appendix g stakeholder and public input › content › delivery › region9 › ... · 14 scarlett...
TRANSCRIPT
June 2009 FINAL DESIGN REPORT PIN 9067.17
APPENDIX G Stakeholder and Public Input
• Public involvement plan • Correspondence • June 27, 2007 public information meeting brochure • April 28, 2009 Public Hearing Transcripts • Public Hearing Comment Response
Public Involvement PlanPIN 9067 17 Rte 17 Over the Neversink
State of New YorkDepartment of Transportation
44 Hawley StreetBinghamton, N.Y. 13901-3200
htt2:ffwww.doLstatenyus
John R. Williams Thomas J. Madison, Jr.Regional Director Acting Commissioner
August 2, 2005
Honorable Anthony Cellini, SupervisorTown of Thompson4052 Route 42Monticello, New York 12701
Dear Supervisor Cellini:
RE: PIN 906717, ROUTE 17 OVER THE NEVERSINK RIVERTOWN OF THOMPSON, SULLIVAN COUNTY
Our Department seeks your assistance in planning the above-referenced capital project.This project as proposed seeks to replace the existing bridge BIN 1013799 on Route 17 overthe Neversink River located between Interchanges 107 and 108 in the Town of Thompson,Sullivan County see attached map.
Constructed in 1953, this bridge has deteriorated beyond the point where it can bemamtamed by normal maintenance activities. This project proposes to replace the bridge on anew alignment just north of the current location. It is proposed to build twin structures whichwill better accommodate current and future traffic volumes that use this section ofRoute 17 eachday. During consnuction, traffic will be maintained on the existing structures.
Our Department is currently engaged in the scoping phase of the project, whereby alimited concept, as described above, is progressed to a project scoping report with sufficientdetail to minimize major changes in scope, cost, and schedule during later phases of the project’sdevelopment. The scoping phase is followed by preliminary design, detailed design, bidding,and assignment of a construction contract. Construction is tentatively scheduled to begin in2007.
Currently, the construction cost is estimated to he 515 million. Cost and schedule aresubject to change pending completion of project scoping and are subject to further adjustments asdetailed design and overall capital program resources may dictate.
Public Involvement PlanPIN 9067 17 Rte 17 Over the Neversink
Honorable Anthony Cellini, SupervisorAugust 2, 2005Page Two
At this point in our project planning process we would appreciate input from you, otherrepresentatives of local government and concerned agencies. Please provide any informationthat may be important for our Department to consider while the project is in this formativescoping phase. For example, we are interested in land development plans and other public worksprojects planned for the area. To help us maintain the project schedule, please provide commentsby August 26, 2005.
Additionally, in the interest of capital project programming and long-range masterplanning, we invite you and other local officials to identify any other transportation problems inthe project area, in the respective area of local jurisdiction, or of a regional nature. Do nothesitate to express your ideas to address specific needs or solutions to problems. OurDepartment seeks input on a continuous basis for planning improvements and initiatives for allmodes of transportation.
By copy of this letter, we are soliciting your input. Your participation in our projectscoping and transportation planning process is appreciated. If you would like to providecomments for the referenced project or would like to discuss the ject in more detail, pleasecontact the Project Manager, Pete Larson at 07 721-8206 /1 plarson4ot.state.ny.us
DAy E S,P.Reonal P1 and Program Manager
DL1CM IjabATTACHMENT
PIN 9067.17NYS Route 17 - over the
Neversink River
Visualization of preferred alternative C-2
Feasible Alternatives
Alternative C-2 (preferred alternative) This alternative maintains the existing bridge as an on-site detour, while a new bridge is built on new alignment to
the north side. Traffic will be shifted to the new bridge, the existing bridge removed and a second bridge built on theexisting alignment.
The existing approach grades will be improved to 5%, and the vertical alignment would be lowered at Interchange107 to minimize right-of-way and environmental impacts, and to facilitate the design of the west bound on and offramps.
Right-of-way - 2.1 acres Wetland - 0.7 acres Estimated Construction Cost - $23.5 M
PLAN VIEW
PROFILE5:1 VERTICAL EXAGGERATION
County Rte 161 bridgeat Interchange 107
Interchange 108
County Rte 173
Proposed bridges overthe Neversink River
County Rte 161 bridgeat Interchange 107
Proposed bridge
Existing bridge
Proposed vertical alignment
Existing vertical alignment
Page 4 PIN 9067.17
Existing view of the Neversink Bridgelooking west toward Interchange 107
Proposed view of the Neversink Bridgelooking west toward Interchange 107
Rte 17 EB
Rte 17 WB
Alternative C-4 This alternative shares the same horizontal alignment as the preferred alternative C-2. The existing bridge would
be maintained as an on-site detour while a new bridge is built on new alignment to the north side. Traffic will beshifted to the new bridge, the existing bridge removed and a second bridge built on the existing alignment.
The existing approach grades would be improved to the Interstate Standard of 4%, and the vertical alignmentwould be lowered at Interchange 107 to minimize right-of-way and environmental impacts, and to facilitate thedesign of the west bound on and off ramps.
Right-of-way - 3.8 acres Wetland - 1.3 acres Estimated Construction Cost - $ 25.2 M
PIN 9067.17Page 2 Page 3 PIN 9067.17
Eliminated AlternativesAlternative B This alternative would construct two new struc-
tures to the north leaving the existing bridge inplace due to it’s eligibility for the historic register based on its unique use of a below deck truss.
Improve existing non-standard grades to 4%. Right-of-way - 6.6 acres Wetland - 1.9 acres Estimated Construction Cost - $23.4 MReason for elimination:The realignment of the approaches to the newbridges would require large impacts to wetlands andright-of-way, and require the removal of at least tworesidential buildings.
Alternative C-1 This alternative shares the same horizontal alignment as the preferred alternative C-2. The existing approach grades will be improved to the Interstate Standard of 4% without lowering the NYS Route 17 profile at Inter-
change 107. Right-of-way - 4.5 acres Wetland - 1.5 acres Estimated Construction Cost - $24.3 MReason for elimination:Obtaining acceptable vertical grades for the west bound off ramp at Interchange 107 in order for designation as I-86 requires loweringof the NYS Route 17 vertical alignment at the County Route 161 bridge. This alternative would also have more impacts to right-of-wayand wetlands than the preferred alternative.
Alternative C-3 This alternative shares the same horizontal alignment as the preferred alternative C-2. The existing approach grades would be improved to 5% without lowering the NYS Route 17 profile at Interchange 107. Right-of-way - 2.7 acres Wetland - 1.0 acres Construction Cost - $20.3 MReason for elimination:Obtaining acceptable vertical grades for the west bound off ramp at Interchange 107 in order for designation as I-86 requires loweringof the NYS Route 17 vertical alignment at the County Route 161 bridge. This alternative would also have more impacts to right-of-wayand wetlands than the preferred alternative.
County Rte 161 bridgeat Interchange 107 Proposed vertical alignment
for Alt C-4
Proposed vertical alignmentfor Alt C-2 (preferred)Existing vertical alignment
County Rte 161 bridgeat Interchange 107
County Rte 173
Interchange 108
Proposed bridges overthe Neversink River
Alt C-2 (preferred) cut and filllines shown for comparison
PROFILE5:1 VERTICAL EXAGGERATION
PLAN VIEW
Proposed vertical alignmentfor Alt C-1
Existing vertical alignment
Proposed vertical alignmentfor Alt C-2 (Preferred)
County Rte 161 bridgeat Interchange 107
County Rte 161 bridgeat Interchange 107
Existing vertical alignment
Proposed vertical alignmentfor Alt C-2 (Preferred)
Proposed vertical alignmentfor Alt C-3
PROFILE5:1 VERTICAL EXAGGERATION
PROFILE5:1 VERTICAL EXAGGERATION
Feasible Alternatives Continued
Rte 17 EB
Rte 17 WB
In The Matter Of:NEW YORK STATE
DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17
April 28, 2009
Jeric Corporation
Court Reporting Services
P.O. Box 385
Narrowsburg, NY 12764
(845) 252-3515
Original File DOT.txt
Min-U-Script® with Word Index
NEW YORK STATE DEPARTMENT OF TRANSPORTATION REGION 9 - - - - - - - - - - - - - - - - - - - - - - - - - - - X Public Hearing in the Matter of: THE NEVERSINK RIVER BRIDGE REPLACEMENT PROJECT PIN 9067.17 - - - - - - - - - - - - - - - - - - - - - - - - - - - X Town of Thompson Town Hall April 28, 2009 6:34 P.M. DEPARTMENT OF TRANSPORTATION STAFF Bill Naylor,P.E., Project Manager Pete Larson, P.E, Job Manager Daniel Odigie,P.E, Project Engineer Jillian Draper, Planning Office Sandi Scarlett, Real Estate Office Elizabeth French, Real Estate Office Denise Orzekel, Planning Department Shah Zaman, P.E., Resident Engineer Himabindu Samudrala, Design Team Peter St. Louis, Design Team Mark Jakubiak, R.L.A., Design Team Brad Bortnick,P.E., Design Team JERIC CORPORATION Court Reporting Services P.O. Box 385 Narrowsburg, New York 12764 Reported By: Rosemary A. Meyer
2 1 - NEVERSINK BRIDGE REPLACEMENT PROJECT -
2 MR. ODIGIE: Ladies and gentlemen, good afternoon.
3 Please try to have our seats.
4 My name if Daniel Odigie and I'm a project engineer with
5 the New York State Department of Transportation Region 9
6 Office in Binghamton. I want to welcome you to the Public
7 Hearing for the replacement of the New York State Route 17
8 Bridge over the Neversink River in the Town of Thompson,
9 Sullivan County, Project Identification Number 9067.17.
10 The Department Staff is on hand to help people
11 understand the display materials and answer questions during
12 an open house period that began at 6:00 p.m. The time is
13 6:34 p.m., and we are starting the comment portion of this
14 hearing.
15 This hearing is being conducted in accordance with the
16 with the requirements of the National Environmental Policy
17 Act, the State Environmental Quality Review and the New York
18 State Eminent Domain Procedure Law.
19 The objective of this meeting is to inform the public
20 and the stakeholders of the progress made and to receive
21 comments on the proposed feasible alternative being
22 considered.
23 This hearing was advertised in the legal notices
24 published in the Times-Herald Record and Sullivan County
25 Democrat. Notices were sent to public offices. Letters were
3 1 - NEVERSINK BRIDGE REPLACEMENT PROJECT -
2 sent to property owners with property that may be acquired by
3 the Department of Transportation. Letters were also sent to
4 nearby residents and to people to had previously expressed
5 interest in the project.
6 A stenographer is present to record these proceedings.
7 A transcript of the presentation and your comments will be
8 prepared as part of the official project documentation.
9 The following representatives of the New York State
10 Department of Transportation are with us tonight. Kindly
11 briefly stand up when your name is called, or wave your hand.
12 Pete Larson, the Job Manager; Bill Naylor, the Project
13 Manager; Jillian Draper, with our Planning Office; Sandi
14 Scarlett and Elizabeth French, with our Real Estate Office.
15 Denise Orzelek, with our Planning Department will with assist
16 in the sign-in. Sullivan County DOT Resident Engineer, Shah
17 Zaman.
18 Thank you.
19 Present here from our main office in Albany are some
20 members of the design team responsible for the project. We
21 have here Himabindu Samudrala. Thank you. Peter St. Louis,
22 Mark Jakubiak and Brad Bortnick.
23 Brad leads the team and will be making a presentation to
24 us soon.
