arup journal 1-2009 beijing stadium

Upload: andrada-grosu

Post on 14-Apr-2018

395 views

Category:

Documents


26 download

TRANSCRIPT

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    1/52

    1/THE BEIJING NATIONAL STADIUM SPECIAL ISSUE

    The Arup Journal

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    2/52

    2 The Arup Journal 1/2009

    Contents 4 Introduction

    Stephen Burrows

    5 Competition, team, and site

    Tony Choi Michael Kwok

    Sports architecture

    8 The architectural

    design concept

    J Parrish

    The main roof

    16 The Stadium geometry

    Stephen Burrows

    Martin Simpson

    20 Analysis model and results

    Kylie Lam Thomas Lam

    24 Seismic design of the roof

    Xiaonian Duan Goman Ho

    28 The retractable roof design

    John Lyle

    The bowl

    32 Layout and analysis model

    Tony Choi Thomas Lam

    34 Seismic design of the bowl

    Xiaonian Duan Goman Ho

    Specialist engineering design

    36 Roof cladding and

    acoustic ceiling

    Tony Choi

    37 Wind conditions in the

    Stadium and external plaza

    Alex To

    38 Thermal comfort in the Stad

    Rumin Yin

    40 Fire engineering concepts

    Mingchun Luo

    41 Building services design

    Lewis Shiu

    44 The lighting concept designJeff Shaw

    Rogier van der Heide

    Construction and conclusio

    48 Completing the programme

    Tony Choi Michael Kwok

    49 Constructing a stadium

    50 Credits

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    3/52

    The Arup Journal 1/

    The Beijing

    National Stadium

    Known universally as the Birds Nest, the 91 000-sea

    National Stadium was conceived and built as the

    primary venue for the XXIX Olympiad, held in Beijing i

    August 2008. This special edition of The Arup Journal

    documents the sports architecture design and the full

    engineering design by Arup over the six and a half yea

    from initial concept to project delivery.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    4/52

    4 The Arup Journal 1/2009

    Cantilever structures or the roo will be virtually impossible to build or spans o

    approximately 60m with the additional loading o the removable roo.

    These principles, agreed at the beginning, were important rst steps in our de

    and set in place rm oundations or what ollowed. The very rst sketch o the ro

    emerged some weeks later (Fig 2): this was our starting point or the Birds Nest

    design. The competition was won in April 2003 and so began the process odelivering one o the worlds greatest buildings.

    But the e-mail trail doesnt tell the whole story. In Basle we worked days and n

    to nd a cultural clue to the design that would win such a competition. The mode

    building went on day and night too. We had un, we still tell the stories, and we

    utilised Arups power wherever the skills lay to put the best people onto the proje

    My recollection o the entire process, rom the initial idea o a consortium to th

    integrated working o teams rom Herzog & de Meuron, CADG (China Architectur

    Design & Research Group, the Local Design Institute partner) and ArupSport, wa

    o a smooth and harmonious development. We had a single aim to win and w

    ocused on how to achieve that. So it didnt matter that ArupSport determined th

    unctional geometry, our ideas or the roo carried weight alongside those o othe

    we agonised over the scale o the spans and the scale o the project, we constan

    had a better idea (and some were actually quite good, though many were not),

    arguments were ew, and dinners were lively aairs.

    I remember, when we won, Michael Kwok calling me Steve, we won! and

    a moment I had to think what he meant. Then the reality hit home, the calls bega

    and the opportunity to shape a piece o history grew to enormity.

    For Arup the schematic design stage was carried out in Europe. Manchester a

    London were the core oces, and many people played their part. We have tried t

    credit everyone who made a signicant contribution (see p50) but some have m

    on to pastures new.

    However, all o us have a shared experience; all o us will have watched the 20

    Olympic Games with a sense o shared pride, wherever we were; all o us know o

    contribution to the project and its important contribution to Arups goal to shape

    better world.

    This is no overstatement. The Olympic Games is a global event, the decision t

    hold it in China was a pivotal political moment, and the Stadium will long remain asymbol o that decision, an important part o an important moment in history and

    symbol o the power o positive thought and action by the Peoples Republic o C

    I am proud o what we achieved, and I am also in awe o the skill and dedicati

    our sta, o the ease with which Arup worked across geographic boundaries, o t

    incredible perormances o our collaborators, and not least o the builder o this

    wonderul piece o engineering architecture.

    As we say in the North o England, twas a bloody great eort!

    In January 2003, alongside 13 competitor rms rom

    all over the world, Arup began work on the design

    competition or the Beijing National Stadium.

    In writing this introduction to The Arup Journal

    eature on this great project, I looked back to the rst

    meeting notes rom 10 January 2003, when J Parrish

    and I met with the architects Herzog & de Meuron at

    their oce in Basle, Switzerland. These struck a

    chord with me as I recalled how we interpreted the

    brie and how it would infuence our design.

    To quote these notes: Bowl shape design will be

    carried out essentially by ArupSport throughout the

    competition works, HdeM will incorporate these and

    co-ordinate with other areas o building. It is perhaps

    possible or the running track to be completely

    covered by the roo, ArupSport to check with IOC.

    The track cannot however be only partly covered as

    this will induce uneven conditions on dierent lanes.

    Introduction

    Stephen Burrows

    2. Initial design sketch for the roof.

    Structuraldepth oftrusses

    Bottom mat

    Top mat

    1. Typical elevation of the structures exterior.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    5/52

    The Arup Journal 1/

    NationalAquatics

    Centre

    NationalIndoor

    Stadium

    NationalStadium

    Sports CentreGymnasium

    EthnicCulture

    Park

    OlympicsVillage

    ChineseScience &

    TechnologyMuseum

    BeijingOlympics

    Park

    OlympicGreen

    Fencing Hall

    North 4th Ring Road

    The design competition

    Selecting the winning scheme for the National Stadium also involved the citizens ofBeijing. All 13 competition schemes were displayed at the Beijing Exhibition Centre in

    March 2003, attracting thousands of visitors, and alongside the deliberations of the

    international jury panel, votes by the general public were also taken into account.

    By the end of March 2003, it was announced that the Birds Nest scheme was

    selected as the winner, both by the jury panel and by public voting.

    However, the route from winning the design competition to winning the contract

    as designer for the implementation of the project was not a simple journey.

    In parallel with the design competition, the Beijing Development Planning

    Commission (BDPC) called for an ownership tender for the National Stadium.

    The bid winner was to join the Beijing state-owned Assets Management Corporation

    (BSAM) to form the project company, which would be responsible for the investment,

    construction, operation, and transfer of the project. A consortium led by CITIC was

    selected as the successful bidder, and duly joined with BSAM to form the project

    company National Stadium Co Ltd, which became Arups client for the project.

    Negotiation of the design contract between the design consortium (Herzog &

    De Meuron, Arup, and CADG) and the client started in July 2003, and the tough

    commercial negotiation took more than four months to conclude with contract signed

    in early December 2003. Concurrently, the schematic design was progressed at fast

    pace, with the Birds Nest groundbreaking ceremony held on 24 December 2003.

    The Arup team

    Arups success in delivering the project was truly a result of team effort and global

    collaboration, with everyone working seamlessly as one Arup. The ArupSport teams

    in London and in Manchester, the teams in Beijing, Hong Kong and Shenzhen, and

    the London Advanced Technology and Lighting groups, all gave of their very best.

    Within weeks of commencing the schematic design stage, engineers from Beijing and

    Hong Kong were assigned to the Manchester office to work with the team there.At the same time, another team was mobilised in the Beijing office to liaise and

    co-ordinate closely with the client, with CADG, and with local authorities. During the

    preliminary design stage, some UK members stayed in Beijing to work with the team

    at critical stages to ensure smooth implementation. Arups ability to mobilise global

    expertise and deliver locally was key to the success of the project.

    Arups scope of service covered sports architecture and all engineering disciplines

    including structural, mechanical, electrical, public health, wind, fire, and seismic

    engineering, environmental and microclimate studies, acoustics, and lighting design.

    Arup global expertise was deployed to achieve a world-class, state-of-the-art design.

    The firm was responsible for schematic design and preliminary design for the above

    scope, whilst CADG was responsible for construction documentation.

    Site profile

    The National Stadium is located in the southern part of the Olympic Green, which was

    masterplanned by Sasaki Associates and covers an area of 1135ha on the north side

    of Beijing, close to the citys central axis (Fig 1). The Stadium is the centrepiece venue

    of the Olympic Green, on an irregular quadrangle approximately 20.4ha in extent

    (Fig 2). The terrain is relatively flat, with ground elevations ranging from 42m to 47m,

    highest at the south-west corner and lowest at the north-east corner. The position

    was chosen so that there would be a gradual rise in level from the city roads in the

    north-east, forming a gentle slope up to the Stadium plinth, about 5.3m higher.

    The plinth connects to the main concourse, level 1 of the Stadium.

