appendix f - noise impact assessment · ttm soundmatters has been engaged by cdm smith to undertake...
TRANSCRIPT
Appendix F – Noise Impact Assessment
Moray Power Project
North Galilee Basin, Central Queensland
Environmental Noise Assessment Report
Moray Power Pty Ltd
Reference: 14BRA0064 R01_3
10 November, 2014
Site: Moray Power 1 Reference: 14BRA0064 R01_3
© 2014 - TTM Consulting Pty Ltd
ABN 65 010 868 621
41A Quay Street, Sanctuary Cove
PO Box 930 Sanctuary Cove QLD 4212
T: (07) 5514 8000 F: (07) 5514 8144 E: [email protected]
Rev No.
Author Reviewed/Approved Description Date
Name Signature
B J Fox K Hewett Internal review 19/06/2014
0 J Fox Draft report 20/06/2014
1 J Fox Client review 18/07/2014
2 J Fox 07/11/2014
3 J Fox Acoustic report 10/11/2014
Site: Moray Power 2 Reference: 14BRA0064 R01_3
Table of Contents
Executive Summary 5 1.
Introduction 6 2.
2.1. Project Overview 6
2.2. Scope 6
2.3. Site Location 7
2.4. Noise Sensitive Locations 7
2.5. Site Layout 8
Ambient Noise Measurements 9 3.
3.1. Measurement Methodology 9
3.2. Measured Noise Levels 9
Noise Criteria 10 4.
4.1. Legislation 10
4.2. Construction Noise Criteria 11
4.3. Operational Noise Criteria 11
4.4. Sleep Disturbance Criteria 13
4.5. World Health Organization Guidelines for Community Noise 13
4.6. Industrial and Commercial Noise Criterion 14
Noise Modelling 15 5.
5.1. Noise Modelling Parameters 15
Construction Phase 16 6.
6.1. Noise Sources 16
6.2. Results of Modelling 16
Commissioning Phase 21 7.
7.1. Noise Sources 21
7.2. Results of Modelling 21
Operational Phase 26 8.
8.1. Noise Sources 26
8.2. Location of Noise Sources 27
8.3. Results of Modelling 29
Recommendations and Conclusion 33 9.
Site: Moray Power 3 Reference: 14BRA0064 R01_3
Table Index
Table 1: Noise Sensitive Receivers 8
Table 2: Noise Survey Locations (sourced from GHD 2012) 9
Table 3: Measured Ambient Noise Levels 9
Table 4: Acoustic Quality Objectives at Noise Sensitive Properties 10
Table 5: Project Specific Noise Levels 12
Table 6: Summary of WHO Guidelines for Community Noise 14
Table 7: Noise Modelling Parameters 15
Table 8: Construction Phase Noise Sources 16
Table 9: Predicted Construction Noise Levels 19
Table 10: Commissioning Phase Noise Sources 21
Table 11: Predicted Commissioning Noise Levels 24
Table 12: Operational Phase Noise Sources 26
Table 13: Location of Operational Noise Sources in the SoundPLAN model 27
Table 14: Predicted Operational Noise Levels 31
Figure Index
Figure 1: Site Locality and Noise Sensitive Receivers 7
Figure 2: Construction Noise – No wind 17
Figure 3: Construction Noise – E wind 17
Figure 4: Construction Noise – SE wind 18
Figure 5: Construction Noise – SW wind 18
Figure 6: Construction Noise – N wind 19
Figure 7: Commissioning Noise – No wind 22
Figure 8: Commissioning Noise – E wind 22
Figure 9: Commissioning Noise – SE wind 23
Figure 10: Commissioning Noise – SW wind 23
Figure 11: Commissioning Noise – N wind 24
Figure 12: Site Layout 28
Figure 13: Operational Noise – No wind 29
Figure 14: Operational Noise – E wind 29
Figure 15: Operational Noise – SE wind 30
Figure 16: Operational Noise – SW wind 30
Figure 17: Operational Noise – N wind 31
Site: Moray Power 4 Reference: 14BRA0064 R01_3
Appendices
Appendix A References 34
Appendix B Site Layout 36
Appendix C Meteorological Data – Wind Roses 38
Site: Moray Power 5 Reference: 14BRA0064 R01_3
Executive Summary 1.
Moray Power Pty Ltd is proposing to develop a power station in the north Galilee Basin,
Central Queensland to be known as the Moray Power Station Project (the Project).
TTM Soundmatters have been engaged to provide an acoustic assessment as supporting
evidence for a Material Change of Use. The purpose of the acoustic assessment is to provide
an independent assessment of expected noise levels at the potentially affected noise sensitive
receiver locations and determine appropriate noise mitigation measures where required.
Information related to site details, noise sensitive receiver locations, noise criteria, and
proposed equipment was provided by CDM Smith and GHD.
This report was prepared to assess potential noise impacts associated with the three project
stages; construction, commissioning and operational phase. Acoustic modelling was
undertaken using SoundPLAN version 7.3 implementing the CONCAWE prediction method
with consideration of worst case wind scenarios.
Four noise sensitive receiver locations were considered in the assessment, which in terms of
relative distance from the Project were, the primary work area for mine employees, industrial
area, airport, and the workers residential camp. The assessed sensitive locations do not
include any private residences as there are no nearby residences that will be occupied during
the construction or operational phase. Results indicate that noise levels would be above the
criteria at the primary work area for mine employees. The predicted worst case exceedance is
5 dB(A) above the indoor EPP Noise and WHO guideline criteria assuming open windows.
Standard glazing treatments would achieve a further 10dB reduction, and therefore
compliance with the indoor criteria would be achieved if windows of the receiver were closed.
Therefore standard glazing treatments at Receiver 1 would satisfy the acoustic requirements
and no further treatments are required.
Even under worst case conditions, noise levels at Receivers 2, 3, and 4 are predicted to comply
and no further acoustic treatment is required for these locations.
Site: Moray Power 6 Reference: 14BRA0064 R01_3
Introduction 2.
2.1. Project Overview
TTM Soundmatters has been engaged by CDM Smith to undertake an environmental noise
assessment of the Moray Power Station Project (the Project) in the north Galilee Basin,
Central Queensland. The Project is located approximately 147km north-west of the town of
Clermont.
To undertake the assessment TTM utilised the following reference material:
a. Project information and site layout provided by CDM Smith;
b. Carmichael Coal Mine and Rail Project: Mine Technical Report (ref: 25215-D-RP-0017).
Herein referred to as GHD 2012;
c. Noise input memorandum (ref: 41/27532). Herein referred to as GHD 2014. The memo
provided information on equipment, and activity type and sound pressure levels
proposed for construction, commissioning and operation phases, based on the
concept design;
d. Noise criteria of:
i. Environmental Protection Act 1994;
ii. Environmental Protection (Noise) Policy 2008 (EPP Noise);
iii. Planning for Noise Control (PNC) Guideline (EPA2004);
e. Analysis and calculations conducted by TTM Soundmatters.
2.2. Scope
The scope of the assessment addresses the requirements of Department of Environment and
Heritage Protection, Guideline EM962 for environmentally relevant activities (ERAs) in
relation to noise, and contains:
i. Details of the nearest noise sensitive locations;
ii. Noise criteria and established noise limits taken from the GHD 2012 report;
iii. Computer based SoundPLAN noise modelling of the construction,
commissioning, and operational phases of the project;
iv. Analysis of modelled noise levels;
v. Details of noise control recommendations to be incorporated to achieve predicted
compliance.
Site: Moray Power 7 Reference: 14BRA0064 R01_3
2.3. Site Location
The proposed power station is located in the north Galilee Basin approximately 147km north-
west of the town of Clermont, Central Queensland. The site locality is shown in Figure 1.
Figure 1: Site Locality and Noise Sensitive Receivers
The Project is located on land that is dominated by gilgaied topography. Land between the
project site and noise sensitive receivers is undulating in some instances. Noise modelling is
based on a digital ground model of 0.5m resolution and effects from topography have been
taken into account.
2.4. Noise Sensitive Locations
The closest existing residential dwelling is Labona Homestead, located approximately 5.5 km
north-west of the Project area. This homestead is owned by a Galilee Basin mining proponent
who has indicated that the homestead will be removed as part of a separate project.
Therefore, the closest private residence, expected to be occupied during construction and
operation of the Project (Doongmabulla), is approximately 18 km west of the Project area.
The nearest noise sensitive locations considered in this assessment are identified in Figure 1
and detailed in Table 1 over the page. The location and identification (use) of these receivers
was provided by CDM Smith.
Site
Receiver 3
Receiver 4
Receiver 2
Receiver 1 KEY
Receiver 1: Primary work area
Receiver 2: Industrial area
Receiver 3: Airport
Receiver 4: Workers camp
Site: Moray Power 8 Reference: 14BRA0064 R01_3
Table 1: Noise Sensitive Receivers
Receiver
Number
Description Distance from
Project (km)
Direction from
Project
1 Primary work area for mine employees 2.4 NW
2 Industrial area 7.4 N
3 Airport 7.6 NE
4 Workers camp 11.1 NE
Of the nearest locations, only Receiver 4 is considered to be used as a residential area for
sleeping purposes. Privately owned residential dwellings are located at significantly greater
distances from those identified above (approximately 7 km further) and therefore would
experience much less noise impact compared to the results presented in this report. Further,
these receivers are located outside of the ground contour information provided to TTM for
noise modelling purposes.
2.5. Site Layout
The proposed site layout of the Moray Power Station is shown in Appendix B.
Site: Moray Power 9 Reference: 14BRA0064 R01_3
Ambient Noise Measurements 3.
3.1. Measurement Methodology
Ambient noise monitoring was conducted by GHD (2012) to establish specific noise criteria in
areas that surround the Project site. The noise survey was conducted at two locations, as
described in Table 2.
Table 2: Noise Survey Locations (sourced from GHD 2012)
Logger GPS coordinates Description of noise survey location Monitoring period
1 220
04.217’ S
1460
14.664’ E
Doongmabulla Homestead
(18 km west of the Project area)
26 Aug – 7 Sep 2011
2 220
00.660’ S
1460
21.593’ E
Labona Homestead
5.5 km north-west of the Project area)
26 Aug – 6 Sep 2011
The selected measurement locations were considered representative of the acoustic
environment experienced by the nearest noise sensitive receivers located in close proximity to
the project site. Although the original baseline data was collected in 2011, the area has not
had any significant development since that time. Hence, the background noise levels are still
considered relevant to 2014.
The environmental noise monitors were set to measure noise levels in 'A' weighting, 'Fast'
response, over 15 minute statistical intervals. All sampling activities were undertaken with due
consideration to the specifications outlined in AS 1055 (1997) Acoustics - Description and
Measurement of Environmental Noise and the Queensland Government Noise Measurement
Manual (EPA 2000).
3.2. Measured Noise Levels
The results of ambient noise monitoring conducted by GHD are reproduced in Table 3.
Table 3: Measured Ambient Noise Levels
Measured Noise Levels
Logger 1 Logger 2
Day
dB(A)
Evening
dB(A)
Night
dB(A)
Day
dB(A)
Evening
dB(A)
Night
dB(A)
Measured background, LA90 31 31 27 25 25 22
Measured ambient, LAeq 48 41 43 44 41 39
The measured noise levels presented above were used to establish the project specific noise
levels derived in Section 4.3.
Site: Moray Power 10 Reference: 14BRA0064 R01_3
Noise Criteria 4.
The noise criteria used for this assessment was sourced and reproduced from GHD 2012.
4.1. Legislation
The Environmental Protection Act 1994 (EP Act) provides for the protection of environmental
values, including environmental values relating to maintenance of public amenity. The EP Act
establishes a number of environmental protection policies. In relation to noise, the EP Act is
supported by the Environmental Protection (Noise) Policy 2008 (EPP (Noise)). The EPP Noise
Section 7 outlines the key environmental values for the acoustic environment, as set out
below:
The environmental values to be enhanced or protected under this policy are:
a. The qualities of the acoustic environment that are conducive to protecting the health
and biodiversity of ecosystems; and
b. The qualities of the acoustic environment that are conducive to human health and
wellbeing, including by ensuring a suitable acoustic environment for individuals to do
any of the following –
i. Sleep;
ii. Study or learn;
iii. Be involved in recreation, including relaxation and conversation; and
iv. The qualities of the acoustic environment that is conducive to protecting the
amenity of the community.
To further assist in determining noise levels consistent with the identified environmental
values, the EPP Noise also sets out acoustic quality objectives as shown in Table 4. Based on a
typical dwelling façade noise reduction of 10 dB(A) through a partially open window, an
external criterion of 40 dB(A) LAeq,adj,1hr is recommended for health and well-being in relation to
the ability to sleep. Measurement of this acoustic quality objective is at the receptor.
Table 4: Acoustic Quality Objectives at Noise Sensitive Properties
Sensitive Receiver Time of Day Acoustic Quality Objectives, dB(A)
LAeq,adj,1hr LA10,adj,1hr LA1,adj,1hr
Dwelling
(Outdoors)
Day and Evening
(7am – 10pm) 50 55 65
Dwelling
(Indoors)
Day and Evening
(7am – 10pm) 35 40 45
Night (10pm – 7am) 30 35 40
Site: Moray Power 11 Reference: 14BRA0064 R01_3
4.2. Construction Noise Criteria
The construction phase of the project will occur over a period of 24 to 36 months, with
activities occurring 24 hours per day, 7 days per week. Generally work will be restricted to
daylight hours, however some critical-path works will progress overnight particularly during
commissioning. As a conservative approach to the noise assessment, this report has assumed
activities will be undertaken 24 hour per day, 7 days per week.
For construction work occurring during normal daytime hours, provided all mechanical
powered plant is fitted with appropriate mufflers, specific noise limits are not prescribed in
Queensland. In this regard, it is noted that the EPP Noise does not include construction noise
limits.
In Queensland, it is generally accepted that construction activities should be in accordance
with general building work hours as described under section 440R – “Building Work” of the EP
Act. Under the EP Act, no audible noise is permitted:
- Between 6:30 pm and 6:30 am – Monday to Saturday;
- On Sundays and public holidays.
The time restrictions are designed to strike a balance between protecting noise amenity and
the need to start construction activities early in the morning and also recognise the difficulties
of controlling some types of construction noise.
Noise impacts during construction are therefore usually minimised by limiting the hours of
operation and, in particular circumstances, scheduling the noisiest activities to occur at times
when they would generate least disruption. Particular noise limits should be applied to
construction works extending outside normal working hours. As such, the World Health
Organisation (WHO) recommend for quality of sleep, maximum noise levels that should not
exceed 45 dB(A). This guideline is recommended for construction work occurring outside the
hours listed above. Based on a typical building façade noise reduction of 10 dB(A) through a
partially open window, an external criterion of 55 dB(A)Lmax is recommended for sleep
disturbance, assessable at 4 metres (m) from the building façade.
Section 440R restrictions presented above are relevant to typical building works in an urban
environment and are not considered relevant to this Project due to the remote nature.
Accordingly, the proponent is seeking to undertake operations 24 hours per day, 7 days per
week.
4.3. Operational Noise Criteria
Planning for Noise Control (The PNC Guideline; EPA 2004) provides guidance on the
assessment of operational noise impacts. The guideline includes noise criteria designed to
protect sensitive receptors from noise significantly louder than the background level, and to
limit the total noise level from all sources near a receptor, hence protecting the amenity.
Site: Moray Power 12 Reference: 14BRA0064 R01_3
In line with the PNC Guideline, noise from continuous sources should be limited to 3 dB(A)
above the rating background noise level for each period, unless the combined (ambient plus
site contribution) noise level would exceed the recommended ambient noise level for the
receptor zone. In that case, the noise limit for the site is set so that the combined noise level
for the receptor zone does not exceed the recommended level. Table 5 shows the derivations
of the LA90, 1hr and LAeq, 1hr noise criteria with consideration to PNC Guideline for each monitoring
location.
A rural residential area has been selected for setting the recommended outdoor background
planning noise level. A Z1 noise area category (very rural, purely residential, less than 40
vehicles an hour) has been selected for determining the Planning Noise Level (PNL) at the
assessed receptor locations.
The project specific noise levels are based on site specific ambient noise monitoring data.
Ambient noise monitoring was conducted at two locations in 2011 known as Doongmabulla
(Logger 1) and Labona (Logger 2) Homesteads. Further detail is provided in Section 3.
Table 5 shows the project specific noise criteria adopted for this assessment. Comparison
between the criteria shown in Table 5 and the EPP Noise external night-time criterion of 40
dB(A) LAeq,adj,1hr indicates the PNC criteria are more stringent. The PNC criteria are therefore
used in this assessment. By default, adoption of the PNC criteria for the project will ensure
compliance with the EPP Noise 40 dB(A) LAeq,adj,1hr criteria.
Table 5: Project Specific Noise Levels
Criterion
Logger 1 Logger 2
Day
dB(A)
Evening
dB(A)
Night
dB(A)
Day
dB(A)
Evening
dB(A)
Night
dB(A)
Measured background, LA90 31 31 27 25 25 22
Acceptable measured background, LA90
31 31 27 25 25 25
Recommended background, min LA90 (PNC Table 1)
35 30 25 35 30 25
Adjusted background, min LA90 (PNC Table 2)
33 25 25 30 28 25
Measured ambient, LAeq 48 41 43 44 41 39
Recommended PNL LAeq, 1 hour (PNC, Table 3, Category Z1)
40 35 30 40 35 30
Planning noise level (PNC Table 4 adjusted)
38 31 33 34 31 29
Specific/component noise level 36 28 28 33 31 28
Project Specific Noise Level LAeq, 1 hour
36 28 28 33 31 28
Site: Moray Power 13 Reference: 14BRA0064 R01_3
4.4. Sleep Disturbance Criteria
The EPP Noise recommends that for the health and well-being of residents, in relation to the
ability to sleep, the following acoustic quality objectives apply, when measured indoors:
- 30 dB LAeq, adj, 1hour
- 35 dB LA10, adj, 1hour
- 40 dB LA1, adj, 1hour
For these criteria, noise levels are measured over a one hour period and are adjusted for tonal
character or impulsiveness.
Additionally, the purpose of the PNC Guideline is to limit the external maximum noise impact
level, according to the likely number of occurrences and the potential noise reduction from
outside to inside.
Maximum noise levels over the night time period should be restricted to prevent sleep
disturbance. The Guideline recommends that instantaneous internal sound pressure levels do
not exceed a maximum sound pressure level of 45 dB(A)Lmax more than 10-15 times per night
as a rule in planning for short-term or transient events. On this basis, a external noise level of
55 dB(A)Lmax more than 10-15 times per night is considered appropriate for assessment
purposes, as the Guideline states a 10 dB outside to inside reduction in noise level through a
partially open window is typical.
4.5. World Health Organization Guidelines for Community Noise
The WHO discusses the effects of environmental noise in non-industrial environments in its
Guideline for Community Noise (1999). This guideline examines aspects such as sleep
disturbance, annoyance, and speech intelligibility and provides guidance for protecting people
from adverse effects induced by excessive noise. The guideline is also referred to in the PNC
Guideline’s section on sleep disturbance criteria.
Most people are likely to experience a high level of annoyance should daytime sound pressure
levels at outdoor living areas exceed 55 dB(A) Leq for a steady, continuous noise. Moderate
annoyance may be felt should daytime outdoor sound pressure level exceed 50 dB(A) Leq.
Sound pressure levels during the evening and night should be 5 to 10 dB lower than the level
during the day.
When the noise comprises of a large low frequency component, lower guideline values are
recommended as LFN can disturb sleep at lower sound pressure levels. The recommendation
of lower noise levels for LFN also applies for outdoor living areas. For intermittent noise, it is
necessary to take into account the maximum sound pressure level as well as the number of
noise events. Interference to speech intelligibility may be prevented by maintaining
background noise to levels of about 35 dB(A) to 45 dB(A).
Table 6 summarises the WHO Guideline values.
Site: Moray Power 14 Reference: 14BRA0064 R01_3
Table 6: Summary of WHO Guidelines for Community Noise
Descriptor Indoor Guideline Value Outdoor Guideline Value
Speech intelligibility
(dwellings indoors)
35 dB(A) Leq (steady noise) Not applicable
Sleep disturbance (Bedrooms) 30 dB(A) Leq (steady noise)
45 dB(A) Leq (intermittent noise)
45 dB(A) Leq (steady noise)
60 dB(A) Leq (intermittent noise
Annoyance (daytime and evening)
35 dB(A) Leq 50 dB(A) Leq
While the WHO Guidelines provide values for sleep disturbance, external amenity and speech
intelligibility, these values are less stringent than the PNC Guideline goals outlined previously.
The above 30 dB(A) Leq guideline value shown in Table 6 equates to 40 dB(A) Leq external
(based on typical 10 dB(A) façade reduction – as per Australian Standard AS3671 and indeed
WHO recommends 15 dB(A) façade reduction). Given the PNC Guideline criterion is 28 dB(A)
Leq, 1hour outdoor at night-time, it is considered that the adoption of the PNC Guideline
criteria for this Project will also ensure compliance with the WHO guidelines.
4.6. Industrial and Commercial Noise Criterion
The industrial precinct and airport, when developed as part of the Carmichael Coal Mine
Project, may be exposed to a certain degree of noise from the project operations. These areas
are, however, less noise sensitive than residential receivers as they are predominately work
areas and not used for sleeping purposes. The PNC Guideline recommends background noise
planning levels for industrial and commercial noise receivers.
The following noise targets have been adopted for commercial and industrial areas:
Shop or commercial office: 55 dB(A) LAeq, 1hour;
Industrial area or factory: 60 dB(A) LAeq, 1hour.
Site: Moray Power 15 Reference: 14BRA0064 R01_3
Noise Modelling 5.
5.1. Noise Modelling Parameters
Acoustic modelling of the project site was undertaken using SoundPLAN software version 7.3
and implementing the CONCAWE prediction method to predict the effects of construction
and operational noise from the site on the nearest noise sensitive locations.
Various wind conditions were considered. The chosen conditions were the worst case wind
speed and directions taken from the annual, diurnal, and seasonal wind roses provided by
Katestone Environmental Consultants. This information was modelled specifically for the
project and is considered site specific. Based on this information, the chosen wind scenarios
used in the noise assessment are as follows:
1. No wind;
2. Easterly winds at 7m/s;
3. Southeast winds at 5m/s;
4. Southwest winds at 5m/s;
5. Northerly winds at 6m/s.
The following parameters and assumptions were made with regard to the model
configuration:
Table 7: Noise Modelling Parameters
Description Value
Reflection order 1O
Terrain topography 0.5m resolution
Air absorption ISO 9613
Environment Temperature – 10oC; Humidity – 70%
Noise contour calculation grid space 50m
Receiver height above ground 1.8m
Receiver calculations Free-field
Site: Moray Power 16 Reference: 14BRA0064 R01_3
Construction Phase 6.
6.1. Noise Sources
The expected noise sources during the construction phase of the Project are presented in
Table 8. The data used in the assessment was sourced from GHD 2014. A source height of 3m
was used for sources in the construction noise model to represent the worst case.
Table 8: Construction Phase Noise Sources
Equipment No. Sound Power Level of Equipment
SWL, dB(A) LAeq Noise Source
Height (m)
Dozer 20t 4 115 3
Rock breaker 1 120 3
Tracked excavator 30t 8 112 3
Grader 1 109 3
Scraper 4 118 3
Moxie or large truck 2 106 3
Water truck 1 104 3
Roller 1 107 3
Agitator 2 111 3
Large rotary piling rig 1 111 3
Wheeled telescopic crane 4 112 3
Mobile telescopic crane 5 112 3
Light vehicles 50 119 0.5
Diesel generator 3 101 3
Truck mounted concrete pump 1 108 3
6.2. Results of Modelling
The modelled noise levels representing the construction phase for all wind scenarios are
presented in Figure 2 to Figure 6. Construction noise is modelled for worst case, being
constant percentage on-times for a 24 hour a day, seven days a week schedule. Moving noise
sources such as trucks and dozers were located at the nearest position relative to the nearest
receivers. A 1.8m high receiver height was used to represent noise levels at ground floor.
Site: Moray Power 17 Reference: 14BRA0064 R01_3
Figure 2: Construction Noise – No wind
Figure 3: Construction Noise – E wind
Site: Moray Power 18 Reference: 14BRA0064 R01_3
Figure 4: Construction Noise – SE wind
Figure 5: Construction Noise – SW wind
Site: Moray Power 19 Reference: 14BRA0064 R01_3
Figure 6: Construction Noise – N wind
6.2.1. Summary of Construction Noise Levels
Table 9 presents the predicted construction phase noise levels at the receiver locations.
Table 9: Predicted Construction Noise Levels
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
1 No wind 34 No Yes
E 40 No Yes
SE 40 No Yes
SW 38 No Yes
N 26 Yes Yes
2 No wind <15 Yes Yes
E <15 Yes Yes
SE 19 Yes Yes
SW 19 Yes Yes
N <15 Yes Yes
3 No wind <15 Yes Yes
E <15 Yes Yes
SE 16 Yes Yes
SW 18 Yes Yes
N <15 Yes Yes
Site: Moray Power 20 Reference: 14BRA0064 R01_3
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
4 No wind <15 Yes Yes
E <15 Yes Yes
SE <15 Yes Yes
SW <15 Yes Yes
N <15 Yes Yes
*equivalent to an external noise level of 40dB(A) based on typical building façade attenuation of 10 dB(A) through an open window.
For construction work occurring during normal daytime hours, provided all mechanical
powered plant is fitted with appropriate mufflers, specific noise limits are not prescribed in
Queensland. As construction may take place outside of day hours we have assessed noise
against the project specific noise limits and the internal noise limits of EPP Noise and sleep
disturbance. However it should be noted that the majority of construction will be undertaken
between the hours of 6.30am and 6.30pm. Although some critical path activities are proposed
to occasionally occur 24 hours a day, typical heavy vehicle and plant will only be necessary on
an infrequent basis outside of these hours. Therefore this assessment has been based on a
worst case scenario.
Noise levels at Receiver 1 are predicted to exceed the night criteria of 28 dB(A) under all wind
conditions except those originating from the north. Noise level exceedances are relatively low
however, and given construction activities are of a transient nature and the receiver is the
mine infrastructure area and not of residential use, the noise impact is not expected to be
significant. Noise levels would comply with the 30 dB(A) internal criteria of EPP Noise and
sleep disturbance.
Noise levels are predicted to comply with the assessment criteria during all time periods and
under all wind conditions at Receiver 2, 3 and 4.
Site: Moray Power 21 Reference: 14BRA0064 R01_3
Commissioning Phase 7.
7.1. Noise Sources
Activities undertaken during the commissioning phase will be intermittent in nature and
structured so that the overall impact of the activities is reduced (i.e. scheduling activities so
that all noise events are not occurring concurrently). However the worst case scenario for
commissioning has been modelled and is anticipated to be a combination of the following:
1. All construction noise activities as per Section 6;
2. Steam purging;
3. Safety valves discharging.
Table 10 presents the expected noise levels associated with steam purging.
Table 10: Commissioning Phase Noise Sources
Equipment No. Sound Power Level of Equipment SWL, dB(A) LAeq
Noise Source Height (m)
All construction noise sources As per Table 8 As per Table 8
Steam purging 1 120 3
Safety valve discharging 2 116 3
Noise data was sourced from GHD 2014.
7.2. Results of Modelling
The modelled noise levels representing the commissioning phase for all wind scenarios are
presented in Figure 7 to Figure 11. Noise is modelled for worst case being constant
percentage on-times, with moving noise sources such as trucks and dozers located at the
nearest worst case position with respect to the nearest receivers. A 1.8m high receiver height
was used to represent noise levels at ground floor.
Site: Moray Power 22 Reference: 14BRA0064 R01_3
Figure 7: Commissioning Noise – No wind
Figure 8: Commissioning Noise – E wind
Site: Moray Power 23 Reference: 14BRA0064 R01_3
Figure 9: Commissioning Noise – SE wind
Figure 10: Commissioning Noise – SW wind
Site: Moray Power 24 Reference: 14BRA0064 R01_3
Figure 11: Commissioning Noise – N wind
7.2.1. Summary of Commissioning Noise Levels
Table 11 presents the predicted commissioning phase noise levels at the receiver locations.
Table 11: Predicted Commissioning Noise Levels
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
1 No wind 34 No Yes
E 42 No No (+2)
SE 42 No No (+2)
SW 40 No Yes
N 27 Yes Yes
2 No wind <15 Yes Yes
E <15 Yes Yes
SE 20 Yes Yes
SW 20 Yes Yes
N <15 Yes Yes
3 No wind <15 Yes Yes
E <15 Yes Yes
SE 18 Yes Yes
SW 19 Yes Yes
N <15 Yes Yes
Site: Moray Power 25 Reference: 14BRA0064 R01_3
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
4 No wind <15 Yes Yes
E <15 Yes Yes
SE <15 Yes Yes
SW <15 Yes Yes
N <15 Yes Yes
*equivalent to an external noise level of 40dB(A) based on typical building façade attenuation of 10 dB(A) through an open window.
As stated, activities undertaken during the commissioning phase will be intermittent in nature
and structured so that the overall impact of the activities is reduced (i.e. scheduling activities
so that all noise events are not occurring concurrently). Therefore the predicted noise levels
are worst case.
Noise levels at Receiver 1 are predicted to be above the criteria in most cases (i.e. under the
various wind conditions, and day/evening/night periods). Acoustic treatment for Receiver 1
should be considered so that internal noise levels comply with the indoor criteria of EPP Noise
and WHO guidelines. It should be noted that Receiver 1 is the mine infrastructure area which
is a work zone and not for residential use, and therefore the noise impacts are not expected to
be significant.
Commissioning noise levels are predicted to comply with the assessment criteria at Receiver
2, 3 and 4 under all wind conditions.
Site: Moray Power 26 Reference: 14BRA0064 R01_3
Operational Phase 8.
8.1. Noise Sources
The noise sources associated with the operational phase of the project are presented in Table
12. The data used in the assessment was sourced from GHD 2014. The reasonable worst case
scenario expected during operation is four thermal plants and one diesel set in operation. The
number of units operating indicates the quantity of equipment that will be operating
concurrently under the reasonable worst case scenario.
The table identifies those noise sources which will be housed within a type of enclosure. The
enclosures were incorporated into the noise model, however there is only a negligible
difference of 0.4 dB(A) compared to if they were not enclosed. This is because noisier plant
(i.e. Fin Fan coolers and Air Cooled Condenser [ACC] fans) are not enclosed and they make the
largest contribution to overall noise levels at the receiver locations.
Table 12: Operational Phase Noise Sources
Equipment No. Sound Power Level of Equipment SWL,
dB(A) LAeq
Noise Source
Height (m)
Source located within an
enclosure (Yes/No)
Boiler feed pump 4 109 3 Yes
Turbine 4 109 3 Yes
Fin Fan cooler fan 32 128 3 No
Plant air compressor 3 103 1 Yes
Primary air (PA) fan 8 117 3 Yes
Forced draft (FD) fan 8 117 3 Yes
Induced draft (ID) fan 8 117 3 Yes
Diesel generator (DG) sets 1 103 1 Yes
Transformers 4 99 1 No
Air Cooled Condenser (ACC) fan 32 128 3 No
Condensate extraction pumps 4 104 1 Yes
Ash handling system compressors
3 98 1 Yes
Slurry disposal pumps for ash disposal
1 93 1 No
Ash silo fluidizing blowers 2 96 1 Yes
Light vehicles 50 119 0.5 No
Coal handling plant
(open conveyor – per metre)
137 +
182 126 3 TBA (assumed No)
Since original noise modelling was conducted for the Project (June 2014) the proponent has
included coal handling plant within the design. The coal handling plant will primarily include a
Run of Mine (ROM) hopper, conveyors and transfer towers. Partial enclosure and roofing of
Site: Moray Power 27 Reference: 14BRA0064 R01_3
the conveyers and enclosure of the transfer towers is expected to considerably reduce any
noise generated from this infrastructure. Noise modelling results for the Project, without the
coal handling plant, indicates that only one receiver (receiver 1 – the operational mine work
area) exceeds EPP Noise criteria. Due to the noise mitigation measures for the coal handling
plant, it is not expected that this additional infrastructure will cause an exceedance of the
commissioning or operational noise at any of the other receivers and therefore remodelling
has not been completed. Assuming worst case of not enclosing of the conveyors, noise levels
are calculated to increase by only 1 dB with the addition of the coal handling plant. If 50% of
the conveyors were enclosed, there would be no overall increase of total noise levels.
8.2. Location of Noise Sources
The position of operational phase noise sources in the SoundPLAN model are based on the
site layout plan shown in Figure 12 and advice from CDM Smith. Table 13 outlines the site plan
reference area for each of the noise sources in the SoundPLAN model.
Table 13: Location of Operational Noise Sources in the SoundPLAN model
Equipment Site plan Reference number
Boiler feed pump 4
turbine 1
Fin Fan cooler fan 33
Plant air compressor 14
PA fan 4
FD fan 4
ID fan 4
DG sets 22
Transformers 16/17
ACC Fans 13
Condensate extraction pumps 13
Ash handling system compressors 14
Slurry disposal pumps for ash disposal 30
Ash silo fluidizing blowers 11
Light vehicles 43
Site: Moray Power 28 Reference: 14BRA0064 R01_3
Figure 12: Site Layout
Site: Moray Power 29 Reference: 14BRA0064 R01_3
8.3. Results of Modelling
The modelled noise levels representing the operational phase for all wind scenarios are
presented in Figure 13 to Figure 17. A 1.8m high receiver height was used to represent noise
levels at ground floor.
Figure 13: Operational Noise – No wind
Figure 14: Operational Noise – E wind
Site: Moray Power 30 Reference: 14BRA0064 R01_3
Figure 15: Operational Noise – SE wind
Figure 16: Operational Noise – SW wind
Site: Moray Power 31 Reference: 14BRA0064 R01_3
Figure 17: Operational Noise – N wind
8.3.1. Summary of Operational Noise Levels
Table 14 presents the predicted operational phase noise levels at the receiver locations.
Table 14: Predicted Operational Noise Levels
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
1 No wind 38 No Yes
E 45 No No (+5)
SE 45 No No (+5)
SW 44 No No (+4)
N 32 No Yes
2 No wind 18 Yes Yes
E 16 Yes Yes
SE 24 Yes Yes
SW 24 Yes Yes
N <15 Yes Yes
3 No wind 17 Yes Yes
E <15 Yes Yes
SE 22 Yes Yes
SW 23 Yes Yes
N <15 Yes Yes
Site: Moray Power 32 Reference: 14BRA0064 R01_3
Receiver Wind Direction Predicted External Noise Level, Leq dB(A)
Complies with the criteria (Yes/No)
Night 28 dB(A) EPP 30 dB(A) internal*
4 No wind <15 Yes Yes
E <15 Yes Yes
SE <15 Yes Yes
SW <15 Yes Yes
N <15 Yes Yes
*equivalent to an external noise level of 40dB(A) based on typical building façade attenuation of 10 dB(A) through an open window.
Operational noise levels at Receiver 1 are predicted to exceed the indoor criteria (depending
on wind direction) with open windows. Standard glazing treatments would achieve a further
10dB reduction, and therefore compliance with the indoor criteria would be achieved if
windows of the receiver were closed. Therefore no further acoustic treatments are required.
Compliance is achieved at Receiver 2, 3 and 4 under all wind conditions.
Site: Moray Power 33 Reference: 14BRA0064 R01_3
Recommendations and Conclusion 9.
Noise levels are predicted to comply with the most stringent night time noise criteria (28dB(A)
externally) at Receiver 2, 3 and 4 during all stages of the project. Therefore no further
recommendations are required for these receivers.
The highest predicted external noise level at Receiver 1 is 45 dB(A) LAeq, which is due to the
operational phase with E or SE winds. At this noise impact, internal noise levels at the
receiver are predicted to be 5 dB(A) above the indoor EPP Noise and WHO guideline criteria
assuming open windows. Standard glazing treatments would achieve a further 10dB
reduction, and therefore compliance with the indoor criteria would be achieved if windows of
the receiver were closed. Therefore no further acoustic treatments are required.
The noise mitigation measures identified above would likely result in a considerable reduction
in the noise levels experienced at Receiver 1. Given that Receiver 1 will be the operational
work area for the mine, and that no persons will be residing at this location, any impact
resulting from criteria exceedance is likely to be negligible.
Site: Moray Power 34 Reference: 14BRA0064 R01_3
Appendix A References
Site: Moray Power 35 Reference: 14BRA0064 R01_3
References:
GHD 2012, Carmichael Coal Mine and Rail Project: Mine Technical Report (ref: 25215-DRP- 0017)
GHD 2014, Noise inputs memorandum (ref: 41/27532).
State of Queensland 2012, Environmental Protection (Noise) Policy 2008.
Site: Moray Power 36 Reference: 14BRA0064 R01_3
Appendix B Site Layout
Site: Moray Power 37 Reference: 14BRA0064 R01_3
Site: Moray Power 38 Reference: 14BRA0064 R01_3
Appendix C Meteorological Data – Wind
Roses
Site: Moray Power 39 Reference: 14BRA0064 R01_3
Site: Moray Power 40 Reference: 14BRA0064 R01_3