aspen - site observation & proposal

87
ASPEN INFRASTRUCTURES, ANANTAPUR Industrial Internship Programme VIGNESH S BTG-12-037 Internship Period Jan 23 Mar 23/2016 Office Hours 9.00 A.M 6.00 P.M Site Hours 7.00 A.M 7.00 P.M Regd. Office: Godrej Millennium, 5th Floor, 9, Koregaon Park Road, Pune 411 001. Maharashtra, India CIN: U45202PN1998PLC016516 Tel: +91.20.66278000/ 8011 [email protected] www.aspensez.com

Upload: vignesh-sekaran

Post on 20-Feb-2017

213 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: ASPEN - Site Observation & Proposal

ASPEN INFRASTRUCTURES, ANANTAPUR

Industrial Internship Programme

VIGNESH S

BTG-12-037

Internship Period Jan 23 – Mar 23/2016

Office Hours 9.00 A.M – 6.00 P.M

Site Hours 7.00 A.M – 7.00 P.M

Regd. Office: Godrej Millennium, 5th Floor, 9, Koregaon Park Road, Pune – 411 001. Maharashtra, India

CIN: U45202PN1998PLC016516 Tel: +91.20.66278000/ 8011 [email protected] www.aspensez.com

Page 2: ASPEN - Site Observation & Proposal

AGRICULTURAL ENGINEERING COLLEGE & RESEARCH INSTITUTE

TAMIL NADU AGRICULTURAL UNIVERSITY

COIMBATORE – 641 003

INDUSTRIAL INTERNSHIP PROGRAMME

REPORT WORK

2016

WORK DONE BY : S. VIGNESH BTG-12-037

GUIDED BY : Mr. PRADEEP V. PATIL Sr. Manager- ASPEN

COURSE TEACHERS : Dr. ANGEESWARAN, Assis. Prof- BIO ENERGY

Dr. R. MAHENDIRAN, Assis. Prof- BIO ENERGY

Dr. BALAJI KANNAN, Assis. Prof- RS & GIS

Page 3: ASPEN - Site Observation & Proposal

AGRICULTURAL ENGINEERING COLLEGE & RESEARCH INSTITUTE

TAMIL NADU AGRICULTURAL UNIVERSITY

COIMBATORE – 641 003

CERTIFICATE

This is to certify the report entitled “INDUSTRIAL INTERNSHIP PROGRAMME”

submitted in part fulfilment of the requirements for the Award of the degree BACHELOR OF

TECHNOLOGY (Energy and Environmental Engineering) to Agricultural Engineering

College and Research Institute, Tamil Nadu Agricultural University, Coimbatore is a record of

Bonafide Internship work carried out by S. Vignesh, BTG-12-037 under my supervision and

guidance.

Place : Anantapur

Period : Jan 23 – Mar 23

Approved by External Examiner

MR. PRADEEP V. PATIL

Sr. Manager – Projects

Aspen Infrastructures

DR. ANGEESWARAN

Assis. Prof – Bio Energy

DR. MAHENDRAN

Assis. Prof – Bio Energy

DR. BALAJI KANNAN

Assis. Prof – RS & GIS

Page 4: ASPEN - Site Observation & Proposal

ACKNOWLEDGEMENT

I take this chance with massive pleasure to thank countless persons after the receipt of

immense support and guidance during the period of internship. I herewith place the

acknowledgement with cheers and gratefulness.

Mr. Thamarai Selvam Sr. Civil Engineer – ASPEN

Mr. Chandra Kanth Admin – ASPEN

Mr. Ragul Waghmare Civil Engineer – SUZLON

Mr. Praveen Consultant – TUV

Mr. Shankar Consultant – TUV

Mr. Subbarao HR – ASPEN, ATP

Mr. Amish Bhatt HR – SUZLON, Pune

Mr. Eswar Electrical Engineer – ASPEN

Mr. Harsha vardhan Electrical Engineer – ASPEN

Mr. Iyyappan Accountant – ASPEN

Mr. Amal raj Electrical Engineer – SUZLON

Mr. Pranav Sr. Manager – SUZLON SOLAR

Mr. Dharani dharan Sr. Engineer – T & R

Mr. Ganesan Sr. Electrical Engineer – KSE Constructions

Mr. Gomathi Nayagam Sr. Electrical Engineer – SUZLON

Mr. Prasad Engineer- KSE Constructions

Mr. Madhubabu Mechanical Engineer – SUZLON

Mr. Prabagaran Technician – VOLTAG

Page 5: ASPEN - Site Observation & Proposal

My sincere and whole hearted thanks to our internship co-ordinator Dr. BALAJI

KANNAN, Assistant Professor, Dept. of RS & GIS for giving me his untiring guidance. I got the

Internship at ASPEN by his continuous effort. Not only me, lot of students got Good Internships

by him.

I would like to thank to Dr. C. DIVAKER DURAIRAJ, Dean, Agricultural Engineering

College and Research Institute Coimbatore for his fruitful criticism. I’m happy to thank Dr. R.

MAHENDRAN and Dr. ANGEESWARAN, Assistant Professors of Bio Energy.

I express my thanks to Dr. A. RAVIRAJ, Professor, Department of Water Technology

Centre for his moral support and tireless encouragement in finishing my internship programme.

We (Me, Vishnu Ram D, Mohamed Asif. M) also thank Mr. PRADEEP V. PATIL, Sr.

Manager - Projects, ASPEN for providing us internship training, accommodation, food and

answering our queries patiently. We defray our sincere thanks to our seniors and all staff members

of SUZLON, ASPEN and ILLUMINE I for their timely help rendered in each step of the internship.

- Vignesh S

Student of final year B. Tech Energy and Environmental Engineering (2012-16)

Page 6: ASPEN - Site Observation & Proposal

EXECUTIVE SUMMARY

INDUSTRIAL INTERNSHIP PROGRAMME - ASPEN INFRASTRUCTURES

By

Vignesh S

BTG-12-037

Degree : B. Tech – Energy and Environmental Engineering – 4th Year

Supervisor : MR. Pradeep V. Patil

Sr. Manager – Projects

Aspen Infrastructures, Anantapur

E-Mail – [email protected]

Ph.no – 7799916803

2016

Since Jan 23rd 2016, I have been doing the Industrial Internship Programme at ASPEN

INFRASTRUCTURES, Anantapur, Andhra Pradesh. Mainly ASPEN is working for

SUZLON. My objective on internship is that Learning, Hands-on Training, Participating. From

this internship, I have learned from them, and Participated in their projects, and Prepared the

proposal documentation for them. Then Every student should have taken the Practice of their

subject core after completion of education. For Example, Doctors should have taken the

Medical Practice after their education. This practice makes them as a Professionals. Similarly,

Engineers have to practice the engineering in the construction sites and should have discussed

with the professionals. This Internship opportunity gave me an engineering practice to me.

ASPEN is doing the construction works and Power Evacuation arrangements between the

substation and Wind turbines. These works mainly include Mechanical, Civil, Electrical,

Aerodynamics, and Communication Engineering. I have spent the first two months in ASPEN

Sites. From these schedules I have visited the lots of Project areas and Met technical people of

the sites. The Good discussion were going with us. In between these times, we have prepared

the Proposal documentation on Utility Scale Solar Photo-Voltaic (SPV) Power Plant – 1 MW

at Ellutla, Andhra Pradesh. Some amount of Power Evacuation capacity is in the Ellutla

Substation. Based on that Issue, we have prepared.

Page 7: ASPEN - Site Observation & Proposal

Based on my Internship working Schedule, I have listed my works below.

Jan 23 – Mar 23 Besides ASPEN, SUZLON Sites and

Proposal Documentation

Based on my Internship Experience, I have established the Methodology as two sections.

1. Site Observation

2. Proposal for Utility Scale Solar Photo-Voltaic (SPV) Power Plant – 1 MW at Ellutla

Page 8: ASPEN - Site Observation & Proposal

CONTENTS

CHAPTER

NO. TITLE

PAGE

NO.

I INTRODUCTION 1

II

METHODOLOGY WITH RESULTS

A. Site Observation

B. Proposal for Utility Scale Solar Photo-Voltaic (SPV) Power

Plant – 1 MW at Ellutla, Andhra Pradesh

III GALLERY

IV CONCLUSION

V REFERENCE

Page 9: ASPEN - Site Observation & Proposal

CHAPTER 1

INTRODUCTION - ABOUT COMPANY

Established in the year 1998, the company is a Tanti Holding Company and is closely

associated to the US$ 5 Billion Suzlon Group of Companies, the global Wind Energy major.

So that, ASPEN is one of the company of Suzlon Groups. Their scope of operations includes

development of Manufacturing facilities, Commercial spaces, institutes and large industrial

infrastructure projects. Formerly known as Synefra Engineering and Construction. They

provide solutions for Special Economic Zone (SEZ) development requirements such as land

acquisition, Government permissions and direct clearances from any infrastructure sectors and

pioneering in engineering procurement and construction for renewable energy sectors. Aspen

Infrastructure provides marketing of SEZ lands along with the operational maintenance of the

3 SEZs’ through related facility management services. The company is operating successfully

for over 6 years now with India & MNC unit holders operating smoothly for all its 3 SEZs. A

dedicated team comprising of technical and administrative staff is available 24 X 7 for all

common services and utility maintenance. Aspen Infrastructures Ltd. is ISO 9001:2008, ISO

14001: 2004 certified along with OHSAS 18001:2007 certification for safety.

At present, Aspen is doing the projects only for wind division. Later, they will be in solar field.

They are the Pioneer in Engineering, Procurement & Commissioning of infrastructures for

renewable energy

1.1 Renewable Sector in ASPEN

They are the ‘EPC Division’ of SUZLON GROUPS with specific focus on renewable energy.

The Company is one of the leading organizations providing solution in development of

infrastructure for wind farms across geography. Our division primarily focuses on undertaking

infrastructure projects across the spectrum of needs of Wind and Solar industries in varied

regime. They develop infrastructure facilities for erection, installation and commissioning of

wind turbines, development of composite installation of facilities for wind farms and

construction of power evacuation facilities at wind farm sites.

Them in- house team is a group of qualified professionals who bring in rich and diverse skill

sets and experience from the industry. The team has the capability of single- handily

establishing the entire suite of wind power infrastructure, including site development, Electrical

& Civil works, Construction & Erection and Commissioning.

Page 10: ASPEN - Site Observation & Proposal

1.2 Services on “Renewable Sector”

Micrositing for wind turbines

Private, Forest and Revenue land procurement

Design and development of wind farm sites, including development of infrastructure and

power evacuation arrangements

Construction of approach roads and internal roads at sites

Laying of Extra High Voltage Power Transmission Lines

Laying of internal Transmission lines and Sub- stations

Construction of WTG Foundations and associated civil works

Erection and Commissioning of wind turbines

Design and construction of offices and monitoring facilities

Complete logistics management for turnkey projects on EPC basis

1.3 Project Highlights in “Land Sector”

150 projects delivered

1,300 acres of SEZ development

Over 3 million sq. ft. of industrial spaces

Over 1.5 million sq. ft. of office spaces, campuses, R&D, training and social centres.

