximity cryogenics, powersupply, and monitoring,

• General performance test

25

Installation Plan in Pit-1Left-Right direction reversed!

26

Chimney

S.C. Bus Detail

SQD

Shield Cooling Pipe Returen

Coil Cooling Pipe Retuern

Signal Cable Duct

Coil Cooling Pipe

Radiaton Shield

Bus Conduit

Vacuum Shell

Shield Cooling Pipe

Current Lead

Control Valve

Buffer Tank

Heat Exchanger

Bus Connection

Vacuum Couple

Bus Conduit

Spacer

Kapton Tapet 0.05GFRP t1

Upilex / GlassTape

Chimney Cross Section

Spacer ( Bottom Base )

( Subsidary Line )

( Main Line )

IndiumSheet SUS Sheet

Welding

Kapton Sheet

to Coil

C/L

Electric Connection

Welding

WeldingWelding

27

Installation in Point-1

28

Tasks for Roger starting at CERN

• Systematically collect of all information– on the Central Solenoid System and put into the ATLAS databas;

CDD/EDMS/…

• Co-work with ECR for proximity cryogenics test in June2002,– Physical layout,– Control and monitoring,

• Interface with LAr calorimeter– SC bus-line design to be frozen,– Installation work plan,

• Confirm/re-evaluate magnetic force– Magnetic force with LAr support frame in B180, and with hadron

calorimeter in Ponit-1.

29

Works at CERN/ATLAS listed by Herman ten Kate(informed through T. Kondo, as of Sept., 2001?)

....1 Work in B1801.1 Cryogenics [Metselaar/Foussat] - Cryogenic HP+LP piping - Railing, work on platform - Transfer-line to BOC - Transfer-line installation - Transfer-line supports - Connections between CD and Valve box - Scaffolding - Installation (CD+VB+Chimney) - Installation Chimney1.2 MSS in B180 [Sbrissa] - cables & connectors - modifications exsisting - quench heater supplies1.3 MCS in B180 [Tyrvanien] - external cables (10m) - work for patch panel + miscellaneous - racks and racks installation - CPU+network cards - analog channel - digital channels - miscellaneous - software1.4 Busbars/cables (second hand) modifications [Cataneo]

....2 Work in Cavern2.1 Final MSS [Sbrissa]2.2 Final MCS [Tyvainen] - external cables (50m) - racks installation - racks - CPU+network cards - analog channels - digital channels - miscellaneous - software including SCADA bus2.3 Power circuit [Cataneo] - mains etc - UPS - bus bars (CS part) - switch - ramp down unit - power supply 2.4 Cryogenics [Metselaar] - re-installation CD+VB+Chimney - piping between CD and VB (92m) - cables between CD and VB (92m) - transferline between CD and VB (92m) - modificationValve unit (vac pumps, instrumentation) - connections to water, air, etc (not cryo)

3. Manpower - Roger Ruber and his exploitation expence

30

A suggestion given byHerman ten Kate

• It may be wise/valuable to consider thatCERN/ATLAS will manage to include furtherman-power works at CERN;– Such specific works of Superconducting joints, pipe

joints, and monitoring signal wiring,

• It may be realized;– if Japanese F.T. budget could be allocated to this

further works at CERN.

• It will be further studied and– discussed between CERN ATLAS and KEK.

31

Appendix

• Coil Support and alignment

32

ATLAS CS and Supports

(Fixed side) (Slide side)(Slide side)(Slide side)(Slide side)

Type-A

Type-BB

B

B

B B

B

0 deg.

A

A

90 deg.

Slidefixed

33

ATLAS Central SolenoidSide View

34

ATLAS Central Solenoid1/4 Side View

35

Coil End

36

Support Adjustment

Inner WarmVessel

End Ring

CylinderCoil & Support

Fixture

Spherical bearing

Triangle Support

Eccentric Pin

Bracket Fixture

37

Coil Cross Section

38

Individual Support Strength

0 10 20 30 40 50 60 700

1

2

3

4

5

6

7

8

9

10

Breaking point

Deformation(mm)

Applied Load(kN)

0

1

2

3

4

5

6

7

8

9

10

0 10 20 30 40 50 60 70

Triangle support made of: GFRP woven in six-directionsSpherical bearing at joints: to minimize bending moment

Safe cycle testw/ brackets

One-wayBreaking test

1G1G+2G

Max. Load

39

Triangle Support DesignParameters

Type-A Type-B

Length of cross section(mm2) 20 × 20 20 × 15

Location(degree) 75, 105, 255, 285 15, 45, 135,165, 195,225,315,345

Load condition 2G + Self-weight 2G

Break load(kN) 67.5 46.5

Design load/support(kN) 16.5 11

Design deformation(mm) 1.5 1.2

Safety factor >4 >4

40

Coil Displacementunder De-centering Force

Fy = 2G = 120 kN1 mm

Triangle support

Coil

41

Global Test with 1+2 G

Telescope

Strain Guage

Load

0 deg.

90 deg.

Y

X

Z

D1

D2

D3

dy

42

0 10 20 30 40 50 60 70 80 90 100 110 120-0.2

0.0

0.2

0.4

0.6

0.8

1.0

Deformation(mm)

Applied Load(kN)

Defomation Calculation

0 10 20 30 40 50 60 70 80 90 100 110 1200

5

10

15

20

25

30 Stress Calculation

Applied Load(kN)

Stress(MPa)

-0.2

0.0

0.2

0.4

0.6

0.8

1.0

0

5

10

15

20

25

30

0 10 20 30 40 50 60 70 80 90 100 110 120

0 10 20 30 40 50 60 70 80 90 100 110 120

0 30 60 90 120 150 180 210 240 270 300 330 3600

2

4

6

8

10

12

Measured Force(kN)

Position(degree)

Chimney side Anti-chimney side Calculation

Measured Force

Ex-Load Test Results

43

Position Monitoring

Inner Warm Vessel

Coil

44

End-A Potentiometer

45

Position Sensors at End -A

46

ATLASCS

0.71

6810

4430

13000Control Dewar

Valve Unit

Chimney

LAr Vessel

Solenoid Coil

Unit mm