    Competition, team, and site

    Tony Choi Michael Kwok

    2. Key plan.

    3. Artists impression of Olympic site.

    2. Key plan.3. Site plan.

    National Stadium

    AiOther venues

    1. The Olympic Green relative to the city of Beijing.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    6/52

    6 The Arup Journal 1/2009

    3. The Stadium site.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    7/52

    The Arup Journal 1/

    Sports architectur

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    8/52

    8 The Arup Journal 1/2009

    Introduction

    At the time the architectural competition or the

    Beijing National Stadium was announced, Herzog &

    de Meuron and ArupSport (Arups multidisciplinary

    practice specialising in sports architecture) were

    already working together on the Allianz Arena in

    Munich1. This successul creative partnership was

    based on a shared desire to innovate: Herzog & de

    Meuron in creating unique buildings with strong local

    cultural resonances, and Arup in designing stadiums

    that perorm ever better or spectators, athletes, and

    operators. As already noted, or the Beijing

    competition the two practices joined orces with one

    o the leading Chinese Design Institutes, CADG.

    Within this integrated team, the architects at

    ArupSport were responsible in particular or the bowl,

    the concourses, and the spectator acilities, which

    together dened the orm o the Stadium. They also

    produced an initial optimised structural proposal or

    the roo and envelope, which Herzog & de Meuron

    then developed. CADG provided vital local expertise

    during the competition and scheme design, and then

    took the baton or the nal stages o the project,

    liaising with the local authorities, producing

    construction inormation and monitoring the workson site. Backed by Arups engineering expertise,

    the competition team was able to submit a highly

    developed, ully realisable architectural concept.

    As a result, despite some signicant changes to the

    brie, the orm o the built Stadium is very close to

    the original winning design.

    The architectural

    design concept

    I was delighted that the competition areas did

    everything that was set out for them to do. The path

    from drop-off for athletes to the warm-up area, with

    access to the Technical Information Centre for Team

    staff along the route; the fact that there were separate

    corridors to make sure that athletes making their way

    from the Call Room to the track could do so securely

    and without being disturbed by other athletes or

    coaches, without minimising space for others prepari

    themselves, and the space provided for athletes and

    staff to move around, made it the ideal stadium for th

    Paralympics Games. The fact that all of these spaces

    were absolutely accessible for athletes and staff usinwheelchairs made it a delight to use. Added to this, th

    fact that spectator areas provided enough good acce

    for those using wheelchairs was superb.

    Chris Cohen: Chairman o IPC Athletics.

    The brie called or a landmark building that would be the main venue or track an

    eld events during the 2008 Beijing Olympics, with a subsequent working lie o 1

    years. Ater the Games, it would become an important venue or both athletics an

    soccer. The Stadium was to have a capacity o 100 000 during the Games, and

    80 000 seats in legacy mode. (The client subsequently decided to reduce the Olycapacity to 91 000.) There was no dened legacy business plan, and so the desig

    team tried to make the Stadium as fexible and adaptable as possible. There is

    potential, or example, to add a hotel or box holders within the main envelope.

    Originally the Stadium was to have a retractable roo (Fig 1). This was particula

    challenging in structural terms as the building also had to have the resilience to

    withstand a major earthquake. Late in the programme, the client omitted this

    requirement rom the brie as part o the general review o the Olympic venues,

    beore work started on site.

    J Parrish

    1. Original design with retractable roof.

    2.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    9/52

    The Arup Journal 1/

    Bowl design involves a skilul balancing o several

    key criteria. Most importantly, spectators want to

    be as close as possible to the action and to have

    good view o the eld, while the stadium develope

    needs to accommodate a certain number o seats

    within a dened budget.

    These requirements oten confict. For example

    more space between rows creates better sightline

    but draws spectators urther away rom the eld a

    results in a larger stadium with increased construc

    costs. Even a tiny adjustment to the conguration

    the seats can have a huge impact on the overall

    design and cost o the building. To nd the optimu

    solution, it is essential to set priorities.

    The bowl

    The architects ambition was to create not only an instantly recognisable symbol o

    Chinas cultural, sporting, and economic renaissance, but also the most exciting

    stadium in Olympic history. Every Games has its own thrilling I was there moments,

    when athletes perorm miracles and new records are set. The team wanted to create

    a stadium that would harness and ampliy this excitement in the way the worlds

    best-loved soccer venues do.

    Like most modern stadia, the Birds Nest was designed inside out, beginning

    with the bowl the competitive eld and the seating stands around it (Fig 4). This is

    because the orm o the bowl and the distribution o seating types largely determine

    all other aspects o a stadium, including the shape and structure o the roo, the levelsand locations o the concourses and premium acilities, and the amount o natural

    light and ventilation reaching the playing area. The team worked closely with the

    international Olympic and local organising committees to streamline and rationalise

    the on-eld acilities. The result is a more compact bowl with less distance between

    the spectators and the track.

    3.An I was there moment.

    4. Like most modern stadia, the Birds Nest was designed inside out, beginning with the bowl.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    10/52

    10 The Arup Journal 1/2009

    This complex process has been transormed in recent years by parametric

    relationship modelling. Using powerul computer sotware, designers can quickly

    generate the initial orm o a stadium within defned parameters such as geometri

    constraints, environmental actors, and the limitations o construction materials.

    Having produced the initial concept, the architect can rapidly explore and test

    options by adjusting variables such as the height o a row o seats. For the Nation

    Stadium, ArupSport used its own specialist parametric modelling sotware to dev

    a bowl geometry optimised or Olympic athletics that would also work well or soc

    in legacy mode. The team produced 33 versions o the design to fne-tune the o

    o the bowl (Fig 5).

    The team decided that this landmark Stadium should have the same distinctiv

    external orm in both Olympic and legacy modes, and so the temporary additiona

    seating needed to be accommodated within the main envelope. The temporary s

    which are mainly to the rear o the top tier (Fig 6), have the least-avourable views

    the Stadium and are located in zones that can be converted to other revenue-

    generating uses.

    Creating a stadium that will be both an athletics and a soccer venue is always

    a challenge. Athletics felds are bigger than ootball pitches, which means that

    spectators in the stands are urther away rom the action. Consequently, people i

    upper tiers may not be able to see the ball on the pitch, and the atmosphere wh

    is so important to a soccer crowd may be seriously diluted. One solution to thisproblem is to add a moveable lower seating tier or soccer matches, but the brie

    the National Stadium did not allow or this. Instead, the team opted or a cantileve

    middle tier, with the ront 15 rows o seating extending over the lower tier (Fig 7).

    This brings spectators in the middle and upper levels closer to the action and pro

    a quality o view equivalent to that in a stadium with a moveable tier. The colour o

    seats ranges rom red in the lower tier to white at the top, helping to make the

    Stadium look ull, even when some places are empty (Fig 8).

    5. Parametric design of built version 33.

    8. The colour of the seats randomly merge from red to white.

    a)

    7. Fifteen-row cantilever of middle tier over lower tier.

    6. Initial seating capacity of 100 000.

    b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    11/52

    The Arup Journal 1/

    The team members had to design a stadium that conormed to rigorous local seismic

    codes, while providing a structure stable enough to support a moving roo. To meet

    these two key elements o the brie, they decided at an early stage to keep the bowl

    structurally separate rom the aade/roo structure. The bowl consists o six

    structurally-independent segments with 200mm wide movement joints between them.

    The continuously-curved orm o the seating tiers provides better viewing standards

    or all spectators with lateral views as well as an enhanced C value (the quality o a

    spectators view over the row in ront) or VIP and premium seats (Fig 9).

    The elliptical orm o the bowl, the depth o its structure, the acoustic refectivity o

    its envelope, and a special lining below the ETFE (ethyltetrafuoroethylene) roo

    membranes, all give the Stadium an outstanding acoustic quality (Fig 10). During the

    Olympics, many visitors were surprised and delighted by the atmosphere o intense

    excitement and drama.

    The faade/roof structure

    While Arup was working on the bowl, Herzog & de Meuron began gathering ideas or

    the external orm o the Stadium. The team members knew that to win this prestigious

    architectural competition, they would need to come up with an inimitable design that

    would refect both Chinas rich cultural heritage and its 21st century technological

    prowess. The distinctive roo structure does just that. Its appearance, inspired by

    local crackle-glazed pottery and veined scholar stones, dees structural logic.It is an amazing display o architectural, engineering and construction innovation.

    Local people aectionately nicknamed the Stadium the Birds Nest while the initial

    competition entries were on display in Beijing.

    The roo structure spans a 313m x 266m space, closely enveloping the bowl and

    concourses to orm both aade and roo. The aade incorporates the Stadiums

    main staircases. The result is a compact and sinuous external orm uninterrupted by

    masts, arches, or stair cores. While the aade is open, a roo covering made o

    single-layer ETFE membranes stretched between the steelwork sections protects the

    spectators rom wind and rain (Fig 11).

    9. The continuously-curved orm o the seating tiers provides better viewing standards or all spectators .

    10. The acoustic refectivity o its envelope and lining belothe roo membranes, all give the Stadium an outstandiacoustic quality.