Aspen has developed three engineering SEZs at:

Waghodia, near Vadodara – Gujarat

Padubidri, near Mangalore – Karnataka

Karumathamapatti, near Coimbatore – Tamil Nadu

They focus on marketing and maintenance of the three SEZs and the related facility

management services. All three SEZs are fully operational with ready-to-construct engineering

manufacturing facilities. Aspen’s sales team offers customized proficient solutions for

potential manufacturers with the competitive edge of being in a SEZ.

1.4 Project Highlights in “Renewable Sector”

45 major EHV Sub Stations with capacity of 3900 MW established PAN India

More than 650 kms of Transmission power lines laid

More than 2200 Wind Turbines installed

Infrastructure development for more than 25 wind farms across India on turnkey basis

Milestone achieved in 2006 by laying 695 WTG Foundations

World’s largest wind park established in Dhule, Maharashtra

Page 11: ASPEN - Site Observation & Proposal

CHAPTER 2

METHODOLOGY

(With Results)

Previously I stated that ASPEN is doing the projects for SUZLON. And

these works mainly comprises Design and development of wind farm sites, including

development of infrastructure and power evacuation arrangements, Construction of approach

roads and internal roads at sites, Laying of Extra High Voltage Power Transmission Lines,

laying of internal Transmission lines and Sub- stations, Construction of WTG Foundations and

associated civil works, Erection and Commissioning of wind turbines. So that, these works are

wholly civil and electrical. First two months I have spent the time with Project places of

ASPEN & SUZLON. We (Me, Vishnu Ram D, Mohamed Asif M) have observed the lot of

civil and electrical works in the project sites and Met some technical people. They have

explained about core values of engineering in the substation and wind turbine erection sites.

From this visits, we have an idea to make the “Site Observation” section in the methodology.

During the visit, we have noticed that Ellutla’s Phase-I Pooling Substation has an additional

evacuation capacity of nearly 5 MW. Then for the Solar Photovoltaic Power Plant, land is one

of the major investment. But in this case, 5 acres of unused land which is owned by Suzlon.

Proposed Site is situated very close to the Ellutla’s Phase-I Pooling Substation. Thus, there is

no need of construction of a dedicated Substation and the transmission loss will be negligible.

So that, we have prepared the Proposal documentation for that. This proposal documentation

occupied the portion of 2.B in methodology.

This Proposal documentation gave us the opportunity to do work with ILLUMINE I – Solar

Designing Industries, Chennai. This occasion is offered by Solar Head of SUZLON Mr.

Pranay. This industry wants to do Solar PV Residential installation in and around Tamil Nadu.

So, they have given the Research topic which is entitled as “Solar EPC Markets and Policies”.

This is the Installation together with Market Research Topic. So that, this work given the lot

of company contacts and technical discussions to me. From the result of mine, they will do the

SPV Residential Projects in and around Chennai. So that, this act brought me the sincere touch

to me. I will work along with honest. 2.C is the 3rd section Methodology which is as “Solar

EPC Markets and Policies”

Page 12: ASPEN - Site Observation & Proposal

In our internship period, we have visited the following project places;

We were studying the each of following described topic deeply and we were rewinding our

subjects like Wind energy conversion technologies besides Surveying and levelling,

Electricals. So, few days of our internship period, we were studying the basic things related to

EPC in office hours.

Design and development of sites including infrastructure, power evacuation arrangements.

Laying of extra high voltage power lines.

Laying of internal power lines and sub-stations.

Complete logistics management for turnkey projects on EPC Basis.

Then they sent us to site work in their wind projects Near Anantapur (35 Km) – Ellutla with

safety helmets and shoes. Already, they have installed around 830 MW in Anantapur district.

In Ellutla, we are installing the 44.1 MW. Ellutla is a complete mountainous place (non-terrain,

rocky area). Installing 21 wind turbines of 2.1 Mw capacity. Substation construction process,

soil testing process and foundation process are going on right now. In addition, they are also

doing few projects in other places of Andhra Pradesh. They may send us to that places for

training purpose in future and we are trying to propose some projects to them.

In our second week, we were in Ellutla site and they educated the met mast and surveying

technique in windy sites theoretically. Generally, met mast is required to estimate the wind

potential in the particular site for 1 year. Actually windy site has been declared by the Wind

Resource Assessment (WRA) team of Suzlon. For that, we have studied about the substation

and its process, Wind rose diagrams, Theoretical calculation in the wind turbines.

Then, we went to Parnapalli site (from Anantapur – 55 Km) which is also the hilly area. We

trekked 400m in Parnapalli hills. At this site, we had work with forestry department officers of

Andhra Pradesh to site marking. WRA team gave the co-ordinates of met mast site to us. Then

S. No Project Places Company

1 Ellutla, Anantapur ASPEN

2 Uravakonda, Anantapur SUZLON

3 Beluguppa, Anantapur ASPEN & SUZLON

2. A. Site Observation

Page 13: ASPEN - Site Observation & Proposal

we found that place using GPS. Marked 50 m distance from centre point to all four directions.

That distance will be useful for constructing the met mast and also estimate the total biomass

in & around the 50 m distance area. Then, WTG Foundation process is going on. First time

ASPEN is doing the Suzlon’s WTG Foundation works (0.65 Crore worth). On foundation

process, we have cultivated about PCC (Plain Cement-Concrete), RCC (Reinforced Cement-

Concrete), Foundation and its type, width and Depth.

In Ellutla site, we asked to our seniors for getting substation layout. So that, we are taking

survey about substation for find out the working progress. Then we heard about the components

of SS such as Circuit breaker (CB) with Isolator, Potential Transformer (PT), Current

Transformer (CT), Power Transformer (PTR), Bus bar, RYB Lines, Transmission tower and

its types. Then we have collected and studied the following content of materials

Substation

A substation is a part of an electrical generation, transmission, and distribution system.

Substations transform voltage from high to low, or the reverse, or perform any of several other

important functions. Between the generating station and consumer, electric power may flow

through several substations at different voltage levels. It may be owned and operated by an

electrical utility / Large industrial / Commercial customer / Government. Generally, substations

are unattended, relying on SCADA for remote supervision and control.

Elements of Substation

Generally, have switching, protection and control equipment, and transformers.

In a large substation, circuit breakers are used to interrupt any short circuits or overload

currents that may occur on the network. Smaller distribution stations may use recloser

circuit breakers or fuses for protection of distribution circuits.

Substations themselves do not usually have generators, although a power plant may

have a substation nearby. Other devices such as capacitors and voltage regulators may

also be located at a substation.

Where a substation has a metallic fence, it must be properly grounded to protect people

from high voltages that may occur during a fault in the network. Earth faults at a

substation can cause a ground potential rise. Currents flowing in the Earth's surface

during a fault can cause metal objects to have a significantly different voltage than the

ground under a person's feet; this touch potential presents a hazard of electrocution.

Page 14: ASPEN - Site Observation & Proposal

A: Primary power lines' side and

B: Secondary power lines' side

1. Primary power lines 2. Ground wire 3. Overhead lines 4. Transformer for measurement of

electric voltage 5. Disconnect switch 6. Circuit breaker 7. Current transformer 8. Lightning

arrester 9. Main transformer 10. Control building 11. Security fence 12. Secondary power lines

Types of substations

Transmission substation

A transmission substation connects two or more transmission lines. The simplest case

is where all transmission lines have the same voltage. In such cases, substation contains

high-voltage switches that allow lines to be connected or isolated for fault clearance or

maintenance.

A transmission station may have transformers to convert between two transmission

voltages, voltage control/power factor correction devices such as capacitors, reactors or

static VAR compensators and equipment such as phase shifting transformers to control

power flow between two adjacent power systems.

Distribution substation

A distribution substation transfers power from the transmission system to the

distribution system of an area. It is uneconomical to directly connect electricity

consumers to the main transmission network, unless they use large amounts of power,

so the distribution station reduces voltage to a level suitable for local distribution.

The input for a distribution substation is typically at least two transmission or sub

transmission lines. Input voltage may be, for example, 115 kV, or whatever is common

in the area. The output is a number of feeders. Distribution voltages are typically

medium voltage, between 2.4 kV and 33 kV depending on the size of the area served

and the practices of the local utility. The feeders run along streets overhead (or

underground, in some cases) and power the distribution transformers at or near the

customer premises.

Collector substation

In distributed generation projects such as a wind farm, a collector substation may be

required. It resembles a distribution substation although power flow is in the opposite

direction, from many wind turbines up into the transmission grid. Usually for economy

of construction the collector system operates around 35 kV, and the collector substation

steps up voltage to a transmission voltage for the grid. The collector substation can also

Page 15: ASPEN - Site Observation & Proposal

provide power factor correction if it is needed, metering and control of the wind farm.

In some special cases a collector substation can also contain an HVDC converter

station.

Converter substations

Converter substations may be associated with HVDC converter plants, traction current,

or interconnected non-synchronous networks. These stations contain power electronic

devices to change the frequency of current, or else convert from alternating to direct

current or the reverse. Formerly rotary converters changed frequency to interconnect

two systems; such substations today are rare.

Switching Substation

A switching substation is a substation without transformers and operating only at a

single voltage level. Switching substations are sometimes used as collector and

distribution stations. Sometimes they are used for switching the current to back-up lines

or for parallelizing circuits in case of failure. An example is the switching stations for

the HVDC Inga–Shaba transmission line.

A switching substation may also be known as a switchyard, and these are commonly

located directly adjacent to or nearby a power station. In this case the generators from

the power station supply their power into the yard onto the Generator Bus on one side

of the yard, and the transmission lines take their power from a Feeder Bus on the other

side of the yard.

BUSBAR

BUSBAR (or bus, for short) – is a term we use for a main bar or conductor carrying an

electric current to which many connections may be made.

Buses are merely convenient means of connecting switches and other equipment into

various arrangements. The usual arrangement of connections in most substations permit

working on almost any piece of equipment without interruption to incoming or outgoing

feeders. In the switchyard or substation, buses are open to the air. Aluminium or copper

Page 16: ASPEN - Site Observation & Proposal

conductors supported on porcelain insulators, carry the electric energy from point to

point.

