arrival times at highway-railroad grade crossing

26
By: Diego B. Franca, M.Sc. Kittelson and Associates, Inc Elizabeth “Libby” Jones, PhD Assoc. Professor, Civil Engineering, University of Nebraska - Lincoln Assoc. Director , Mid-America Transportation Center Presented at 89th TRB Annual Meeting – Jan 2010 Estimating Train Arrival Times at Highway-Railroad Grade Crossing Using Multiple Sensors

Upload: guest773bc2

Post on 05-Dec-2014

663 views

Category:

Business


0 download

DESCRIPTION

Estimating Train Arrival Times at Highway-Railroad Grade Crossing Using Multiple Sensors. Presented at the 89th TRB Annual Meeting – Jan 2010.

TRANSCRIPT

Page 1: Arrival Times at Highway-Railroad Grade Crossing

By:Diego B. Franca, M.Sc.

Kittelson and Associates, Inc

Elizabeth “Libby” Jones, PhDAssoc. Professor, Civil Engineering, University of Nebraska -

LincolnAssoc. Director , Mid-America Transportation Center

Presented at 89th TRB Annual Meeting – Jan 2010

Estimating Train Arrival Times at Highway-Railroad Grade Crossing Using Multiple Sensors

Page 2: Arrival Times at Highway-Railroad Grade Crossing

Presentation OutlinePresentation Outline

IntroductionProblem StatementLiterature ReviewMethodologyData CollectionData Analysis and ResultsFinal Considerations

Page 3: Arrival Times at Highway-Railroad Grade Crossing

IntroductionIntroduction

Highway-Railroad Grade Crossings (HRGCs) Overview

“The general area where a highway and a railroad’s right of way cross at the same level, within which are included the railroad tracks, highway, and traffic control devices for highway traffic traversing that area” (MUTCD, 2007)

Page 4: Arrival Times at Highway-Railroad Grade Crossing

IntroductionIntroduction

HRGCs Concerns– Collisions at HRGCs represent the second largest

cause of fatalities in railroads (trespassing is the first).

– HRGCs near signalized intersections present a safety concern due to the potential queues of highway traffic that can back up across the tracks.

Page 5: Arrival Times at Highway-Railroad Grade Crossing

IntroductionIntroduction

Traffic Signal Preemption at HRGCs– The MUTCD requires a 20-second minimum time for

the railroad circuit to activate warning devices prior to arrival of a through train.

– When highway-rail grade crossings are within 200 feet of a signalized intersection, preemption should be considered at that location.

Page 6: Arrival Times at Highway-Railroad Grade Crossing

Problem StatementProblem Statement

Motivation– The minimum warning time of 20 seconds to the

signalized intersection is not always adequate to safely clear stopped vehicles from the HRGC area.

– The current traffic signal preemption strategies are viewed as a reactive action to trains approaching a nearby HRGC.

– Advance notice of train arrival times at HRGCs can improve signal preemption strategies and reduce accidents.

Page 7: Arrival Times at Highway-Railroad Grade Crossing

Problem StatementProblem Statement

General Hypothesis:– The hypothesis of this research is that second

generation technologies can provide accurate advanced notice of train arrival at an HRGC near a signalized intersection of at least a cycle length prior to the arrival of a train at an HRGC.

Page 8: Arrival Times at Highway-Railroad Grade Crossing

Problem StatementProblem Statement

Research Objective 1:– Define how the variability of speed measurements

from two 2nd generation technology sensors affects the train arrival time estimation at an HRGC in a multi-track environment.

Research Objective 2:– Determine how to best use the multiple sensor

speed data to improve estimations of train arrival time at an HRGC.

Page 9: Arrival Times at Highway-Railroad Grade Crossing

Literature ReviewLiterature Review

Train Detection Technologies:– First Generation: AC-DC, Motion-Sensitive, Constant

Warning Time.

– Second Generation: Doppler Radar, Video Detection, Infrared.

– Third Generation: GPS, Transponders, Positive Train Control.

Page 10: Arrival Times at Highway-Railroad Grade Crossing

Literature ReviewLiterature Review

• NCHRP 271 - Traffic Signal Operations near Highway-Rail Grade Crossings (Korve, 1999)

• An Analysis of Low-Cost Active Warning Devices for Highway-Rail Grade Crossings (Roop et.al., 2005)

• Non-Vital Advance Rail Preemption of Signalized Intersections near Highway-Rail Grade Crossings: Technical Report (Ruback, Balke and Engelbrecht, 2007)

• Estimating Train Speeds Using Fused Data from Multiple Speed Detectors (Zhou, 2007)

Page 11: Arrival Times at Highway-Railroad Grade Crossing

MethodologyMethodology

1st Objective– Collect train speed data using Doppler radar and video

image detection.

– Manual speeds are needed so the performance of both sensors can be compared.

– Two scenarios considered: multiple trains and single train on the tracks.

Page 12: Arrival Times at Highway-Railroad Grade Crossing

Spee

d

Timet1t0

Area = Train Length

MethodologyMethodology

1st Objective– Train arrival time

estimation methodology from the collected train speed data.

– Required steps to estimate train arrival times: train length and train acceleration estimation.

– Actual train arrival time at the studied HRGC needed to compare the estimations from radar and video.