    11. The ETFE membrane.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    12/52

    12 The Arup Journal 1/2009

    12. Sections through the bowl.Top: north-south.Below: east-west.

    Level -1 and mezzanine levels Level 0 Level 1 Leve13. Successive levels ofthe Stadium.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    13/52

    The Arup Journal 1/2

    Level 4 Level 5Level 3 Levels 6 & 7 Key

    Spectator

    FOP and warm-up

    Event manager

    BroadcastMedia

    Olympic amily

    Sponsors

    Venue operation

    Special events

    Security

    Urban domain

    Others

    Athletes and team

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    14/52

    14 The Arup Journal 1/2009

    Reference(1) BURROWS, S, et al. The Allianz Arena: A new ootball

    stadium or Munich, Germany. The Arup Journal,41(1),

    pp24-31, 1/2006.

    We gratefully acknowledge the assistance of Felicity Parsons,

    independent architectural writer based in London, in preparing

    this article.

    The bowl and external orm o the Stadium were

    developed in parallel, with Herzog & de Meuron

    working on the aade and roo while Arup defned

    the size o the bowl and proposed an optimised roo

    structure. The team agreed at an early stage to work

    with 24 nodes or the primary roo structure support,

    and Arup very quickly defned the top and bottom

    roo planes required or the most efcient structure.

    This provided Herzog & de Meuron with an envelope

    orm that did not change signifcantly, even in the

    projects fnal construction design stage.

    The seemingly accidental arrangement o steel

    members that orms the envelope makes it almost

    impossible to distinguish between the primary

    structural elements supporting the roo, the

    secondary staircase structures, and the tertiary

    elements that add to the random eect.

    Each o the aades steel members retains a

    1.2m wide external profle as it twists and bends to

    ollow the saddle-shaped geometry o the Stadium.

    The steel structure is painted light grey, contrasting

    with the red-painted external concrete wall o thebowl, which is clearly visible through the aade.

    This creates a variety o impressive eects,

    particularly when lit at night.

    Conclusion

    With the lavish opening and closing ceremonies,

    the thrill o broken records, and the tragedy o

    shattered dreams, an Olympic Games is nothing i

    not theatrical. The architectural team wanted the

    audience to eel part o the Olympic spectacle rom

    the moment o arrival. To enhance the sense o

    drama, the team decided to leave the aade unclad,

    allowing the staircases that orm part o the roo

    structure to remain open. Weaving past each other

    and oering clear views into every passing zone, they

    ensure visitors have an unusual degree o interaction

    with the building. The result is arguably one o the

    worlds most exciting architectural experiences.

    Importantly, the Stadium is also one o the most

    comortable, usable and high-perormance sports

    venues in the world. Arup has received an

    unprecedented number o glowing testimonials rom

    athletes (both Olympic and Paralympic), spectators,

    the media, the organisers, and the operators.

    Everyone loves the Birds Nest.

    14. The structure, painting, and lighting create an impressive effect, especially at night.

    15. The open structure offers clear v iews both beyond the building and into the zones, ensuhigh degree of interactivity within the Stadium.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    15/52

    The Arup Journal 1/

    The main roo

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    16/52

    16 The Arup Journal 1/2009

    Introduction

    The overall shape and orm o the National Stadium directly responded to tworequirements o the initial project brie it had to have a moving roo, and it shoul

    be designed to withstand seismic events twice the magnitude o the 1976 Great

    Tangshan earthquake that killed more than a quarter o a million people in Beijing

    This would not be the frst stadium with a moving roo to be constructed in a

    seismic zone, nor would it be the frst or Arup (the frm engineered the 45 000-se

    Toyota Stadium, Japan, and the 42 000-capacity Miller Park baseball stadium in

    Milwaukee, USA1). It would, however, be the largest, with an initial capacity o ov

    100 000 spectators.

    In addition to the requirements o the brie, the team rom ArupSport and

    Herzog & de Meuron also wanted to reduce the Stadiums visual mass and avoid

    such structural solutions as masts and arches. So instead, the team opted to wra

    the roo structure closely to the geometric constraints o the seating bowl and the

    concourses (Figs 1, 2).

    Having adopted a philosophy or the buildings orm, the next task was to crea

    a structural solution that conormed to the requirements o brie, location, and

    aesthetics. The answer lay in separating the roo structure rom the bowl structur

    The ormer could be a complete entity with no movement joints, providing a stab

    platorm or the moving roo and thereby greatly simpliying the mechanisation.

    The bowl structure could also be simplifed, as there would be no signifcant inter

    with the roo. The resulting bowl structure was ultimately realised as six complete

    separate buildings each with its own stability system, and 200mm movement join

    between each building.

    Original inspiration

    Though the Beijing National Stadium is oten reerred to as the Birds Nest, the

    original inspiration was rom a combination o local Chinese art orms - the crackl

    glazed pottery that is local to Beijing (Fig 3), and the heavily veined Chinese schostones2. However, when the artist Ai WeiWei3 frst saw the proposal he quickly d

    a bird in a tree. The panelised approach gave way to infnite lines o structure and

    name Birds Nest quickly became synonymous with the project.

    The challenge or the team was to create a loadpath that was sympathetic to

    the architectural intent but also robust enough to deal with both the vertical loads

    resulting rom the large spans and the horizontal loads rom seismic events.

    The solution was a system in which successive layers o structure are superimpo

    This gives the appearance o a chaotic geometry (Figs 4, 5), but has the underlyi

    logic required to resist loading.

    Centreline geometry defnition

    Most the geometry can be assigned to three categories:

    Primary:Thiscomprisedthespacetrusslinesandthemainstructuralsystem

    Secondary:Thiswasusedtobreakupthepanelsizecreatedbythemainstructural system to acilitate the cladding system panels.

    Stairs:Theaccessstairstothetoptierofthebowlwereintegratedintothew

    supporting the roo structure.

    Firstly, the envelope was defned to wrap as closely as possible to the seating bo

    taking the orm o an ellipse on plan with sloping walls and a torus orming the ro

    suraces (Figs 6a-d).

    The Stadium geometry

    Stephen Burrows Martin Simpson

    1. Optimum seating bowl confguration or Olympic mode.

    2. The resulting enclosed volumethat would orm the roo surace.

    3. Beijing crackle glazed pottery:the original inspiration or theStadium roo.

    4 (above); 5 (below). The appearance o chaos.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    17/52

    The Arup Journal 1/

    The geometry or the primary elements orms a relationship between the supporting

    points at ground level and the size and shape o the opening roo position (Figs 7a-b).

    Initially, this opening was defned as small as possible to keep the moving roo

    efcient. When eventually the moving roo was removed rom the design, the size o

    the opening could become much bigger and relate more to the seating bowl.

    The primary geometry was then developed into a 3-D portalised space truss,

    enabling the roo to ollow closely the architectural orm o the bowl and concourse

    structure, while rising to 60m and spanning the required 313m x 266m (Fig 8).

    The secondary geometry, subdividing the primary elements, was only located in

    the outer layer o the aade. This geometry was related back to the primary roo grid

    on plan, but then adjusted using the centre point to create a rotated plane instead o

    a vertical plane (Fig 9). This plane was then struck through the outer surace to create

    the actual secondary geometry used to defne the centre lines o the elements.

    The fnal elements contributing to the overall geometry ormed the perimeter stairs

    (Fig 10). These elements were defned initially by the requirements o the stairs in

    terms o number o risers beore a balcony, length o balcony, and the overall pitch.

    The defnition lines were then allowed to become continuous and run over the roo

    surace to join the aade on the opposite side.

    Though some scripting was required to create the initial geometry, the fnal

    geometry required much manual intervention in moving elements and tweaking the

    angles. In many ways the project is sculptural, and achieving the fnal eect relied on

    a very close working relationship between engineer and architect.

    9. Defnition o the secondary geometry.

    10. (a) & (b) Stair element geometry.

    8. The primary geometry as 3-D portalised space truss.

    6. (a) Elliptical plan o bowl; (b) sloping sides; (c) roo ormed rom a toroid patch;(d) part o torus surace.

    7. (a) & (b) Primary element geometry around opening position.

    a)

    c)

    c)

    a)

    b)

    d)

    d)

    b)

    a)

    a)

    b)

    b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    18/52

    18 The Arup Journal 1/2009

    Twisted elements

    O all the geometrical conditions within the Stadium, perhaps the most challenging

    rom the abrication viewpoint was the requirement to use a continuous box-prole

    over the whole aade.

    This box section was dened using a control surace that was part o the structure

    envelope. The outer fange o the box always remains parallel to the control surace,

    resulting in a twisting, curving box section that changes as the element progresses

    along the surace o the structure. This twisting orm is most pronounced at the eaves

    o the structure or the low-angle elements such as the stair lines (Fig 11).

    Luckily these are usually very lightly loaded.

    The way the geometry was dened resulted in even the most twisted element

    being ormed rom developable suraces. This meant that the individual suraces

    orming the box sections could be fattened out and cut rom a fat steel plate and

    then rolled to orm the abricated box section (Fig 12). This investigation was crucial to

    proving that, though complex, the structure could actually be built.

    Use of virtual prototyping

    The use o CAD sotware was critical to success o the National Stadium, and the

    platorm adopted was CATIA by Dassault Systme. It is used extensively in the

    automotive and aerospace industries, and at the time was the only sotware that

    could handle the complex suraces and geometry requirements o the elements.