DISCONNECTS

DISCONNECT – is an easily removed piece of the actual conductor of a circuit. The

purpose of disconnects is to isolate equipment. Disconnects are not used to interrupt

circuits; they are no-load devices. A typical use of disconnects is to isolate a circuit

breaker by installing one disconnect on either side of the circuit breaker (in series with

the breaker). Operation of disconnects is one of the most important and responsible jobs

of a power plant operator. One error in isolation of equipment, or the accidental

grounding of line equipment, can be a fatal mistake.

CIRCUIT BREAKER

CIRCUIT BREAKER – is used to interrupt circuits while current is flowing through

them. The making and breaking of contacts in an Oil type circuit breaker are done under

oil, this oil serves to quench the arc when the circuit is opened. The operation of the

breaker is very rapid when opening. As with the transformer, the high voltage

connections are made through bushings. Circuit breakers of this type are usually

arranged for remote electrical control from a suitably located switchboard.

Some recently developed circuit breakers have no oil, but put out the arc by a blast of

compressed air; these are called air circuit breakers. Another type encloses the contacts

in a vacuum or a gas (sulphur hexafluoride, SF6) which tends to self-maintain the arc.

CURRENT TRANSFORMER

CURRENT TRANSFORMER – Current transformer are used with ammeters, watt

meters, power-factor meters, watt-hour meters, compensators, protective and regulating

relays and the trip coil of circuit breakers. One current transformer can be used to

operate several instruments, provided that the combined burden does not exceed that

for which the transformer is designed and compensated. The current transformer is

connected directly in series with the line.

VOLTAGE TRANSFORMER

VOLTAGE TRANSFORMER – also known as potential transformer, are used with

volt-meters, watt meters, watt-hour meters, power-factor meters, frequency meters,

synchro scopes and synchronizing apparatus, protective and regulating relays and the

no-voltage and over-voltage trip coils of automatic circuit breakers. One transformer

Page 17: ASPEN - Site Observation & Proposal

can be used for a number of instruments at the same time if the total current taken by

the instrument does not exceed that for which the transformer is designed and

compensated. The ordinary voltage transformer is connected across the line, and the

magnetic flux in the core depends upon the primary voltage

EARTHING SWITCH

EARTHING SWITCH – also known as ground disconnect, which used to connect the

equipment to a grid of electrical conductors buried in the earth on the station property.

It is intended to protect people working on the grounded equipment. It does this by

completing a circuit path, thereby reducing the voltage difference between the

equipment and its surroundings. For safety reasons, it is important that ground

disconnects and all associated connections have good contact and low resistance. It is

also important that the protective ground not be accidentally remove, that is why all the

earthing switches, disconnect switches and circuit breakers are all interlocked to each

other and proper/correct sequencing must be followed.

SURGE ARRESTOR

SURGE ARRESTOR – are devices used to provide the necessary path to ground for

such surges, yet prevent any power current from following the surge.

OVERHEAD GROUND WIRE – by a ground wire is meant a wire, generally of steel,

supported from the top of transmission-line towers and solidly grounded at each tower.

It is considered a preventive device, but it does not entirely prevent the formation of

travelling waves on a line. Furthermore, those lines which are not equipped with ground

wires will be subjected to disturbances which produce surges that must be allowed to

escaped to ground, or the apparatus connected to the line must be strong enough to

reflect or absorb these surges until they are entirely damped out.

We were downloading the wind and solar data of Anantapur from NREL (National Renewable

Energy Laboratory) website for preparing the WindRose diagram of Anantapur. But, elevation

of the wind speed is not provided. We prepared that diagram for four latlong around the

Anantapur city. We saw all installation points of Ellutla and Knew about soil testing

procedures. And we were preparing the WindRose diagram of Ellutla for reference purpose.

Then we were in another site such as Uravakonda, Beluguppa. First we were in Uravakonda

for seeing the commissioned wind turbine. Met Mr. Amal raj and Mr. Ramakrishnan Who are

Page 18: ASPEN - Site Observation & Proposal

the employees of Suzlon. They explained neatly about single line diagram of wind turbine

plant, Stringing lines of transmission, Power evacuation arrangements. In Uravakonda totally

75 WTG were installed. But, only 64 is running. Another 11 is in construction process. Each

2.1 MW WTG which is the S97 Model (S-Suzlon)

The technologically advanced S97 wind turbine leverages the proven reliability of Suzlon’s

most successful 2.1 MW technology and enhances its performance to create a wind-power

solution specifically for moderate to low wind regimes prevalent in emerging markets such as

India.

They explained about control panel, Power panel, DFIG Panel, Cooling Panel in WTG. Next

day we were in Beluguppa. In that place also got 200 MW Project. So, WTG Erection works

starts and mainly substation construction, Power evacuation arrangements also goes well. Met

Mr. Eswar and Mr. Deepak who are the employees of Aspen. They explained about power

evacuation arrangements and 200 MVA SS. Then we met Mr. Ganesan and Mr. Jayaraj who

are working in KSE Constructions. They explained about basic things in the electrical

construction and WTG Erection. Then we went to Uravakonda 400/220 kV SS. We knew about

the A, B, C, D, Z, and Suspension, Tension tower types in power evacuation arrangements

In there, we have taken the overall process of finished works in the substation.

Beluguppa SS is 33/220 kV. Capacity of the SS is 100 MVA. We Met Mr. Ganesan and Mr.

Prasad who are the senior project managers of KSE Constructions. They have 35 years of

experience on substation construction. They explained the general electrical concepts in the

substation. Knew the behind works involved in the SS. Met Mr. Dharanidharan who is working

in Transformers & Rectifiers. He is explained about the types of transformers, its parts and

working. We have seen the erection of transformers in Beluguppa SS. And also we have seen

the metmast nearby the substation, which is installed by the Suzlon. Knew the working progress

in the metmast installation. At Beluguppa WTG Erection site, we met Mr. Madhubabu who are

the In-charge of the Erection Site. Lively We have seen the Wind turbine foundations and

Mounting of the Nacelle and Blades on the tower by using the L400 Model Lifting Machine

(Hydra). It was the wonderful experience to see it. We heard about some of the balancing

calculations in the erection of the WTG. But, we didn’t see the Tower Erection at the site. We

have seen the inner parts of the machines. Then he explained about energy trading involved in

the Grid Culture. Knew about Energy Banking, Wheeling, Transmission and Distribution

Losses in the SS.

Page 19: ASPEN - Site Observation & Proposal

In Substation, we have seen the Main Busbar connection, Conductors and Insulators. Knew

about HT and LT cables used in the electrical world.

After visited the places of Ellutla, Uravakonda, Beluguppa, we have learned about Substation

and its inner components. We have seen lot of erections, foundations and construction

activities. Through these visits, we could communicate with the technical persons of the

electrical and civil engineering section. Knew some of testing procedures. Saw the Suzlon

WTG Erection, Commissioning.

Page 20: ASPEN - Site Observation & Proposal

2. B. Proposal Documentation

Page 21: ASPEN - Site Observation & Proposal

Disclaimer’s Note: This proposal contains prefeasibility information of Ellutla site such as

Solar potential, Design and Financial analysis of the power plant. Then we have been

collected the documentation about SPV power plants and it’s Engineering, Procurement,

Commissioning works and the reasons for the delays in EPC Sections, and Operating and

Maintenance services of the power plant.

Presented data for Ellutla here are NOT TAKEN from any copyright materials. For finding

out the detailed information of Ellutla, we have used the softwares like ArcGIS, PVsyst,

Google Earth and AutoCAD. The Meteorological data collected from Meteonorm 7.1

Version. NREL (National Renewable Energy Laboratory - US) website and Meteonorm 7.1,

NOAA (National Oceanic and Atmospheric Administration) database which are free over

the internet. Designing of PV system is totally based on the PVsyst software, which is widely

used by all solar companies.

Page 22: ASPEN - Site Observation & Proposal

Table of Contents

Chapter. No Chapter Title Page No

1 Introduction 6

2 Project Details 7

3 Solar Potential of Ellutla 10

4 Design of the plant 18

5 Angle of Installation 26

6 Financial Analysis 33

7 Benchmark of the plant – CERC 36

8 Timeline of the project 41

9 Operation and Maintenance of the plant 43

10 EPC of the plant 45

11 Conclusion 49

Page 23: ASPEN - Site Observation & Proposal

Glossary

Abbreviations Details

DC Direct Current

AC Alternate Current

CERC Central Electricity Regulatory Commission

IEGC Indian Electricity Grid Code

SPV Solar Photovoltaic

I – V Current – Voltage

kVA Kilo Volt Ampere

kWh Kilo Watt Hour

PPA Power Purchase Agreement

MOU Memorandum of Understanding

MU Million Units

MW Mega Watt

MNRE Ministry of New & Renewable Energy, GOI

APSLDC Andhra Pradesh State Load Dispatch Centre

APTRANSCO Andhra Pradesh Power Transmission Corporation Limited

APGENCO Andhra Pradesh Power Generation Corporation Limited

NREDCAP New and Renewable Energy Development Corporation of Andhra Pradesh

Limited

VMPP Maximum Power Point Voltage

IMPP Maximum Power Point Current

VOC Open Circuit Voltage

ISC Short Circuit Current

WP Watt Peak

PM Maximum Power

JNNSM Jawaharlal Nehru National Solar Mission

Page 24: ASPEN - Site Observation & Proposal

GO Government Order

REC Renewable Energy Certification

OMS Operating and maintenance Services

GHI Global Horizontal Irradiation

DNI Direct Normal Irradiation

NOAA National Oceanic and Atmospheric Administration, US Gov.

PV Photo Voltaic

PCU Power Control/Conditioning Unit

IP Ingress Protection

Page 25: ASPEN - Site Observation & Proposal

Chapter 1

Introduction

Installing and successfully operating a Solar Photovoltaic (SPV) power plant will deliver a

steady and continuous electricity of nearly 6 hours/day (in case of the proposed site).

Moreover, overall expenditure on power production will be lowered as the solar power

production is cheaper. By implementing 1 MW SPV power plant, fossil fuel consumption

like coal and oil will be reduced which in turn reduces CO2 emission of 1260 Tonnes per

year. Solar Power is the Clean and Green Power. Generally domestic and commercial

buildings will require more power in day time. Solar power helps in meeting this increased

day time load demand. India is densely populated and has high solar insolation, which is an

ideal combination for using solar power in India. India is already a leader in wind power

generation and it has the solar energy potential of 4-7 kWh/m2/day with the irradiation of

1000 W/m2. India has 300-320 Sunny days per year.

MNRE, Jawaharlal Nehru National Solar Mission (JNNSM) envisages

installation of around 10 GW utility scale solar power projects in Phase-II. In 12th five-year

plan (2012-2017) also targets capacity addition of 10 GW of grid connected solar power in

India. It is envisaged that out of this 10 GW target, 4 GW would be developed under central

scheme and 6 GW under various state specific schemes.

