assessing changes in contaminant fluxes following removal of a dam in the pawtuxet river results and...

1
Assessing changes in contaminant fluxes following removal of a dam in the Pawtuxet River Results and Discussion Methods and Approach Passive samplers (polyethylene; PE) and sediment traps were deployed at three sites in the river to establish contaminant fluxes in the dissolved and particulate phases prior to dam removal (Figure 1). Dam removal commenced on August 10, 2011 and was completed by late August 2011. Following removal of the impoundment, sediments traps have been continuously deployed to monitor changes in the flux of contaminants over time. Passive samplers have been deployed at all three sites so far on the following dates: - Pre Dam removal deployment July 9, 2011-August 9, 2011 - Post Dam removal deployment 1: December 5, 2011-December 19, 2011* - Post Dam removal deployment 2: February 28, 2012-March 13, 2012 *Site 2 sampler lost Mark G. Cantwell , Monique M. Perron , Julia C. Sullivan , David R. Katz , Robert M. Burgess †US EPA, ORD/NHEERL, Atlantic Ecology Division, Narragansett, RI, ‡ NRC/EPA, ◊ University of Rhode Island/EPA Abstract Restoration of rivers and their associated ecosystems is a growing priority for government agencies (e.g., NOAA, USDA), as well as conservation organizations. Dam removal is a major component of many restoration projects credited with reintroducing fish species, improving water and habitat quality, and increasing recreation potential. Many proposed locations for restoration, however, have been impacted by past discharges of chemical pollutants resulting in contaminated sediment. As a result, the potential exists for release of sequestered contaminants following dam removal or other restoration activities. Few, if any, dam removal projects have studied the release of contaminants from the sediments following removal. In this study, we measured dissolved and particulate concentrations of polynuclear aromatic hydrocarbons (PAHs) before and after removal of an existing low head dam at several sites in the Pawtuxet River, an urbanized river in Cranston, RI. Preliminary results indicate that dissolved concentrations of PAHs decreased at one site above the dam location following removal, while concentrations remained unchanged below the dam at the mouth of the river which discharges to Narragansett Bay. Particulate concentrations of PAHs collected in sediment traps showed a decrease following dam removal at all sites within the river and at the river mouth. Results from this study will be used to evaluate methods under development to assess the short- and long-term impact of ecological restoration activities such as dam removal. Introduction Pawtuxet River had been dammed from 1870s or earlier, with the last impoundment constructed in 1924 of concrete. Located at the mouth of the river, this was a low head dam approximately 170’ long, 5’ high. The Pawtuxet Falls dam was removed in early August, 2011 in order to improve fish passage and restore the river ecosystem. Average river flow of 28 m 3 /s, with a watershed drainage area of 588 km 2 Lower Pawtuxet River is prone to flooding, with sediments impacted by past industrial discharges. Sediments characterized as moderately to highly contaminated with numerous classes of organic compounds (e.g., PAHs, PCBs). Remedial clean-up of contaminated sediments up-river was completed in 2002. Sediment Traps • Deployed in locations where deposition occurs • Sinking particles are collected in deployed traps over a time scale similar to passive samplers • Following retrieval, particles are extracted and measured for contaminant concentrations •Measure dissolved organic contaminants by absorption into PE •Technique relies upon contaminant partitioning between the aqueous phase and the PE polymer •Samplers are deployed and allowed to equilibrate for approximately a month before retrieval, clean-up, and solvent extraction Accumulated contaminants in the PE (C PE ) are measured and passive sampler-water partition coefficients (K PE-water ) used to calculated dissolved concentrations (C water ) •Cheap and easy to use •Less interference from colloids and small particles