25 I'm pleased to also introduce Anthony Cellini,
4 1 - NEVERSINK BRIDGE REPLACEMENT PROJECT -
2 Supervisor in the Town of Thompson; Richard Benjamin, Highway
3 Superintendent, Town of Thompson; Robert Meyer, Commissioner
4 of Public Works, Sullivan County; Ed Mc Andrew, of Sullivan
5 County Public Works.
6 In case of emergency, you can exit through the doors you
7 entered, or listen to instructions.
8 Restrooms are available off the corridor.
9 This a no smoking facility. We ask that you abide by
10 its regulations.
11 This project will replace the bridge that is near the
12 end of its useful life and can no longer be maintained with
13 reasonable expense. The project also intends to reduce the
14 steep vertical grade approaches to the bridges; reduce the
15 accident rate associated with those grades; and provide for
16 future increases to the traffic capacity. The improvements
17 are designed in accordance with interstate standards to
18 permit the future designation of New York State Route 17 as
19 Interstate 86.
20 A Draft Design Report, DDR, for the project has been
21 completed and copies are available at the Thompson Town Hall,
22 the public library in Monticello, DOT Regional Office in
23 Binghamton, as well as on-line at
24 www.nysdot.gov/neversinkbridge. This link is shown in the
25 handout you received when you came in.
5 1 - PRESENTATION -
2 This project has received the Federal Highway
3 Authority's concurrence that we have followed the
4 requirements of the National Environmental Policy Act, NEPA;
5 and is in compliance with the provisions of Section 36 of the
6 Code of Federal Regulations, CFR 800.6, which addresses an
7 adverse effect on the bridge eligible for the National
8 Register of Historic Places. The construction phase of the
9 Neversink River Bridge Project is scheduled to start in
10 summer, 2011, and to be completed in summer, 2013.
11 Brad Bortnick will now begin the technical presentation.
12 We ask that you hold your comments until after the technical
13 presentation is completed.
14 Brad.
15 UNIDENTIFIED SPEAKER: When did you say it would
16 commence?
17 MR. BORTNICK: We'll get to that. I'm going to go over
18 the project schedule, as well. But it was supposed to
19 commence in the spring of 2011.
20 UNIDENTIFIED SPEAKER: Thank you.
21 MR. BORTNICK: All right. Good evening. Again, I'm
22 Brad Bortnick. I work for the main office, New York State
23 Department of Transportation main office. Thank you for
24 coming tonight.
25 And we will now go through the design presentation for
6 1 - PRESENTATION -
2 the project which proposes to reconstruct the bridge over the
3 Neversink River and the east and westbound approaches between
4 the interchanges 107 and 108.
5 Okay. The project summary: We will start by going over
6 the project location, the existing conditions out on Route
7 17. We'll go over the project objectives and what we hope to
8 accomplish with this project. We'll go over the accident
9 analysis that was performed, as well as a traffic analysis.
10 We'll go over the alternatives that were considered as part
11 of this project, including the eliminated alternatives, as
12 well as our preferred. And we will go over the environmental
13 concerns associated with our third alternative.
14 The project is located in the Town of Thompson and just
15 southeast of Monticello along Route 17 between interchanges
16 107 and 108. Here we have an aerial view of the project
17 site. You can see Interchange 107, and that's the County
18 Route 161 bridge. Interchange 108, the existing Neversink
19 Bridge and the Neversink River. And this is County Route
20 173.
21 The existing bridge was built in 1953 and is listed as
22 eligible for the Historic Register based on its unique use of
23 a warren truss below deck as you see here, excuse me, as you
24 see here, sorry, flicker, as opposed to the more common
25 through. So the truss would be up top. So because of that,
7 1 - PRESENTATION -
2 it's considered historic and is listed on the National
3 Register.
4 Now, the bridge has a poor condition rating. And you
5 can see some of that here with the deterioration of the
6 concrete on the lower side of the piers, and the spalling of
7 the concrete on the deck.
8 Now, a condition rating, you give each bridge a value
9 between one and seven, one being very poor and seven being
10 excellent. This bridge is about a 3.8 so it is in poor
11 shape. And we inspect it regularly, though, and it is
12 completely safe. But the high cost of maintenance puts this
13 bridge on a list of high priority for the Region to replace.
14 Okay. Now, there are nonstandard vertical grades on
15 both approaches. There's the westbound approach that you see
16 coming in here is steeper, is seven percent. And the back
17 side is five percent. Now, interstate standard would be four
18 percent. Okay?
19 Now, there's also a nonstandard stopping sight distance,
20 and I put a slide together to sort of show you, explain what
21 stopping sight distance is. Now, in this case, we have two
22 downgrades, which is the case out at the Neversink River.
23 Now, when you have a steep downgrade, our stopping sight
24 distance refer to as headlight sight distance because at
25 night you're not going to be able to see this because your
8 1 - PRESENTATION -
2 headlights are not going shine on that. So we use the term
3 "headlight sight distance" to sort of correspond with our
4 stopping sight distance. Now, you can see in the steep grade
5 the headlight sight distance is pretty short. But if you
6 flatten out those grades, which we hope to do in this
7 project, you see your headlight sight distance will increase.
8 Now, your headlight sight distance should be sufficient for
9 the driver driving at design speed, to stop before he sees an
10 object in the road, or a deer in this case. And as part of
11 this project, we hope to bring that up to an interstate
12 standard of 720 feet. Again, the existing is 348 feet so
13 it's quite a difference.
14 Other existing conditions, the shoulder and median
15 widths are also nonstandard. The narrowest section is at the
16 Neversink River Bridge with one foot on the right shoulder
17 and six foot on the left. Here's left. And interstate
18 standards should be four feet on the left and ten feet on the
19 right. The existing median width is as narrow as six and a
20 half feet currently. Interstate standard calls for 36 feet.
21 And there's also deficient side gutters and ditches. And you
22 see that pavement falling apart there in that gutter.
23 Here we see the existing wetlands on the project. And
24 if we disturb any of these wetlands as part of this project,
25 we have to mitigate them at a rate of one and half to two
9 1 - PRESENTATION -
2 times. So that would mean for every acre of wetland we
3 impact we need to create one and a half to two acres of new
4 wetlands. So, of course, we try to minimize that as much as
5 possible because there's not a lot of area to put new
6 wetlands.
7 There's also a historic eligible home located in the
8 southeast corner by the County Route 161 bridge. Now, there
9 will be some work done in this area as part of another
10 project where we will be cutting back the slope here, but it
11 should not affect that house.
12 We'll go through our project objectives. We would hope
13 to bring the segment of New York State Route 17 up to
14 interstate standards for future designation as I-86,
15 Interstate 86; restore the functional condition and
16 structural vulnerability rating of the bridge; establish a
17 safe and efficient corridor and provide an acceptable level
18 of service for a design period of 30 years. And what level
19 of service is, it's basically a term that we at NYSDOT use to
20 measure traffic flow, and it's based on, as well as other
21 factors, speed, travel time and maneuverability. And
22 basically, we'll assign a letter from A to F, A being the
23 best and free flow, and F being the worst at stop and go
24 traffic. Now, interstate standard is B, which is reasonably
25 free flow, which we will hope to meet.
10 1 - PRESENTATION -
2 We also hope to provide geometric improvements to the
3 vertical grades, flatten slopes where possible, and set back
4 cut slopes and remove trees to minimize icing conditions on
5 the roadway; and upgrade deficient pavement guide rail, signs
6 and roadside pertinence for overall improved safety.
7 Okay. We did perform an accident analysis for the
8 project on a 1.8 mile segment of Route 17 encompassing the
9 project area. A three-year period of accident data was
10 evaluated from March 1, 2004 to February 28, 2007. You see
11 we had a total of 45 accidents during that period. Sixteen
12 resulted in injuries and 29 were property damage only.
13 Our breakdown of accidents were environmental, 42
14 percent. And under environmental, that would be accidents
15 that occur because of slippery pavement, weather related
16 accidents and animal strikes. Forty percent were human,
17 which would be unsafe speed, alcohol or drug use or driver
18 inattention. And 18 percent were vehicle problems such as
19 bad brakes. And I think one of them was a defective tow
20 hitch, things of that nature, but vehicle related. And that
21 yielded an accident rate of 1.15 accidents per million
22 vehicle mile, which probably doesn't mean anything to you,
23 but we can compare that to the statewide average of .84
24 accidents per million vehicle mile for this type of facility.
25 So it is a little higher.
11 1 - PRESENTATION -
2 As a result of the accident analysis, two accident
3 clusters were identified. The first cluster is located at
4 the 107 interchange, here. And we realized that the 107
5 eastbound on ramp had a nonstandard length. Now, that will
6 be lengthened under a proposed project, PIN 9666.96, which
7 our office is also working on, at a later date. But it's
8 pertinent in preliminary design, and it's going to improve
9 the interchanges from 102 through 108 to New York State, to
10 upgrade to interstate standards. They will also be cutting
11 back the slopes in that area because there is steep rock cuts
12 there which is contributing to icing on the roadway. So
13 hopefully, that accident cluster will be addressed in that
14 project.
15 The second cluster, which is at the bottom of the steep
16 grade of the western approach approaching the Neversink
17 Bridge, is a seven percent grade and is at a section where
18 the shoulders and median widths are narrowing at the bridge.
19 Now, our project should address these. It will address these
20 issues by widening the shoulders, give more room to avoid
21 accidents and flatten the vertical grade so it's not as
22 steep.
23 Recommendations from the accident analysis: Reduce the
24 vertical grades as feasible; flatten slopes to eliminate rail
25 where possible; cut back the trees and rock slopes to reduce
12 1 - PRESENTATION -
2 the icing on the pavement; improve the roadway drainage to
3 keep the water off the road and thus reduce icing; improve
4 horizontal curves as practical; and bring shoulder widths up
5 to standard.
6 We performed a traffic analysis for the project. And we
7 found that the traffic is seasonal with the highest volumes
8 occurring in the summer months. And there is heavy
9 directional traffic occurring on the weekends which is
10 probably caused, which is caused by motorists traveling to
11 and from the New York City area to seasonal homes located
12 adjacent to Route 17. The heavy directional movement is
13 westbound on Fridays as the people are coming out from the
14 New York City area; and then again, eastbound on Sunday as
15 they return back.
16 Traffic volumes from 2004 were used to forecast out a
17 30-year period from the estimated time of construction.
18 Because this is a bridge, an interstate project, that's our
19 standard. And we used a one percent, 1.7 percent per year
20 growth rate, and that yielded this table. And I'll just
21 explain a couple of things. The AADT, which is the annual
22 average daily traffic, which is basically the average number
23 of cars traveling on the road in a particular day.
24 Now, the proposed project will be constructed to allow
25 for future expansion of the Route 17 corridor to three lanes
13 1 - PRESENTATION -
2 in each direction. Until that expansion is necessary, the
3 project will be striped for two lanes. This table is based
4 on two lanes of travel in each direction. We also have
5 climbing lanes on each approach. And you can see that in the
6 design here, we meet the interstate standard level of service
7 of B.
8 We will now go through the alternatives, the different
9 alternatives that were considered for this project, and we'll
10 start with the alternatives that we eliminated.
11 Alternative A was the rehabilitation alternative. And
12 basically, we retain the existing bridge and fix it. And
13 there was a couple of reasons why we decided this was not a
14 good alternative. And we had our Regional Structures group
15 do an estimate and they found that the rehab cost would be
16 greater than 85 percent of the replacement cost. Now, that's
17 not the only factor we look at, but it's a guide that tells
18 us that this might not be a cost effective alternative. The
19 other reasons would be even after doing that, we would still
20 be left with the nonstandard grades and shoulder widths, and
21 thus the high accident rate. And the alternative wouldn't
22 meet any of the project objectives.
23 The next alternative would be realignment. Basically,
24 we looked at this alternative because of the bridge's, it's
25 historic and is listed on the National Register eligible. So
14 1 - PRESENTATION -
2 we need to look at alternatives that would avoid the existing
3 bridge. So what we did was we put the two new bridges to the
4 north of the existing, leaving the existing bridge in place.
5 We improved the vertical grades to an interstate standard of
6 four percent, as well.
7 Now, here's the aerial view. And we have what that
8 might look like. We can see the existing bridge here, and
9 two proposed bridges to the north. And you see, there is
10 quite a bit of impact to the wetlands here and to the
11 business. This business and residence would be hit, as well
12 as this residence, right here, would have to the acquired.
13 So it would be two residential structures and a commercial
14 business.
15 So the impacts are pretty significant: 10.3 acres of
16 right-of-way acquisitions; two acres of wetland impacts so we
17 would have to create four acres of new wetland; and a total
18 project cost of 39 million dollars. Now, again, the reason
19 for elimination was the substantial environmental impacts,
20 the large amounts of right-of-way. And on top of that, we'd
21 still be left continuing to maintain and inspect the existing
22 bridge. So we eliminated that alternative.
23 Now we get to our C alternatives. Now, we group these
24 together because they all share the same horizontal
25 alignment, but each one, C-1 through C-4, has a different
15 1 - PRESENTATION -
2 vertical alignment.
3 The existing bridge will be used as a on site detour
4 while the new westbound bridge is built on the north side.
5 The new westbound bridge would have to be built wide enough
6 to accommodate two 12-foot lanes in each direction during
7 construction so that we could shift traffic over to the new
8 westbound bridge. The existing bridge would then be removed
9 and a new eastbound bridge built on the existing alignment.
10 Okay, and here's an aerial view of that. And that
11 would be just the horizontal alignment of what it might look
12 like. You can see we're building the new bridge to the
13 north. And then the eastbound bridge would be on the
14 existing alignment.
15 Now, all the C alternatives will do the same thing as
16 far as the layout. They will increase the shoulder widths to
17 interstate standards, widen the existing median widths to a
18 20-foot minimum. And they will both be, both eastbound and
19 westbound, will be built to accommodate three 12-foot lanes
20 in each direction. And the horizontal curve will be
21 flattened.
22 Okay. Now, what you're looking at here is the profile
23 of the existing New York State Route 17. I'll just point out
24 a few features to make this a little more clear. Here's the
25 County Route 161 bridge and here is the westbound approach
16 1 - PRESENTATION -
2 which is your seven percent grade, the steeper one. Here you
3 see the Neversink Bridge and the Neversink River here, and
4 then our five percent slope out. Now, this profile is
5 exaggerated five times vertically for illustrative purposes
6 just so you can see what's going on here a little easier.
7 Now, here would be our first alternative. And
8 basically, that would be four percent grades and no cut at
9 the existing County Route 161 bridge. And I'll get into that
10 a little more, why that's important. But that would be four
11 percent on each side.
12 C-2 alternative would be a compromise to five percent
13 grades on each side and a lowering the profile approximately
14 eight feet at the County Route 161 bridge.
15 Alt C-3 would be five percent slopes on each side but no
16 lowering at the County Route 161 bridge.
17 And our final alternative was Alternative C-4, which is
18 four percent grades on each side and an eight foot lowering
19 at the County Route 161 bridge.
20 Now we'll zoom in on the bridge area so you can get a
21 better look at that, at what these elevation differences are,
22 and we'll start from the lowest and work our way up. So
23 Alternative C-2 would be the lowest one, and that is still 23
24 feet higher than the existing bridge. C-3 would be the next
25 highest at 28 feet. That's C-4, and that would be 38 feet.
17 1 - PRESENTATION -
2 And the highest was the C-1 alternative, which is 44 feet.
3 So there's quite a difference between this alternative and
4 this alternative. It's another 20 feet so it's significant.
5 Okay. And now I want to zoom in on the County Route 161
6 area, County Route Bridge 161. And you can see here, that
7 here is the existing County Route 161 bridge, and this is
8 where the proposed one which will be done under another
9 project, PIN 9666.96, as I explained earlier. But we had to
10 coordinate that design with our design to make this
11 worthwhile.
12 Now, what you can see here is this is the C-2 and C-4
13 alternative that does have the eight foot cut at the bridge.
14 And what happens is that allows this proposed bridge to be
15 lowered in elevation and still maintain a vertical clearance.
16 But lowering that bridge makes the grade of the ramps leading
17 up to that an acceptable slope because they were too steep.
18 If we had to make that vertical clearance from here, the
19 bridge would be up higher. And to get those ramps to match
20 in, the slope would be higher, would be steeper. So because
21 much that, Alt C-1 and C-3 does not help the design of the
22 other project being proposed, County Route 161 bridge. So we
23 pretty much eliminated them for further consideration. But
24 we'll take a look at the impacts from C-1 and C-3.
25 The right-of-way impacts from C-1 and C-3, we would have
18 1 - PRESENTATION -
2 8.9, nearly nine acres of right-of-way impacts, and that
3 would include one residence and two commercial structures.
4 Alternative C-3 would be six and a half acres of right-of-way
5 takes, and that would include two commercial structures. C-1
6 was the one that was significantly higher, higher in
7 elevation, so you should see more right-of-way and wetland
8 impact. So you see one and a half acres and one acre.
9 Total project costs for these alternatives, as expected,
10 the higher one is going to be more costly, 39.9 million, and
11 33.6 million for Alt C-3.
12 So the main reason for elimination was profile, it needs
13 to be lower to accommodate the Interchange 107 design. But
14 it also has more right-of-way acquisitions and environmental
15 impacts than the preferred alternative. And both
16 alternatives also have a higher project cost.
17 So that brings us to our other, last eliminated
18 alternative, C-4. Under this alternative, we would
19 reconstruct the bridge, of course, and we would construct the
20 four percent grades on both approaches of the bridge. But
21 importantly, we would lower the profile of the County Route
22 161 bridge.
23 Now, I have the aerial view of what that will look like,
24 and I will zoom in a little to show you. So basically, for
25 this, you can see this line right here, this green line.
19 1 - PRESENTATION -
2 That would be the comparative hill slope to the preferred
3 Alternative C-2. So you can see how much farther the fill
4 comes out with the C-4 alternative. We would be impacting
5 this commercial business here. And you can see our fill line
6 go over County Route 173 so we'd have to build a retaining
7 wall. And we would also affect this commercial structure
8 here.
9 So impacts for Alternative C-4: Seven acres of
10 right-of-way acquisition, including the two commercial
11 structures; 1.25 acres of wetland impacts; a total project
12 cost of 35.2 million dollars. And we eliminated this based
13 on there was more right-of-way acquisitions, more
14 environmental impacts and higher project cost than the
15 preferred alternative.
16 So that brings us to our preferred alternative. And
17 while this is our preferred alternative, it will not be
18 finalized until comments from the hearing are addressed and
19 FHWA grants approval. We're still in the preliminary design
20 process at this stage.
21 Okay. So as part of Alternative C-2, we would
22 reconstruct the bridge but we would compromise to a five
23 percent grade instead of the interstate standard four
24 percent. Now, the five percent grade is consistent with the
25 butting segments of New York State Route 17. And FHWA, at
20 1 - PRESENTATION -
2 this point, has expressed agreement with going this route.
3 And this one, you can see the bridge building to the
4 westbound lanes built to the north of the existing bridge.
5 And we'll zoom in a little bit on that. So we can see the
6 impacts would be this commercial structure would be impacted
7 but there would be no other impacts. We would avoid impacts
8 here and to the other residence. And you can see County
9 Route 173 is not impacted anymore. Now, we do impact some
10 wetlands and we will have to mitigate those, and we have a
11 preliminary mitigation area shown up here. You can see this
12 area here. So there would be 6.25 acres of right-of-way
13 acquisitions, including the acquisition of one commercial
14 structure; .75 acres of wetland impact. The total project
15 cost would be 31.3 million dollars.
16 And the reason for selecting this as our preferred
17 alternative was it all meets the project goals of improving
18 the segment of Route 17 to allow for designation as
19 Interstate 86. It restores the condition of the bridge;
20 provides for future traffic capacity; improves the geometrics
21 and the vertical grades; cuts back the slopes and the trees
22 to reduce icing; and improves overall safety by providing new
23 guide rail, signs and drainage facilities. It also has the
24 least amount of right-of-way acquisitions and environmental
25 impacts and is the least expensive alternative.
21 1 - PRESENTATION -
2 So here you can see the summary of the alternatives.
3 You can see for all the categories, right-of-way, wetland,
4 structures impacted and total cost, the preferred alternative
5 has the least impacts.
6 Now, to build this, what we'll do is during construction
7 we will have two 12-foot travel lanes in each direction and
8 we'll put that on the existing eastbound lanes during Stage
9 1. And on the existing bridge, as well, there will be two
10 travel lanes, two 12-foot lanes in each direction while we
11 build the westbound lanes and the westbound structure.
12 Now, to be able to build this new elevation, the new
13 profile which is a higher elevation, we'll have to use what
14 is called a GRES wall, which is a geosynthetic reinforcer
15 system. And basically how that happens, you have
16 geosynthetic strips that extend into the embankment, and
17 you'll have a bunch of those. And what is it, the weight of
18 the embankment itself on those strips creates a friction
19 force which will hold up that embankment and allow us to
20 build it where it's supposed to be and still have lanes next
21 to it.
22 In Stage 2 traffic would then be shifted to the newly
23 constructed westbound lane and westbound bridge. The
24 westbound bridge would be built wide enough to accommodate
25 two lanes in each direction during construction of the
22 1 - PRESENTATION -
2 eastbound lanes and the eastbound bridge.
3 Environmental concerns: This alternative will have
4 minor amounts of wetland impacts that will have to be
5 mitigated as explained earlier. The wetland mitigation will
6 be done on site. One business will need to be relocated.
7 And there a New York State Department of Environmental
8 Conservation parking lot which is located on the east side of
9 the Neversink River near the existing bridge. That will have
10 to be relocated south. But we will move that down on Edward
11 Islands Road a little ways.
12 Okay. Now we'll go through a little bit of the project
13 schedule. So at this point the Draft Design work has been
14 put out and given to agencies for comments. The Draft Design
15 Report documents the project history, existing conditions,
16 design criteria, alternatives considered and environmental
17 impacts. And that has been completed and made available to
18 the public for review and comment. So after tonight, after
19 the public hearing, the comments will be compiled and
20 addressed, and then the Design Report will be finalized. And
21 then design approval will be sought from FHWA. We expect
22 design approval to be granted in June of this year and then
23 we can go into final design. Now, at this point, the
24 right-of-way acquisition process can begin, and affected
25 property owners will be contacted by Regional Real Estate
23 1 - PRESENTATION -
2 representatives to get that process moving.
3 Okay. Then we will be in final design. And Main Office
4 Structures will be designing new bridges, and my design squad
5 will design the highway approaches and prepare the final
6 plans, specifications and estimate package. We hope to have
7 that completed by January of 2011.
8 The project will then be let out for bid and a
9 contractor will be selected. We expect the letting and award
10 to occur in the spring of 2011. Then construction will begin
11 that spring, 2011. And we expect two full years of
12 construction. So the construction will end somewhere in the
13 spring to summer of 2013.
14 Now, we have a visualization of what the new bridge, as
15 far as elevation wise, might look like. Now, the bridge type
16 and the pier placement at this point, we're just doing this
17 for illustrative purposes. And would be decided in final
18 design by our Main Office Structures group. But I'll go
19 back. And you can see that it's quite a difference in
20 elevation. That's 23 feet.
21 Thank you. That concludes my presentation. And we have
22 contact information, and this information is also available
23 in the brochures. But Bill Naylor, who is our Project
24 Manager, he has his mailing address and e-mail and phone
25 number up there.
24 1 - PRESENTATION -
2 At this point, I'd like to turn it back over to Daniel,
3 Daniel Odigie. Thank you very much.
4 MR. ODIGIE: Thank you, Brad.
5 We have presented an overview of the project and the
6 studies that have gone into the preliminary engineering.
7 The New York State Department of Transportation
8 encourages you to make comments and observations on this
9 project. Your comments and observations will be taken into
10 consideration as we progress with the project. These will be
11 additional recommendations that will define the Final Design
12 Report.
13 The Real Estate Division of the New York State
14 Department of Transportation will acquire the necessary
15 right-of-ways for this project. Although a number of
16 properties will be affected, we have identified one
17 commercial property that will be acquired and the occupant
18 displaced. While performing our relocation study, we found
19 seven commercial properties for sale or lease to accommodate
20 the displaced occupant. Acquisition of property will
21 commence only after the federal design approval is obtained.
22 We have two booklets available which describes our
23 acquisition and relocation procedures. The first booklet is
24 "If You Must Move, We Can Help." It outlines the services
25 and financial benefits available to eligible occupants who
25 1 - PRESENTATION -
2 will be required to move. The second one, "How Your State
3 Acquires Property For Public Purposes." It contains a resume
4 of the questions most frequently asked by affected property
5 owners. In addition, a representative of our Real Estate
6 group is available to answer your individual inquiries.
7 We have also included our mailing address and phone
8 number in the booklets. If you have more questions or
9 additional information after this meeting, please feel free
10 to call upon us.
11 We will now begin the formal comment portion of this
12 hearing. We invite the Job Manager, Pete Larson, to conduct
13 this part of the hearing.
14 Pete.
15 MR. LARSON: All comments given tonight will be recorded
16 and become part of the Public Hearing record. In addition to
17 this comment period, you may submit written comments using
18 the pre-addressed comment forms that were available with the
19 brochure. There are extra copies available out front. You
20 may also submit it on your stationery. Just please be sure
21 to send those comments to the same address that's on that
22 pre-printed form or in the brochure. Written comments may be
23 handed in this evening or mailed to that address. Comments
24 received or postmarked prior to May 12, 2009 will become part
25 of the Public Hearing record. Comments received or
26 1 - PUBLIC COMMENT -
2 postmarked after that date will still become part of the
3 project record but not part of the Public Hearing report.
4 During tonight's comment period we'll first take
5 comments from those who have filled out the comment cards at
6 the front desk. If you have not filled out a card and would
7 like to comment, you will still have a chance to do so. When
8 called on, please begin by stating your name, spelling it if
9 necessary, and providing your address. Make sure to speak
10 clearly so that the stenographer can understand what you are
11 saying and get it down into the record. Please keep your
12 initial comments to two to three minutes so that everyone
13 gets a turn. If you have additional comments, you'll have
14 another opportunity once everybody has had a chance.
15 We will not be able to answer questions during this
16 phase of the formal hearing. This is strictly an opportunity
17 for you to have your comments and concerns added to the
18 public record as a statement. We will be available after the
19 formal portion of the hearing is over to answer any of your
20 questions and talk with you individually.
21 At this point, do we have any comment cards filled out?
22 MS. UNIDENTIFIED SPEAKER: No, we do not.
23 MR. LARSON: Then is there anyone in the audience who
24 would like to make a comment on the project? Sir.
25 MR. LOCASCIO: I thought I filled one out. When I
27 1 - VINNIE LOCASCIO -
2 filled out my name I thought that was it.
3 My name is Vinnie Locascio. I'm pretty near a lifetime
4 member of the people who live here. And I'm an operating
5 engineer. I run heavy equipment. I run heavy equipment that
6 builds these roads. I've been doing it all my life, 48
7 years. Anyway, I've been part of four sections of Route 17 I
8 helped build. I paved the one up in Livingston Manor in
9 1963.
10 And I've seen a lot of bad accidents. I've almost got
11 involved in a few right here in Bridgeville. And I'm here
12 because I'd like to see that you guys -- can you get a
13 picture, the overhead, so I can show you what I'm talking
14 about? In other words, an aerial view? Because I'd like to
15 see this change for the better. I'll tell you why.
16 In my lifetime here, and the rest of you guys who live
17 here, I'm sure you've seen a lot of this, there's some bad
18 accidents in Bridgeville. I almost got run over by a
19 tractor-trailer about, in the early 1970's. It was coming
20 down eastbound and I was going westbound. He just missed me.
21 And I thought he was going to be all right, but he ran over a
22 couple behind me and killed them, before there was a median
23 there. But it's kind of a poor design, the road.
24 There's a friend of mine named Al Mitchell who you guys
25 might know. He was coming down with a tractor-trailer down
28 1 - VINNIE LOCASCIO -
2 this hill one time with a load of gas tanks, a load of
3 bottled gas tanks. A bunch of Hasidic guys that had a
4 station wagon, they dropped something out of the station
5 wagon. They were covering both lanes. He missed them
6 without killing them. He went down over the bridge and he
7 got pretty well hurt. And if you look at over here now, the
8 guard rails are down from somebody who went through there
9 this winter.
10 A couple of years ago, coming this way here, Route 17
11 was blocked because there were two tractor-trailers there for
12 half a day.
13 So this is a turn. It has to be taken out over here.
14 My idea would be to take some of this out and put your road
15 through here. Cut out this here and put it. There's only
16 woods and rock here. Take out those few buildings there, put
17 Old 17 over here someplace, and take out this turn over here.
18 And the real reason why the bridge is low, I was here
19 when they built it, was because they ran out of money with
20 the project. It was supposed to be 20 foot higher, that
21 bridge. But they didn't have the money to do it anymore so
22 they made it 20 foot lower. The bridge has got to be a lot
23 higher. And I don't think you have to have any piers in the
24 water. If you build massive piers on each side of the river
25 in case anything ever happens with the Neversink River so it
29 1 - VINNIE LOCASCIO -
2 doesn't flood and break the piers, like it could happen, and
3 build it higher like it should be, you wouldn't have to worry
4 about five percent grade and six percent grade because it
5 wouldn't be that steep. And like I said, if you take this
6 turn out so the people can see, and take this road and put it
7 right through here, you won't have to worry about the wetland
8 over here. There's only one over here, I think.
9 And this road is not that important. The few businesses
10 there on that sharp curve, that was always a problem in the
11 50's anyway, that road. And put this further in here. In
12 other words, you build Old 17 and put this where it belongs,
13 right here, and straighten out that curve, and you wouldn't
14 have to disrupt much traffic and you'd save lives. If you
15 don't do that, your design over here is making it more of a
16 curve, further on the outside, which is going to make the
17 conditions worse for safety. And I don't think that's the
18 right way to go. And I've been doing this all my life, I
19 lived here all my life, so I know what I'm talking about. I
20 think you've got to take some of this curve out of here and
21 make this better. And that's all I have to stay.
22 MR. LARSON: Did you get the gentleman's name?
23 STENOGRAPHER: Yes.
24 MR. LARSON: Okay. For the record, because the
25 stenographer can't record where you're pointing on the
30 1 - VINNIE LOCASCIO -
2 screen, I'm just going to point out that you suggested
3 straightening out the curve on the east side of the river and
4 moving 17 southward.
5 MR. LOCASCIO: Yes. And making it safe, because what
6 you guys are doing is not going to make it safer. You're
7 going to have a sharper turn than what we got now, and it's
8 already a problem. Go look at the guard rails when you leave
9 here and see. They're all down yet from the winter, on the
10 outside. That's now. And then on the inside, there's no
11 accidents now, but I've seen them. Almost been part of them.
12 It's too steep. It's just not right. If you're going to
13 make an interstate road from that, you got to do a better job
14 than what we got there. Okay?
15 MR. LARSON: Thank you for your comments.
16 Anyone else?
17 (No verbal response.)
18 MR. LARSON: If no one else wishes to make a comment for
19 the record, then we will conclude the formal portion of this
20 hearing. Department Staff will remain and answer questions
21 on an individual basis until everybody's had a chance to talk
22 with us.
23 Thank you for coming tonight.
24 (Time noted: 7:18 p.m.)
25 * * * * *
31 1
2 REPORTER'S CERTIFICATION
3
4
5 I, ROSEMARY A. MEYER, a Shorthand Reporter and
6 Notary Public in and for the State of New York, do
7 hereby certify:
8 That the foregoing transcript is an accurate record
9 of the proceedings herein, to the best of my knowledge
10 and belief, having been stenographically recorded by me
11 and transcribed under my supervision.
12 I further certify that I am in no way related to
13 any of the parties to this action and that I have no
14 personal interest whatsoever in the outcome thereof.
15
16
17
18 ______________________________________
19 ROSEMARY A. MEYER
20
21
22
23 Date Transcribed: May 17, 2009
24
25
32 1
2 K E Y W O R D I N D E X
3 T O P I C S
4 Page Line
5
6 Presentation................ 5 17
7 Public Comment.............. 25 15
8 * * * * *
9 PUBLIC COMMENTS
10 Locascio, Vinnie .......... 26 25
11 * * * * *
12
13
14
15
16
17
18
19
20
21
22
23
24
25
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
1
1 (2) 10:10;21:91.15 (1) 10:211.25 (1) 19:111.7 (1) 12:191.8 (1) 10:810.3 (1) 14:15102 (1) 11:9107 (6) 6:4,16,17;11:4,4; 18:13108 (4) 6:4,16,18;11:912 (1) 25:2412-foot (4) 15:6,19;21:7,10161 (12) 6:18;9:8;15:25; 16:9,14,16,19;17:5,6, 7,22;18:2217 (16) 2:7;4:18;6:7,15; 9:13;10:8;12:12,25; 15:23;19:25;20:18; 27:7;28:10,17;29:12; 30:4173 (3) 6:20;19:6;20:918 (1) 10:181953 (1) 6:211963 (1) 27:91970's (1) 27:19
2
2 (1) 21:2220 (3) 17:4;28:20,222004 (2) 10:10;12:162007 (1) 10:102009 (1) 25:242011 (5) 5:10,19;23:7,10,112013 (2) 5:10;23:13
20-foot (1) 15:1823 (2) 16:23;23:2028 (2) 10:10;16:2529 (1) 10:12
3
3.8 (1) 7:1030 (1) 9:1830-year (1) 12:1731.3 (1) 20:1533.6 (1) 18:11348 (1) 8:1235.2 (1) 19:1236 (2) 5:5;8:2038 (1) 16:2539 (1) 14:1839.9 (1) 18:10
4
42 (1) 10:1344 (1) 17:245 (1) 10:1148 (1) 27:6
5
50's (1) 29:11
6
6.25 (1) 20:126:00 (1) 2:126:34 (1) 2:13
7
7:18 (1) 30:24
720 (1) 8:1275 (1) 20:14
8
8.9 (1) 18:2800.6 (1) 5:684 (1) 10:2385 (1) 13:1686 (3) 4:19;9:15;20:19
9
9 (1) 2:59067.17 (1) 2:99666.96 (2) 11:6;17:9
A
AADT (1) 12:21abide (1) 4:9able (3) 7:25;21:12;26:15acceptable (2) 9:17;17:17accident (10) 4:15;6:8;10:7,9, 21;11:2,2,13,23; 13:21accidents (10) 10:11,13,14,16,21, 24;11:21;27:10,18; 30:11accommodate (5) 15:6,19;18:13; 21:24;24:19accomplish (1) 6:8accordance (2) 2:15;4:17acquire (1) 24:14acquired (3) 3:2;14:12;24:17Acquires (1) 25:3acquisition (5) 19:10;20:13; 22:24;24:20,23acquisitions (5) 14:16;18:14;
19:13;20:13,24acre (2) 9:2;18:8acres (11) 9:3;14:15,16,17; 18:2,4,8;19:9,11; 20:12,14Act (2) 2:17;5:4added (1) 26:17addition (2) 25:5,16additional (3) 24:11;25:9;26:13address (7) 11:19,19;23:24; 25:7,21,23;26:9addressed (3) 11:13;19:18;22:20addresses (1) 5:6adjacent (1) 12:12adverse (1) 5:7advertised (1) 2:23aerial (5) 6:16;14:7;15:10; 18:23;27:14affect (2) 9:11;19:7affected (3) 22:24;24:16;25:4afternoon (1) 2:2Again (4) 5:21;8:12;12:14; 14:18agencies (1) 22:14ago (1) 28:10agreement (1) 20:2Al (1) 27:24Albany (1) 3:19alcohol (1) 10:17alignment (5) 14:25;15:2,9,11,14allow (3) 12:24;20:18;21:19allows (1) 17:14almost (3) 27:10,18;30:11along (1) 6:15Alt (3)
16:15;17:21;18:11alternative (34) 2:21;6:13;13:11, 11,14,18,21,23,24; 14:22;16:7,12,17,17, 23;17:2,3,4,13;18:4, 15,18,18;19:3,4,9,15, 16,17,21;20:17,25; 21:4;22:3alternatives (12) 6:10,11;13:8,9,10; 14:2,23;15:15;18:9, 16;21:2;22:16Although (1) 24:15always (1) 29:10amount (1) 20:24amounts (2) 14:20;22:4analysis (6) 6:9,9;10:7;11:2, 23;12:6Andrew (1) 4:4animal (1) 10:16annual (1) 12:21Anthony (1) 3:25anymore (2) 20:9;28:21apart (1) 8:22approach (4) 7:15;11:16;13:5; 15:25approaches (5) 4:14;6:3;7:15; 18:20;23:5approaching (1) 11:16approval (4) 19:19;22:21,22; 24:21approximately (1) 16:13area (10) 9:5,9;10:9;11:11; 12:11,14;16:20;17:6; 20:11,12assign (1) 9:22assist (1) 3:15associated (2) 4:15;6:13audience (1) 26:23Authority's (1) 5:3
Min-U-Script® Jeric Corporation (845) 252-3515 (1) 1 - Authority's
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
available (10) 4:8,21;22:17; 23:22;24:22,25;25:6, 18,19;26:18average (3) 10:23;12:22,22avoid (3) 11:20;14:2;20:7award (1) 23:9
B
back (9) 7:16;9:10;10:3; 11:11,25;12:15; 20:21;23:19;24:2bad (3) 10:19;27:10,17based (4) 6:22;9:20;13:3; 19:12basically (8) 9:19,22;12:22; 13:12,23;16:8;18:24; 21:15basis (1) 30:21become (3) 25:16,24;26:2began (1) 2:12begin (5) 5:11;22:24;23:10; 25:11;26:8behind (1) 27:22belongs (1) 29:12below (1) 6:23benefits (1) 24:25Benjamin (1) 4:2best (1) 9:23better (4) 16:21;27:15; 29:21;30:13bid (1) 23:8Bill (2) 3:12;23:23Binghamton (2) 2:6;4:23bit (3) 14:10;20:5;22:12blocked (1) 28:11booklet (1) 24:23booklets (2)
24:22;25:8Bortnick (5) 3:22;5:11,17,21,22both (6) 7:15;15:18,18; 18:15,20;28:5bottled (1) 28:3bottom (1) 11:15Brad (6) 3:22,23;5:11,14, 22;24:4brakes (1) 10:19break (1) 29:2breakdown (1) 10:13BRIDGE (67) 2:1,8;3:1;4:1,11; 5:7,9;6:2,18,19,21; 7:4,8,10,13;8:16;9:8, 16;11:17,18;12:18; 13:12;14:3,4,8,22; 15:3,4,5,8,8,9,12,13, 25;16:3,9,14,16,19, 20,24;17:6,7,13,14, 16,19,22;18:19,20, 22;19:22;20:3,4,19; 21:9,23,24;22:2,9; 23:14,15;28:6,18,21, 22bridges (4) 4:14;14:3,9;23:4bridge's (1) 13:24Bridgeville (2) 27:11,18briefly (1) 3:11bring (3) 8:11;9:13;12:4brings (2) 18:17;19:16brochure (2) 25:19,22brochures (1) 23:23build (9) 19:6;21:6,11,12, 20;27:8;28:24;29:3, 12building (2) 15:12;20:3buildings (1) 28:16builds (1) 27:6built (8) 6:21;15:4,5,9,19; 20:4;21:24;28:19bunch (2)
21:17;28:3business (5) 14:11,11,14;19:5; 22:6businesses (1) 29:9butting (1) 19:25
C
C-1 (6) 14:25;17:2,21,24, 25;18:5C-2 (5) 16:12,23;17:12; 19:3,21C-3 (7) 16:15,24;17:21,24, 25;18:4,11C-4 (7) 14:25;16:17,25; 17:12;18:18;19:4,9call (1) 25:10called (3) 3:11;21:14;26:8calls (1) 8:20came (1) 4:25can (30) 4:6,12;6:17;7:5; 8:4;10:23;13:5;14:8; 15:12;16:6,20;17:6, 12;18:25;19:3,5; 20:3,5,8,11;21:2,3; 22:23,24;23:19; 24:24;26:10;27:12, 13;29:6capacity (2) 4:16;20:20card (1) 26:6cards (2) 26:5,21cars (1) 12:23case (5) 4:6;7:21,22;8:10; 28:25categories (1) 21:3caused (2) 12:10,10Cellini (1) 3:25CFR (1) 5:6chance (3) 26:7,14;30:21change (1) 27:15
City (2) 12:11,14clear (1) 15:24clearance (2) 17:15,18clearly (1) 26:10climbing (1) 13:5cluster (3) 11:3,13,15clusters (1) 11:3Code (1) 5:6coming (7) 5:24;7:16;12:13; 27:19,25;28:10; 30:23commence (3) 5:16,19;24:21comment (12) 2:13;22:18;25:11, 17,18;26:1,4,5,7,21, 24;30:18comments (19) 2:21;3:7;5:12; 19:18;22:14,19;24:8, 9;25:15,17,21,22,23, 25;26:5,12,13,17; 30:15commercial (10) 14:13;18:3,5;19:5, 7,10;20:6,13;24:17, 19Commissioner (1) 4:3common (1) 6:24comparative (1) 19:2compare (1) 10:23compiled (1) 22:19completed (5) 4:21;5:10,13; 22:17;23:7completely (1) 7:12compliance (1) 5:5compromise (2) 16:12;19:22concerns (3) 6:13;22:3;26:17conclude (1) 30:19concludes (1) 23:21concrete (2) 7:6,7
concurrence (1) 5:3condition (4) 7:4,8;9:15;20:19conditions (5) 6:6;8:14;10:4; 22:15;29:17conduct (1) 25:12conducted (1) 2:15Conservation (1) 22:8consideration (2) 17:23;24:10considered (5) 2:22;6:10;7:2; 13:9;22:16consistent (1) 19:24construct (1) 18:19constructed (2) 12:24;21:23construction (8) 5:8;12:17;15:7; 21:6,25;23:10,12,12contact (1) 23:22contacted (1) 22:25contains (1) 25:3continuing (1) 14:21contractor (1) 23:9contributing (1) 11:12coordinate (1) 17:10copies (2) 4:21;25:19corner (1) 9:8correspond (1) 8:3corridor (3) 4:8;9:17;12:25cost (10) 7:12;13:15,16,18; 14:18;18:16;19:12, 14;20:15;21:4costly (1) 18:10costs (1) 18:9County (20) 2:9,24;3:16;4:4,5; 6:17,19;9:8;15:25; 16:9,14,16,19;17:5,6, 7,22;18:21;19:6;20:8couple (4)
Min-U-Script® Jeric Corporation (845) 252-3515 (2) available - couple
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
12:21;13:13; 27:22;28:10course (2) 9:4;18:19covering (1) 28:5create (2) 9:3;14:17creates (1) 21:18criteria (1) 22:16currently (1) 8:20curve (6) 15:20;29:10,13,16, 20;30:3curves (1) 12:4cut (5) 10:4;11:25;16:8; 17:13;28:15cuts (2) 11:11;20:21cutting (2) 9:10;11:10
D
daily (1) 12:22damage (1) 10:12Daniel (3) 2:4;24:2,3data (1) 10:9date (2) 11:7;26:2day (2) 12:23;28:12DDR (1) 4:20decided (2) 13:13;23:17deck (2) 6:23;7:7deer (1) 8:10defective (1) 10:19deficient (2) 8:21;10:5define (1) 24:11Democrat (1) 2:25Denise (1) 3:15Department (10) 2:5,10;3:3,10,15; 5:23;22:7;24:7,14; 30:20
describes (1) 24:22design (27) 3:20;4:20;5:25; 8:9;9:18;11:8;13:6; 17:10,10,21;18:13; 19:19;22:13,14,16, 20,21,22,23;23:3,4,5, 18;24:11,21;27:23; 29:15designation (3) 4:18;9:14;20:18designed (1) 4:17designing (1) 23:4desk (1) 26:6deterioration (1) 7:5detour (1) 15:3difference (3) 8:13;17:3;23:19differences (1) 16:21different (2) 13:8;14:25direction (7) 13:2,4;15:6,20; 21:7,10,25directional (2) 12:9,12displaced (2) 24:18,20display (1) 2:11disrupt (1) 29:14distance (9) 7:19,21,24,24;8:3, 4,5,7,8disturb (1) 8:24ditches (1) 8:21Division (1) 24:13documentation (1) 3:8documents (1) 22:15dollars (3) 14:18;19:12;20:15Domain (1) 2:18done (3) 9:9;17:8;22:6doors (1) 4:6DOT (2) 3:16;4:22down (8)
22:10;26:11; 27:20,25,25;28:6,8; 30:9downgrade (1) 7:23downgrades (1) 7:22Draft (3) 4:20;22:13,14drainage (2) 12:2;20:23Draper (1) 3:13driver (2) 8:9;10:17driving (1) 8:9dropped (1) 28:4drug (1) 10:17during (8) 2:11;10:11;15:6; 21:6,8,25;26:4,15
E
earlier (2) 17:9;22:5early (1) 27:19easier (1) 16:6east (3) 6:3;22:8;30:3eastbound (9) 11:5;12:14;15:9, 13,18;21:8;22:2,2; 27:20Ed (1) 4:4Edward (1) 22:10effect (1) 5:7effective (1) 13:18efficient (1) 9:17eight (3) 16:14,18;17:13elevation (7) 16:21;17:15;18:7; 21:12,13;23:15,20eligible (5) 5:7;6:22;9:7; 13:25;24:25eliminate (1) 11:24eliminated (6) 6:11;13:10;14:22; 17:23;18:17;19:12elimination (2)
14:19;18:12Elizabeth (1) 3:14else (2) 30:16,18e-mail (1) 23:24embankment (3) 21:16,18,19emergency (1) 4:6Eminent (1) 2:18encompassing (1) 10:8encourages (1) 24:8end (2) 4:12;23:12engineer (3) 2:4;3:16;27:5engineering (1) 24:6enough (2) 15:5;21:24entered (1) 4:7Environmental (13) 2:16,17;5:4;6:12; 10:13,14;14:19; 18:14;19:14;20:24; 22:3,7,16equipment (2) 27:5,5establish (1) 9:16Estate (4) 3:14;22:25;24:13; 25:5estimate (2) 13:15;23:6estimated (1) 12:17evaluated (1) 10:10even (1) 13:19evening (2) 5:21;25:23everybody (1) 26:14everybody's (1) 30:21everyone (1) 26:12exaggerated (1) 16:5excellent (1) 7:10excuse (1) 6:23existing (27) 6:6,18,21;8:12,14,
19,23;13:12;14:2,4, 4,8,21;15:3,8,9,14, 17,23;16:9,24;17:7; 20:4;21:8,9;22:9,15exit (1) 4:6expansion (2) 12:25;13:2expect (3) 22:21;23:9,11expected (1) 18:9expense (1) 4:13expensive (1) 20:25explain (2) 7:20;12:21explained (2) 17:9;22:5expressed (2) 3:4;20:2extend (1) 21:16extra (1) 25:19
F
facilities (1) 20:23facility (2) 4:9;10:24factor (1) 13:17factors (1) 9:21falling (1) 8:22far (2) 15:16;23:15farther (1) 19:3feasible (2) 2:21;11:24features (1) 15:24February (1) 10:10Federal (3) 5:2,6;24:21feel (1) 25:9feet (13) 8:12,12,18,18,20, 20;16:14,24,25,25; 17:2,4;23:20few (4) 15:24;27:11; 28:16;29:9FHWA (3) 19:19,25;22:21fill (2)
Min-U-Script® Jeric Corporation (845) 252-3515 (3) course - fill
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
19:3,5filled (5) 26:5,6,21,25;27:2final (6) 16:17;22:23;23:3, 5,17;24:11finalized (2) 19:18;22:20financial (1) 24:25first (4) 11:3;16:7;24:23; 26:4five (8) 7:17;16:4,5,12,15; 19:22,24;29:4fix (1) 13:12flatten (4) 8:6;10:3;11:21,24flattened (1) 15:21flicker (1) 6:24flood (1) 29:2flow (3) 9:20,23,25followed (1) 5:3following (1) 3:9foot (6) 8:16,17;16:18; 17:13;28:20,22force (1) 21:19forecast (1) 12:16form (1) 25:22formal (4) 25:11;26:16,19; 30:19forms (1) 25:18Forty (1) 10:16found (3) 12:7;13:15;24:18four (10) 7:17;8:18;14:6,17; 16:8,10,18;18:20; 19:23;27:7free (3) 9:23,25;25:9French (1) 3:14frequently (1) 25:4friction (1) 21:18Fridays (1)
12:13friend (1) 27:24front (2) 25:19;26:6full (1) 23:11functional (1) 9:15further (3) 17:23;29:11,16future (5) 4:16,18;9:14; 12:25;20:20
G
gas (2) 28:2,3gentleman's (1) 29:22gentlemen (1) 2:2geometric (1) 10:2geometrics (1) 20:20geosynthetic (2) 21:14,16gets (1) 26:13given (2) 22:14;25:15goals (1) 20:17good (3) 2:2;5:21;13:14grade (11) 4:14;8:4;11:16,17, 21;16:2;17:16;19:23, 24;29:4,4grades (12) 4:15;7:14;8:6; 10:3;11:24;13:20; 14:5;16:8,13,18; 18:20;20:21granted (1) 22:22grants (1) 19:19greater (1) 13:16green (1) 18:25GRES (1) 21:14group (4) 13:14;14:23; 23:18;25:6growth (1) 12:20guard (2) 28:8;30:8
guide (3) 10:5;13:17;20:23gutter (1) 8:22gutters (1) 8:21guys (5) 27:12,16,24;28:3; 30:6
H
half (6) 8:20,25;9:3;18:4, 8;28:12Hall (1) 4:21hand (2) 2:10;3:11handed (1) 25:23handout (1) 4:25happen (1) 29:2happens (3) 17:14;21:15;28:25Hasidic (1) 28:3headlight (5) 7:24;8:3,5,7,8headlights (1) 8:2Hearing (14) 2:7,14,15,23; 19:18;22:19;25:12, 13,16,25;26:3,16,19; 30:20heavy (4) 12:8,12;27:5,5help (3) 2:10;17:21;24:24helped (1) 27:8Here's (4) 8:17;14:7;15:10, 24high (3) 7:12,13;13:21higher (13) 10:25;16:24; 17:19,20;18:6,6,10, 16;19:14;21:13; 28:20,23;29:3highest (3) 12:7;16:25;17:2Highway (3) 4:2;5:2;23:5hill (2) 19:2;28:2Himabindu (1) 3:21Historic (5)
5:8;6:22;7:2;9:7; 13:25history (1) 22:15hit (1) 14:11hitch (1) 10:20hold (2) 5:12;21:19home (1) 9:7homes (1) 12:11hope (7) 6:7;8:6,11;9:12, 25;10:2;23:6hopefully (1) 11:13horizontal (4) 12:4;14:24;15:11, 20house (2) 2:12;9:11human (1) 10:16hurt (1) 28:7
I
I-86 (1) 9:14icing (5) 10:4;11:12;12:2,3; 20:22idea (1) 28:14Identification (1) 2:9identified (2) 11:3;24:16illustrative (2) 16:5;23:17impact (5) 9:3;14:10;18:8; 20:9,14impacted (3) 20:6,9;21:4impacting (1) 19:4impacts (17) 14:15,16,19;17:24, 25;18:2,15;19:9,11, 14;20:6,7,7,25;21:5; 22:4,17important (2) 16:10;29:9importantly (1) 18:21improve (3) 11:8;12:2,3improved (2)
10:6;14:5improvements (2) 4:16;10:2improves (2) 20:20,22improving (1) 20:17inattention (1) 10:18include (2) 18:3,5included (1) 25:7including (3) 6:11;19:10;20:13increase (2) 8:7;15:16increases (1) 4:16individual (2) 25:6;30:21individually (1) 26:20inform (1) 2:19information (3) 23:22,22;25:9initial (1) 26:12injuries (1) 10:12inquiries (1) 25:6inside (1) 30:10inspect (2) 7:11;14:21instead (1) 19:23instructions (1) 4:7intends (1) 4:13Interchange (4) 6:17,18;11:4; 18:13interchanges (3) 6:4,15;11:9interest (1) 3:5interstate (17) 4:17,19;7:17;8:11, 17,20;9:14,15,24; 11:10;12:18;13:6; 14:5;15:17;19:23; 20:19;30:13into (6) 16:9;21:16;22:23; 24:6,9;26:11introduce (1) 3:25invite (1) 25:12
Min-U-Script® Jeric Corporation (845) 252-3515 (4) filled - invite
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
involved (1) 27:11Islands (1) 22:11issues (1) 11:20
J
Jakubiak (1) 3:22January (1) 23:7Jillian (1) 3:13Job (3) 3:12;25:12;30:13June (1) 22:22
K
keep (2) 12:3;26:11killed (1) 27:22killing (1) 28:6kind (1) 27:23Kindly (1) 3:10
L
Ladies (1) 2:2lane (1) 21:23lanes (16) 12:25;13:3,4,5; 15:6,19;20:4;21:7,8, 10,10,11,20,25;22:2; 28:5large (1) 14:20Larson (8) 3:12;25:12,15; 26:23;29:22,24; 30:15,18last (1) 18:17later (1) 11:7Law (1) 2:18layout (1) 15:16leading (1) 17:16leads (1) 3:23lease (1)
24:19least (3) 20:24,25;21:5leave (1) 30:8leaving (1) 14:4left (5) 8:17,17,18;13:20; 14:21legal (1) 2:23length (1) 11:5lengthened (1) 11:6letter (1) 9:22Letters (2) 2:25;3:3letting (1) 23:9level (3) 9:17,18;13:6library (1) 4:22life (4) 4:12;27:6;29:18, 19lifetime (2) 27:3,16line (3) 18:25,25;19:5link (1) 4:24list (1) 7:13listed (3) 6:21;7:2;13:25listen (1) 4:7little (8) 10:25;15:24;16:6, 10;18:24;20:5;22:11, 12live (2) 27:4,16lived (1) 29:19lives (1) 29:14Livingston (1) 27:8load (2) 28:2,2LOCASCIO (7) 26:25;27:1,3;28:1; 29:1;30:1,5located (5) 6:14;9:7;11:3; 12:11;22:8location (1) 6:6
longer (1) 4:12look (10) 13:17;14:2,8; 15:11;16:21;17:24; 18:23;23:15;28:7; 30:8looked (1) 13:24looking (1) 15:22lot (5) 9:5;22:8;27:10,17; 28:22Louis (1) 3:21low (1) 28:18lower (4) 7:6;18:13,21; 28:22lowered (1) 17:15lowering (4) 16:13,16,18;17:16lowest (2) 16:22,23
M
mailed (1) 25:23mailing (2) 23:24;25:7main (6) 3:19;5:22,23; 18:12;23:3,18maintain (2) 14:21;17:15maintained (1) 4:12maintenance (1) 7:12makes (1) 17:16making (3) 3:23;29:15;30:5Manager (4) 3:12,13;23:24; 25:12maneuverability (1) 9:21Manor (1) 27:8March (1) 10:10Mark (1) 3:22massive (1) 28:24match (1) 17:19materials (1)
2:11may (5) 3:2;25:17,20,22,24Mc (1) 4:4mean (2) 9:2;10:22measure (1) 9:20median (5) 8:14,19;11:18; 15:17;27:22meet (3) 9:25;13:6,22meeting (2) 2:19;25:9meets (1) 20:17member (1) 27:4members (1) 3:20Meyer (1) 4:3might (5) 13:18;14:8;15:11; 23:15;27:25mile (3) 10:8,22,24million (7) 10:21,24;14:18; 18:10,11;19:12; 20:15mine (1) 27:24minimize (2) 9:4;10:4minimum (1) 15:18minor (1) 22:4minutes (1) 26:12missed (2) 27:20;28:5Mitchell (1) 27:24mitigate (2) 8:25;20:10mitigated (1) 22:5mitigation (2) 20:11;22:5money (2) 28:19,21months (1) 12:8Monticello (2) 4:22;6:15more (11) 6:24;11:20;15:24; 16:10;18:7,10,14; 19:13,13;25:8;29:15
most (1) 25:4motorists (1) 12:10move (3) 22:10;24:24;25:2movement (1) 12:12moving (2) 23:2;30:4much (6) 9:4;17:21,23;19:3; 24:3;29:14Must (1) 24:24
N
name (6) 2:4;3:11;26:8; 27:2,3;29:22named (1) 27:24narrow (1) 8:19narrowest (1) 8:15narrowing (1) 11:18National (5) 2:16;5:4,7;7:2; 13:25nature (1) 10:20Naylor (2) 3:12;23:23near (3) 4:11;22:9;27:3nearby (1) 3:4nearly (1) 18:2necessary (3) 13:2;24:14;26:9need (3) 9:3;14:2;22:6needs (1) 18:12NEPA (1) 5:4NEVERSINK (15) 2:1,8;3:1;4:1;5:9; 6:3,18,19;7:22;8:16; 11:16;16:3,3;22:9; 28:25New (29) 2:5,7,17;3:9;4:18; 5:22;9:3,5,13;11:9; 12:11,14;14:3,17; 15:4,5,7,9,12,23; 19:25;20:22;21:12, 12;22:7;23:4,14; 24:7,13
Min-U-Script® Jeric Corporation (845) 252-3515 (5) involved - New
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
newly (1) 21:22next (3) 13:23;16:24;21:20night (1) 7:25nine (1) 18:2nonstandard (5) 7:14,19;8:15;11:5; 13:20north (5) 14:4,9;15:4,13; 20:4noted (1) 30:24notices (2) 2:23,25Number (5) 2:9;12:22;23:25; 24:15;25:8NYSDOT (1) 9:19
O
object (1) 8:10objective (1) 2:19objectives (3) 6:7;9:12;13:22observations (2) 24:8,9obtained (1) 24:21occupant (2) 24:17,20occupants (1) 24:25occur (2) 10:15;23:10occurring (2) 12:8,9ODIGIE (4) 2:2,4;24:3,4off (2) 4:8;12:3Office (10) 2:6;3:13,14,19; 4:22;5:22,23;11:7; 23:3,18offices (1) 2:25official (1) 3:8Old (2) 28:17;29:12once (1) 26:14one (26) 7:9,9;8:16,25;9:3; 10:19;12:19;14:25;
16:2,23;17:8;18:3,6, 8,8,10;20:3,13;22:6; 24:16;25:2;26:25; 27:8;28:2;29:8; 30:18on-line (1) 4:23only (5) 10:12;13:17; 24:21;28:15;29:8open (1) 2:12operating (1) 27:4opportunity (2) 26:14,16opposed (1) 6:24Orzelek (1) 3:15out (28) 6:6;7:22;8:6; 12:13,16;15:23;16:4; 19:4;22:14;23:8; 25:19;26:5,6,21,25; 27:2;28:4,13,14,15, 16,17,19;29:6,13,20; 30:2,3outlines (1) 24:24outside (2) 29:16;30:10over (22) 2:8;5:17;6:2,5,7,8, 10,12;15:7;19:6; 24:2;26:19;27:18,21; 28:6,7,13,17,17;29:8, 8,15overall (2) 10:6;20:22overhead (1) 27:13overview (1) 24:5owners (3) 3:2;22:25;25:5
P
package (1) 23:6parking (1) 22:8part (13) 3:8;6:10;8:10,24; 9:9;19:21;25:13,16, 24;26:2,3;27:7;30:11particular (1) 12:23paved (1) 27:8pavement (4) 8:22;10:5,15;12:2
people (5) 2:10;3:4;12:13; 27:4;29:6per (3) 10:21,24;12:19percent (24) 7:16,17,18;10:14, 16,18;11:17;12:19, 19;13:16;14:6;16:2, 4,8,11,12,15,18; 18:20;19:23,24,24; 29:4,4perform (1) 10:7performed (2) 6:9;12:6performing (1) 24:18period (7) 2:12;9:18;10:9,11; 12:17;25:17;26:4permit (1) 4:18pertinence (1) 10:6pertinent (1) 11:8Pete (3) 3:12;25:12,14Peter (1) 3:21phase (2) 5:8;26:16phone (2) 23:24;25:7picture (1) 27:13pier (1) 23:16piers (4) 7:6;28:23,24;29:2PIN (2) 11:6;17:9place (1) 14:4placement (1) 23:16Places (1) 5:8Planning (2) 3:13,15plans (1) 23:6Please (5) 2:3;25:9,20;26:8, 11pleased (1) 3:25pm (3) 2:12,13;30:24point (8) 15:23;20:2;22:13, 23;23:16;24:2;
26:21;30:2pointing (1) 29:25Policy (2) 2:16;5:4poor (4) 7:4,9,10;27:23portion (4) 2:13;25:11;26:19; 30:19possible (3) 9:5;10:3;11:25postmarked (2) 25:24;26:2practical (1) 12:4pre-addressed (1) 25:18preferred (8) 6:12;18:15;19:2, 15,16,17;20:16;21:4preliminary (4) 11:8;19:19;20:11; 24:6prepare (1) 23:5prepared (1) 3:8pre-printed (1) 25:22present (2) 3:6,19presentation (27) 3:7,23;5:1,11,13, 25;6:1;7:1;8:1;9:1; 10:1;11:1;12:1;13:1; 14:1;15:1;16:1;17:1; 18:1;19:1;20:1;21:1; 22:1;23:1,21;24:1; 25:1presented (1) 24:5pretty (5) 8:5;14:15;17:23; 27:3;28:7previously (1) 3:4prior (1) 25:24priority (1) 7:13probably (2) 10:22;12:10problem (2) 29:10;30:8problems (1) 10:18Procedure (1) 2:18procedures (1) 24:23proceedings (1) 3:6
process (3) 19:20;22:24;23:2profile (6) 15:22;16:4,13; 18:12,21;21:13progress (2) 2:20;24:10PROJECT (60) 2:1,4,9;3:1,5,8,12, 20;4:1,11,13,20;5:2, 9,18;6:2,5,6,7,8,11, 14,16;8:7,11,23,24; 9:10,12;10:8,9;11:6, 14,19;12:6,18,24; 13:3,9,22;14:18; 17:9,22;18:9,16; 19:11,14;20:14,17; 22:12,15;23:8,23; 24:5,9,10,15;26:3, 24;28:20properties (2) 24:16,19property (8) 3:2,2;10:12;22:25; 24:17,20;25:3,4proposed (7) 2:21;11:6;12:24; 14:9;17:8,14,22proposes (1) 6:2provide (3) 4:15;9:17;10:2provides (1) 20:20providing (2) 20:22;26:9provisions (1) 5:5Public (14) 2:6,19,25;4:4,5,22; 22:18,19;25:3,16,25; 26:1,3,18published (1) 2:24purposes (3) 16:5;23:17;25:3put (11) 7:20;9:5;14:3; 21:8;22:14;28:14,15, 16;29:6,11,12puts (1) 7:12
Q
Quality (1) 2:17quite (4) 8:13;14:10;17:3; 23:19
R
Min-U-Script® Jeric Corporation (845) 252-3515 (6) newly - quite
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
rail (3) 10:5;11:24;20:23rails (2) 28:8;30:8ramp (1) 11:5ramps (2) 17:16,19ran (2) 27:21;28:19rate (5) 4:15;8:25;10:21; 12:20;13:21rating (3) 7:4,8;9:16Real (5) 3:14;22:25;24:13; 25:5;28:18realignment (1) 13:23realized (1) 11:4reason (4) 14:18;18:12; 20:16;28:18reasonable (1) 4:13reasonably (1) 9:24reasons (2) 13:13,19receive (1) 2:20received (4) 4:25;5:2;25:24,25Recommendations (2) 11:23;24:11reconstruct (3) 6:2;18:19;19:22Record (10) 2:24;3:6;25:16,25; 26:3,11,18;29:24,25; 30:19recorded (1) 25:15reduce (6) 4:13,14;11:23,25; 12:3;20:22refer (1) 7:24Region (2) 2:5;7:13Regional (3) 4:22;13:14;22:25Register (4) 5:8;6:22;7:3;13:25regularly (1) 7:11regulations (2) 4:10;5:6rehab (1) 13:15rehabilitation (1)
13:11reinforcer (1) 21:14related (2) 10:15,20relocated (2) 22:6,10relocation (2) 24:18,23remain (1) 30:20remove (1) 10:4removed (1) 15:8replace (2) 4:11;7:13REPLACEMENT (5) 2:1,7;3:1;4:1; 13:16Report (5) 4:20;22:15,20; 24:12;26:3representative (1) 25:5representatives (2) 3:9;23:2required (1) 25:2requirements (2) 2:16;5:4residence (4) 14:11,12;18:3; 20:8Resident (1) 3:16residential (1) 14:13residents (1) 3:4response (1) 30:17responsible (1) 3:20rest (1) 27:16restore (1) 9:15restores (1) 20:19Restrooms (1) 4:8result (1) 11:2resulted (1) 10:12resume (1) 25:3retain (1) 13:12retaining (1) 19:6return (1)
12:15Review (2) 2:17;22:18Richard (1) 4:2right (11) 5:21;8:16,19; 14:12;18:25;27:11, 21;29:7,13,18;30:12right-of-way (13) 14:16,20;17:25; 18:2,4,7,14;19:10, 13;20:12,24;21:3; 22:24right-of-ways (1) 24:15River (11) 2:8;5:9;6:3,19; 7:22;8:16;16:3;22:9; 28:24,25;30:3road (10) 8:10;12:3,23; 22:11;27:23;28:14; 29:6,9,11;30:13roads (1) 27:6roadside (1) 10:6roadway (3) 10:5;11:12;12:2Robert (1) 4:3rock (3) 11:11,25;28:16room (1) 11:20Route (29) 2:7;4:18;6:6,15,18, 19;9:8,13;10:8; 12:12,25;15:23,25; 16:9,14,16,19;17:5,6, 7,22;18:21;19:6,25; 20:2,9,18;27:7;28:10run (3) 27:5,5,18
S
safe (3) 7:12;9:17;30:5safer (1) 30:6safety (3) 10:6;20:22;29:17sale (1) 24:19same (3) 14:24;15:15;25:21Samudrala (1) 3:21Sandi (1) 3:13save (1)
29:14saying (1) 26:11Scarlett (1) 3:14schedule (2) 5:18;22:13scheduled (1) 5:9screen (1) 30:2seasonal (2) 12:7,11seats (1) 2:3second (2) 11:15;25:2Section (3) 5:5;8:15;11:17sections (1) 27:7sees (1) 8:9segment (3) 9:13;10:8;20:18segments (1) 19:25selected (1) 23:9selecting (1) 20:16send (1) 25:21sent (3) 2:25;3:2,3service (3) 9:18,19;13:6services (1) 24:24set (1) 10:3seven (7) 7:9,9,16;11:17; 16:2;19:9;24:19Shah (1) 3:16shape (1) 7:11share (1) 14:24sharp (1) 29:10sharper (1) 30:7shift (1) 15:7shifted (1) 21:22shine (1) 8:2short (1) 8:5shoulder (5)
8:14,16;12:4; 13:20;15:16shoulders (2) 11:18,20show (3) 7:20;18:24;27:13shown (2) 4:24;20:11side (11) 7:6,17;8:21;15:4; 16:11,13,15,18;22:8; 28:24;30:3sight (9) 7:19,21,23,24;8:3, 4,5,7,8significant (2) 14:15;17:4significantly (1) 18:6sign-in (1) 3:16signs (2) 10:5;20:23site (3) 6:17;15:3;22:6six (4) 8:17,19;18:4;29:4Sixteen (1) 10:11slide (1) 7:20slippery (1) 10:15slope (5) 9:10;16:4;17:17, 20;19:2slopes (7) 10:3,4;11:11,24, 25;16:15;20:21smoking (1) 4:9somebody (1) 28:8someplace (1) 28:17somewhere (1) 23:12soon (1) 3:24sorry (1) 6:24sort (2) 7:20;8:3sought (1) 22:21south (1) 22:10southeast (2) 6:15;9:8southward (1) 30:4spalling (1) 7:6
Min-U-Script® Jeric Corporation (845) 252-3515 (7) rail - spalling
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
speak (1) 26:9SPEAKER (3) 5:15,20;26:22specifications (1) 23:6speed (3) 8:9;9:21;10:17spelling (1) 26:8spring (4) 5:19;23:10,11,13squad (1) 23:4St (1) 3:21Staff (2) 2:10;30:20stage (3) 19:20;21:8,22stakeholders (1) 2:20stand (1) 3:11standard (9) 7:17;8:12,20;9:24; 12:5,19;13:6;14:5; 19:23standards (5) 4:17;8:18;9:14; 11:10;15:17start (4) 5:9;6:5;13:10; 16:22starting (1) 2:13State (15) 2:5,7,17,18;3:9; 4:18;5:22;9:13;11:9; 15:23;19:25;22:7; 24:7,13;25:2statement (1) 26:18statewide (1) 10:23stating (1) 26:8station (2) 28:4,4stationery (1) 25:20stay (1) 29:21steep (9) 4:14;7:23;8:4; 11:11,15,22;17:17; 29:5;30:12steeper (3) 7:16;16:2;17:20stenographer (4) 3:6;26:10;29:23, 25still (8)
13:19;14:21; 16:23;17:15;19:19; 21:20;26:2,7stop (2) 8:9;9:23stopping (4) 7:19,21,23;8:4straighten (1) 29:13straightening (1) 30:3strictly (1) 26:16strikes (1) 10:16striped (1) 13:3strips (2) 21:16,18structural (1) 9:16structure (4) 19:7;20:6,14; 21:11Structures (8) 13:14;14:13;18:3, 5;19:11;21:4;23:4,18studies (1) 24:6study (1) 24:18submit (2) 25:17,20substantial (1) 14:19sufficient (1) 8:8suggested (1) 30:2Sullivan (5) 2:9,24;3:16;4:4,4summary (2) 6:5;21:2summer (4) 5:10,10;12:8; 23:13Sunday (1) 12:14Superintendent (1) 4:3Supervisor (1) 4:2supposed (3) 5:18;21:20;28:20sure (3) 25:20;26:9;27:17system (1) 21:15
T
table (2) 12:20;13:3
talk (2) 26:20;30:21talking (2) 27:13;29:19tanks (2) 28:2,3team (2) 3:20,23technical (2) 5:11,12tells (1) 13:17ten (1) 8:18term (2) 8:2;9:19third (1) 6:13Thompson (5) 2:8;4:2,3,21;6:14though (1) 7:11thought (3) 26:25;27:2,21three (3) 12:25;15:19;26:12three-year (1) 10:9thus (2) 12:3;13:21times (2) 9:2;16:5Times-Herald (1) 2:24together (2) 7:20;14:24tonight (5) 3:10;5:24;22:18; 25:15;30:23tonight's (1) 26:4top (2) 6:25;14:20total (6) 10:11;14:17;18:9; 19:11;20:14;21:4tow (1) 10:19Town (5) 2:8;4:2,3,21;6:14tractor-trailer (2) 27:19,25tractor-trailers (1) 28:11traffic (13) 4:16;6:9;9:20,24; 12:6,7,9,16,22;15:7; 20:20;21:22;29:14transcript (1) 3:7Transportation (6) 2:5;3:3,10;5:23; 24:7,14
travel (4) 9:21;13:4;21:7,10traveling (2) 12:10,23trees (3) 10:4;11:25;20:21truss (2) 6:23,25try (2) 2:3;9:4turn (6) 24:2;26:13;28:13, 17;29:6;30:7two (22) 7:21;8:25;9:3; 11:2;13:3,4;14:3,9, 13,16;15:6;18:3,5; 19:10;21:7,9,10,25; 23:11;24:22;26:12; 28:11type (2) 10:24;23:15
U
under (4) 10:14;11:6;17:8; 18:18UNIDENTIFIED (3) 5:15,20;26:22unique (1) 6:22unsafe (1) 10:17up (12) 3:11;6:25;8:11; 9:13;12:4;16:22; 17:17,19;20:11; 21:19;23:25;27:8upgrade (2) 10:5;11:10upon (1) 25:10use (5) 6:22;8:2;9:19; 10:17;21:13used (3) 12:16,19;15:3useful (1) 4:12using (1) 25:17
V
value (1) 7:8vehicle (4) 10:18,20,22,24verbal (1) 30:17vertical (10) 4:14;7:14;10:3;
11:21,24;14:5;15:2; 17:15,18;20:21vertically (1) 16:5view (5) 6:16;14:7;15:10; 18:23;27:14VINNIE (5) 27:1,3;28:1;29:1; 30:1visualization (1) 23:14volumes (2) 12:7,16vulnerability (1) 9:16
W
wagon (2) 28:4,5wall (2) 19:7;21:14warren (1) 6:23water (2) 12:3;28:24wave (1) 3:11way (3) 16:22;28:10;29:18ways (1) 22:11weather (1) 10:15weekends (1) 12:9weight (1) 21:17welcome (1) 2:6westbound (15) 6:3;7:15;12:13; 15:4,5,8,19,25;20:4; 21:11,11,23,23,24; 27:20western (1) 11:16wetland (10) 9:2;14:16,17;18:7; 19:11;20:14;21:3; 22:4,5;29:7wetlands (6) 8:23,24;9:4,6; 14:10;20:10what's (1) 16:6wide (2) 15:5;21:24widen (1) 15:17widening (1) 11:20
Min-U-Script® Jeric Corporation (845) 252-3515 (8) speak - widening
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Neversink River Bridge Replacement, PIN 9067.17April 28, 2009
width (1) 8:19widths (6) 8:15;11:18;12:4; 13:20;15:16,17winter (2) 28:9;30:9wise (1) 23:15wishes (1) 30:18without (1) 28:6woods (1) 28:16words (2) 27:14;29:12work (4) 5:22;9:9;16:22; 22:13working (1) 11:7Works (2) 4:4,5worry (2) 29:3,7worse (1) 29:17worst (1) 9:23worthwhile (1) 17:11written (2) 25:17,22wwwnysdotgov/neversinkbridge (1)
4:24
Y
year (2) 12:19;22:22years (4) 9:18;23:11;27:7; 28:10yielded (2) 10:21;12:20York (15) 2:5,7,17;3:9;4:18; 5:22;9:13;11:9; 12:11,14;15:23; 19:25;22:7;24:7,13
Z
Zaman (1) 3:17zoom (4) 16:20;17:5;18:24; 20:5
Min-U-Script® Jeric Corporation (845) 252-3515 (9) width - zoom
tç j1i*-
STATE OF NEW YORKDEPARTMENT OF TRANSPORTATION
REGION NINE44 HAWLEY STREET
BINGHAMTON, NEW YORK 13901-3200WWW. NYSDOT.GOV
JOHN R. WILLIAMS, P.E. STANLEY GEE
REGIONAL DIRECTOR ACTING COMMISSIONER
28 May 2009
Mr. Vincent LocascioUnion of International Operating Engineers141 Pleasant St. Ext.Monticello, New York 12701
Dear Mr. Locascio:
RE: PIN 9067.17ROUTE 17 OVER THE NEVERSINK RIVERPUBLIC HEARING COMMENTS
Thank you for your comments at the public hearing for PIN 9067.17 -
Reconstruction of Route 17 over the Neversink River. Receiving public input is avery important part of the design process and helps improve the constructedproject.
In your comments at the hearing, you recommended raising the elevation ofthe proposed bridge to reduce the vertical grades of the approaches andconstructing the proposed bridge piers on either side of the Neversink River asopposed to retaining a pier in the center of the river. We agree with yourrecommendation to raise the elevation of the proposed bridge. Our preferreddesign alternative will raise the bridge approximately 23 ft. higher than the existingbridge. This will allow us to reduce the 7% vertical grade on the western approachto 5%. We also agree the proposed piers should be constructed outside of theNeversink River if financial constraints allow. In preliminary investigations done byour structures group, it was determined this may be a feasible option.
You also recommended shifting the horizontal alignment to the south of theexisting bridge to help flatten the horizontal curve on the eastern approach.Shifting the horizontal alignment to the south of the existing bridge would extendthe project limits, require the realignment of County Route 1 73 and the removal ofseveral residential structures located along this route. Additionally, a National
Mr. Vincent LocascioPage Two28 May 2009
Register Eligible archeological site, located to the southeast of the existing bridge,would be impacted. This alternative was eliminated from further consideration dueto the estimated cost and the social, economic and environmental impacts. Underthe preferred alternative, the existing 1935 ft. radius horizontal curve on theeastern approach will be flattened to 1970 ft. for the eastbound alignment and2067 ft. for the westbound. In comparison, the minimum curvature required forinterstate standard is 1 650 ft.
If you have any further comments or questions regarding this project, pleasecontact Bill Naylor of this office at 607 721-8631 or by e-mail:[email protected].
Sincerely,
J3OSE3IA. FOGLIETTA, P.E.r’megional Design Engineer
JA F/WNlayc: W. Naylor, Project Manager, Region 9
R. Wilder, P.E., Design Services Bureau, POD 2-4B. Bortnick, P.E., Design Services Bureau, POD 2-4D. Odigie, P.E., Design Job Manager, Region 9File 2
O52BWN1