    A

    Referencesurface

    Centre line

    of beamA

    C

    A

    InsideOutside

    C

    AC

    A

    C

    Referencesurface

    Relative position of beam surface

    is the same as reference surface

    11. Detail o curved element at the eaves.

    12. Twisted element, showing the our suraces fattened

    13. Stadium models in CATIA, showing the roo (a) closeand (b) open.

    10. Curved elements at the eaves.

    a)

    b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    19/52

    The Arup Journal 1/

    CATIAs ability to deal with a vast number o components allowed the whole Stadiu

    to be assembled in a single environment (Fig 13). The model contained all the

    structural elements, including the perimeter stairs, and the interactions between all

    components were also managed in the same environment. This approach is called

    virtual prototyping4 as all elements can be assembled and tested in a virtual

    environment beore commitment to building the physical reality.

    CATIA is a parametric component-based modelling package. The advantage o

    using parametric sotware is signifcant when dealing with design that is required to

    be adjustable and continually changing like the Stadium. The basic premise is that

    instead o assigning rigid values to geometry such as length, angle, depth, etc, the

    can be assigned parameters that can be adjusted later. Because the sotware is al

    associative, relationships can be set between geometries that allow changes in

    parameters to be propagated through the model and downstream implications o

    changes assessed.

    A simple example is the geometry o the stair line, which was controlled by an

    angle at the level 5 landing. This angle changed the geometry o the stair so that al

    the treads and landing could be hidden behind the supporting structure. However,

    though the stairs terminated at the top level, they ormed part o a continuous line t

    was rom fve separate parts but maintained tangency between each line (Fig 14).

    Using a component modelling system also allowed multiple design scenarios to

    investigated and then deployed throughout the structure. Even though the controll

    geometry was dierent at each location, with the Stadium only having two-oldrotational symmetry, the details that components shared were generally part o a

    amily. The advanced replication acilities with CATIA allowed these amily details to

    propagated throughout the model even i the local geometry conditions were dier

    Physical prototypes

    At each stage o the project, the design team had to satisy itsel and the client tha

    the structure was buildable. Early prototypes were constructed rom card, oamboa

    or 3-D wax printers (Fig 15a). Herzog & de Meuron also built a ull-scale oam-boar

    model to illustrate the scale o the elements being considered (Fig 15b).

    Beore the end o the preliminary design, one o the steel abricators bidding or

    project also completed a ull-scale mock-up o one the nodes rom 40mm steel pla

    (Fig 16). This exercise showed the whole team that this was a realistic design that

    could be abricated in time or the Olympics.

    Final geometry

    The original geometry changed late in the design process due to the omission o th

    moving roo, due to the client needing to reduce the resources and overall cost o t

    Games. It should be noted that the actual cost o the Stadium itsel was comparing

    well to its original estimate, but the overall budget or the Games had to be cut.

    However, due to the advanced sotware technique developed by the team in te

    both o geometry and also analysis, design, and optimisation, the project was able

    be completed on time with only a small delay in the construction programme.

    References

    (1) CHAN, C, et al. Miller Park. The Arup Journal, 37(1), pp24-33, 1/2002.

    (2) http://en.wikipedia.org/wiki/Chinese_scholar%27s_rocks

    (3) http://en.wikipedia.org/wiki/Ai_Weiwei(4) BAILEY, P, et al. The Virtual Building. The Arup Journal,43(2), pp15-25, 2/2008.

    14. Tangency was maintained between the fve sets ogeometry or the stair line by adjusting only one parameteror the angle o the original stair line.

    15. (a) Small-scale card prototype;(b) Full-scale oam board prototype.

    16. Full-scale steel prototype.

    a)

    b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    20/52

    20 The Arup Journal 1/2009

    Original roof analysis model and results

    The main roo comprises interconnected 12m deep plane trusses, orming a thre

    dimensional truss network structural system. A 3-D structural analysis model was

    to carry out static and dynamic analysis o the roo structure, with the complete

    primary and secondary steelwork structure modelled as a skeletal space rame in

    ArupsGSA sotware (Fig 1).

    The analysis model was created using beam elements. The roo is supported

    24 column truss structures, each comprising two inclined truss elements and one

    vertical diamond-shaped element. Fig 2 shows the truss member arrangement o

    column head. At their lower portions, the three column truss elements are very clo

    to each other, and detailed so that all three members merge to orm a single large

    steel element. The column truss structures were assumed to be fxed to the pilec

    with the oundation spring stiness estimated based on the pile load test results.

    The retractable roo included in the original design was attached in its closed

    position to the top o this ull model to allow dynamic analysis with the correct ma

    distribution. Springs with dierent restraints were used to model the bearings and

    bogies that would support the retractable roo (Fig 3).

    Two basic GSA analyses o the roo were perormed, and the results verifed o

    SAP2000 analyses.

    Analysis and prototype testing

    Kylie Lam Thomas Lam

    1. Main components o the original roo design: The retractable section (top right); the main steel trusses supporting the roo, the aade and the retractable section (ar lesecondary members as bracing elements to the main trusses, orming the Stadium geometry (centre). The complete structural model is at the bottom right.

    2. Column head, showing principal elements.

    3. Interace between retractable and fxed roos, andmodelling o the support points restraint.

    Table 1. Limiting element utilisation ratio.

    Element type

    Primary structure:columns

    Primary structure:main truss

    Secondaries

    Static

    80%

    80%

    90%

    80%

    80%

    80%

    90%

    90%

    100%

    Seismiclevel 1

    Seismiclevel 2

    Seismiclevel 3

    100% for slender sectioand 110% for others

    100% for slender sectioand 110% for others

    Not limited: member desassessed by non-linear ana

    Retractableroof

    Primary trusssuporting theretractableroof

    Spring elementto simulate thesupport condition

    Link element tosimulate thebogies

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    21/52

    The Arup Journal 1/

    A static analysis under various combinations o dead,

    live, wind, snow, temperature, and seismic loading

    was carried out. The eects o pattern loading due to

    snow driting and the eects o dierent positions o

    the retractable roo were evaluated separately.

    Dynamic analysis established the undamental

    requencies o vibration and mode shapes, and a

    modal analysis was also undertaken on the ull

    3-D analysis model.

    Detailed seismic analyses were also perormed

    to study the structural behaviour under a level 2

    earthquake. In addition, the rare level 3 earthquake

    was studied to ensure that the roo would not

    collapse under this condition.

    Member design check criteria and force/capacity

    utilisation ratio

    On the roo truss member design, design check

    criteria and limit o orce/capacity utilisation ratios o

    members were set up or dierent types o element in

    terms o their unction and importance to the whole

    structural system (Table 1).Fig 4 shows the members utilisation ratio o the

    main truss under static load combinations.

    Redesign of Stadium roof

    Ater the rst preliminary design submission, the

    Stadium roo was redesigned to meet the reduced

    budget. The major changes included removal o the

    retractable roo and enlargement o the roo opening.

    Fig 5 shows the roo plan, including the retractable

    roo, at the early stage, and Fig 6 shows the nal

    stage o the preliminary design. Fig 7 shows the

    evolution o the arrangement o the main trusses

    during the roo redesign.

    It was essential to maintain the Stadiums

    architectural design principle that secondary

    members should be indistinguishable in size rom

    primary members. To save costs, however, the sizes

    o some 1.2m x 1.2m box sections were revised.

    For example, the cross-section o some top chord

    truss members, invisible rom the plaza level, was

    reduced to 1.0m square. The aade element section

    size, however, was kept at 1.2m x 1.2m.

    Construction stage analyses

    Staged analyses o the xed roo were perormed

    in conjunction with the assumed construction

    sequence. The true refection o constructionsequence to analysis is important or a long-span

    stadium structure, in which the lock-in stress eect

    on secondary members is corrected and prevented i

    the analysis is carried out as a unied whole.

    4. Members utilisation ratio o main truss understatic load combinations.

    5. Preliminary roo design, March 2004.

    6. Preliminary roo design: redesign in November 2004.

    7. Evolution o the roredesign, rom

    preliminary desigstructural concepthe unifcationscheme.

    1.0

    0.8

    0.6

    0.4

    0

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    22/52

    22 The Arup Journal 1/2009

    The construction stage analyses that reected th

    actual erection sequence included 78 installation

    support points or alsework or the roo structur

    erection. The key installation sequence is illustrat

    in Figs 8a-g.

    Based on the loading stage o the structure,

    key construction phases were determined or the

    static construction stage analysis, as ollows:

    Phase1:Construct24columns,faade

    secondary structure, ring trusses in the midd

    and the primary truss (with temporary suppor

    Phase2:Removethetemporarysupportafte

    assembly o primary trusses in sections

    (completion o the main structure).

    Phase3:Constructsecondarystructureonth

    top surace and acade stairs.

    Phase4:Installthepipelinesforcladding

    structure, catwalks, light fttings, and drainpip

    Finite element analysis at nodes

    Forthecurvedandtwistedmembersoftheroof

    the connection nodes where many members metogether, fnite element analysis was used to stud

    the stress distribution. Assuming the material is i

    elastic stage, the results o the calculations were

    expressedinthevonMisesstressdiagram.