makes for cleaner analytical sample •Less interference from colloids and small particles makes for cleaner analytical samples •Lower detection limits •Obtain a time-weighted average concentration rather than a “snap-shot” concentration at a particular time point Passive Samplers K C C water - PE PE water Particulate PAHs •Concentrations of individual PAHs decline downriver from Site 1- Site 3 (Figure 2) •Certain individual PAHs were much higher than others, suggesting past industrial use rather than pyrogenic sources such as combustion as being the origin. •Below the dam at Site 3, a time series of ΣPAH concentrations varied between 18 and 56 ug g -1 , showing no correspondence to river flow (Figure 3) •A total suspended solids (TSS) model is currently being constructed to determine the quantity of suspended particles at any given flow rate in the river. •This will permit accurate determination of particulate phase contaminant fluxes during our study period using sediment trap data. •This will also enable proper apportionment of contaminant fluxes between phases and provide a predictive capability for fluxes under a ranges of conditions Dissolved PAHs Individual PAHs in the dissolved phase showed the same behavior as the particulate phase, with concentrations declining downriver from Sites 1-3. For pre and post dam deployments, most of the differences in individual PAH concentrations were not significant (p> 0.05) (Figure 4) •Post removal deployment 1 observed a steep decline in many high molecular weight PAHs which continued to drop in post removal deployment 2 (Figure 4) •At Site 3, below the dam site, concentrations show a sustained decline for most of the PAHs measured in this study (Figure 5) Next Steps • Proceed with fourth and potentially final deployment • Finish data analysis of sediment core taken from site 2 to reconstruct temporal record of contamination • Analyze data for PCBs and other contaminants • Measure surficial sediments within river at key locations Figure 1. Study area Figure 2. Particulate PAH concentrations before (a) and after (b) dam removal Figure 4. Dissolved PAH concentrations before (a) and after (b) dam removal Figure 5. Dissolved PAH concentrations of each deployment at Site 3 Figure 3. Particulate total PAH concentrations at Site 3 in relation to water flow Contact: Mark Cantwell [email protected] v Figure 6. Total suspended solids at Site 3 0 5 10 15 20 25 30 0 200 400 600 800 1000 1200 f(x) = 30.9206726546651 x + 285.659097085443 R² = 0.752324438968913 Total Suspended Solids mg/L Flow (cfs) 2,6 d imethylnapt halene 2,3,5 trimethyln apthal en e acenapthyle ne acena pthene fluorene phe nanthrene ant hr acene flu oranthen e pyr ene ben z[ a]anth racen e chrys ene benzo[b]+[k]fluor anthene benzo [e]pyr ene benzo[a]pyr ene per y l ene ind en o[1,2,3,c,d]pyren e dib en z[a,h]anthracene ben zo[g,h,i ]perylene 1 10 100 August 2011 Deployment Site 1 Site 2 Site 3 Concentration ng L-1 2,6 d imethylnapt halene 2,3,5 trimethyln apthal en e acenapthyle ne acena pthene fluorene phe nanthrene ant hr acene flu oranthen e pyr ene ben z[ a]anth racen e chrys ene benzo[b]+[k]fluor anthene benzo [e]pyr ene benzo[a]pyr ene per y l ene ind en o[1,2,3,c,d]pyren e dib en z[a,h]anthracene ben zo[g,h,i ]perylene 1 10 100 March 2012 Deployment Site 1 Site 2 Site 3 Concentration ng L--1 0.01 0.1 1 10 100 August 2011 Deployment Site 1 Site 2 Site 3 µg g-1 Nap th alene 1-m ethylnapthale ne 2-m ethylnap thalen e 2,6 di methylnapt halen e 2,3 ,5 tri m ethylnapthalene acenapthale ne acena pthene flu orene phe n a nthren e ant hr acene flu or anthen e pyrene ben z[a]anth racene chr ys ene benzo[b]+[k]fluo ranthene benzo [e]pyr ene ben z o [a]pyr ene peryl ene ind en o[1,2, 3-cd-]pyren e dib enz[a,h]anthracene ben zo [g,h,i]pery lene 0.01 0.1 1 10 100 March 2012 Deployment Site 1 Site 2 Site 3 µg g-1 7/26/2011 9/14/2011 11/3/2011 12/23/2011 2/11/2012 4/1/2012 5/21/2012 0 10 20 30 40 50 60 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Sediment Traps And Flow Data PAH Flow (cfs) PAH ng g-1 F l o w ( C F S ) Sediment Traps Passive Samplers 0.4 4 40 Site 3 (Below Dam) Deployment 1: pre-dam Deployment 2: post-dam Deployment 3: post-dam ng L-1

Upload: jocelin-bates

Post on 04-Jan-2016

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Assessing changes in contaminant fluxes following removal of a dam in the Pawtuxet River Results and Discussion Methods and Approach Passive samplers (polyethylene;

Assessing changes in contaminant fluxes following removal of a dam in the Pawtuxet River

Results and Discussion

Methods and ApproachPassive samplers (polyethylene; PE) and sediment traps were deployed at three sites in the river to establish contaminant fluxes in the dissolved and particulate phases prior to dam removal (Figure 1). Dam removal commenced on August 10, 2011 and was completed by late August 2011. Following removal of the impoundment, sediments traps have been continuously deployed to monitor changes in the flux of contaminants over time. Passive samplers have been deployed at all three sites so far on the following dates:

- Pre Dam removal deployment July 9, 2011-August 9, 2011- Post Dam removal deployment 1: December 5, 2011-December 19, 2011*- Post Dam removal deployment 2: February 28, 2012-March 13, 2012 *Site 2 sampler lost

Mark G. Cantwell †, Monique M. Perron‡, Julia C. Sullivan◊, David R. Katz†, Robert M. Burgess†

†US EPA, ORD/NHEERL, Atlantic Ecology Division, Narragansett, RI, ‡ NRC/EPA, ◊ University of Rhode Island/EPA

Abstract Restoration of rivers and their associated ecosystems is a growing priority for government agencies (e.g., NOAA, USDA), as well as conservation organizations. Dam removal is a major component of many restoration projects credited with reintroducing fish species, improving water and habitat quality, and increasing recreation potential. Many proposed locations for restoration, however, have been impacted by past discharges of chemical pollutants resulting in contaminated sediment. As a result, the potential exists for release of sequestered contaminants following dam removal or other restoration activities. Few, if any, dam removal projects have studied the release of contaminants from the sediments following removal. In this study, we measured dissolved and particulate concentrations of polynuclear aromatic hydrocarbons (PAHs) before and after removal of an existing low head dam at several sites in the Pawtuxet River, an urbanized river in Cranston, RI. Preliminary results indicate that dissolved concentrations of PAHs decreased at one site above the dam location following removal, while concentrations remained unchanged below the dam at the mouth of the river which discharges to Narragansett Bay. Particulate concentrations of PAHs collected in sediment traps showed a decrease following dam removal at all sites within the river and at the river mouth. Results from this study will be used to evaluate methods under development to assess the short- and long-term impact of ecological restoration activities such as dam removal.

Introduction• Pawtuxet River had been dammed from 1870s or earlier, with the last impoundment constructed in 1924 of concrete. Located at the mouth of the river, this was a

low head dam approximately 170’ long, 5’ high.

• The Pawtuxet Falls dam was removed in early August, 2011 in order to improve fish passage and restore the river ecosystem.

• Average river flow of 28 m3/s, with a watershed drainage area of 588 km2

• Lower Pawtuxet River is prone to flooding, with sediments impacted by past industrial discharges.

• Sediments characterized as moderately to highly contaminated with numerous classes of organic compounds (e.g., PAHs, PCBs).

• Remedial clean-up of contaminated sediments up-river was completed in 2002.

Sediment Traps• Deployed in locations where deposition occurs

• Sinking particles are collected in deployed traps over a time scale similar to passive samplers

• Following retrieval, particles are extracted and measured for contaminant concentrations

•Measure dissolved organic contaminants by absorption into PE

• Technique relies upon contaminant partitioning between the aqueous phase and the PE polymer

• Samplers are deployed and allowed to equilibrate for approximately a month before retrieval, clean-up, and solvent extraction

• Accumulated contaminants in the PE (CPE) are measured and passive sampler-water partition coefficients (KPE-water) used to calculated dissolved concentrations (Cwater)

• Cheap and easy to use

• Less interference from colloids and small particles makes for cleaner analytical sample

• Less interference from colloids and small particles makes for cleaner analytical samples

• Lower detection limits

• Obtain a time-weighted average concentration rather than a “snap-shot” concentration at a particular time point

Passive Samplers

K

C C

water-PE

PEwater

Particulate PAHs• Concentrations of individual PAHs decline downriver from Site 1- Site 3 (Figure 2)

• Certain individual PAHs were much higher than others, suggesting past industrial use rather than pyrogenic sources such as combustion as being the origin.

• Below the dam at Site 3, a time series of ΣPAH concentrations varied between 18 and 56 ug g-1, showing no correspondence to river flow (Figure 3)

• A total suspended solids (TSS) model is currently being constructed to determine the quantity of suspended particles at any given flow rate in the river.

• This will permit accurate determination of particulate phase contaminant fluxes during our study period using sediment trap data.

• This will also enable proper apportionment of contaminant fluxes between phases and provide a predictive capability for fluxes under a ranges of conditions

Dissolved PAHs• Individual PAHs in the dissolved phase showed the same behavior as the particulate phase, with concentrations declining downriver from Sites 1-3. For pre and post

dam deployments, most of the differences in individual PAH concentrations were not significant (p> 0.05) (Figure 4)

• Post removal deployment 1 observed a steep decline in many high molecular weight PAHs which continued to drop in post removal deployment 2 (Figure 4)

• At Site 3, below the dam site, concentrations show a sustained decline for most of the PAHs measured in this study (Figure 5)

Next Steps• Proceed with fourth and potentially final deployment

• Finish data analysis of sediment core taken from site 2 to reconstruct temporal record of contamination

