appendix a route permit application completeness checklist...appendix b subd. 3b within 30 days of...

27
APPENDIX A Route Permit Application Completeness Checklist

Upload: others

Post on 18-Sep-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

APPENDIX A

Route Permit Application Completeness Checklist

Page 2: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

1

HUNTLEY – WILMARTH PROJECT ROUTE PERMIT APPLICATION COMPLETENESS CHECKLIST

Authority Required Information Location in Application

Minn. Stat. § 216E.03 – Project Notice

Subd. 3a

At least 90 days before filing an application with the commission, the applicant shall provide notice to each local unit of government within which a route may be proposed. The notice must describe the proposed project and the opportunity for a preapplication consultation meeting with local units of government as provided in subdivision 3b.

Appendix B

Subd. 3b

Within 30 days of receiving a project notice, local units of government may request the applicant to hold a consultation meeting with local units of government. Upon receiving notice from a local unit of government requesting a preapplication consultation meeting, the applicant shall arrange the meeting at a location chosen by the local units of government. A single public meeting for which each local government unit requesting a meeting is given notice satisfies the meeting requirement of this subdivision.

§ 7.1; Appendix B

Minn. R. 7850.1900, Subp. 2 – Route Permit for a High Voltage Transmission Line (“HVTL”)

A. A statement of proposed ownership of the facility at the time of filing the Application and after commercial operation. § 1.1

B.

The precise name of any person or organization to be initially named as permittee or permittees and the name of any other person to whom the Route Permit may be transferred if transfer of the Route Permit is contemplated.

§ 1.2

C.

At least two proposed routes for the proposed HVTL and identification of the preferred route and the reasons for the preference.

Note: Applicants’ description of their proposed routes complies with Minn. Stat. 216E.03, subd. 3 which states “Neither of the two proposed routes may be designated as a preferred route and all proposed routes must be numbered and designated as alternatives.”

§ 2.2 and

Chapter 4

D. A description of the proposed HVTL and all associated facilities, including the size and type of the HVTL.

Chapter 2 and Appendix D

Page 3: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

2

E. The environmental information required under Minn. Rules 7850.1900, Subp. 3.

Chapter 6 and Table 3.3.2-1

F. Identification of land uses and environmental conditions along the proposed routes. § 6.1 and § 6.2

G. The names of each owner whose property is within any of the proposed routes for the HVTL. Appendix J

H. United States Geological Survey (“USGS”) topographical maps or other maps acceptable to the Commission showing the entire length of the HVTL on all proposed routes.

Appendix C

I. Identification of existing utility and public rights-of-way along or parallel to the proposed routes that have the potential to share right-of-way with the proposed HVTL.

§ 3.2, Table 3.3.2-1, Figure 3.2.2-1, and Appendix C

J. The engineering and operational design concepts for the proposed HVTL, including information on the electric and magnetic fields of the HVTL.

Chapter 5

K. Cost analysis of each route, including the costs of constructing, operating and maintaining the HVTL that are dependent on design and route.

§ 2.9 and § 5.4

L. A description of possible design options to accommodate expansion of the HVTL in the future. § 2.10

M. The procedures and practices proposed for the acquisition and restoration of the right-of-way and for construction and maintenance of the HVTL.

Chapter 5

N. A listing and brief description of federal, state and local permits that may be required for the proposed HVTL.

Chapter 8 and Table 8.0-1

O.

A copy of the Certificate of Need or the certified HVTL list containing the proposed HVTL or documentation that an application for a Certificate of Need has been submitted or is not required.

§ 1.3

Minn. R. 7850.1900, Subp. 3 – Environmental Information

A. A description of the environmental setting for each site or route. § 6.1

Page 4: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

3

B.

A description of the effects of construction and operation of the facility on human settlement, including, but not limited to, public health and safety, displacement, noise, aesthetics, socioeconomic impacts, cultural values, recreation and public services.

Table 3.3.2-1 and § 6.5

C. A description of the effects of the facility on land-based economies, including, but not limited to, agriculture, forestry, tourism, and mining.