    Based on the analysis results, the member an

    connection node design were optimised. The iss

    stressconcentrationcanbeimprovedbymeans

    local member thickening and adjusting the locat

    stieners. Fig 9 shows the fnite element analysis

    theelbowtrussattheeave.

    Prototype testing

    To ensure the saety o the design, prototype tes

    werecarriedoutasverication.A1:2.5scaleelb

    truss and a twisted thinned wall box section wer

    testedattheBeijingTsingHuaUniversity(Figs1

    11),whilst1:2.5scaleprototypesofthedouble

    K-node o primary truss and column top, where

    members merge at the node, were tested at the

    ShanghaiTongjieUniversity(Figs12,13).

    8. Key installation sequence for steel structure: (a) Column bases; (b) Columns and faadesecondary structure; (c) Primary truss and inner ring truss lifted panel by panel and jointed athigh level; (d) Removal of temporary support; (e) Secondary structure of the top surface;(f) Construction of facade stairs; (g) Completion of installation.

    9. Finite element analysis at the elbow truss at the eave.

    a)

    e)

    c)

    b)

    f)

    g)

    d)

    Maximumnode

    Minimumnode

    Von Mises(max (Z1Z2

    > 3.3

    < 3.3

    < 2.7

    < 2.2

    < 1.6

    < 1.1

    < 5.8

    < 3.3

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    23/52

    The Arup Journal 1/

    11. A twisted and bent member at a top roundcorner connecting the top chord truss elementand the raking outer column (elbow truss).

    12. Double K-node of a primary truss.

    13. Column truss connection.

    14. Intersection of inner side of spokes memberswith diamond-shaped inner column.

    15.

    10. Twisted thin-walled box secondary memberbeing tested at Beijing Tsing Hua University.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    24/52

    24 The Arup Journal 1/2009

    The challenge

    The unique structural orm, the architectural constraints, and the clients and the Arupteams desire to reduce the steel tonnage, all posed great challenges to the seismic

    design o the main roo o the Birds Nest.

    The very long 313m span caused the seismic design to be signifcantly dierent in

    several ways rom that o typical tall buildings. Seismic design measures that usually

    achieve the collapse prevention perormance objective or tall buildings under the level

    3 earthquake, or instance limiting inter-storey drits and detailing or ductility, were

    insufcient or the Birds Nest roo structure. It could have collapsed straight

    downwards without lateral sway, due to damage to its gravity orce-resisting system

    rom vertical earthquake ground shaking alone.

    The long span also causes the strength capacity o the primary truss members to

    be taken up primarily by gravity loads. The box section top chord and diagonal

    members in the primary trusses are subject to high axial compression orces under

    gravity loads, and will sustain damage and degrade in strength due to global as well

    as local buckling. They may not retain sufcient strength to prevent collapse when

    damaged by a level 3 earthquake.

    Ductile detailing measures or the bracing members in special concentrically

    braced rames were thus insufcient to prevent collapse o the roo, because the

    bracing members in special concentrically braced rames o normal buildings are not

    part o the gravity orce-resisting system. It was necessary to limit the post-buckling

    axial shortening o the top chords and the compression diagonals o the primary

    trusses, thereby limiting degradation o compressive strength. This, however, was

    beyond the conceptual ramework o the conventional code prescriptive seismic

    design methodology.

    A critical architectural constraint was the uniorm 1.2m x 1.2m cross-section o the

    box section truss members. This is central to the architectural language o the Birds

    Nest a seemingly arbitrary pattern that leaves spectators wondering which

    members are primary structures and which are secondary. To meet the limiting plate

    Seismic design of the roof

    Xiaonian Duan Goman Ho

    width-to-thickness ratio (b/t) o 16 (16:1) and to

    achieve the seismically compact sections require

    GB50011-2001, the minimum thickness needed

    be approximately 70mm. Such a plate thickness

    would result in the use o unacceptably large

    amounts o steel, and lead to very high structura

    sel-weight. This would urther increase the gravi

    load on the structure as well as stiening it, leadto even higher seismic orces. In addition to bein

    uneconomical, using thicker steel plates would

    also have been less eective in achieving the

    collapse prevention perormance objective or a

    level 3 earthquake.

    From the structural design point o view, an

    eective and cost-efcient solution to reducing s

    tonnage and thereby gravity loads and meet th

    ductile detailing requirement o b/t 16 would

    substantially reduce the outer dimension o the b

    section members in both primary and secondary

    trusses. It would be ar easier to achieve seismic

    compact sections with much thinner plates, but

    to the architectural constraints, this option was r

    out in the early stages.

    The behaviour o box section members with t

    walls beyond the elastic limit is governed by thei

    post-buckling behaviour. The Arup team investig

    the eectiveness o welding longitudinal stiener

    transverse diaphragms to the box section walls o

    improving the ductility capacity o these member

    Nonlinear fnite element simulations o the post-

    buckling behaviour o a typical member with a ra

    o stiener sizes and a range o diaphragm dista

    showed that, while the stieners and diaphragm

    eective in postponing local buckling o the walls

    and thereby increasing member axial compressiv

    1. The Stadium illuminated at night against its Beijing backdrop.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    25/52

    The Arup Journal 1/

    strength, their eect on improving post-buckling

    ductility is negligible, because the stieners

    themselves buckle in the post-buckling range o

    response (Fig 2). This set o nonlinear nite elementsimulation results convinced the Arup team early in

    the project to abandon the option o seeking ductility

    so as to meet code prescriptive rule, and instead to

    adopt an alternative seismic design methodology.

    The Arup solution: performance-based

    seismic design

    Having examined several options, the Arup team

    adopted the perormance-based seismic design and

    analysis approach or the roo structure. This is not

    only the most technically rigorous, but also leads to

    the most cost-ecient design. To achieve the

    collapse prevention perormance objective or a level

    3 earthquake, Arup established the ollowing

    perormance targets or the structural members:

    Primarytrussmembersshallremainelasticor

    nearly elastic.

    Secondarytrussmembersarepermittedto

    sustain severe damage.

    Arup used its own Oasys LS-DYNA nonlinear nite

    element analysis sotware to demonstrate how the

    collapse prevention perormance objective could be

    achieved. The nonlinear response history analysis

    captures the time histories o orces and

    deormations in every primary and secondary truss

    member in the inelastic range when subjected to

    triaxial earthquake acceleration time histories,

    representing the ground shaking rom a level 3

    earthquake. A total o three sets o strong motion

    records were used to represent the level 3

    earthquake ground motion input.

    The plate thickness o the box-section primary

    truss members was determined by the need to

    remain elastic or nearly elastic when subjected to the

    level 3 earthquake, without meeting the b/t 16

    requirement or ductile detailing. As a result o this

    Beijing is in an area o moderately high

    seismicity. The regions most recent

    destructive event, the 1976 magnitude 7.8

    Great Tangshan earthquake, had its epicentre

    some 150km south-east o Beijing, which

    suered severe and widespread structural

    damage. Ocial gures indicate that in total

    some 250 000 died as a result o theearthquake, and in Beijing itsel many were

    orced to live in temporary housing or years

    ater. The Beijing municipality implemented an

    extensive programme to retrot surviving

    buildings, and some o the multi-storey

    masonry residences strengthened by

    reinorced concrete rames can still be easily

    identied in the newly-emerging CBD around

    Arups Beijing oce.

    The 1990 edition o the Chinese earthquake

    intensity zonation map1 divides the country

    into ve seismic zones, varying rom V (low) to

    IX (high). Beijing is assigned to intensity zone

    VIII. According to the 2001 edition o the

    Chinese seismic ground motion parameter

    zonation maps2, the peak ground acceleration

    corresponding to 10% o probability o

    exceedance in 50 years is 0.2g. The level oprobability o exceedance adopted or

    drawing up these maps is consistent with

    those in the 1997 edition o the Uniform

    building code3 in the US and Eurocode 84 in

    the EU. Compared to the seismic zone map

    o the USA published in the 1997 UBC, the

    seismicity o Beijing is equivalent to zone 2B

    a level lower than that o Caliornia and

    comparable to most parts o Washington,

    Oregon, and Nevada.

    Performance objectives required by the

    Chinese seismic design code for buildings

    The 1989 edition o the Chinese seismic

    design code or buildings, GBJ 11-895,

    established the ramework or seismic

    perormance objectives o buildings in China.

    The ollowing three levels o perormance haveto be achieved:

    (1) no structural damage and limiting

    non-structural damage in small but

    requent earthquakes (50-year

    return period)

    (2) repairable damage when subjected to

    an intermediate earthquake (500-year

    return period)

    (3) collapse prevention when subjected to

    a large but rare earthquake (2500-year

    return period).

    The intermediate earthquake (level 2)

    corresponds to ground motion intensity value

    as shown in the Chinese seismicity zoning

    maps. The small but requent earthquake

    (level 1) is a once-in-a-lietime event or thedesign working lie o a building. The rare

    earthquake (level 3) has a very low probability

    o being exceeded during a buildings design

    working lie.

