Session 1 – Overview of main M&E challenges
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
The first miles…. …. the next thousand ones.
??
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
You will need directions!
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Your Monitoring and Evaluation system
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
A successful journey….
InputsActivities
Outcomes
Outputs
Impact
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
From a focus on Monitoring …. (“beans counting” exercise focusing on activities
and outputs)
….. to a focus on Evaluation! (informed reflection on performance)
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Evaluation questions
Are we doing the right thing?Are we doing it right?
What should be done differently?
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
MFI and project records:• 120 Credit and Saving Groups formed• 13,500 active borrowers (72% women)
• 22,220 savers (80% women)
• Average repayment rate: 75%• Portfolio at risk: 20%
Example:
Objective is to increase access of poor women to microfinance services in 3 provinces
“Beans’ counting” exercise
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Case study: “My husband wanted a new car, so I asked the
MFI Officer. He told me that if I would form a group, I could access credit. So I asked all my friends and relatives to join me in a group, after which I got a loan from the MFI and my husband bought his car…”
A women beneficiary
Reflection on performance
Example:
Objective is to increase access of poor women to microfinance services in 3 provinces
“Reflection on real performance”
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Each step in the results’ chain shall be monitored
Cost-effective outcome measurementEach step in the results’ chain shall be
monitoredNeed for baseline dataNeed for SMART indicators
Evaluation challenges
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
InputsActivities
Outcomes
Outputs
Impact
Challenge #1: Monitoring each step in the results’ chain
Are our activities implemented according to plans; are inputs efficiently mobilized?
Are project outputs according to plans , relevant to address beneficiary needs and of the required quality?
Is the project producing the desired outcomes in terms of introducing positive behavioural changes in the community, increasing agricultural productivity, etc.
Is the project achieving its objectives in terms of poverty reduction
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Limited reporting on outcomes
• 80% of available RIMS data concern Outputs
• Some 80% of outcomes indicators are not reported upon
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Example
• People trained in crop production practices and technologies
Missing indicators:Missing indicators:
Farmers reporting production or yield increases Farmers adopting recommended technologies Nb of ha of incremental crops grown
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Concrete results (RIMS)
21
16
20
4
6
9
7
Nb project
s
816,896
777,581
483,178
68,184
24,328
153,632
165,894
Data
2008/09
28814,76020456,60918263,492Active borrowers
152,467,39919939,42716502,580Nb of active savers
29457,25120316,63022241,526Persons trained in crop and livestock production and development
7616,13511807,27811218,088Nb of farmers adopting technology recommended by project
10120,92310679,89711132,319Farmers reporting production or yield increased/herd size
2ND22928,59321763,671Persons receiving project services
985,47513289,974782,689Households reporting improved food security
Nb project
sData
Nb project
sDataNb
projectsData
2009/20102007/08 2006/07 RIMS data
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Quality versus quantity
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
You need baseline data!
As compared to what?
Is your life better?
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Few projects with “real” baseline data
• 33% of projects have no baseline survey
• Only 20% of baseline surveys have been conducted during first year of implementation
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Even reporting on outputs is problematic:
1) Reliability of data
Double counting of results:• Nb of persons trained? (same people trained several times)• Nb of beneficiaries?• Nb of persons receiving project services?
Monitoring challenges
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
How well is performance measured?
Persons receiving project services: “Population of villages where PRA was done”
Number of persons trained: “The project, since PY1, records persons as new
participants every time they take part in a training (regardless if the same person is trained several times). In this way the cumulative total exceeds by far the number of target villagers as the same persons may have been counted several times”
Example: How do you measure…?
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Tracking “cumulative” achievements: main challenges
Cumulative achievements are not necessary the sum of annual achievements!!
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
2) Inefficient data collection exercises
Overly complex data collection exercises, with little evaluation of data
Proper Information Management Systems often lacking
No staff dedicated to data entry
Other monitoring challenges
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
What to avoid: data collected but not used!
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Remember!
“Not everything that can be counted counts, and not everything that counts can be counted.”
- Albert Einstein (1879-1955)
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Weak national systems
Lack of standard approaches, definitions and tools
Lack of continuity in support from IFAD
Other monitoring challenges
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Other issues
Unclear Logframes
Missing targets
Turn-over of M&E staff and M&E consultants
Poor in-country capacities
Impact on quality of M&E data
High
Some M&E champions
M&E Officers lack operating budget
IFAD may abandon
RIMS
Good/trained M&E Officers will leave
Good M&E consultants
available
Poor M&E Officers capacities
IFAD not negotiating strongly
enough
Some CPOs are building M&E
support capacities
Low Growing number of RB COSOP
High
Intensity (strength) Lack of continuity in external
support
PI willing to provide more support
Likelihood (Threat/Opportunity
Lack of Gov
commitment
PDs have no interest in
M&E
Lack of IFAD commitment to
support M&E
Growing number of DSF countries
Project designs don't pay enough attention to M&E
)
IFAD failing to offer good guidelines
Lack of PI ability to provide direct
suort
Increasing donors' interest in results
Low
Strengths, Weaknesses, Opportunities and Threats - Analysis
PDs have no interest in M&E
Yyy
RIMS surveys do not measure impact well
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Project recordsOutput indicators
Outputs
Impact surveys; National/local statistics
Impact indicators
Overall Goal
Project recordsProcess indicators
Activities
Surveys; Observations; Interviews with key informants
Outcome indicators
Component/ Sub-Component
Impact surveysImpact indicators
Project Purpose
Data Collection MethodsTypes of Indicators
Objectives
Increasingly expensive, time consuming, technically complex and skill intensive
… AND there are cost implications!
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Do you have the necessary budget, and staff, to do proper M&E?
2010 Annual Performance Review Workshop M&E Side Event – Day 1 (Session 1)
Minimum M&E budget necessary
•RIMS: 10,000 to 16,000 per survey
• Annual (staff time)• 3 “RIMS+” surveys
• Annual outcome surveys
• Min. 5 case studies:[Gender] – [Empowerment] – [Environmental impact] – [Sustainability] – [Infrastructure O&M] – [Agric. innovation uptake] – [Microfinance] [Etc]
Surveys and studies:
• Transportation
• Per diem
• Workshops, meetings
Operating budget:
Minimum costs:
• 36 m/m per year; Senior, Junior and clerk levels
• 36 m/m ST staff whole project duration (RIMS)
•2 m/m per year (other surveys)
At least:
• 1 M&E Officer
• 1 M&E Assistant
• 1 full time data entry pers.
• short term enumerators
Staff: