greece
TRANSCRIPT
Clickable contents
In focus
Tunnels under study
Invitations to tender
Contract announcements
Safety and rehabilitation
Site reports
Inaugurations
Events & recognition
23 Oct. 2009
Site reports
#49
As a consequence, the TBM was obliged to stand still for an extended
period while personnel undertook an extensive maintenance campaign
under hyperbaric conditions to remove iron and substitute the damaged
tools. In one week, a record eight hyperbaric interventions were carried
out under a pressure of 1.7 bar.
The north TBM faced the further challenge of passing under the 15th
century Alkazar mosque. The religious building showed a top level risk
of falling equal to 3 and an extremely frail structure, as proved by
several extended fractures on the dome and on walls. This was due to
the fact that the mosque had been enlarged and recast several times
and suffered earthquake damage. A further critical event then occurred:
while building up the diaphragm walls of the station next to the mosque,
the variation of the hydro geological balance caused the structure a
differential crush of 55 mm, concentrated at the angle under which the
TBM passed. The TBM successfully passed under the Alkazar mosque
in late August 2009.
On the whole, excavation proceeded in an extremely controlled and
optimal way thanks to strict application of excavation and control
procedures, constant parameter analysis and the organisation of
periodical meetings with operators.
The €958 million contract – awarded by Attiko Metro in 2007 to a
consortium of Aegek, Impregilo, Ansaldo Trasporti, Ansaldo Breda and
SELI – includes the design, construction and commissioning of a 7.7 km
twin tunnel, 13 new stations, an operation control centre, connection
works of the line with the rolling stock depot, an administration building
and the rolling stock material. SELI is in charge of boring the tunnels,
utilising two EPB TBMs driving from two opposite portals. The final
tunnels will have an internal diameter of 5.30 m and an external
diameter of 5.90 m and will be lined with 30 cm thick precast concrete
segments. Geology along the alignment is comprised of stiff clay, silty
clay, gravels and clay.
The TBMs are equipped with special safety systems and AFS for the
automatic injection of bentonite to the face in the event of a pressure
Greece
TBMs successfully face several challenges at Thessaloniki metro
The two Herrenknecht EPB TBMs involved in the Thessaloniki metro
construction entered into full production in July 2009. Excavation by
the SELI-Aegek joint venture is now proceeding regularly. After
crossing four metro stations and passing under a 600-year old
mosque with top level risk of caving in, the two EPB TBMs are now
advancing regularly with a daily output of 18.75 m/day and 16.05
m/day, respectively. Since start of excavation, the average output of
the south and north machines has been 12.47 m/day and 14.17
m/day, respectively.
The south TBM output has increased from 6.7 m/day in April 2009 to
18.75 m/day in August 2009. A maximum output of 27 m/day was
achieved on 28 August 2009.
The north TBM output has increased as well, from 5.35 m/day in April
2009 up to 16 m/day in August 2009. A maximum advance of 22.46
m/day was reached on 5 August 2009.
In early 2009, excavation of the first stretch proved to be complex and
was slowed down by several challenges. Several critical situations
complicated work even more: crossing four stations, the presence of
historical buildings and a shallow geology of sand, clay and sandy
clay. Primary grouting was carried out using the bi-component
technique.
The south TBM passed through the first four metro stations where
only diaphragm walls were completed. The station body will be
excavated at a later stage. SELI-Aegek personnel, however,
discovered unexpectedly that diaphragm reinforcement was made of
iron, rather than fibre glass, as previously believed, in two walls of the
first two stations. The second, north TBM found steel reinforcement in
one diaphragm wall of the same station.
© Copyright Tunnel Info Services 2009 – All rights reserved
www.tunnelinfo.com
23 Oct. 2009
Clickable contents
In focus
Tunnels under study Invitations to tender
Contract announcements Safety and rehabilitation
Site reports Inaugurations
Companies
Site reports
#49
hour and reaches mechanical resistances varying from 0.05 to 0.1
N/mm². The resistance to compression depends on cement dosage
and the silicate used. The injection pressure of the backfilling
grouting begins working on the outer surface of the lining,
immediately after the TBM tail shield has passed.
Distribution of grout pressure uniforms immediately after injection,
because the mixture is still in a liquid/plastic status. When the grout
hardens, the surrounding pressure changes in function of the grout
mix compression, the lining deformation and the load of the
surrounding ground.
The ground conditioning agents supplied by InnoTek were added
and mixed with the muck in the TBM excavation chamber. These
agents contribute to form, when mixed with the muck, an
impermeable thick past that is necessary for a proper EPB
operation. These products were sprayed directly to the tunnel face
through the cutterhead as well injected in the excavation chamber.
The same agents also contribute to reduce the energy consumption
and the wear of the cutterhead as well of the screw conveyor.
INNtens TK 57 is a high-performance liquid foaming agent based on
biodegradable anionic surfactants, which can be used both in fresh
and salt water. INNtens TK 57 is biodegradable, non toxic and easy
to use.
INNtens TK 70 is a liquid foaming agent based on a high-efficiency
natural polymer. The foam generated has a high mechanical
resistance and is an excellent lubricant. INNtens TK 70 is quickly
soluble in water, biodegradable and non toxic.
decrease.
Works started in early 2009 and will be completed in 2012. When
operational in 2013, the line will offer capacity for 18,000 passengers
per hour for every track and a train frequency of 90 seconds.
InnoTek products for Thessaloniki metro construction
The successful application of InnoTek products in the Thessaloniki
metro construction project has made excavation easier and facilitated
work progress. These products make it easier to confront geologically
critical situations during excavation and guarantee the stability of the
excavation face. Innotek supplied its special TBM cutting tools made
of tungsten carbide steel extremely resistant to wear (ex. rippers,
cutter bits and scrapers), the EPB ground conditioning agents (i.e.
INNtens TK 57 and INNtens TK 70) and two bi-component grout
plants, for the backfilling of the segmental lining, expressively
designed and manufactured for the Thessaloniki project needs.
InnoTek supplied two backfilling grout injection plants. The plants
themselves are custom-made products that InnoTek designed and
built, based on the real working needs of the Thessaloniki project.
The backfilling grout injection plants enable bi-component, a special
cement compound, to be dosed, mixed and pumped into the annulus
gap behind the segments, through the tail shield of the TBM. The gap
is filled simultaneously with TBM advancement, thanks to injection
pipes positioned in the TBM tail shield.
This system utilises a liquid component “A” (cement, bentonite, water
and setting retarder) and a liquid component “B” (sodium silicate).
When combined, the two components in few seconds react and
change status from liquid to plastic. The plastic status is maintained
for approx. 30 minutes. The compound then hardens in approx. one
© Copyright Tunnel Info Services 2009 – All rights reserved
www.tunnelinfo.com