assessing changes in contaminant fluxes following removal of a dam in the pawtuxet river results and...
TRANSCRIPT
Assessing changes in contaminant fluxes following removal of a dam in the Pawtuxet River
Results and Discussion
Methods and ApproachPassive samplers (polyethylene; PE) and sediment traps were deployed at three sites in the river to establish contaminant fluxes in the dissolved and particulate phases prior to dam removal (Figure 1). Dam removal commenced on August 10, 2011 and was completed by late August 2011. Following removal of the impoundment, sediments traps have been continuously deployed to monitor changes in the flux of contaminants over time. Passive samplers have been deployed at all three sites so far on the following dates:
- Pre Dam removal deployment July 9, 2011-August 9, 2011- Post Dam removal deployment 1: December 5, 2011-December 19, 2011*- Post Dam removal deployment 2: February 28, 2012-March 13, 2012 *Site 2 sampler lost
Mark G. Cantwell †, Monique M. Perron‡, Julia C. Sullivan◊, David R. Katz†, Robert M. Burgess†
†US EPA, ORD/NHEERL, Atlantic Ecology Division, Narragansett, RI, ‡ NRC/EPA, ◊ University of Rhode Island/EPA
Abstract Restoration of rivers and their associated ecosystems is a growing priority for government agencies (e.g., NOAA, USDA), as well as conservation organizations. Dam removal is a major component of many restoration projects credited with reintroducing fish species, improving water and habitat quality, and increasing recreation potential. Many proposed locations for restoration, however, have been impacted by past discharges of chemical pollutants resulting in contaminated sediment. As a result, the potential exists for release of sequestered contaminants following dam removal or other restoration activities. Few, if any, dam removal projects have studied the release of contaminants from the sediments following removal. In this study, we measured dissolved and particulate concentrations of polynuclear aromatic hydrocarbons (PAHs) before and after removal of an existing low head dam at several sites in the Pawtuxet River, an urbanized river in Cranston, RI. Preliminary results indicate that dissolved concentrations of PAHs decreased at one site above the dam location following removal, while concentrations remained unchanged below the dam at the mouth of the river which discharges to Narragansett Bay. Particulate concentrations of PAHs collected in sediment traps showed a decrease following dam removal at all sites within the river and at the river mouth. Results from this study will be used to evaluate methods under development to assess the short- and long-term impact of ecological restoration activities such as dam removal.
Introduction• Pawtuxet River had been dammed from 1870s or earlier, with the last impoundment constructed in 1924 of concrete. Located at the mouth of the river, this was a
low head dam approximately 170’ long, 5’ high.
• The Pawtuxet Falls dam was removed in early August, 2011 in order to improve fish passage and restore the river ecosystem.
• Average river flow of 28 m3/s, with a watershed drainage area of 588 km2
• Lower Pawtuxet River is prone to flooding, with sediments impacted by past industrial discharges.
• Sediments characterized as moderately to highly contaminated with numerous classes of organic compounds (e.g., PAHs, PCBs).
• Remedial clean-up of contaminated sediments up-river was completed in 2002.
Sediment Traps• Deployed in locations where deposition occurs
• Sinking particles are collected in deployed traps over a time scale similar to passive samplers
• Following retrieval, particles are extracted and measured for contaminant concentrations
•Measure dissolved organic contaminants by absorption into PE
• Technique relies upon contaminant partitioning between the aqueous phase and the PE polymer
• Samplers are deployed and allowed to equilibrate for approximately a month before retrieval, clean-up, and solvent extraction
• Accumulated contaminants in the PE (CPE) are measured and passive sampler-water partition coefficients (KPE-water) used to calculated dissolved concentrations (Cwater)
• Cheap and easy to use
• Less interference from colloids and small particles makes for cleaner analytical sample
• Less interference from colloids and small particles makes for cleaner analytical samples
• Lower detection limits
• Obtain a time-weighted average concentration rather than a “snap-shot” concentration at a particular time point
Passive Samplers
K
C C
water-PE
PEwater
Particulate PAHs• Concentrations of individual PAHs decline downriver from Site 1- Site 3 (Figure 2)
• Certain individual PAHs were much higher than others, suggesting past industrial use rather than pyrogenic sources such as combustion as being the origin.
• Below the dam at Site 3, a time series of ΣPAH concentrations varied between 18 and 56 ug g-1, showing no correspondence to river flow (Figure 3)
• A total suspended solids (TSS) model is currently being constructed to determine the quantity of suspended particles at any given flow rate in the river.
• This will permit accurate determination of particulate phase contaminant fluxes during our study period using sediment trap data.