Page 13: Arrival Times at Highway-Railroad Grade Crossing

TIME UPDATE (Prediction)

MEASUREMENT UPDATE (Correction)

velocity and acceleration kinematics equations

radar and video speed measurements

Fused speed estimations

Kalman Filter Algorithm

MethodologyMethodology

2nd Objective– Fuse train speed data from

Doppler radar and video image detection.

– Estimate train arrival times using methodology for the 2nd objective.

– Ideally, the fused data should improve the estimates from radar and video detection.

Page 14: Arrival Times at Highway-Railroad Grade Crossing

Data Collection SiteData Collection Site

Upstream Salt Creek

Adams St. HRGC

Upstream 44th St.

• UNL HRGC TEST BED

Page 15: Arrival Times at Highway-Railroad Grade Crossing

• Installed equipment helps monitor highway traffic.

• Vehicles are constantly caught stopping at the tracks.

Day/Night Camera aimed at the HRGC

Traffic signal near the HRGC

N Adams St.

Camera Location

Camera field of view

NN

N 35th St.

Adams St.

Data Collection SiteAdams Street HRGC LocationAdams Street HRGC Location

Page 16: Arrival Times at Highway-Railroad Grade Crossing

Upstream Salt Creek LocationUpstream Salt Creek Location

• Located 1.85 miles upstream of the HRGC location;

• City of Lincoln Public Works installation support;

• Connected to the UNL-ITS Lab via internet.

Data Collection Site

Page 17: Arrival Times at Highway-Railroad Grade Crossing

Data CollectionData Collection

1st Objective– Video and radar speed data collected at Salt Creek

location. Single train and multiple-train scenarios considered.

– Manual speeds measured by computing railcar length and time interval on recorded videos.

Page 18: Arrival Times at Highway-Railroad Grade Crossing

Data CollectionData Collection

1st Objective– Actual train arrival times

needed to compare estimations from radar and video.

– Camera time stamps from Salt Creek and HRGC locations used to compute actual train arrival times.

Page 19: Arrival Times at Highway-Railroad Grade Crossing

Data CollectionData Collection

2nd Objective– Data collected for 1st objectives used.

– Speed data fused using the Kalman filter model and train arrival time estimations obtained from the new speed estimates.

Page 20: Arrival Times at Highway-Railroad Grade Crossing

Data Analysis & ResultsData Analysis & Results

1st Objective– Multiple-Train Scenario

RADAR PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

1.58 0.14 (-0.61, 3.68)

VIDEO (AUTOSCOPE) PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

0.58 0.571 (-2.47, 4.27)

Page 21: Arrival Times at Highway-Railroad Grade Crossing

Data Analysis & ResultsData Analysis & Results

1st Objective– Single Train Scenario

RADAR PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

3.15 0.007 (0.98, 5.06)

VIDEO (AUTOSCOPE) PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

0.09 0.929 (-4.30, 4.69)

Page 22: Arrival Times at Highway-Railroad Grade Crossing

Data Analysis & ResultsData Analysis & Results

2nd Objective– Multiple-Train Scenario

KALMAN FILTER PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

1.79 0.099 (-0.32, 3.25)

• Kalman filter presented the narrowest 95% C.I.

Page 23: Arrival Times at Highway-Railroad Grade Crossing

Data Analysis & ResultsData Analysis & Results

2nd Objective– Single Train Scenario

KALMAN FILTER PAIRED T-TEST

T-Statistic P-value95% Confidence Interval for Mean Difference (sec)

1.44 0.171 (-0.86, 4.44)

• Radar presented the narrowest 95% C.I., but Kalman filter 95% C.I. includes the zero mean difference.

Page 24: Arrival Times at Highway-Railroad Grade Crossing

Data Analysis & ResultsData Analysis & ResultsTrain Arrival Time Estimation Comparison

MULTIPLE-TRAIN SCENARIO  Count PercentageDifference from Actual Arrival

Time

Radar Estimation

Autoscope Estimation

Kalman Filter Estimation

Radar Estimation

Autoscope Estimation

Kalman Filter Estimation

Within +/- 2 seconds

6 4 8 46% 31% 62%

Within +/- 5 seconds

9 7 12 69% 54% 92%

within +/- 10 seconds

13 13 13 100% 100% 100%

SINGLE TRAIN SCENARIO  Count PercentageDifference from Actual Arrival

Time

Radar Estimation

Autoscope Estimation

Kalman Filter Estimation

Radar Estimation

Autoscope Estimation

Kalman Filter Estimation

Within +/- 2 seconds

6 6 7 38% 38% 44%

Within +/- 5 seconds

12 7 13 75% 44% 81%

within +/- 10 seconds

15 12 15 94% 75% 94%

Page 25: Arrival Times at Highway-Railroad Grade Crossing

Final RemarksFinal Remarks

Lessons learned from Doppler radar and video performances will help to develop algorithms to predict train arrival times at HRGCs and improve traffic signal preemption (and safety as well).

Data fusion process showed to be reliable and it could improve train arrival time estimations in a real time system application.

In the event of failure of either sensor, the Kalman filter could still be used to provide consistent measurements.

Page 26: Arrival Times at Highway-Railroad Grade Crossing

CreditsCredits

Federal Railroad Administration (FRA)

Nebraska Department of Roads (NDOR)

City of Lincoln