• Analyze data for PCBs and other contaminants

• Measure surficial sediments within river at key locations

• Develop flux models for particulate and dissolved phase contaminants

Figure 1. Study area

Figure 2. Particulate PAH concentrations before (a) and after (b) dam removal

Figure 4. Dissolved PAH concentrations before (a) and after (b) dam removal

Figure 5. Dissolved PAH concentrations of each deployment at Site 3

Figure 3. Particulate total PAH concentrations at Site 3 in relation to water flow

Contact: Mark [email protected]

Figure 6. Total suspended solids at Site 3

0 5 10 15 20 25 300

200

400

600

800

1000

1200

f(x) = 30.9206726546651 x + 285.659097085443R² = 0.752324438968913

Total Suspended Solids

mg/L

Flow

(cfs

)

2,6 dimeth

ylnap

thale

ne

2,3,5 trim

ethyln

apth

alene

acenap

thyle

ne

acenap

thene

fluorene

phenanth

rene

anth

racene

fluoranth

ene

pyrene

benz[a]an

thrac

ene

chrys

ene

benzo[b]+[

k]fluoran

thene

benzo[e]pyre

ne

benzo[a]

pyrene

perylene

indeno[1,2,3,c,d]pyre

ne

dibenz[a,h]an

thrac

ene

benzo[g,

h,i]peryl

ene1

10

100

August 2011 Deployment

Site 1Site 2Site 3

Conc

entr

ation

ng

L-1

2,6 dimeth

ylnap

thale

ne

2,3,5 trim

ethyln

apth

alene

acenap

thyle

ne

acenap

thene

fluorene

phenanth

rene

anth

racene

fluoranth

ene

pyrene

benz[a]an

thrac

ene

chrys

ene

benzo[b]+[

k]fluoran

thene

benzo[e]pyre

ne

benzo[a]

pyrene

perylene

indeno[1,2,3,c,d]pyre

ne

dibenz[a,h]an

thrac

ene

benzo[g,

h,i]peryl

ene1

10

100

March 2012 Deployment

Site 1Site 2Site 3

Conc

entr

ation

ng

L--1

Napth

alene

1-meth

ylnap

thale

ne

2-meth

ylnap

thale

ne

2,6 di meth

ylnap

thale

ne

2,3,5 tri m

ethyln

apth

a...

acenap

thale

ne

acenap

thene

fluorene

phenanth

rene

anth

racene

fluoranth

ene

pyrene

benz[a]an

thrac

ene

chrys

ene

benzo[b]+[

k]fluoran

thene

benzo[e]pyre

ne

benzo[a]

pyrene

perylene

indeno[1,2,3-cd-]p

yrene

dibenz[a,h]an

thrac

ene

benzo[g,

h,i]peryl

ene0.01

0.1

1

10

100 August 2011 Deployment

Site 1Site 2Site 3µg

g-1

Napth

alene

1-meth

ylnap

thale

ne

2-meth

ylnap

thale

ne

2,6 di meth

ylnap

thale

ne

2,3,5 tri m

ethyln

apth

alene

acenap

thale

ne

acenap

thene

fluorene

phenanth

rene

anth

racene

fluoranth

ene

pyrene

benz[a]an

thrac

ene

chrys

ene

benzo[b]+[

k]fluoran

thene

benzo[e]pyre

ne

benzo[a]

pyrene

perylene

indeno[1,2,3-cd-]p

yrene

dibenz[a,h]an

thrac

ene

benzo[g,

h,i]peryl

ene0.01

0.1

1

10

100

March 2012 Deployment

Site 1Site 2Site 3

µg g

-1

7/26/2011 9/14/2011 11/3/2011 12/23/2011 2/11/2012 4/1/2012 5/21/20120

10

20

30

40

50

60

0

200

400

600

800

1000

1200

1400

1600

1800

2000Sediment Traps And Flow Data

∑ PAH

Flow (cfs)

PAH

ng g

-1 Flow (CFS)

Sediment Traps Passive Samplers

2,6 dimeth

ylnap

thale

ne

2,3,5 trim

ethyln

apth

alene

acenap

thyle

ne

acenap

thene

fluorene

phenanth

rene

anth

racene

fluoranth

ene

pyrene

benz[a]an

thrac

ene

chrys

ene

benzo[b]+[

k]fluoran

thene

benzo[e]pyre

ne

benzo[a]

pyrene

perylene

indeno[1,2,3,c,d]pyre

ne

dibenz[a,h]an

thrac

ene

benzo[g,

h,i]peryl

ene0.4

4

40Site 3 (Below Dam)

Deployment 1: pre-damDeployment 2: post-damDeployment 3: post-dam

ng L-

1