Under the AP Solar Power Policy (2012 – G.O No.39 & 44) 34.85 MW

capacity solar power projects were only commissioned before 30th June, 2014 though it was

envisaged to add 2 GW capacity by the AP Government for the purpose of promotion of

renewable energy. This policy is applicable up to the year of 2017. AP Government

welcomes the power trading between the AP Discom and Third party/Captive use, Solar

Parks, Solar Rooftop Projects. Cost of the energy is Rs.5.25/kWh for solar rooftop projects.

The MW plant’s unit cost is in the range of Rs.5-6/kWh.

The Electricity Act, 2003, paves way for an innovative approach to solve our

country’s power problems. It has paved the way for a competitive environment; open access

to existing transmission and distribution network to transmit electricity across regions; de-

licensing of generation, captive power and dedicated transmission lines; licensing of

distribution and supply companies and the restructuring of State Electricity Boards.

******

Page 26: ASPEN - Site Observation & Proposal

Chapter 2

Project Details

For this project, Poly-crystalline technology based 3rd Generation of Solar PV modules will

be used. Along with this, highly efficient, photon-tested Array inverters are going to be

integrated to the system. These technologies are the best in the industry. So, It’s clear that

our project is not compromising with the quality of the materials and these are the latest

components which obviously lead this project to success.

The grid connected solar PV power generation scheme will

mainly consist of solar PV array, power- conditioning units (PCU), which convert DC power

to AC power and associated switchgears (with metering and protection).

Project Details

Type of installation Fixed Plane with Seasonal/Monthly Tilt Angle

Changeable

Estimated Array Peak power 1001 kWp

Project Life 20 Years

Shading Consideration Shade Free

Substation Voltage 33/220 kV

Destination SS Goddumari, 220/11 kV

Phase Connection 3

Substation frequency 50 Hz

Available/Required area 10000 m2 (Approx.)

Safety Level IP65 & IP20

Project Location is Ellutla which is located in Anantapur District of Andhra Pradesh. It is a

village panchayat which is in Putlur Block. Ellutla is the Hilly terrain, Semi-arid area.

Page 27: ASPEN - Site Observation & Proposal

2.1 Metrological details of Proposed Location at Ellutla

Location 1 Co-ordinates 14°40 N, 77°55 E

Location 2 Co-ordinates 14°40 N, 77°55 E

Area of the Location 1 10830 m2 / 8801 m2

Area of the Location 2 8687 m2 / 8516 m2

Total area (taken) 17317 m2 = 4.27 acres

Altitude of the Location 1 336 m

Altitude of the Location 2 330 m

Time zone 5.5

Amb. Temperature (oC) Max Ave Min

38°C 30°C 24°C

Daily Solar Irradiation (GHI) 5.55 kWh/m2/day

Relative Humidity (RH) 60 %

Atmospheric Pressure (kPa) 100.1

Wind Speed (m/s) 2.7

In Ellutla, we have chosen the two locations (4.27 acres) adjacent to the substation. These

metrological data are not given for the whole Ellutla. These data are specifically found for

the proposed location of Ellutla. Ellutla is a high temperature region with second lowest

rainfall in India. Solar radiation such as DNI (Direct Normal Radiation) and GHI (Global

Horizontal Radiation) level are excellent in Ellutla. Flat Plate collector such as Solar PV

Nearest railway station Tadipatri 29 Km

Nearest airport Sri Satya Sai Airport,

Puttaparthi

59 Km

Nearest state capital Bangalore 190 Km

Nearest District Anantapur 36 Km

Page 28: ASPEN - Site Observation & Proposal

Technology mainly depends upon GHI Radiation. GHI records both Beam radiation (Direct

Radiation) and Diffuse radiation (Reflected radiation from sky).

Aerial view of the proposed site – Google Earth

2.2 Fixed flat panel PV Installation

The simplest configuration for a PV system is a

fixed position flat panel module. Generally, for 'all round' performance, the module is

inclined at the site’s latitude angle which is known as tilt angle of the panel. A fixed flat

panel system has no moving parts and offers the solution with the least ongoing cost of the

PV options. Its output will however be less per module than the PV systems that track the

Sun.

2.3 Tracking flat panel PV Installation

A tracking array can move on one or two axes in

order to expose the PV module surface to follow the Sun and capture the greatest amount of

solar radiation possible. Compared to a fixed system, a tracking system can provide 30%

greater electrical output per module. It will also have both a higher capital and

operating/maintenance cost due to the more complex mounting system. While the greatest

possible output is desired, this must be evaluated over the life of the project against these

higher ongoing costs.

More area is required for this type of installation. So, Area is the main factor for

choosing the fixed installation in Ellutla.

Site 1

Site 2

Substation

Page 29: ASPEN - Site Observation & Proposal

Chapter 3

Solar Potential of Ellutla

Solar Potential

India has a comparatively higher solar insolation. MNRE and NREL unitedly released the

Solar Potential Map (GHI) for India, which shows Anantapur as a hot region of Andhra

Pradesh. Ellutla has 4-6 sunshine hours per day, 4-6 kWh/m2/day of Global Horizontal

radiation and it has 300-320 sunny days. We have been using the PVsyst software to finding

out following terms;

Page 30: ASPEN - Site Observation & Proposal

Global Horizontal Irradiance (GHI) is the total amount of shortwave radiation received

from the sky by a surface horizontal to the ground. This value is of particular interest to

photovoltaic installations.

Monthly Cumulative GHI of Ellutla

Month No. of

days

Sunshine

Hrs (Hours)

GHI

(kWh/m2/day)

Monthly GHI

(kWh/m2)

Jan 31 5.37 5.37 166.47

Feb 28 5.97 5.97 167.16

Mar 31 6.62 6.62 205.22

Apr 30 6.62 6.62 198.6

May 31 6.26 6.26 194.06

Jun 30 5.33 5.33 159.9

Jul 31 4.92 4.92 152.52

Aug 31 4.75 4.75 147.25

Sep 30 5.42 5.42 162.6

Oct 31 5.21 5.21 161.51

Nov 30 5.06 5.06 151.8

Dec 31 4.9 4.9 151.9

Year 365 5.54 5.54 2020.58

GHI at each month

When we put 1 MW plant in Ellutla, that will give the energy of 2.1 MU per year. But, due

to some losses like mismatch losses, soiling losses, temperature increase losses, DC cable

losses, inverter, AC cable losses. While considering these losses, we get an energy of around

1.57 MU per year as shown below.

5.375.97

6.62 6.626.26

5.334.92 4.75

5.42 5.21 5.06 4.9

0

1

2

3

4

5

6

7

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

kw

h/m

2/d

ay

Month

GLOBAL HORIZONTAL IRRADIATION

Page 31: ASPEN - Site Observation & Proposal

Assumption of Losses for calculation

Losses Range Value Taken

Temperature Increase 10-20 % 13.5 %

Soiling Losses 1-2 % 1.5 %

Mismatch Losses 0-3 % 1.5 %

DC Cable Losses 1-3 % 1.2 %

Radiation Losses 2-4 % 2.5 %

Inverter Losses 1-3 % 2.0 %

AC losses (Transformer, Cables) 0.2-1 % 0.5 %

Overall Losses 20-30 % 22.7 %

1 MW Plant Production at Ellutla

Month No. of

days

Sunshine Hrs

(Hours)

Energy Production

(kWh)

Losses

(%)

Total

Production

(kWh)

Jan 31 5.37 166470 22.7 % 129535.2678

Feb 28 5.97 167160 22.7 % 130072.1774

Mar 31 6.62 205220 22.7 % 159687.7976

Apr 30 6.62 198600 22.7 % 154536.5783

May 31 6.26 194060 22.7 % 151003.869

Jun 30 5.33 159900 22.7 % 124422.955

Jul 31 4.92 152520 22.7 % 118680.3571

Aug 31 4.75 147250 22.7 % 114579.6131

Sep 30 5.42 162600 22.7 % 126523.9055

Oct 31 5.21 161510 22.7 % 125675.744

Nov 30 5.06 151800 22.7 % 118120.1036

Dec 31 4.9 151900 22.7 % 118197.9166

Year 365 5.79 2018990 22.7 % 1571036.285

3.1 Day Hour at Ellutla

We used the NOAA Geographical model to find the sunrise and sunset of

the proposed site. It is useful for solar panel positioning. We have cross checked the value

obtained by NOAA with the GPS device.

Day hours in every month

The proposed plant performance ratio will be around 78 %

Page 32: ASPEN - Site Observation & Proposal

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Sun Rise 6:43 6:46 6:34 6:13 5:55 5:48 5:52 6:01 6:06 6:07 6:13 6:27

Sun Set 5:59 6:16 6:26 6:30 6:35 6:44 6:51 6:47 6:29 6:07 5:49 5:47

Day Hour 11:16 11:30 11:52 12:17 12:40 12:56 12:59 12:46 12:23 12:00 11:36 11:20

* Reading of first day of every month in 2016

In Ellutla, Peak solar energy production months are April, May, June, July, August,

September. These months alone have the day hour value more than 12 hours. Solar energy

production is marginal in other months like October to March.

3.2 Sun Position at Ellutla

We found the sun paths at each month with respective solar altitude

angle and solar azimuth angle. Solar Altitude Angle is the elevation angle of the sun with

respect to the horizontal plane. Generally, lies between the angle of 8.8 N and 38.1 S from

the zenith for the proposed site.

Tilt Angle for Ellutla

The azimuth angle varies throughout the day. At the equinoxes, the sun rises directly east

and sets directly west regardless of the latitude, thus making the azimuth angles 90° at sunrise

and 270° at sunset. But, Sunrise won’t happen at perfect east direction throughout the year.

It will slant somewhat in south or north side. Sun is active at south side for 8 months (Sep-

Apr), North side for 4 months (May-Aug). Mostly sun is inclined in the south direction. So,

Page 33: ASPEN - Site Observation & Proposal

the solar panel should be tilted in south direction in case of fixed mounting with the angle of

the site’s latitude angle.

Sun Pathway at each month with respective Solar Altitude and Solar Azimuth angle

Summer Solstice is longest day of the year - June 21-22 known as “Summer solstice” which means that

day time is more than the night time.

Winter Solstice is shortest day of the year - Dec 21-22 known as “Winter solstice” which means that

day time is lower than the night time.

Equinox is the day in which is day and night time are equal. Mar 22-23 and Sep 22-23 known as equinox

day. Sun rises in perfect east and sets in perfect west.

Page 34: ASPEN - Site Observation & Proposal

Sun path ways of Ellutla in respective months - PVsyst

3.3 Solar window

It is the duration at which the peak solar production takes place. In

general, it will be taken as 4-6 hours per day according to the place. Increase in solar Window

leads to increase in production, though the shade area will increase. That in turn increases

the overall area required for installation of the plant. Solar Noon is the time of a day at which

the sun will be at its maximum Solar Altitude angle.