Table 3.3.2-1 and § 6.6

D. A description of the effects of the facility on archaeological and historic resources.

Table 3.3.2-1 and § 6.7

E. A description of the effects of the facility on the natural environment, including effects on air and water quality resources and flora and fauna.

Table 3.3.2-1 and § 6.8

F. A description of the effects of the facility on rare and unique natural resources.

Table 3.3.2-1 and § 6.9

G. Identification of human and natural environmental effects that cannot be avoided if the facility is approved at a specific site or route.

Table 3.3.2-1 and Chapter 6

H.

A description of measures that might be implemented to mitigate the potential human and environmental impacts identified in items A to G and the estimated costs of such mitigation measures.

Table 3.3.2-1 and Chapters 5, 6, and

7

Page 5: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

APPENDIX B

90-Day Preapplication Letter to Local Units of Government and Affidavits of Mailing

Page 6: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to
Page 7: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

May 12, 2017  Re:  Huntley‐Wilmarth 345 kilovolt (kV) transmission line  Dear Administrator,  Xcel Energy and ITC Midwest are proposing a new 40‐50 mile 345 kV transmission line between the Xcel Energy’s Wilmarth Substation north of Mankato and ITC Midwest’s Huntley Substation, currently under construction south of Winnebago. The project is needed to reduce congestion on the transmission grid in southern Minnesota and northern Iowa that is inhibiting low‐cost electricity from generation facilities, including wind farms in the area, from reaching customers. By mitigating this congestion and strengthening the regional transmission system, the project will provide economic benefits by enabling the more low‐cost electric generation to reach customers in the region.  The project was approved by Midcontinent Independent Transmission System Operator (MISO) in December 2016 and the two companies have been authorized to seek regulatory approvals to build the line.   Xcel Energy and ITC Midwest are currently developing potential routes for the proposed transmission line to connect the Huntley and Wilmarth substations.  To gather landowner and stakeholder feedback, we plan to hold public open houses on the project in June.  The open houses will provide us an opportunity to present preliminary route options, obtain feedback and answer questions on the Project. We expect to file regulatory applications for the project with the Minnesota Public Utilities Commission in late 2017. Two major approvals must be obtained from the Commission before a high voltage transmission line like the proposed Project can be built: a Certificate of Need and a Route Permit.  In the Certificate of Need proceeding, the Commission determines whether the project is needed and the appropriate size, configuration, and timing..  If the Commission determines that the project is needed, the Commission will then determine the route for the proposed project.  There are multiple opportunities for stakeholder and public input in both of these proceedings.    We would appreciate an opportunity to update your board about the project and discuss any questions you may have.   We’d  also  be  happy  to  discuss  the  right‐of‐way  acquisition  and  construction  process.  To  schedule  a briefing, please contact Xcel Energy’s area community relations manager, Trisha Rosenfeld at (507) 387‐9633 or [email protected].  Tom Hillstrom                 Routing Lead Xcel Energy  Lori Broghammer Local Government and Community Affairs Area Manager ITC Midwest 

EXHIBIT 1

Page 8: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

Huntley ‐ Wilmarth 345kV Transmission ProjectTownships and Cities in Study Area

Township County Clerk Address City State Zip CodeBeauford Township Blue Earth Kim Krengel 57236 148th Street Good Thunder MN 56037

Butternut Valley Township Blue Earth Adam Jones 49492 200th Street Lake Crystal MN 56055

Cambria Township Blue Earth Brenda Thorson 116 Main Street New Ulm MN 56073

Caresco Township Blue Earth Tammy Sonnabend 49588 145th Street Vernon Center MN 56090

Danville Township Blue Earth Laurie Stenzel 61383 129th Street Mapleton MN 56065

Decoria Township Blue Earth Valeria Levos 19035 Kodiak Lane Mankato MN 56001

Garden City Township Blue Earth Liz Thiesse PO Box 296 Lake Crystal MN 56055

Jamestown Township Blue Earth James Anderson 60392 239th Street Madison Lake MN 56063

