applied technology council project updates...prepared phase 1 report identified six potential study...
TRANSCRIPT
ATC Project Updates: Provisions Update Committee Meeting
Applied Technology Council Project Updates
Provisions Update Committee MeetingJuly 19, 2016
Jon A. HeintzExecutive Director
ATC Project Updates: Provisions Update Committee Meeting
Agenda
Review Issue Team activities Highlight ATC projects of relevance Outline expected outcomes and timelines
ATC Project Updates: Provisions Update Committee Meeting
Issue Teams
IT1 – Seismic Performance Objectives IT2 – Seismic Systems and Design Coefficients IT3 – Modal Response Spectrum Analysis IT4 – Shear Wall Design IT5 – Nonstructural Components IT6 – Nonbuilding Structures IT7 – Soil-Structure Interaction Updates IT8 – Base Isolation and Energy Dissipation IT9 – Rigid-Wall Flexible Diaphragm (RWFD)
ATC Project Updates: Provisions Update Committee Meeting
ATC Projects of Relevance
Primary mission– ATC-116 (IT2 – Systems and Coefficients)– ATC-123 (IT2 – Systems and Coefficients)– ATC-120 (IT5 – Nonstructural)
Bonus information– ATC-58-2 (IT1 – Performance Objectives)– ATC-94 (IT4 – Shear Wall Design)
ATC Project Updates: Provisions Update Committee Meeting
ATC-116
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Project
Solutions to the Issue of Short Period Building Performance– Kircher et al.– Improve simulation of short
period building response (T<0.5 sec)
– Develop design and analytical guidance
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Project
Completing third year of a multi-year FEMA-funded effort
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Project Context
Quantification of Building Seismic Performance Factors (FEMA P-695, 2009)– Explicit simulation of collapse
Collapse analyses show increased probability of collapse for T<0.5 sec Observed earthquake
performance does not appear to match
0%
5%
10%
15%
20%
25%
30%
35%
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5Design Period, T (seconds)
Col
laps
e P
roba
bilit
y
Bearing Wall Systems (A.7, A.9. A.15)Building Frame Systems (B.2, B.4, B.5, B.25)Moment Frame Systems (C.1, C.5. C.7)
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Project Context Possible causes:
– As-built strength of actual buildings is different from archetypes
– Use of overly conservative failure criteria
– Diaphragm flexibility– Soil-structure interaction– Mass distribution– Other sources of flexibility or
displacement (e.g., connections)
204 ft.
204 ft.
24ft.
Column Lines
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Objectives
Bridge the gap between simulated and observed performance of short period buildings– Improve simulation techniques to better
match observed performance – Change design provisions to improve
performance (if needed)
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Status
Completed studies of wood frame buildings for:– Configuration (height/interior walls)– Collapse Displacement Capacity– SSI/Foundation Flexibility– Imperfect Connectivity– Interior/Exterior Wall Finishes
Currently developing recommendations for wood systems and initiating study on masonry systems
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Results – Sound Bite
0%
5%
10%
15%
20%
25%
30%
35%
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5Design Period, T (seconds)
Col
laps
e P
roba
bilit
y
Bearing Wall Systems (A.7, A.9. A.15)Building Frame Systems (B.2, B.4, B.5, B.25)Moment Frame Systems (C.1, C.5. C.7)
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Findings
Issues that mattered for wood frame buildings:– Configuration (height/interior walls)– Collapse Displacement Capacity– SSI/Foundation Flexibility– Imperfect Connectivity– Interior/Exterior Wall Finishes
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Implications
Findings related to Configuration:– All walls/finishes matter– Single-story archetypes performed well– Multi-story archetypes developed first
story mechanisms– Taller (4-story) archetypes did not meet
collapse safety criteria Potential code implications
– Adjust design rules in lower stories of multi-story stacked systems??
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Implications
Findings related to Finishes:– Nonstructural finishes (stucco/gyp) are a
significant contributor to total strength– Finishes were significant contributors
(positive and negative) to collapse behavior of multi-story archetypes
Potential code implications– Adjust design rules to account for
nonstructural finishes??