Variation of Solar noon across the year

Page 35: ASPEN - Site Observation & Proposal

3.4. Analysing obstructions

Identifying the obstructions around the proposed site is the major factor for

consideration. This consideration also judges the solar energy production with shading losses.

Panorama view of the site (0°-180°)

Solar Window of Ellutla

Generally, Fish-Eye Camera or some online software are used for identifying

the obstructions around the place. We took the panorama view of the site which is similar to

In Ellutla, as 6-hour solar window is adapted, 3 hours before and after the solar noon has to

be considered. As the solar noon varies from 12:03 to 12:33 across the year, the solar

window is calculated by adding 3 hours before 12:03 P.M and after 12:33 P.M. which gives

our solar window as 9:03 A.M to 3:33 P.M

Page 36: ASPEN - Site Observation & Proposal

the fish eye photography. We have the mountain barrier at 60° of the site. North side of the

site is considered as 0° and we calculated the highly elevated place by using Google Earth.

Due to obstructions, we don’t get any shading losses as these losses don’t come under our

solar window as shown in the Fig. solar window.

Horizon Obstacle Elevation Calculation - Google Earth

Obstructions around the site – Pvsyst

Angle Ele.of

Location

(m)

Elevation

(m)

Distance

(m)

Barrier

Height (m)

Barrier

Angle (°)

0° 336 451 890 115 7.36

30° 336 424 650 88 7.71

60° 336 462 500 126 14.14

90° 336 430 500 94 10.65

120° 336 405 950 69 4.15

150° 336 324 500 -12 -1.37

180° 336 324 500 -12 -1.37

-150° 336 330 500 -6 -0.69

-120° 336 362 650 26 2.29

-90° 336 376 1000 40 2.29

-60° 336 353 500 17 1.95

-30° 336 382 650 46 4.05

Page 37: ASPEN - Site Observation & Proposal

Chapter 4

Design of the Plant – Based on Pvsyst

System Description

Capacity of the Module 320 kWp

SPV Plant Peak Power 1008 kWp

Connection of PV modules in each

Array Series

Connection of each Array Parallel

Inverter 3Nos of 300 kW

Inverter Technology LF Transfo, IGBT Based 3 Phase

Central Inverter

Modular Components

Components Specifications Quantity

SPV Modules Max. Peak power 320 WP

IMPP – 8.37 A, ISC – 8.96 A,

VMPP – 38.20 V, VOC – 46.10 V

3150

Non-Modular Components

Components Electrical Specifications Quantity

Inverter LF Transfo, IGBT Based 3 Phase Central

Inverter

3*300 kW

Transformer 400V/33 kV, 1250 kW 1

SCADA/

Monitoring

System

Integrated with Remote

Monitoring system web based

1

Cables DC Side= 10 mm2

AC Side= LT: 16mm2 & HT:

185mm2

-

Page 38: ASPEN - Site Observation & Proposal

Specification and sizing details of PV Panels

Electrical Characteristics of SPV Panels

Company Name SolarWorld

Design Criteria Sunmodule XL SW 320 poly

Watt Peak 320 WP

VOC 46.10 V

VMPP 38.20 V

ISC 8.96 A

IMPP 8.37 A

Module Efficiency 16.05 %

Power tolerance (+1.6) Or (-1.6)

Technology Si-Poly Crystalline

No. of Cells 72 Cells in series,

Sizes and Technology of the Panels

Length 1993 mm

Width 1001 mm

Thickness 33.0 mm

Weight 18.0 Kg

Module Area 1.995 m2

Frame & Structure Aluminum and Glass

No. of Bypass Diodes used 4 Used

Panel Design Parameters

R Shunt 400 Ohm

R Shunt (G=0) 2400 Ohm

R Series Model 0.33 Ohm

R Series Max 0.42 Ohm

R Series Apparent 0.53 Ohm

Page 39: ASPEN - Site Observation & Proposal

Panel / Module Behavior at different irradiation level

PV Parameters @ 1000 W/m2 @ 800 W/m2 @ 400 W/m2

PMPP 320.2 W 256.8 W 127.6 W

VOC 46.1 V 45.7 V 44.5 V

VMPP 37.8 V 38.0 V 37.8 V

ISC 8.96 A 7.17 A 3.59 A

IMPP 8.47 A 6.76 A 3.38 A

Module Efficiency 16.05% 16.09% 15.98%

Temperature Co-eff -0.42% / oC -0.42% / oC -0.43% / oC

Module Behavior at different irradiation level-PVsyst

Loss with respect to increase in temperature

Conditions At STC 25oC At AATC 30oC

Suggested Array size 1008 kWp 1008 kWp

Actual Power Production 996 KWp 987 KWp

Watt peak of each SPV Module 320 WP 313 WP

Page 40: ASPEN - Site Observation & Proposal

Total Nos of SPV Module

required 3150 3150

Total Nos of Arrays 210 210

Nos of SPV Module in each

Array 15 15

Each Array Voltage (VOC/VMPP) 691.5 V / 567 V 679.5 V / 555 V

Each Array Current (ISC / IMPP) 8.96 A / 8.37 A 8.98 A / 8.47 A

Total Voltage (VOC/VMPP) 691.5 / 567 V 679.5 / 555 V

Total Current (ISC / IMPP) 1881.6 / 1757.7 A 1885.8 / 1778.7 A

Details of Solar Inverter Specification and Design details

Inverter type 300 kW MPPT Based LF Transfo 3

Phase Central Inverter

Quantity 3

Input (DC) 450-750 V

Max. Power 315 KW

Max. absolute input voltage 900 V

Start Voltage 450 V

Max. Input Current 589 A

Output (AC)

Rated Output Power 315 KW

Max. Apparent AC Power 315 KW

Power Threshold 1500 W

Max. Output Current 459 A

Power factor at rated power 0.9

Efficiency

Max. Efficiency 96 %

Inverter Connection Details

Page 41: ASPEN - Site Observation & Proposal

Total nos. of inverter 3

Nos. of Arrays per inverter 70

Connection of Arrays/inverter Parallel

Inter-Inverter isolator Provided

Transformer Sizing

Transformer type Power transformer, core type with oil-

immersed; 65⁰ C winding temp rise

Cooling type ONAN (Oil Natural Air Natural)

Rated KVA 1250

High Voltage Rating 33000 V

Low Voltage Rating 690

Nominal Impedance 4.75 %

Impedance tolerance 7.5 %

Nominal Secondary Amps 1250 A

Max SC withstand current 20kA/3s

HV Connection Delta

LV Connection Wye

Operating Frequency 50 Hz

Tap Changer NLTC 2 X 2.5%

Page 42: ASPEN - Site Observation & Proposal

Electrical Flow diagram

Page 43: ASPEN - Site Observation & Proposal
Page 44: ASPEN - Site Observation & Proposal

Array (210) Placement in the Proposed sites

******

Page 45: ASPEN - Site Observation & Proposal

Chapter 5

Angle & Spacing of installation

Generally, the tilt angle of the photovoltaic (PV) array is the key to an optimum energy yield.

Solar panels or PV arrays are most efficient, when they are perpendicular to the sun's rays.

The default value is a tilt angle equal to the station's latitude plus 15 degrees in winter, or

minus 15 degrees in summer. (Approx. Actual seasonal panel angle is given below).

As our solar window is 9:03 A.M to 3:33 P.M we have to find the minimum

solar altitude angle across the year at this timing.

Note that 9:03 A.M will occur in different Altitude angles in different days.

Lowest angle should be considered for maximum production.

By Checking the Solar Altitude angle across the year, we found that 10th January

has the minimum altitude angle of 28o in East by 9:03 A.M. Similarly, By Checking the Solar

Altitude angle across the year, we found that 2nd December has the minimum altitude angle

of 28o in West by 3:33 P.M. Thus in East to west the panel should tilt from -62o (East) to +

62o (West) from zenith in case of Tracking System.

Minimum Solar Altitude Angle in East and West

Tilt Angle (N-S Panel Tilted angle)

In general, the sites latitude angle is taken as N-S panel tilt angle. But the actual tilt angle

calculation is as follows.

The North most Solar Altitude angle occurs on 21st June (Summer Solstice) as 81.8o.

Similarly, South most Solar Altitude angle occurs on 21st December (Winter Solstice) as

51.9o.

The Angle between these two extents is 46.9o i.e. 23.45o North and 23.45o South of the

Equinox (21st March & 21st September)

Page 46: ASPEN - Site Observation & Proposal

Tilt angle = 90-(South Solar altitude extent+23.45)

Tilt angle = 90-(51.9+23.45) = 14.65oS

So, the Power production will be increased, if the tilt angle is adjusted every

month. Minimum Solar Altitude Angle were considered for shading calculation in respective

directions.

Similarly, we did the calculations for panel angle at each month and we cross-

checked the values from www.solarelectricityhandbook.com. This webpage gives the panel

angle for Anantapur District. Ellutla is in Anantapur District. So that, we can take this value

for reference.

Mon Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

SAA 59° 67° 75° 83° 91° 98° 91° 83° 75° 67° 59° 52°

TA 31°_S 23°_S 15°_S 7°_S 1°_N 8°_N 1°_N 7°_S 15°_S 23°_S 31°_S 28°_S

Optimum tilt angles for the Anantapur for respective months

Page 47: ASPEN - Site Observation & Proposal

Seasonal tilt adjustment

Spacing of installation

The spacing between the panels depends upon the Shading of one panel on

another. The Minimum Solar Altitude Angle to be considered for shading calculation in

respective directions for the proposed direction were calculated as given in the figure.

The angles are derived from the NOAA Solar Calculator for the proposed site as shown in

the figure

Page 48: ASPEN - Site Observation & Proposal

3 steps in calculating the shade distance

1) Calculate the Maximum height of the solar panel in maximum tilt.

2) Calculate the East – West Maximum shade distance

3) Calculate the North – South Maximum Shade distance

As given in the diagram, to find the N-S pitch distance between the panels we

need the Angle Alpha. It is minimum of 51.9 and 81.2. thus we choose Alpha as 51.9 for N-

S and 28 for E-W.