• This will also enable proper apportionment of contaminant fluxes between phases and provide a predictive capability for fluxes under a ranges of conditions
Dissolved PAHs• Individual PAHs in the dissolved phase showed the same behavior as the particulate phase, with concentrations declining downriver from Sites 1-3. For pre and post
dam deployments, most of the differences in individual PAH concentrations were not significant (p> 0.05) (Figure 4)
• Post removal deployment 1 observed a steep decline in many high molecular weight PAHs which continued to drop in post removal deployment 2 (Figure 4)
• At Site 3, below the dam site, concentrations show a sustained decline for most of the PAHs measured in this study (Figure 5)
Next Steps• Proceed with fourth and potentially final deployment
• Finish data analysis of sediment core taken from site 2 to reconstruct temporal record of contamination
• Analyze data for PCBs and other contaminants
• Measure surficial sediments within river at key locations
• Develop flux models for particulate and dissolved phase contaminants
Figure 1. Study area
Figure 2. Particulate PAH concentrations before (a) and after (b) dam removal
Figure 4. Dissolved PAH concentrations before (a) and after (b) dam removal
Figure 5. Dissolved PAH concentrations of each deployment at Site 3
Figure 3. Particulate total PAH concentrations at Site 3 in relation to water flow
Contact: Mark [email protected]
Figure 6. Total suspended solids at Site 3
0 5 10 15 20 25 300
200
400
600
800
1000
1200
f(x) = 30.9206726546651 x + 285.659097085443R² = 0.752324438968913
Total Suspended Solids
mg/L
Flow
(cfs
)
2,6 dimeth
ylnap
thale
ne
2,3,5 trim
ethyln
apth
alene
acenap
thyle
ne
acenap
thene
fluorene
phenanth
rene
anth
racene
fluoranth
ene
pyrene
benz[a]an
thrac
ene
chrys
ene
benzo[b]+[
k]fluoran
thene
benzo[e]pyre
ne
benzo[a]
pyrene
perylene
indeno[1,2,3,c,d]pyre
ne
dibenz[a,h]an
thrac
ene
benzo[g,
h,i]peryl
ene1
10
100
August 2011 Deployment
Site 1Site 2Site 3
Conc
entr
ation
ng
L-1
2,6 dimeth
ylnap
thale
ne
2,3,5 trim
ethyln
apth
alene
acenap
thyle
ne
acenap
thene
fluorene
phenanth
rene
anth
racene
fluoranth
ene
pyrene
benz[a]an
thrac
ene
chrys
ene
benzo[b]+[
k]fluoran
thene
benzo[e]pyre
ne
benzo[a]
pyrene
perylene
indeno[1,2,3,c,d]pyre
ne
dibenz[a,h]an
thrac
ene
benzo[g,
h,i]peryl
ene1
10
100
March 2012 Deployment
Site 1Site 2Site 3
Conc
entr
ation
ng
L--1
Napth
alene
1-meth
ylnap
thale
ne
2-meth
ylnap
thale
ne
2,6 di meth
ylnap
thale
ne
2,3,5 tri m
ethyln
apth
a...
acenap
thale
ne
acenap
thene
fluorene
phenanth
rene
anth
racene
fluoranth
ene
pyrene
benz[a]an
thrac
ene
chrys
ene
benzo[b]+[
k]fluoran
thene
benzo[e]pyre
ne
benzo[a]
pyrene
perylene
indeno[1,2,3-cd-]p
yrene
dibenz[a,h]an
thrac
ene
benzo[g,
h,i]peryl
ene0.01
0.1
1
10
100 August 2011 Deployment
Site 1Site 2Site 3µg
g-1
Napth
alene
1-meth
ylnap
thale
ne
2-meth
ylnap
thale
ne
2,6 di meth
ylnap
thale
ne
2,3,5 tri m
ethyln
apth
alene
acenap
thale
ne
acenap
thene
fluorene
phenanth
rene
anth
racene
fluoranth
ene
pyrene
benz[a]an
thrac
ene
chrys
ene
benzo[b]+[
k]fluoran
thene
benzo[e]pyre
ne
benzo[a]
pyrene
perylene
indeno[1,2,3-cd-]p
yrene
dibenz[a,h]an
thrac
ene
benzo[g,
h,i]peryl
ene0.01
0.1
1
10
100
March 2012 Deployment
Site 1Site 2Site 3
µg g
-1
7/26/2011 9/14/2011 11/3/2011 12/23/2011 2/11/2012 4/1/2012 5/21/20120
10
20
30
40
50
60
0
200
400
600
800
1000
1200
1400
1600
1800
2000Sediment Traps And Flow Data
∑ PAH
Flow (cfs)
PAH
ng g
-1 Flow (CFS)
Sediment Traps Passive Samplers
2,6 dimeth
ylnap
thale
ne
2,3,5 trim
ethyln
apth
alene
acenap
thyle
ne
acenap
thene
fluorene
phenanth
rene
anth
racene
fluoranth
ene
pyrene
benz[a]an
thrac
ene
chrys
ene
benzo[b]+[
k]fluoran
thene
benzo[e]pyre
ne
benzo[a]
pyrene
perylene
indeno[1,2,3,c,d]pyre
ne
dibenz[a,h]an
thrac
ene
benzo[g,
h,i]peryl
ene0.4
4
40Site 3 (Below Dam)
Deployment 1: pre-damDeployment 2: post-damDeployment 3: post-dam
ng L-
1