    The current Chinese seismic design code,

    GB50011-20016, urther developed this

    conceptual ramework and design/analysis

    methodology by introducing modern,

    non-linear response history analysis and

    non-linear static pushover analysis methods

    to quantitatively veriy satisaction o the

    collapse prevention perormance requirement

    under the level 3 earthquake.

    For buildings within the limitations and scope

    o applicability oGB50011-2001, a dual-leve

    seismic design approach is prescribed. Both

    the level 1 and level 3 perormance objectivesare required to be veried explicitly: strength

    design and limiting inter-storey drit under the

    level 1 earthquake, and checking and limiting

    inter-storey drit and inelastic deormation

    o members under the level 3 earthquake.

    In addition, detailing measures or ductility are

    prescribed or various seismic load-resisting

    systems in various seismic zones.

    The acceptable limits on inter-storey drit

    under the level 1 earthquake are very

    restrictive, refecting the intent o

    GB50011-2001 to limit non-structural

    damage. For instance, the limits on drit ratios

    in reinorced concrete moment-resisting rame

    systems and moment rame/shear wall

    systems are 1/550 and 1/800, respectively.

    The restrictive drit limits prescribed in

    GB50011-2001 oten result in stierstructures compared to similar structures in

    comparable seismic zones but designed to

    other codes.

    The level 2 earthquake perormance objective

    is deemed to have been achieved by

    GB50011 - 2001 i the design has satised

    the level 1 and level 3 perormance

    requirements and those or ductile detailing.

    Regional seismicity

    design approach, the lowest plate thickness o the primary truss box-section

    members was reduced to 8mm, with the highest being 100mm. Most members ha

    a plate thickness

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    26/52

    26 The Arup Journal 1/2009

    AXIAL DEFORMATION (m)

    FEMA 356 backbone curve

    Non-linear finite element simulation

    0.060.050.040.030.020.010

    AXIALFORC

    E(MN)

    8

    6

    5

    4

    3

    2

    1

    0

    -1

    4. Damage states of (a) primary truss members and (b) primaryand secondary truss members.

    5. The varying plate thicknesses of the box section members are entirely concealed.

    3. Post-buckling axial force/axial deformation relationship of atypical primary truss member.

    The Arup teams computer simulation suggested that the box section members

    possess, to some extent, higher strength and deormation capacities, but the gre

    curve was adopted so as to be conservative in the global structures nonlinear

    response history analysis.

    Initial nonlinear computer simulations indicated that, in some analysis cases,

    collapse may occur when subjected to the strong ground shaking o the level 3

    earthquake. Arup examined the collapse process in these computer runs and

    identifed the critical primary truss members that needed to be strengthened.

    Ater a ew iterations, the collapse prevention perormance objective was achieve

    in all analysis cases.In the damage states o the roo truss members (Fig 4), most primary membe

    remained elastic (green), but some sustained moderate damage (blue: the immed

    occupancy damage state), entering slightly into the post-buckling range o respo

    Only a ew reached the signifcant damage state (yellow: the lie saety damage st

    responding well into the post-buckling range o response but without reaching th

    point at which strength starts to degrade.

    On the other hand, as the perormance objective had intended, many second

    truss members were damaged severely (red: the collapse prevention perormanc

    objective), exhibiting signifcant strength degradation.

    Elastic Immediate occupancy

    Life safe Collapse prevention

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    27/52

    The Arup Journal 1/

    The expert panel review process for approval

    The importance o the National Stadium project meant that, besides the normal

    approval procedure, the Beijing Municipal government set up an expert panel

    committee to review the structural design, a process similar to that in Japan.

    In both countries, expert panel review and approval oten requires explicit verifcatio

    o perormance under all three earthquake levels, and nonlinear response history

    analysis is required to demonstrate that the collapse prevention perormance

    objective under the level 3 earthquake has been achieved.In May 2004, the expert panel met or two days in Beijing to review the prelimina

    design o all disciplines or the Birds Nest. The panel included several chie

    structural engineers o local architectural design institutes, as well as members o t

    China Academy o Engineering who are recognised experts in long-span roo

    structures. At the end o the rigorous review meeting, Arups structural preliminary

    design passed the review and was endorsed by the panel or approval.

    Added value

    Arups perormance-based seismic design is not only innovative and rigorous,

    but also cost-efcient, creating exceptional value or the client. The innovative conc

    o nearly elastic design subjected to the level 3 earthquake, assisted by the

    perormance-based seismic design and analysis methodology using state-o-the-a

    nonlinear numerical simulation technology, not only convincingly demonstrated

    achievement o the collapse prevention perormance objective, but also resulted in

    very signifcant reduction in the quantity o steel used. The plate thickness o most

    1.2m x 1.2m box-section roo members is substantially lower than the 70mm requ

    by the ductile detailing rules specifed in many international seismic design codes,

    instance American Institute o Steel Constructions Seismic Provisions or Structura

    Steel Buildings10, or achieving seismically compact (equivalent to class 1 plastic in

    terms o Eurocode 37) sections.

    Figs 6 and 7 illustrate the distributions o plate thickness o the chord members

    the primary trusses. Only two groups o top chord members and our groups o

    bottom chord members reach or exceed 70mm plate thickness.

    References

    (1) CHINA EARTHQUAKE ADMINISTRATION. Earthquake intensity zonation map o China. State Coo the Peoples Republic o China, 1990.

    (2) CHINA EARTHQUAKE ADMINISTRATION. GB18306-2001: Seismic ground motion parameter

    zonation map o China. General Administration o Quality Supervision, Inspection and Quarantine o

    Peoples Republic o China, 2001.

    (3) INTERNATIONAL CONFERENCE OF BUILDING OFFICIALS. 1997 Uniorm building code. Volume

    Structural engineering design provisions. UBC, 1997.

    (4) EUROPEAN COMMITTEE FOR STANDARDIZATION, EN 1998-1: 2004/Eurocode 8: Design o

    structures or earthquake resistance Part 1: general rules, seismic actions and rules or buildings,

    December 2004.

    (5) MINISTRY OF CONSTRUCTION. National Standard of the Peoples Republic of China GBJ 11-89

    Code or seismic design o buildings. The Ministry, 1989.

    (6) MINISTRY OF CONSTRUCTION. National Standard of the Peoples Republic of China

    GB50011-2001. Code or seismic design o buildings. The Ministry, 20 July 2001. Actualised: 1 Jan

    2002.

    (7) EUROPEAN COMMITTEE FOR STANDARDIZATION. EN 1993-1-1: 2005/Eurocode 3. Design o

    structures. Part 1-1: general rules and rules or buildings. EC, May 2005.

    (8) FEDERAL EMERGENCY MANAGEMENT AGENCY. FEMA 356. Prestandard and commentary o

    seismic rehabilitation o buildings. American Society o Civil Engineers, 2000.

    (9) MINISTRY OF CONSTRUCTION. National Standard of the Peoples Republic of China GB50017

    2003. Code or design o steel structures. The Ministry, 25 April 2003. Actualised: 1 December 20

    (10) AMERICAN INSTITUTE OF STEEL CONSTRUCTION.AISC/ANSI 34105. Seismic provisions o

    structural steel buildings. AISC, March 2005.

    20 x 20

    20 x 25

    25 x 25

    25 x 30

    30 x 30

    30 x 36

    30 x 42

    36 x 36

    36 x 42

    42 x 42

    42 x 50

    50 x 60

    60 x 60

    20 x 20

    20 x 25

    25 x 25

    20 x 30

    25 x 30

    20 x 36

    30 x 30

    25 x 36

    30 x 36

    36 x 36

    30 x 42

    36 x 42

    42 x 42

    42 x 50

    50 x 60

    25 x 30

    20 x 36

    30 x 30

    25 x 36

    30 x 36

    25 x 42

    30 x 42

    36 x 42

    30 x 50

    50 x 50

    50 x 60

    50 x 70

    70 x 70

    80 x 80

    90 x 90

    20 x 20

    20 x 25

    25 x 25

    20 x 30

    25 x 30

    30 x 30

    30 x 36

    36 x 36

    42 x 42

    42 x 50

    50 x 50

    60 x 60

    70 x 70

    70 x 80

    6. Plate thickness distribution of (a) 1.2m deep x 1.2m wide,and (b) 1.0m deep x 1.2m wide top chord members of theprimary truss (all thicknesses in mm).

    7. Plate thickness distribution of (a) 0.8m deep x 1.2m wide,and (b) 1.2m deep x 1.2m wide bottom chord members ofthe primary truss (all thicknesses in mm).

    a)

    a)

    b)

    b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    28/52

    28 The Arup Journal 1/2009

    The retractable roof design

    John Lyle

    2. The retractable roo in open position.

    1. The fnal design allowed a larger opening above the pitch and a reduction in the amount o steel used in the fxed roo.

    Design concept

    Arups brie or the retractable roo covered the

    development o a perormance specication

    alongside the structural, mechanisation, and con

    system scheme design to demonstrate easibility

    The original competition entry comprised two

    large retractable roo panels that split at the halw

    line and parked at the ends over the xed roo w

    open. Further development o this concept led to

    retractable roo structure that refected the seem

    irregular Birds Nest structure o the xed roo.