Then we need to find the maximum height of the mounting. Using trigonometry,

we can find the Pitch using the height and the angle as given in the table and pics

A1 B C D E F G H I J K

2 Fixed Axis with Variable Tilt N-S Tilt AngleMin Sun Angle

Considered

Panel

Perpendicular

Length

Maximum Tilt Angle

3 14.65 38.1 1.001 38.1

4 E-W 3

5 Min Sun Angle Considered 0

6 Panel Perpendicular Length 1.993 5

7 Solar Window minimum angle 28

8

9

10 N-S Height Panel 1.8530

11 E-W Height Panel 0.0000

12 1 Total Ht of Panel 1.8530

13 2 E-W Pitch Dist 3.4849 E-W Panel + Pitch 13.4499 =(C6*D6)+D13

14 3 N-S Pitch Dist 2.1503 N-S Panel + Pitch 5.1533 =(G3*G4)+D14

15 Mounting Area 69.3116 =I13*I14

16

=D13*SIN(RADIANS(H3))

=G3*G4*SIN(RADIANS(F3))

=C6*D6*SIN(RADIANS(C5))

=SUM(D10:D11)

=D12/(TAN(RADIANS(C7)))

Page 49: ASPEN - Site Observation & Proposal

Panel Dimension

Systematic arrangement of the panels in single

Page 50: ASPEN - Site Observation & Proposal

Comparison of Single and Array

Systematic arrangement of the panels in Array of 15

Page 51: ASPEN - Site Observation & Proposal

Already, we have discussed in Chapter 4 - Design of the plant. If we put the 15 modules in

series connection as an Array, totally 208 Arrays will be required.

Total length of the Array = 13.4499 m

Total width of the Array = 5.1533 m

Array Area = 70 m2

Total No. of Arrays Required = 208

Total Module Area = 14560 m2

Available Plant Area = 17317 m2

******

Page 52: ASPEN - Site Observation & Proposal

Chapter 6

Financial Analysis

In the following analysis, we have to consider the AD Benefit for the SPV Plant. So that we

Save up to 80% of taxation in first year.

A. Generally, SPV Plant lifetime is 20-25 Years.

B. As previously stated, 1MW SPV Plant generates the energy of 2.1 Million Units. But, we

should consider some losses around 20-30% from the production. So that, we have taken the

value of 1.57 Million Units. In addition to that, we have to take 1% loss for every year in the

first 10 Years and 0.66% in the 10-25 years.

C. No. of Units generated per year.

D. As per AP Power policy (2015-2017), Unit cost is 5.85 Rs and Escalation charges 2% for

every year. Levelized cost of energy is the method used to determine the energy generation

cost, which is the ratio of total investment of the plant in certain period to total energy

generation in that period.

E. Amount raised by energy.

F. First year investment is 6.15 crores. Then we have to invest the money in the form of

Operation and Maintenance (2% of the total investment), Insurance (0.5% of the total

investment). It will come around 15,00,000 lakhs per year.

G. Total Profit which is the difference between energy generation and yearly investment.

H. Cash flow is term to find out the Time to recover the cost of investment

Payback = cost of project / annual cash flows

Issues: Ignores benefits after payback period (Eg: solar has 25 years’ lifetime. Other products

may have little). Thus no profitability analysis Ignores time value of money

From the Analysis, we could find that the payback period is 7 years.

LCOE - Levelized cost of energy

Years 10 years 15 years 25 years

Total Cost ₹ 7,50,00,000 ₹ 8,25,00,000 ₹ 9,75,00,000

Total Gen ₹ 1,49,22,891 ₹ 2,19,11,519 ₹ 2,86,72,547

Rs. /unit ₹ 5.03 ₹ 3.77 ₹ 3.40

Page 53: ASPEN - Site Observation & Proposal

Year Losses Generation EB Tariff Generation

Price Investment Net Amount Cash Flow

A B C D E=C*D F G=E-F H=G-6crore

% Units

(kWh) INR INR INR INR INR

1 1% 15,60,679 ₹ 5.85 ₹ 91,29,974 ₹ 6,15,00,000 ₹ 76,29,974 -₹ 5,23,70,026

2 1% 15,45,072 ₹ 5.97 ₹ 92,19,447 ₹ 15,00,000 ₹ 77,19,447 -₹ 4,46,50,579

3 1% 15,29,622 ₹ 6.09 ₹ 93,09,798 ₹ 15,00,000 ₹ 78,09,798 -₹ 3,68,40,781

4 1% 15,14,326 ₹ 6.21 ₹ 94,01,034 ₹ 15,00,000 ₹ 79,01,034 -₹ 2,89,39,747

5 1% 14,99,182 ₹ 6.33 ₹ 94,93,164 ₹ 15,00,000 ₹ 79,93,164 -₹ 2,09,46,582

6 1% 14,84,190 ₹ 6.46 ₹ 95,86,197 ₹ 15,00,000 ₹ 80,86,197 -₹ 1,28,60,385

7 1% 14,69,349 ₹ 6.59 ₹ 96,80,142 ₹ 15,00,000 ₹ 81,80,142 -₹ 46,80,243

8 1% 14,54,655 ₹ 6.72 ₹ 97,75,007 ₹ 15,00,000 ₹ 82,75,007 ₹ 35,94,764

9 1% 14,40,109 ₹ 6.85 ₹ 98,70,802 ₹ 15,00,000 ₹ 83,70,802 ₹ 1,19,65,566

10 1% 14,25,707 ₹ 6.99 ₹ 99,67,536 ₹ 15,00,000 ₹ 84,67,536 ₹ 2,04,33,103

11 0.66% 14,16,298 ₹ 7.13 ₹ 1,00,99,786 ₹ 15,00,000 ₹ 85,99,786 ₹ 2,90,32,888

12 0.66% 14,06,950 ₹ 7.27 ₹ 1,02,33,790 ₹ 15,00,000 ₹ 87,33,790 ₹ 3,77,66,678

13 0.66% 13,97,664 ₹ 7.42 ₹ 1,03,69,571 ₹ 15,00,000 ₹ 88,69,571 ₹ 4,66,36,249

14 0.66% 13,88,440 ₹ 7.57 ₹ 1,05,07,155 ₹ 15,00,000 ₹ 90,07,155 ₹ 5,56,43,404

15 0.66% 13,79,276 ₹ 7.72 ₹ 1,06,46,564 ₹ 15,00,000 ₹ 91,46,564 ₹ 6,47,89,968

16 0.66% 13,70,173 ₹ 7.87 ₹ 1,07,87,822 ₹ 15,00,000 ₹ 92,87,822 ₹ 7,40,77,790

17 0.66% 13,61,130 ₹ 8.03 ₹ 1,09,30,955 ₹ 15,00,000 ₹ 94,30,955 ₹ 8,35,08,746

18 0.66% 13,52,146 ₹ 8.19 ₹ 1,10,75,987 ₹ 15,00,000 ₹ 95,75,987 ₹ 9,30,84,733

19 0.66% 13,43,222 ₹ 8.36 ₹ 1,12,22,943 ₹ 15,00,000 ₹ 97,22,943 ₹ 10,28,07,676

20 0.66% 13,34,357 ₹ 8.52 ₹ 1,13,71,849 ₹ 15,00,000 ₹ 98,71,849 ₹ 11,26,79,526

21 0.66% 13,25,550 ₹ 8.69 ₹ 1,15,22,731 ₹ 15,00,000 ₹ 1,00,22,731 ₹ 12,27,02,257

22 0.66% 13,16,801 ₹ 8.87 ₹ 1,16,75,615 ₹ 15,00,000 ₹ 1,01,75,615 ₹ 13,28,77,871

23 0.66% 13,08,111 ₹ 9.04 ₹ 1,18,30,527 ₹ 15,00,000 ₹ 1,03,30,527 ₹ 14,32,08,398

24 0.66% 12,99,477 ₹ 9.22 ₹ 1,19,87,494 ₹ 15,00,000 ₹ 1,04,87,494 ₹ 15,36,95,892

25 0.66% 12,90,900 ₹ 9.41 ₹ 1,21,46,544 ₹ 15,00,000 ₹ 1,06,46,544 ₹ 16,43,42,437

Page 54: ASPEN - Site Observation & Proposal

Financial Analysis of the SPV plant

Payback Period of the SPV Plant

Performance of the SPV plant

******

₹(10,00,00,000.00)

₹(5,00,00,000.00)

₹-

₹5,00,00,000.00

₹10,00,00,000.00

₹15,00,00,000.00

₹20,00,00,000.00

1 2 3 4 5 6 7 8 9 10111213141516171819202122232425TO

TA

L A

MO

UN

T

NO. OF YEARS

Payback Period

Page 55: ASPEN - Site Observation & Proposal

Chapter 7

Benchmark of the Project

AS PER CERC (Central Electricity Regulatory Commission) Report

This benchmark only applicable during the year of 2015-16. The Commission has considered

the comments/suggestions/objections received from the stakeholders on benchmark Capital

Cost of Solar PV projects and has decided as under: -

Land-Requirement of the SPV Plants

The land required for a 1 MW power plant setup is around 4.5-5 acres

for Crystalline technology and around 6.5-7.5 acres for Thin-Film technology. This is only a

rough benchmark and may vary based on technology and efficiency of panels.

Life-time of the SPV Plants

The useful life of a typical Solar Power plant is considered to be 25

years. This is the duration for which long-term PPAs are signed and financial models are

built. However, Solar Power plants can run beyond 25 years while producing a lower output.

Many Solar Panel manufacturers guarantee an output of 90% at the end of 10 years and 80%

at the end of 25 years.

Annual Energy Generated from the 1 MW SPV Plant

The usual benchmark for energy generated from a 1 MW Solar Power

plant is considered as 1.5 Million units. This is only a benchmark and should not be

considered as the actual output for a given location. The amount of actual energy generated

from a Solar Power Plant in a year depends on both internal and external factors.

Extern

al factors which are beyond the control of a Solar developer can include the following:

Number of sunny days

Solar Irradiation

Day Temperatures

Air Mass

Internal factors all of which are within the control of a Solar Developer:

Plant Location

Usage of Solar Tracking systems

Page 56: ASPEN - Site Observation & Proposal

Quality of equipment used

Workmanship of the EPC contractor

O&M activities

Operation & Maintenance cost for SPV Plant

Central Electricity Regulatory Commission (CERC) benchmark costs

for O&M is Rs.12.3 lakhs/year/MW for 2014-15 with a 5.72% increase every year. This

varies from project to project based on the number of people you employ for maintenance,

frequency of cleaning of panels, onsite-engineer availability etc.