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Implications Findings related to Collapse Displacement
Capacity:– FEMA P-695 studies to date have used overly
conservative failure criteria
0 5 10 150
2
4
6
8
10
12
14
16
18
Drift (%)
For
ce (
kip
)
OSB NonstrucOSB Low
OSB Medium
OSB High
Gyp MinGyp Max
Gyp Nonstruc
StuccoSiding
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Implications
Findings related to Collapse Displacement Capacity (cont’d):– If you increase residual strength and
displacement capacity, collapse capacity goes up (magic number: 30%)
– Possible sources of residual strength attributed to: components; system effects
Potential code implications– Consider in analysis/design or not??– Testing needed to quantify
ATC Project Updates: Provisions Update Committee Meeting
ATC-116 Schedule By September 2016
– Develop preliminary recommendations for implementation of findings for wood systems
– Possible workshop to test ideas By September 2017
– Investigation of short-period masonry systems
ATC Project Updates: Provisions Update Committee Meeting
ATC-123
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Project
Improving Seismic Design of Buildings With Configuration Irregularities– Valley et al.– Based on recommendations
in the NIST-GCR-917-23 Roadmap (BSSC project)
– Calibrate quantitative triggers related to irregularities
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Project
Completing first year of a three-year FEMA-funded effort
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Expected Outcomes Identify baseline collapse probability for
selected systems Quantify change in collapse probability
as irregularities are introduced Determine revised irregularity criteria
that result in no change in collapse probability Determine revised design criteria to
adjust collapse probability for irregular conditions
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Scope of Work 30 baseline archetypical systems
– RCMF, SMF, RCSW, RCMF+RCSW– Special and ordinary variants– 1-story to 20-story height variants– ELF and MRS design variants– SDC D and SDC B variants
Parametric introduction of horizontal and vertical irregularities
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Scope of Work
ATC Project Updates: Provisions Update Committee Meeting
ATC-123 Schedule By September 2016
– All baseline designs complete– Analysis results for RCSW system with H1
(torsional stiffness) irregularity– Analysis results for SMF and RCMF
systems with V2 (mass) irregularity By September 2017
– All other system/irregularity combinations complete
ATC Project Updates: Provisions Update Committee Meeting
ATC-120
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Project
Seismic Analysis and Design of Nonstructural Components and Systems– Phipps et al.– Improve nonstructural system
design for public safety and economic welfare
– Investigate disconnect between design and observed (or expected) performance
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Project
Half-way through a three-year NIST-funded effort
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Project Status Prepared Phase 1 Report Identified six potential
study recommendations Selected two:
– Develop nonstructural performance objectives
– Conduct holistic assessment of current code design approaches
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Scope of Work Performance Objectives
– To create a set of performance objectives for nonstructural components and systems that covers all components in all seismic design categories that has broad acceptance and dovetails with proposed design recommendations
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Scope of Work Holistic Assessment
– Determine the adequacy of current nonstructural design provisions using analytical, experience, and testing data
– Revise nonstructural provisions to provide appropriate seismic performance and improve usability for typical users
– Identify areas of further study needed
ATC Project Updates: Provisions Update Committee Meeting
Adequacy of current nonstructural design provisions
Develop an analytical method that will predict nonstructural component response for generic structures with reasonable accuracy (Task 39.14.2)
ATC Project Updates: Provisions Update Committee Meeting
Determine if the design equations are appropriate(Task 39.14.3)
Adequacy of current nonstructural design provisions
ATC Project Updates: Provisions Update Committee Meeting
Determine if the procedures produce compatible design demands for different elements in the load path (Tasks 39.14.4 and 39.14.5)
"A" "B" "C"1
1
Support 1-SectionA
2'-6
"
2'-6"
Rp = 2.5, 3, 4.5, 6, 9,or 12
Rp = 2.5, 3, 4.5, 6, 9,or 12
Rp = 2.5, 3, 4.5, 6
Adequacy of current nonstructural design provisions
ATC Project Updates: Provisions Update Committee Meeting
ATC-120 Schedule By September 2016
– Performance objective and holistic studies planned and initiated
By September 2017– Performance objective and holistic studies
completed
ATC Project Updates: Provisions Update Committee Meeting
Bonus Information
ATC Project Updates: Provisions Update Committee Meeting
IT1 - ATC-58-2 Project
Phase 2: Development of Performance-Based Seismic Design Guidelines– Hamburger et al.– Stakeholder interactions– Exercising the FEMA P-58
Methodology in a design context
– Benchmarking code performance
ATC Project Updates: Provisions Update Committee Meeting
ATC-58-2 Code Benchmarking
Identified parametric design space of code-conforming systems
ATC Project Updates: Provisions Update Committee Meeting
Initial Runs – Phase I
Structural Types RC Wall RC SMRF
CMU Wall SCBF OBF BRBF
Steel SMRF
Lt Frame
Stories II IV II IV II IV II IV II IV II IV II IV II IV Total2 3 3 3 3 3 3 3 3 3 1 3 3 3 3 3 3 95 3 3 3 3 3 3 3 3 3 1 3 3 3 3 3 912 3 3 3 3 3 3 3 3 3 3 3 3 9
9 9 9 9 9 9 9 9 6 2 9 9 9 9 6 3 27
• High SDC D, SDC D, and Low SDC D • 4 strength/stiffness combinations for each subset• 11 intensities (10%, 20%, 30%, 50%, 60%, 67%, 70%, 80%, 90%,
and100% MCE)
Semi complete Completed
ATC Project Updates: Provisions Update Committee Meeting
12‐story SMRF, Point 3: Median Loss Ratios
Case 2
Case 4
Case 1 Case 3
Case 5
old PACT ‐ old fragilities new PACT ‐ old fragilities
Case 8
new PACT updated fragilities 1
F&L ‐ new PACT ‐ updated fragilities 1 new PACT ‐ updated fragilities 2 new PACT ‐ updated fragilities 3 ‐ Un‐Correlated Fragilities‐Factored T1
ATC Project Updates: Provisions Update Committee Meeting
ATC-58-2 Schedule
Running code benchmarking analyses Summer 2016 Look for more information soon
ATC Project Updates: Provisions Update Committee Meeting
Performance of Reinforced Concrete Buildings in the 2010 Chile Earthquake– Maffei et al.– Evaluate critical issues in the
design of reinforced concrete walls and develop improved wall design requirements
IT4 – ATC-94 Project
ATC Project Updates: Provisions Update Committee Meeting
Group 1a – developed simple relation for bar buckling
Group 1b – developed simple relation for wall buckling
Group 2a – developed new ASCE 31 checklist criteria for building irregularities
Group 2b – recommended advanced simulation techniques for shear wall behaviors
10
25
20
15
5
00.00 0.01 0.02 0.03 0.04
Maximum tensile strain, sm
Leng
th-to
-thic
knes
s rat
io, kl n/b
ATC-94 Areas of Work
ATC Project Updates: Provisions Update Committee Meeting
Thank You!