    Retractable roos and the systems required to

    move them need rom the start to be considered

    holistically with the xed structure. The sheer size

    weight o what is being moved means that its

    Background

    Any account o the development o Beijing National Stadium would be incomplete

    without some reerence to the retractable roo. Its design dominated much o the

    Stadiums early development beore it was nally omitted as a cost-saving measure in

    June 2004, due both to the rising cost o steel and political pressures to keep the

    Olympic budget under control.

    When planning Olympiads, the use o the stadium ater the Games has become a

    major part o the sustainability and economic discussions - Olympic venues are oten

    noted more or their poor utilisation ollowing the Games than their long-term

    contributions to regenerate or add new acilities to host cities. The Beijing Organising

    Committee (BOCOG) intended to resolve these issues by including a retractable roo

    that could transorm the Stadium into a large indoor arena and thereore extend the

    range o events that could be held throughout the year. This did not happen. However,

    removing the retractable roo rom the design allowed a larger opening above the

    pitch and a reduction in the amount o steel used in the xed roo, and in hindsight,

    the iconic architecture around the Beijing Olympic Park and the overall success o the

    National Stadium (even without its retractable jewel) justies the decision.

    Arup took the design o the retractable roo rom its early concept up to a airly

    advanced scheme design stage. All this work, including discussions with specialist

    contractors and initial meetings with the expert panel review team in Beijing, was

    completed beore the decision was taken to cancel the retractable roo.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    29/52

    The Arup Journal 1/

    behaviour infuences the perormance o the other components, and vice versa.

    Arups concept, thereore, needed to address the compatibility o movements

    between the xed and the movable structures induced by the latter as well as

    imposed loads (such as snow, wind and seismic), thermal movements, and

    construction tolerances.

    Fabrication and erection issues also had to be considered rom the outset.The overall erection strategy adopted by Arup was to maximise preabrication and

    minimise in situ assembly undertaken 70m-80m above ground. The scheme reduced

    construction and commissioning time by using ground level-based assembly

    methods, allowing near-nished components to be craned onto the xed roo.

    This approach was combined with an o-site test and development programme

    to eliminate any development during nal installation, as part o the overall risk

    reduction process.

    Preliminary design

    A retractable roo design that met both the architectural ambitions and was

    mechanically reliable was the obvious goal, and these targets became the key drivers.

    Retractable roof structure

    The retractable roo structure geometry comprised two halves, each spanning 75mand 70m long. At the back edge o each hal (ie the ends urthest rom the opening),

    the perimeter ollowed the same curve (in plan) as the xed roo perimeter so that

    back edge o the retractable roo would merge with the xed roo when in the open

    position. At the ront o each hal, the edge was a more complex curve: when the two

    halves moved rom open to closed, they would orm the distinctive yin-yang shape

    at the halway line (Fig 3).

    The adopted design split each hal-roo into ve dierent triangular panels so that

    each hal o the roo would move as a train o connected panels (Fig 3). This approach

    would reduce the loads in both retractable and xed structure considerably.

    The triangular panels consisted o primary and secondary steel trusses, the ormer

    (maximum 8.2m deep) spanning between bogie support points and carrying the load

    across the main span. The secondary members, spanning between the primary

    trusses, would act both as lateral restraint or the primaries and as a method o

    transerring vertical loads back to the main spans.

    Separating the roo into discrete panels had signicant benets:

    Supportingthethreecornersofeachtr iangularpanelmeantthatthesupports

    were always in contact with the main roo. This statically determinate condition

    allowed the support conditions to be simplied.

    Theseparatepanelsalsoallowedtheretractablerooftoarticulate,meaningthat

    the xed roo did not need to conorm to strict displacement criteria; vertical

    movements in it would be easily accommodated.

    Separatingtheroofintosmallerpanelsmeantthat itcouldbebuiltontheground

    and lited in, reducing the amount o in situ construction.

    The layout o the primary and secondary trusses w

    co-ordinated with the xed roo geometry to reduc

    the visual density o steelwork when seen rom ab

    during TV coverage o major events. In the open

    position, the secondary structural members in the

    retractable roo aligned directly above the steelwoin the xed roo. When closed, the retractable roo

    primary members aligned with the xed roo

    members to provide visual continuity (Fig 4).

    Structural analysis

    A 3-D structural model o the panels was construc

    and analysed using the Oasys program GSA to

    assess static and dynamic load cases on all ve

    panels and to check compliance with the Chinese

    steel code.

    Imposed loads were similar to those used or th

    xed roo, with the ollowing additions:

    Seismic: A rst pass seismic analysis was

    perormed using a code-based spectra and dynam

    response analysis. Because o the complexity in th

    load paths, this was later developed into a combin

    xed and retractable non-linear seismic model usi

    LS/DYNA non-linear nite element analysis sotwa

    3. (a) Retractable roo truss structure; (b) detail.

    4. Continuity between fxed and retractable roo.

    a) b)

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    30/52

    30 The Arup Journal 1/2009

    Racking loads: Two additional static loads were reviewed or out-o-tolerance

    positions during movement (100mm longitudinal racking load and a 200mm verti

    dierential movement within a panel.)

    Mechanisation system

    This comprised the bogies and drive components needed to move the retractabl

    roo. While there is no universally preerred approach or retractable roo bogies a

    drive systems, the mechanisation design strove or several objectives in pursuit o

    reliability and cost-eectiveness. The key eature connecting these objectives wa

    mechanical simplicity.

    Bogie design

    Each bogie, typically weighing about 3 tonnes, would support the corners o the

    triangular roo panels. At the interace between the bogie and panels, proprietary

    spherical thrust and sliding bearings would accommodate the movements and ca

    the lateral loads induced by the drive system and inclined tracks.

    The bogies also had to provide stability in an extreme seismic event, and addi

    restraint was provided by sliding restraints transerring loads onto the xed roo

    structure. These tie-downs also transerred any uplit loads induced by wind.

    Drive system

    The gradient o the curved track on the xed roo (10 at its steepest) meant that

    powered railway-type bogie system could not be driven reliably without a rack-anpinion drive or winch-driven system. While there was sucient space within the b

    to package the ormer, the design progressed using a wire rope (cable) winch sys

    as this was the most cost-eective option.

    The reeving arrangement chosen conveniently houses the winches within the

    retractable roo, reducing the amount o exposed equipment on the xed roo.

    Mounting the haul ropes, drums and winches on the bogies also reduced the ove

    length o steel cables required and improved positional control. The cable would

    move relative to the xed roo, so additional sheave rollers on the roo or return pu

    would not be needed (Fig 4).

    Based on the scheme selected, either hydraulic motor drives or three-phase

    electric induction motor systems (around 150kW) could be used to move the roo

    Control system

    An automatic system was selected to control the movement o the roo, with onlyminimal operator intervention. A sel-equalising drive system would ensure that th

    roo moved without skewing on the rails. Accurate positional control would minim

    position errors caused by tolerances, structural defection, wind, or lack o

    synchronisation between motor drives on each side, and i errors did occur,

    they could be corrected quickly.

    Electrically-controlled ail-sae brakes were included in the design to eliminat

    risk o control system ailures. Arup also completed an initial FMEA (ailure modes

    eects analysis) or the retractable roo to evaluate the system-wide risks or

    potentially catastrophic events such as cable ailures.

    Retractable roo perormance specifcation

    A signicant reason or undertaking the retractable roo scheme design was to

    develop a robust perormance specication, which as a result not only developed

    basic unctional requirements such as opening and closing speeds, design lie,

    operating wind, and temperature envelopes, but also allowed relevant structural

    interace loads, defections, and tolerances to be described. Other details, such a

    drainage and sealing and control and maintenance requirements, were also ident

    in the specications.

    The combination o the reerence design and perormance specication allowe

    competitive tenders to be obtained or the mechanisation systems as part o a

    retractable roo procurement process that was based on a properly integrated de

    8. Plan of retractable roof showing positions of bogies.

    Closing seal to otherhal o retractable roo Anchor block

    Track

    Rollerbearing unit

    Slidingconnection

    Pinnedconnection

    Pinnedconnection

    Tip lock device

    Brakingunit

    Runway beam - topchord o 12m truss

    Anchor block

    Bogie withcable drum

    Cable

    Passive bogie

    Passive bogie

    Bogie withcable drum

    Front oretractable roo

    Rear oretractable roo

    6. Bogie in place.

    7. Detail of bogie.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    31/52

    The Arup Journal 1/

    The bow

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    32/52

    32 The Arup Journal 1/2009

    Geometry and profle

    The plan geometry comprises a radial grid that denes the rames and a aceted grid

    dening the circumerence (Fig 3). The east and west seating radius varies rom about

    270m to 320m, whilst the north and south seating radius is between 60m and 110m.

    The nominal spacing o the radial grid is 7.5m, tapering towards the pitch. To suit the

    roos overall saddle shape, the number o storeys varies at dierent places, rom a

    maximum o seven (51m tall) on the east/west centreline to ve (45m tall) on the

    north/south centreline (Figs 4, 5).

    Foundations

    All vertical loadbearing elements are supported on reinorced concrete pile

    caps supported by cast in situ concrete bored piles with a diameter between

    800mm and 1000mm, ounded in the cobble/gravel stratum layer, about 38m below

    existing ground. A plinth with a one-storey basement surrounds the concrete bowl

    area, resting on a shallow pad oundation on the natural subgrade at about 8.5mbelow existing ground.

    Superstructure

    The bowl is split into six segments (Fig 3) with 200mm wide movement joints between

    them. Each segment orms an independent structure with its own stability system

    provided by column-beam rame action and the concrete staircase and lit cores.

    The six segments are between 120m and 150m long. The movement joints that

    separate them are continuous through every foor o the bowl, including the terracing,

    but are not required at basement level. The lower ground level is o 500mm thick fat

    slab construction, acting as a foor diaphragm to tie together the oundations.

    The upper foors are generally 175-225mm thick reinorced concrete slabs

    spanning between 600mm x 1000mm deep primary beams at about 7.5m centres on

    the radial gridlines that dene the rames. The slab thickness changes due to the

    increasing span caused by the tapering o these gridlines.

    Layout and analysis model

    For the middle and upper tiers, the terracing is

    ormed rom precast L-shaped units spanning

    between the primary rames, and supported on

    inclined tribune beams (Fig 6). For the middle tie

    the tribune beams are 1000mm x 1000mm deep

    on the upper tier, due to increased spans, their d

    increases to 1.2m.

    The columns are generally located on every ra

    grid line. Under the lower tier they are all vertical,or the middle and upper tiers, the ront column i

    inclined towards the pitch in the radial plane to

    reduce the cantilever length o the tribune beams

    At the back, the columns are inclined both radia

    and circumerentially. Inclining the columns is a

    eature o the architectural design, bringing the

    designedly chaotic aade member arrangeme

    into the concourse area (Fig 7).

    Tony Choi Thomas Lam

    1. Inclined tribune beams to support precast units that form the terracing.

    North/southsegments

    East/westsegments

    3. Grid system and movement joint disposition.

    2. Columns are inclined both radially and circumferentiathe back of the bowl.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    33/52

    The Arup Journal 1/

    Ring beam

    Tribune beam

    Tribune beam

    Ring beam

    Tribune beam

    Tribune beam

    7. Inclined columns in concourse area.

    5. East/west segment.

    6. (a) Section through north/south segment;(b) Section through east/west segment.

    (a)

    (a)

    (c)

    (e)

    (g)

    (b)

    (d

    (f)

    (b)

    8. Modelling analysis of the structure.

    4. North/south segment.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    34/52

    34 The Arup Journal 1/2009

    Compared with that o the roo, the seismic design o the bowl structure o theBirds Nest was more straightorward, within the limits and scope o the seismic

    code GB50011-2001. Apart rom being supported on a single continuous pile

    oundation system, the two structures are completely separated rom each other,

    and as already noted, the bowl is divided into six independent structures by

    movement/seismic joints, wide enough to accommodate both thermal expansion

    seismic moments (Fig 1). In dividing the bowl, the symmetrical plan layout adopte

    had the eect o reducing the number o dierent bowl structures to two: the eas

    west bowls and the north\south bowls, respectively approximately 150m and 120

    long. The east\west bowl structure has six to seven storeys with a maximum

    structural height o 51m; the north\south bowl has ve to six storeys and a struct

    height o 45m on the lowest point on the north/south centreline.

    In each independent bowl structure, the two lit cores eccentrically located tow

    the back o the structure orm two structural shear wall cores, resisting both grav

    orces and most o the lateral orces delivered to them by the foor diaphragms (F

    The moment-resisting rames primarily support gravity loads and, together with th

    cores and diaphragms, orm a combined reinorced concrete moment rame\she

    wall lateral orce resisting system.

    As required by GB50011-2001, a dual-level seismic design approach was ado

    or the bowl structure. Moment rames and core walls are sized and proportioned

    that member strength capacities equal or exceed member orce demands, and

    inter-storey drit ratios are limited to 1/800 when subjected to a level 1 earthquak

    Arup was responsible or the bowl structures up to scheme design level, and

    subsequently assisted the Local Design Institute CADG on the preliminary design

    and construction drawings.

    Seismic design of the bowl

    Xiaonian Duan Goman Ho

    2. Structural system, showing lift cores.

    1. Movement/seismic joint between segments of thebowl structure.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    35/52

    The Arup Journal 1/

    Specialist engineering desig

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    36/52

    36 The Arup Journal 1/2009

    The roof comprises two membrane layers. The outer is a single-layer transparent

    ETFE (ethyltetrafluoroethylene) stretching membrane system (Fig 2), which functio

    as weatherproof protection to the spectator stands. The inner and ceiling membr

    is a single-layer translucent PTFE (polytetrafluoroethylene) membrane system (Fig

    which serves as the acoustic ceiling and provides shade for the spectators.

    The separation between the membranes is approximately 13m (Fig 4).

    Because of the interwoven truss structure, the shapes of the roof segments ar

    entirely irregular, varying between triangular and octagonal. There are around 100

    ETFE panels on the roof, ranging in size from 1m2 to 230m2. Altogether, the ETFE

    panels total some 38 000m2. The ETFE membrane is stressed over a subframe oarches in tubular steel supported on the structural gutter elements, welded to the

    top chord (Fig 1).

    The approximately 800 PTFE panels for the acoustic ceiling range from 5m2 to

    250m2, and total about 53 000m2. The PTFE acoustic ceiling membrane system

    is stretched to the tube subframe structure suspended from the underside of

    the roof truss.

    Arups scope on the roof cladding and acoustic ceiling was to design for the

    loading effects onto the supporting roof structure.

    Tony Choi

    Roof cladding and

    acoustic ceiling

    Shade for spectators

    Minimal TV shadow

    Matt ETFE film

    Protection fromcold air

    Warm air releasedthrough openings

    Outer ETFE membrane

    Inner PTFE membrane

    PTFmem

    Acousticabsoption

    100%

    Daylighttransmission

    93.0%

    55.8%

    18.4%

    TransparentETFE film

    Outer ETFE membrane

    Stretching wireshemed with ETFE film

    ETFE film

    ETFE film

    Weldedgutter

    Weldedgutter

    Steel pipearches

    Steel pipearches

    Steel platebrackets

    Steel platebrackets

    Stretching wires for acousticceiling suspension poles

    Watertightaluminium strip

    Watertightaluminium strip

    Security system along all beams

    1. Details of fixing for ETFE cladding.

    4. Section through Stadium showing locations of ETFE and PTFE cladding.

    3. The innermembrane is a single-layer translucent PTFE membrane, which serves as the acoceiling and provides shade for the spectators.

    2. Outer ETFE cladding.

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    37/52

    The Arup Journal 1/

    A combined boundary layer wind tunnel and numerical modelling study was

    carried out to assess spectator comort levels or the Stadium, with wind tunnel

    measurements being made or the external plaza surrounding it, and or the

    concourses and key seating areas within. These wind speeds were used in assessing

    pedestrian saety and comort in and around the Stadium (Figs 1, 2). Wind conditions

    in the Stadium and external plaza are generally suitable to strolling or or short periods

    o standing or sitting. No areas would be uncomortable or strolling, which was

    entirely acceptable or the intended usage.

    The International Association o Athletics Federations (IAAF) competition rules

    stipulate that, or all athletics records up to and including 200m, the long jump and

    the triple jump, inormation concerning wind speed must be available. I the wind

    velocity behind the athlete in the direction o running averages more than 2m/sec, the

    record will not be accepted. Measurements were thereore also made o wind speeds

    around the tracks, and the results presented in terms o percentage o the time that

    mean and gust wind speeds would exceed around 2m/sec on the track, notably or

    the sprint and horizontal jumps area (Table 1). The results showed wind conditions in

    the athletic arena during the summer months to be, on average, very benign.

    In addition, wind speed measurements were made over the tured areas o the feld

    so as to develop appropriate turfng strategies or the Stadium (Fig 3). An important

    aspect o tur health and growth is air movement. Assuming a reasonable criterion or

    acceptable ventilation to be 1m-2m/sec, Fig 3 shows that the south-west and

    north-west corner zones are better ventilated than other areas o the feld (north is at

    the right). In addition, the tur ventilation data are combined by the tur consultant with

    assessments o sunlight patterns and daily temperatures and humidity to determine

    how well tur grass will thrive under the given combined conditions.

    Alex To

    Wind conditions in the Stadium

    and external plaza

    3. Wind speed contour over the turfed area.

    2. Wind comfort range in the external plaza.

    1. External plaza.

    Table 1. Exceedances of 2m/sec tailwind for various evenduring summer.

    EventsAmount of time ta

    exceeds 2m/

    100m/200m sprints 5.44%

    100m/110m hurdles 4.80%

    Long and triple jumps (north to south) 0.00%

    Long and triple jumps (south to north) 7.07%

  • 7/30/2019 Arup Journal 1-2009 beijing stadium

    38/52

    38 The Arup Journal 1/2009

    The Beijing Olymp