Permissions from State Government

A certain set of permissions need to be obtained and documents need

to be submitted in order to setup a Solar PV plant. While these may vary from state-to-state,

in order to get a Solar PV Project Accredited by AP State Load Dispatch Centre (AP SLDC)

for REC mechanism, the following are the statutory clearances and environmental clearances

to be furnished:

1. Industrial Clearance

2. Land conversion (Agricultural to Non-Agricultural)

3. Environmental Clearance Certificate from APPCB, Hyderabad

4. Contract labour license from AP Labour Department

5. Fire Safety certificate from AP Fire Department

6. Latest tax receipt from the Municipal/Gram Panchayat for the factory land.

7. Auditor compliance certificate regarding fossil fuel utilization

8. Approval from Chief Electrical Inspector

9. Clearance from Forest department

Also, all necessary approvals/agreements before start of Solar PV project construction are to

be furnished as and when necessary. These include the following:

10. Land purchase

11. Power Evacuation arrangement permission letter from DISCOM

12. Confirmation of Metering Arrangement and location

13. ABT meter type, Manufacture, Model, Serial No. details for Energy Metering.

14. Copy of PPA (Preferential PPA projects are not eligible for REC mechanism)

15. Proposed Model and make of plant equipment

Page 57: ASPEN - Site Observation & Proposal

16. Undertaking for compliance with the usage of fossil fuel criteria as specified by MNRE

17. Details of Connectivity with DISCOM

18. Connectivity Diagram and Single Line Diagram of Plant

19. Details of pending court cases with APERC, Supreme Court of India, High Court of A.P. or

any other courts

20. Any other documents requested by AP SLDC

While these are the documents that AP SLDC requires for REC project accreditation, these

are typically the clearances/documents required in general for a Solar PV project.

Available Bank Loan Percentage for Solar PV Plant

There are 2 kinds of Financing mechanisms that are usually discussed –

Recourse Financing

Non-Recourse Financing

Recourse Financing requires collaterals and other extensive guarantees from the Solar

developer who wishes to avail loan. Recourse Financing is the prevalent mechanism in India

currently owing to lack of confidence of banks in the Power and Solar Power sector.

Non-Recourse Financing, on the other hand, does not require any additional collateral as the

Asset or Power Plant itself is the collateral in this case.

The typical Debt-Equity Ratio (Loan to Investment Ratio) for Solar Power plants is 70:30.

And the typical collaterals required for a 70% project cost loan could be in the range of 40-

60% project cost. This, however, varies from bank to bank as each bank has its own risk

perception/mitigation strategy, exposure targets to various sectors and Non-Performing Asset

(NPA) limits.

Benefits for Solar Power plants

Kind of Central/State benefits available for Solar Power plant setup

Solar plants can be categorized into 2 broad categories:

Grid Connected PV Plants

Off-Grid plants.

The usual Govt. support available for an Off-Grid plant is a Capital Subsidy of 15% on the

project cost upto a maximum size of 500 KW. This can be claimed by the

Manufacturer/Supplier/EPC Contractor (should be an MNRE accredited supplier) on behalf

of the customer.

Page 58: ASPEN - Site Observation & Proposal

Subsidy is not available for Grid Connected plants that engage in sale of power either to

the local DISCOM or 3rd party. Following are the benefits a Solar Power Developer involved

in Sale of Power Generated can avail:

Accelerated Depreciation – AD benefits can be claimed by Off-Grid and Grid-Connected

Solar Power Developers in order to offset taxes on profits from their connected businesses.

Typically, 90% depreciation is allowed with 80% allowed in the first year.

10 years Tax Holiday – Tax holiday can be availed for 10 years during which time Minimum

Alternate Tax is still applicable (19.9305%) which can be offset against tax payable later and

Other State specific exemptions which vary from state to state.

RECs and Carbon Credits (CERs)

Solar Power Plants need to be Grid-Connected on order to avail REC benefits. Though there

have been recommendations on multiple occasions that Off-Grid Solar Power plants be made

eligible for RECs, the proposal is still under discussion. Solar Power plants setup under the

following 3 modes are eligible for REC benefits:

Captive Power plants

Sale of power to Govt. at APPC

Sale of power to 3rd party at mutually agreed price

Captive Power Plants are eligible for RECs subject to the condition that

Concessional/Promotional Transmission or Wheeling Tariffs and/or banking facility benefit

are not availed. Also, Solar Power plants setup under Preferential Tariff schemes are not

eligible for RECs.

Expected Sale Price of Energy Units

Depends on the mode of sale of power and the consumer of power.

In the case of sale of power to DISCOM, the prevailing Average Pooled Power Purchase

Cost (APPC) will be applicable.

In the case of sale of power to 3rd Party consumer, a mutually agreed price can be agreed

upon and accordingly a PPA can be signed.

It is to be kept in mind that several additional charges such as Wheeling Charges, Distribution

Charges, Open-Access Charges, Cross-Subsidy Charges are applicable in the case of sale of

power to 3rd party. These charges vary from State-to-State and DISCOM-to-DISCOM and

even based on voltage levels.

Page 59: ASPEN - Site Observation & Proposal

S. No Particulars Capital Cost

(Rs. Cr/MW) % of total cost

1 SPV Modules 3.32 54.8 %

2 Land Cost 0.25 4.1 %

3 Civil and General Works 0.5 8.3 %

4 Mounting Structures 0.5 8.3 %

5 Power Conditioning Unit (PCU) 0.45 7.4 %

6 Evacuation Cost up to Inter-Connection

Point (Cables and Transformers) 0.55 9.1 %

7 Preliminary and Pre-Operative Expenses

including IDC and contingency 0.48 8.0 %

Total Capital Cost 6.05 Crores 100 %

Page 60: ASPEN - Site Observation & Proposal

Chapter 7

Timeline of the project

Design

Preparation of design & estimation of the plant

15 working days required.

Land Acquisition

As per design requirement, proper land selection & acquisition processed.

Time required 1 month

PPA

Power Purchase Agreement (PPA) with private power purchaser need to be finalized at a

feasible rate.

Required time is 15 working days

DPR

Preparation of Detailed Project Report including technical feasibility of the project prepared.

Time required 6 working days.

Finance

Arrangement of finance/fund for the project from nationalized or private financing agency

with significant interest rate and equity share will be finalized.

Required time for this stage is 1 month.

Procurement

After finalizing PPA and arrangement of fund for the project, procurement work starts

including preparation & finalizing of vendor selection, BOM, BOQ, order placing, follow-

ups of delivery to site/warehouse.

Estimated time for this step is 1 month.

Construction

After the processing of procurement, first civil construction at the site starts for PV mounting

structure set-up and control-room, administrative building. Finishing the civil works, PV

installation & all electrical construction works including the Grid Evacuation will be

processed.

Estimated time for this whole work is 2 months.

Page 61: ASPEN - Site Observation & Proposal

Commissioning

Commissioning of the plant by authorized govt. body or certified 3rd party will be done

followed by Completion of project execution.

Required time for this step is 6 working days.

Timeline of the SPV Project

******

Page 62: ASPEN - Site Observation & Proposal

Chapter 8

Operation and Maintenance

As every plant needs a regular maintenance work to make it functional & in well-condition,

so in this case also, a PV power plant also requires a sound & efficient operation &

management team to perform all the work after plant commissioning. Routine maintenance

is an ongoing concern for utility-scale PV systems and helps to ensure safe and effective

system operations over their lifetimes. In general, due to their simplicity and minimal moving

parts, O&M requirements for solar PV power plants are considerably less intensive than for

other forms of electricity generation. However, maintenance is still an important factor in

maximizing the performance and lifetime of both the plant and its components.

Maintenance activities for PV systems involve a number of potential hazards to

workers, including electrical and fall hazards. PV system safety involves the safety of both

workers and of the equipment installed. A safe PV system is typically installed according to

the Authority Having Jurisdiction (AHJ), which follow applicable codes and standards such

as NEC, NFPA, OSHA and the Code of Federal Regulations (CFR), IEC, and UL. Worker

safety includes considerations for a safe work area, safe use of tools and equipment, safe

practices for personnel protection, and awareness of safety hazards and how to avoid them.

Routine maintenance requirements for solar PV plants comprise several major categories,

including the following:

Visual inspections

PV modules and arrays

Inverter

Balance of plant

Grounds Maintenance

Testing, Measurements and Calibration

Test Reports/Recordkeeping

Troubleshooting progresses from the system to subsystem to component levels, and involves

the following:

Recognizing a problem

Observing the symptoms

Diagnosing the cause

Page 63: ASPEN - Site Observation & Proposal

Taking corrective actions

General details for troubleshooting common problems are provided in inverter manufacturer

installation instructions and operating manuals. At some point, a PV power plant will reach

the end of its useful life as a generation asset. A decommissioning procedure then is used to

safely disconnect and disable the components for disassembly and disposition for salvage.

******

Page 64: ASPEN - Site Observation & Proposal

Chapter 9

Engineering, Procurement and Construction of the Solar PV Plant

Engineering of a Solar Power Plant is based on various technical data including Site Contour

Survey, Soil Load Bearing Capacity, Module & Inverter Specifications etc. Further, choice

of technology plays an important role in Plant Engineering.

In Engineering, there are approximately 110 drawings and design documents including

Electrical DC, Electrical AC and Structural Engineering which need to be prepared to start

execution.

In Procurement, the Request for Proposals are floated for approximately 25 different

packages including – Modules, Inverters, Mounting Structures, Cables, Transformers, HT &

LT Panels, Electrical, Civil & Transmission Line Contractors etc. Negotiation and

Finalization of vendors is done based on Techno Commercial reasons.

In Construction, the Contractors appointed execute the plant in a phased manner often using

specialized machinery including ramming & auguring machines, hydras, loaders, cranes,

mixers, AJAX, tractors etc. Typically, multiple gangs of labor are used taking the total

number from 50 to 300 depending on size of the plant and execution time.

Reasons for delay during Engineering phase are

Delay in conducting the preliminary surveys & studies required for Engineering. Typically,

these studies cost less than 0.1% of the project cost and should be undertaken as soon as site

is finalized

Improper or incomplete assessment of all the Technical Parameters like fault level of the

substation where the solar power is to be evacuated

Repeated Change in Specifications of Equipment, possibly because of Procurement

Indecision – A change of panel wattage from 250 Wp to 300 Wp would alter at least 50

drawings including all layouts & structure drawings.

Carrying out different aspects of engineering in isolation. For eg. The Layout for Trenches

if designed without due concerns for roads & drainage.

Page 65: ASPEN - Site Observation & Proposal

Delays in delivery of Solar project

Transformers: Lead time 6 – 10 weeks

Solar Power Plants typically use Double Primary Winding, low loss transformers which are

made to order for projects. The typical lead time is 6 – 10 weeks based on the make and spec

of transformer. It is often not possible to squeeze the timelines further as the raw material

procurement for transformer assembly takes approximately 3 weeks to reach the

manufacturing plant. Further, drawing & inspection approval add to the problems.

CT, PT & Meters: Lead time 8 weeks

This equipment typically installed at the Plant Switchyard can be procured only from

particular empaneled suppliers for that state. Although, manufacturing time of these

equipment is not long, however, the testing of these equipment takes place in presence of

respective Discom representative’s presence and equipment is issued in the name of the

project.

HT Panels: Lead Time – 8 weeks

HT Panels are custom made according to the Voltage & Current ratings and design of the

particular project. The HT Panels contain protection equipment for the power plant at high

voltage levels. The relays required to construct such a panel are often not readily available

and leads to delays.