Judson Township Blue Earth Jeff Davis 50683 207th Street Lake Crystal MN 56055

Le Ray Township Blue Earth Karyn Block 61093 200th Street Eagle Lake MN 56024

Lime Township Blue Earth Laurie DeGezelle 205 Pheasant Court Mankato MN 56001

Lincoln Township Blue Earth Tammy Petterson 18858 484th Avenue Lake Crystal MN 56055

Lyra Township Blue Earth Sandra Miller 13474 560th Avenue Mapleton MN 56065

Mankato Township Blue Earth Dan Fogal 18727 Ridge Drive Mankato MN 56001

Mapleton Township Blue Earth Gail Jaeger 11498 587th Lane Mapleton MN 56065

McPherson Township Blue Earth Lynda Kruse 16754 605th Avenue Janesville MN 56048

Medo Township Blue Earth Sheryl Olson 13402 618th Avenue Mapleton MN 56065

Pleasant Mound Township Blue Earth Dennis Urban 48254 105th Street Amboy MN 56010

Rapidan Township Blue Earth Maria Bartsch 55173 190th Street Mankato MN 56001

Shelby Township Blue Earth John Mack 12682 514th Avenue Amboy MN 56010

South Bend Township Blue Earth Jamie Malvin 306 South McKinzie Street Mankato MN 56001

Sterling Township Blue Earth Judy Conrad 56199 111th Lane Amboy MN 56010

Vernon Center Township Blue Earth Janice Roelofs 78 Cree Point Drive Mankato MN 56001

Barber Township Faribault Charles Cory 14338 470th  Avenue Easton MN 56025

Delavan Township Faribault Martha Bleess 41058 200th Street Delavan MN 56023

Lura Township Faribault Marie Schrader 20122 480th Avenue Easton MN 56025

Minnesota Lake Township Faribault Scott Radke 52203 217th Street Minnesota Lake MN 56068

Prescott Township Faribault Jan Rauenhorst 16233 405th Avenue Delavan MN 56023

Verona Township Faribault Nina Patten 16868 340th Avenue Winnebago MN 56098

Walnut Lake Township Faribault Amber Hubbard 51481 145th Street Wells MN 56097

EXHIBIT 2

Page 9: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

Winnebago City Township Faribault Deb Claeys 344 Timberwolf Lane Winnebago MN 56098

Center Creek Township Martin Kim Shoemaker 2849 150th Street Granada MN 56039

Nashville Township Martin Mary Tomlinson 2528 220th Street Truman MN 56088

Belgrade Township Nicollet Lori Cullen 38310 490th Street St Peter MN 56082

Courtland Township Nicollet Tim  Harmening 43370 541st Avenue Courtland MN 56021

Nicollet Township Nicollet Eileen Darling 44464 478h Street Nicollet MN 56074

City County Adminstrator Address Ctiy State ZipcodeCity of North Mankato Nicollet John Harrenstein PO Box 2055 North Mankato MN 56003

City of Amboy Blue Earth Patty Smith PO Box 250 Amboy MN 56010

City of Eagle Lake Blue Earth Brad Potter PO Box 159 Eagle Lake MN 56024

City of Good Thunder Blue Earth Heather Lowe PO Box 97 Good Thunder MN 56037

City of Lake Crystal Blue Earth Taylor Gronau PO Box 86 Lake Crystal MN 56055

City of Mankato Blue Earth Patrick Hentges PO Box 3368 Mankato MN 56002

City of Mapleton Blue Earth Patty Woodruff PO Box 366 Mapleton MN 56065

City of Minnesota Lake Blue Earth Dawn Whitehead PO Box 98 Minnesota Lake MN 56068

City of Pemberton Blue Earth Darla Ward 141 Fourth Street Pemberton MN 56078

City of St Clair Blue Earth Catherine Seys PO Box 97 St. Clair MN 56080

City of Skyline Blue Earth Cathy Dahl 164 S Skyline Drive Mankato MN 56001

City of Vernon Center Blue Earth Patricia Krosch PO Box 385 Vernon Center MN 56090

City of Delavan Faribault Trudy Anderson PO Box 136 Delavan MN 56023

City of Easton Faribault Rose Doyle 51 Main Street Easton MN 56025

City of Winnebago Faribault Chris Ziegler PO Box 35 Winnebago MN 56098

EXHIBIT 2

Page 10: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to
Page 11: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

May 12, 2017  Re:  Huntley‐Wilmarth 345 kilovolt (kV) transmission line  Dear Administrator,  Xcel Energy and ITC Midwest are proposing a new 40‐50 mile 345 kV transmission line between the Xcel Energy’s Wilmarth Substation north of Mankato and ITC Midwest’s Huntley Substation, currently under construction south of Winnebago. The project is needed to reduce congestion on the transmission grid in southern Minnesota and northern Iowa that is inhibiting low‐cost electricity from generation facilities, including wind farms in the area, from reaching customers. By mitigating this congestion and strengthening the regional transmission system, the project will provide economic benefits by enabling the more low‐cost electric generation to reach customers in the region.  The project was approved by Midcontinent Independent Transmission System Operator (MISO) in December 2016 and the two companies have been authorized to seek regulatory approvals to build the line.   Xcel Energy and ITC Midwest are currently developing potential routes for the proposed transmission line to connect the Huntley and Wilmarth substations.  To gather landowner and stakeholder feedback, we plan to hold public open houses on the project in June.  The open houses will provide us an opportunity to present preliminary route options, obtain feedback and answer questions on the Project. We expect to file regulatory applications for the project with the Minnesota Public Utilities Commission in late 2017. Two major approvals must be obtained from the Commission before a high voltage transmission line like the proposed Project can be built: a Certificate of Need and a Route Permit.  In the Certificate of Need proceeding, the Commission determines whether the project is needed and the appropriate size, configuration, and timing..  If the Commission determines that the project is needed, the Commission will then determine the route for the proposed project.  There are multiple opportunities for stakeholder and public input in both of these proceedings.    We would appreciate an opportunity to update your board about the project and discuss any questions you may have.   We’d  also  be  happy  to  discuss  the  right‐of‐way  acquisition  and  construction  process.  To  schedule  a briefing, please contact Xcel Energy’s area community relations manager, Trisha Rosenfeld at (507) 387‐9633 or [email protected].  Tom Hillstrom                 Routing Lead Xcel Energy  Lori Broghammer Local Government and Community Affairs Area Manager ITC Midwest 

EXHIBIT 1

Page 12: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

Emailed mailer on 5/30/2017

City/Organization Name Title Address Suite City State Zip code Phone Email NotesCity of North Mankato John Harrenstein Administrator 1001 Belgrade Avenue PO Box 2055 North Mankato MN 56003 507-625-4141 [email protected] of North Mankato Michael Fischer Community Development Director 1001 Belgrade Avenue PO Box 2055 North Mankato MN 56003 507-625-4141 [email protected] of North Mankato Mark Dehen Mayor 1706 LorRay Drive North Mankato MN 56003 507-345-7614 [email protected] City of Mankato Patrick Hentges Manager 10 Civic Center Plaza PO Box 3368 Mankato MN 56002 507-387-8695 [email protected] of Mankato Paul Vogel Community Development Director 10 Civic Center Plaza PO Box 3368 Mankato MN 56002 507-387-8695 [email protected] of Mankato Eric Anderson Mayor 10 Civic Center Plaza Mankato MN 56001 507-387-8693 [email protected] County Marie Dranttel Commission Chair 201 South Minnesota Avenue St. Peter MN 56082 [email protected] Nicollet County Seth Greenwood Engineer 201 South Minnesota Avenue St. Peter MN 56082 [email protected] Nicollet County Mandy Landkamer Property Services Director 201 South Minnesota Avenue St. Peter MN 56082 507-934-7074 [email protected] Nicollet County Ryan Krosch Administrator 201 South Minnesota Avenue St. Peter MN 56082 [email protected] Blue Earth County George Leary Planner 410 S 5th Street/PO Box 3566 Mankato MN 56002-3566 507-304-4381 [email protected] Blue Earth County Scott Fichtner Environmental Service Director 410 S 5th Street/PO Box 3566 Mankato MN 56002-3566 507-304-4381 [email protected] Blue Earth County Bob Meyer Administrator 410 S 5th Street/PO Box 3566 Mankato MN 56002-3566 [email protected] Blue Earth County Mark Piepho Commission Chair 8 Skyline Drive Mankato MN 56001 507-387-4380 [email protected]

EXHIBIT 2

Page 13: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

APPENDIX C

Detailed Route Maps and Land Use Maps

Page 14: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

APPENDIX C1

Detailed Route Maps

Page 15: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

")

T: 109R: 27S: 25

T: 109R: 26S: 29

T: 109R: 26S: 30

T: 109R: 26S: 28

T: 108R: 26S: 3

T: 109R: 26S: 31

T: 108R: 27S: 1

T: 108R: 26S: 2

T: 108R: 26S: 4

T: 108R: 26S: 6

T: 108R: 26S: 5

T: 109R: 26S: 34

T: 109R: 26S: 33

T: 109R: 26S: 35

T: 109R: 26S: 32

T: 109R: 26S: 26

T: 109R: 27S: 36

T: 109R: 26S: 27

Blue Ear thCounty

NicolletCounty

NorthMankato

Mankato

B e l g r a d eTo w n s h i p

L i m eTo w n s h i p

M a n k a t oTo w n s h i p

WilmarthSubstation

MinnesotaRiver

Minnesota River

UV26

UV5

UV82

UV12

UV3

UV57

UV86

"̄³22

"̄³922A

Harper St

N River Dr

Lundin Blvd

Thompson RavineRd

Mabel St

N Rive

rfron

t Dr

May St

W Lind St

Webster Ave

Technology Dr

583

Ave

Rivera Dr

Rock St

PebbleCreek Dr

Mills St

Goodyear Ave

Sher

man

St

Flag

ston

eLa

Adams St

Wal

l St

Fairway Dr

Dukes St

5th

Ave

4th

Ave

N 6th S

t

Fred St

N 4th S

t

Cro

ss S

t

Cen

ter S

t

Willo

w St

Park Ave

N Bro

ad S

t

N5th

St

1st A

ve

2nd

Ave

Brooks St

Lim

e Va

lley

Rd

Ruth St

7th

Ave

6th

Ave

Prem

ier

Dr

8th

Ave

2nd

St

N2n

dSt

Inverness Dr

Shad

yLa

T-304

Harrison Ave

Mary La

Tyler AveJefferson AveMc Kinley Ave

Pierce St

Hop

eCtMonroe Ave

222 La

NH

i llC

t

Isak

atah

Dr

Kingswood Rd

Pega

sus

Cir

Gra

yhaw

kCir

T-653Garfield Ave

Mohr Dr

Butterworth St

231st La

Sohl

er D

r

594

Ave

238 La238 St

230th La

LynxRd

Raintree Rd

Wayside Rd

232nd St

Sain

t And

rew

s D

r

Kestre l

Dr

Excel Dr

Pine St

WoodhillC

t

Lake St

Bittersweet La

Lynd

ale

St

Pine

hurs

t Dr

Deephaven

Dr

Park

St

Summit Ave

Castle Pines Dr

Airport Dr

594t

h Av

e

M-36

Pow

er D

r

Augu

sta

Dr

Mar

y O

ak C

t

591s

t Ave

Lim

eVa

lley

Rd

N

£¤169

£¤14

Nicollet County

0 1Miles1:24,000

Map 1") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 16: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

#*

#*

#*

#*

#*

#*

#*

T: 108R: 27S: 9

T: 108R: 28S: 12

T: 109R: 27S: 27

T: 109R: 27S: 29

T: 109R: 28S: 25 T: 109

R: 27S: 26

T: 108R: 27S: 7

T: 108R: 27S: 8

T: 108R: 27S: 5

T: 108R: 27S: 3

T: 109R: 27S: 32

T: 109R: 28S: 36

T: 109R: 27S: 31

T: 108R: 27S: 2

T: 108R: 27S: 6

T: 108R: 28S: 1

T: 108R: 27S: 4

T: 109R: 27S: 34

T: 109R: 27S: 33

T: 109R: 27S: 35

T: 109R: 27S: 30

T: 109R: 27S: 28

NorthMankato

Mankato

B e l g r a d eTo w n s h i p

J u d s o nTo w n s h i p

N i c o l l e tTo w n s h i p

S o u t h B e n dTo w n s h i p

Minnesota River

MinnesotaRiver

%,B

%,A

Swan LakeWMA: Johnson

Marsh Unit

UV13

UV50

UV6

UV25

UV17

UV41

"̄³68Sharon D

r

500th St

Kern

sDr

Can

d iLa

Lee Blvd

Ray

mon

dDr

Mar

yLa

Timm Rd

Commerce Dr

ArlingtonLa

Nottingham

Dr

Country Side Dr

NR

idge

Dr

Castle Dr

Alek

Ct

Balsam Dr

Valle

yV i

ewD

r

Lexington La

Fairbanks

La

Lamar Ct

Pleasant ViewD

r

Purrier Ct

522nd St

Red

Tail

La

Ravin

e Rd

FairbanksDr

Abby

woo

dLa

Northway DrTow

er B

lvd

Carlson Dr

Linda

La

502nd St

Leona

Dr

Mi n

n ew

a ko n

Dr

Orchid Dr S

512th St

James Dr

Ringhofer Dr Green Acres Dr

219 St

405t

hAv

e

Dee

rwoo

d Tr

415t

h Av

e

Honeysuckle La

506th St

526th St

Howard Dr

T-12

7

532

La

498th St

510th St

Lookout Dr

Orc

hard Dr N

Eagle Ridge

Dr

Sheridan Ct

Nor

th

Ridge Dr

Hau

ghto

n Av

e

Aspen La

LorrayDr

Mary Cir

Old

River Bluff

Rd

409th

Ave

Coventry La

Birch BluffDr

Fernwood

La

421s

t Ave

£¤14

£¤169

Blue

Ear

th C

ount

yN

icolle

tCou

nty

Blue

Ear

th Co

unty

0 1Miles1:24,000

Map 2") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 17: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

#*#*#*#*

#*

#*

#*

#*#*#*

#*

#*

T: 108R: 28S: 7

T: 108R: 29S: 12 T: 108

R: 28S: 10

T: 109R: 29S: 25

T: 109R: 28S: 26

T: 108R: 28S: 9

T: 108R: 28S: 11

T: 108R: 28S: 8

T: 109R: 29S: 36

T: 108R: 28S: 3

T: 108R: 28S: 5

T: 109R: 28S: 34

T: 108R: 28S: 6

T: 109R: 28S: 31

T: 108R: 28S: 4

T: 108R: 29S: 1

T: 108R: 28S: 2

T: 109R: 28S: 35

T: 109R: 28S: 27

T: 109R: 28S: 28

T: 109R: 28S: 29

T: 109R: 28S: 30

T: 109R: 28S: 32

T: 109R: 28S: 33

B u t t e r n u tVa l l e y

To w n s h i p

C a m b r i aTo w n s h i p

J u d s o nTo w n s h i p

N i c o l l e tTo w n s h i p

Unnamed (Horseshoe)

Minnesota River

Unnamed (Judson)Swan Lake Outlet

%,E

%,F

Swan LakeWMA: North

Star Unit

UV23

UV42

UV20

UV25

UV41

"̄³68

Main St

224 St

219 St

223 St

Oak St

513

Ave

Railroad St

222 St

510th St

524

Ave

221La

230 La

515

Ave

Broa

d S

t

443r

d Av

e

511

Ave

513

La

Judson Ft Rd

Hilltop La

227 St

505

Ave

231 La

Deer

Rd

501

Ave

506th St

518

Ave

233 La

499

Ave

Heb

ron

Dr

465thAve

503

Ave

PrairieSt

505 La

443rd

La

506

Ave

4 75t

hAv

e

Nicollet County

Blue Ear th County

Nicollet County

0 1Miles1:24,000

Map 3") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 18: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#* #*

T: 108R: 28S: 15

T: 108R: 28S: 17

T: 108R: 29S: 14

T: 108R: 29S: 13

T: 108R: 28S: 16

T: 108R: 29S: 23

T: 108R: 28S: 18

T: 108R: 28S: 20

T: 108R: 29S: 24

T: 108R: 28S: 19

T: 108R: 28S: 21

T: 108R: 28S: 22

T: 108R: 29S: 26

T: 108R: 29S: 25

T: 108R: 28S: 29

T: 108R: 28S: 28

T: 108R: 28S: 30

T: 108R: 28S: 27

LakeCrystal

B u t t e r n u tVa l l e y

To w n s h i pJ u d s o n

To w n s h i p

MinneopaCreek

Minneopa Creek

Minneopa Creek

Minneopa Creek

Minneopa Creek

Minneopa

Creek

%,E

UV11

UV6

UV20

UV42

"̄³60

206 St

515

Ave

505

Ave

200th St

523

Ave

499

Ave

208 St

518

Ave

524

Ave

207 St

517

Ave211 St

494

Ave

0 1Miles1:24,000

Map 4") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 19: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

T: 107R: 29S: 15

T: 107R: 29S: 16 T: 107

R: 28S: 18

T: 107R: 28S: 17

T: 107R: 29S: 14

T: 107R: 29S: 17

T: 107R: 29S: 13

T: 107R: 29S: 10

T: 107R: 29S: 8 T: 107

R: 28S: 8

T: 107R: 28S: 7

T: 107R: 29S: 11

T: 107R: 29S: 12

T: 107R: 28S: 6

T: 107R: 28S: 5

T: 107R: 29S: 9

T: 107R: 29S: 3

T: 107R: 29S: 5 T: 107

R: 29S: 1

T: 107R: 29S: 2

T: 107R: 29S: 4

T: 108R: 29S: 35

T: 108R: 29S: 36

T: 108R: 28S: 32

T: 108R: 28S: 31

LakeCrystal

B u t t e r n u tVa l l e y

To w n s h i p

G a r d e n C i t yTo w n s h i p

J u d s o nTo w n s h i p

L i n c o l nTo w n s h i p

Minneopa Creek

UV32

UV76

UV9

UV20

UV74

UV79

UV6

UV77

UV30

"̄³60

N L

inco

ln S

t

499

Ave

194 St

Silver St

WN

ath a

nSt

T-279

Col

wyn

Way

RadichelSt

Judson

St

Bert St

Humphrey St

S Li

ncol

n S

t

N H

unt S

t

M-1

0

Loraine St

Richard Rd

Scott St

489

La

186 St

489

Ave

505

Ave

190 St

195 St

182 St

185 St

507 Ave

E N

atha

n St

LoraineDr

S H

unt S

t

SAnna

Ave

179 St

0 1Miles1:24,000

Map 5") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 20: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

T: 107R: 29S: 24

T: 107R: 29S: 23

T: 107R: 28S: 19

T: 107R: 29S: 21

T: 107R: 29S: 26

T: 107R: 28S: 20

T: 107R: 29S: 27

T: 107R: 28S: 29

T: 107R: 29S: 28

T: 107R: 28S: 30

T: 107R: 29S: 25

T: 107R: 29S: 22

T: 106R: 29S: 3

T: 106R: 29S: 1

T: 106R: 29S: 2

T: 106R: 29S: 4 T: 106

R: 28S: 6

T: 106R: 28S: 5

T: 107R: 29S: 36

T: 107R: 28S: 31

T: 107R: 29S: 35

T: 107R: 29S: 33

T: 107R: 29S: 34

T: 107R: 28S: 32

C e r e s c oTo w n s h i p

G a r d e n C i t yTo w n s h i p

L i n c o l nTo w n s h i p

Ve r n o nC e n t e r

To w n s h i p

WatonwanRiver

Watonw

an Riv

er

Watonwan River

WaterfowlProduction

Area

WaterfowlProduction

Area

WaterfowlProduction

Area

UV32

UV20

UV30

UV13

165 St

505

Ave

484

Ave

Ash Rd

169 La

486

Ave

160 La

512

La

491

La

486

La

171 St

160 St

164 St

499

Ave

176 St

176th La

171 La

166 St

169 St

510

Ave

507

Ave

0 1Miles1:24,000

Map 6") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 21: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