Solar Modules: Lead Time – 6 – 12 weeks

The Solar Modules in most Indian Solar Projects are imported. Even when made with

Domestic Cells, these cells have a long lead time. On placement of order, the schedule for

production is frozen which then follows the shipping period of 14 – 21 days depending on

vessel availability. Further transportation from port to site would take another 7 days.

Inverters: Lead Time – 8 - 12 weeks

Inverters till last year were mostly imported. However, with multiple inverter suppliers

setting up assembly plants in India, the lead time is reduced. In critical situations, it is not

uncommon to airlift inverters meant to be imported.

Page 66: ASPEN - Site Observation & Proposal

Mounting Structures: 4 – 6 Weeks

Typically, hot dipped galvanized iron (GI) is used for rafters and legs of module mounting

structures, while cold rolled pre galvanized sheets are made to desired sections and shapes

for purlins on which the modules are fixed. There are limited manufacturers of cold rolled

steel like Jindal, Tata etc and though, there are multiple suppliers of hot dipped GI, however,

the zinc bath is often not deep enough leading to defects. Although, the lead time of Mounting

Structures is not high. However, it is the most important as Mounting Structures are the first

equipment to be installed on site.

Cables: 4 – 6 Weeks

Cables are classified into 2 categories: DC Cables from module upto inverters and AC Cables

from inverter upto transmission line. Although, there are very reputed suppliers of both

cables available in India, the Copper Cables are often imported. When manufactured in India,

the lead time can be as less as 4 weeks, while when imported it may increase upto 6 – 8

weeks.

Reasons for delay during Construction phase

Inadequate Labor and/or machinery

Labor and machinery planning typically needs to be carried at least 2 – 4 weeks in advance

in accordance with the requirements of the implementation schedule. Skilled labor in the

Solar Sector are easy to come across in states of Rajasthan and Gujarat, while they need to

be supervised closely in others.

Right of Way

The transmission line when being erected, encounters various problems of crossing private

lands where the owners might not be cooperative and demand unreasonable compensation

for transmission poles / towers falling in their land. Transmission Line for Solar Projects is

covered under Activities for Public Good according to Section 63 E of the Electricity Act

and hence, the work may be carried out with Administrative Support once permissions are

taken. However, considering that the Project has a life of 25 years, it is best to establish good

relations with the land owners.

Local Issues

Page 67: ASPEN - Site Observation & Proposal

Solar Power Plants are typically constructed away from cities. It is typical to encounter

demands of employment and usage of locally available machinery and labor (mostly

unskilled) and sometimes even sand and cement during construction and O&M. It is

advisable to take local population in confidence in the beginning of construction. For large

power plants, it would help if developmental activities like construction of a temple, school

or housing is also done.

Civil Works

Civil Works wherever done require minimum curing time, else the quality of the civil

structure will deteriorate overtime. There is a shift towards Pre Fab structures to avoid this

nowadays.

Cable & Allied Items Quantity Mismatch

It is not uncommon to encounter quantity mismatch of cables among other equipment during

construction because of under calculation of lengths for bending radius, terminations and in

some cases even theft on site. It is best to order a contingency of at least 5 – 10% extra.

Guide on selection of various components

******

Page 68: ASPEN - Site Observation & Proposal

Conclusion

We would like to thank you for reading our proposal, the methodology and data

used in this proposal are reliable and true to our knowledge. In our internship

period in Aspen infrastructures – Suzlon Groups, we found that Suzlon’s Ellutla

substation had enough evacuation capacity and a huge land will be available after

the commissioning of wind project which is owned by Suzlon. In Addition to that

we found that Anantapur and Kurnool region of Andhra Pradesh has the highest

Solar potential next to the Gujarat region. As all the situations for a SPV were

favourable, we proposed the 1 MW SPV power plant that could be put up in the

available area. Approach roads are already built for the site, thus logistics, land

and licensing work are minimised and those expenses could be considered as

profit. At this time AP government have allotted with 2 GW of grid connected

SPV from JNNSM (Phase) it will be easy to get PPA. As the “Suzlon” and Ellutla

wind Project’s client “Renew Power” is entering into Solar, we hope that the

scope of success of the project is higher. In that case we are eager in developing

further details required for the execution of the project, in addition to that we are

ready to raise similar proposals in any new site. As we have visited many

Working and execution SPV power plants we are happy to work in the project

execution too.

From this effort, we knew the procedure for expressing the prefeasibility report

for Government and Private Parties. Similarly, we can prepare these types of

reports on cost and quality effective also.

Page 69: ASPEN - Site Observation & Proposal

CHAPTER 3

GALLERY

Fig 3.1 Site Surveying at Ellutla - ASPEN

Fig 3.2 Transmission tower Erection - ASPEN

Page 70: ASPEN - Site Observation & Proposal

Fig 3.3 Soil testing at Ellutla - ASPEN

Fig 3.4 Types of soil in the different earth layers - ASPEN

Page 71: ASPEN - Site Observation & Proposal

Fig 3.5 Parnapalli Site, from Anantapur 55 Km - ASPEN

Fig 3.6 Taken the measurements of the tree for calculating the total biomass content - ASPEN

Page 72: ASPEN - Site Observation & Proposal

Fig 3.7 Marking the centre point of the met mast site - ASPEN

Fig 3.8 Point marking in all four directions - ASPEN

Page 73: ASPEN - Site Observation & Proposal

Fig 3.9 Ellutla Site Substation Layout - ASPEN

Fig 3.10 Aerial view of total substation and our proposed site - ASPEN

Page 74: ASPEN - Site Observation & Proposal

Fig 3.11 Mountains for wind power plant installation - ASPEN

Fig 3.12 Uravakonda Site – For WTG Erection - SUZLON

Page 75: ASPEN - Site Observation & Proposal

Fig 3.13 S97 Model with tubular tower - SUZLON

Fig.3.14 Beluguppa Substation Construction - ASPEN

Page 76: ASPEN - Site Observation & Proposal

Fig 3.15 Control Panel and Transmission lines - ASPEN

Fig 3.16 Final Stage at Beluguppa 33/220 kV SS - ASPEN

Page 77: ASPEN - Site Observation & Proposal

Fig 3.17 OLTC Part of Transformer (On Load Tap Changer like Gear Box) - ASPEN

Fig 3.18 WTG Foundation - SUZLON

Page 78: ASPEN - Site Observation & Proposal

Fig 3.19 Hub Part of the WTG - SUZLON

Fig 3.20 Pitch DC Motor and its Sensor - SUZLON

Page 79: ASPEN - Site Observation & Proposal

Fig 3.21 Inner part of the Turbine - SUZLON

Fig 3.22 Lifting of the equipment’s - SUZLON

Page 80: ASPEN - Site Observation & Proposal

Fig 3.23 Lifting of the equipment’s - SUZLON

Fig 3.24 Lifting of the equipment’s - SUZLON

Page 81: ASPEN - Site Observation & Proposal

Fig 3.25 Lifting of the equipment’s - SUZLON

Fig 3.26 Lifting of the equipment’s - SUZLON

Page 82: ASPEN - Site Observation & Proposal

Fig 3.27 Lifting of the equipment’s - SUZLON

Fig 3.28 RCC Phase – WTG Foundation – ASPEN & SUZLON

Page 83: ASPEN - Site Observation & Proposal

Fig 3.29 Digging Phase – For Plain Cement Concrete to WTG Foundation– ASPEN & SUZLON

Fig 3.30 Starting of Foundation– ASPEN & SUZLON

Page 84: ASPEN - Site Observation & Proposal

Fig 3.31 Arrangements of Solar Components – ILLUMINE I

Fig 3.32 10 kWp SPV Site Visit – ILLUMINE I

Page 85: ASPEN - Site Observation & Proposal

Fig 3.33 SPV Site Visit – ILLUMINE I

Fig 3.34 SPV Site Visit – ILLUMINE I

Page 86: ASPEN - Site Observation & Proposal

CHAPTER 4

CONCLUSION

From this Internship Opportunity, I have learned a lot about Civil and

Electrical things in Substation. Then I knew the format of feasibility report for preparing

the Government and Private proposals. SUZLON and ASPEN gave me a site visit

arrangement. From these visits, I have met the technical people and they were sharing them

Knowledge and Experience with me. Visually I have seen the project developments.

Especially Foundations, Erection of Electrical Equipments in Substation, and Wind

Turbine Erection was the Good Experience to me. From these visuals, I have felt the

engineering participation in these works. Then I have collected the marketing and technical

stuffs from our teams such as Electrical, Civil, Management, Labour and Safety. First two

months of mine includes site visits, telephonic conversation with our seniors for preparing

the feasibility report, Conversation with our technical team. Then Last month I have

worked for ILLUMINE I – Designing Industries, Chennai. Illumine I gave me a chance

for Solar EPC Market analysing in Tamil Nadu. From this opportunity, I have met Installer

Companies in the range of Micro and Macro level. Then I Enquired about their products

like Batteries, Inverters, Panels and their installation procedures. So that, Market analysing

topic presented me a chance to deeply research experience in Solar Markets. On the whole

this internship brought the Overwhelming Experience to me.

Page 87: ASPEN - Site Observation & Proposal

CHAPTER 5

REFERENCE

Chetan Singh Solanki, 2013. Solar Photovoltaic Technology and Systems – A Manual for

Technicians, Trainers and Engineers, PHI Learning Private Limited – Delhi 110092

Government of Tamil Nadu, Energy Department – Solar Energy Policy 2012. To Promote

research and development of Solar Thermal and PV Technologies.

Government of Tamil Nadu, Tamil Nadu Electricity Regulatory Commission (TNERC) –

Comprehensive Tariff order on Solar Power, Order No 2 of 2016, Dated 28/03/16

Government of Tamil Nadu, Tamil Nadu Electricity Regulatory Commission (TNERC) –

Comprehensive Tariff order on Wind Power, Order No 2 of 2016, Dated 28/03/16

Government of Tamil Nadu, Tamil Nadu Energy Development Agency (TEDA), Guidelines

for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tamil Nadu

E. Sreevalsan, National Institute of Wind Energy (NIWE), Chennai - Wind Resource

Assessment in India.

Suzlon Groups – Department of R&D, Pune. Brochures of Wind Turbines and their Technical

and Economic feasibility resources 2016.

BRIDGE-TO-INDIA, Delhi, India-Solar-Consultancy Materials-2016

Det Norske Veritas, Copenhagen, Wind Energy Department, National Laboratory, Guidelines

for Design of Wind Turbines, 2nd Edition

Aspen Infrastructures – Department of Electrical, Substation – Construction, Electrical

Installation, Operation and Maintenance Source, 2012

Softwares - PVsyst, AutoCAD, Google Earth, Skelion, NREL Database

------------------