T: 106R: 28S: 16

T: 106R: 28S: 17

T: 106R: 28S: 18

T: 106R: 29S: 14

T: 106R: 29S: 23

T: 106R: 29S: 22

T: 106R: 29S: 13

T: 106R: 29S: 15

T: 106R: 28S: 19

T: 106R: 28S: 20

T: 106R: 28S: 21

T: 106R: 29S: 24

T: 106R: 29S: 11

T: 106R: 29S: 10

T: 106R: 29S: 12

T: 106R: 28S: 8

T: 106R: 28S: 7

T: 106R: 28S: 9

C e r e s c oTo w n s h i p

Ve r n o nC e n t e r

To w n s h i pPerch Creek

Watonwan River

AltenburgWPA

UV31

UV32

UV20

UV10

154 St

499

Ave

518

Ave

157 St

502

Ave

153 St

148 St

142 La

158 St

142 St

515

Ave

510

Ave

150th St

County 135 Rd

0 1Miles1:24,000

Map 7") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 22: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

T: 106R: 28S: 28

T: 106R: 29S: 25

T: 105R: 28S: 4

T: 106R: 28S: 31

T: 105R: 28S: 6

T: 105R: 29S: 3

T: 105R: 29S: 2

T: 105R: 29S: 1

T: 105R: 28S: 5

T: 105R: 28S: 7

T: 105R: 28S: 9

T: 105R: 29S: 10 T: 105

R: 28S: 8

T: 105R: 29S: 11

T: 105R: 29S: 12

T: 106R: 28S: 29

T: 106R: 29S: 35

T: 106R: 29S: 36

T: 106R: 28S: 33

T: 106R: 28S: 30

T: 106R: 29S: 34

T: 106R: 28S: 32

C e r e s c oTo w n s h i p

P l e a s a n tM o u n d

To w n s h i pS h e l b y

To w n s h i p

Ve r n o nC e n t e r

To w n s h i p

Willow Creek

Blue Earth

River

Blue E

arth R

iver

Blue Earth River

EvansSloughWMA

Altenburg WPA

Evans SloughComplex-Ikier

Evans SloughComplex-Marble

UV32

UV25

UV20

129 St

514

Ave

499

Ave

137 St

125 St

140 St

121 St

124 St

Cattail

Rd

136 St

137th St

492

Ave

502

Ave

124 La

136

La

511

Ave

132 St

127 St

518

Ave

5 13

A ve

129 La

489

Ave

494

Ave

0 1Miles1:24,000

Map 8") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 23: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

T: 105R: 28S: 20

T: 105R: 29S: 14

T: 105R: 28S: 18

T: 105R: 28S: 17

T: 105R: 29S: 24

T: 105R: 28S: 19

T: 105R: 29S: 22

T: 105R: 28S: 29

T: 105R: 29S: 23 T: 105

R: 28S: 21

T: 105R: 29S: 35

T: 105R: 28S: 33

T: 105R: 28S: 32

T: 105R: 29S: 34

T: 105R: 28S: 31

T: 105R: 29S: 15

T: 105R: 29S: 13

T: 105R: 28S: 16

T: 105R: 29S: 26

T: 105R: 29S: 27

T: 105R: 29S: 25

T: 105R: 28S: 28

T: 105R: 29S: 36

T: 105R: 28S: 30

P l e a s a n tM o u n d

To w n s h i p S h e l b yTo w n s h i p

BlueEarth

RiverBlue Earth River

Willow Creek

Blue E

arth R

iver

BlueEarthRiver

UV40

UV20

UV32

"̄³30

507

Ave

104 St

499

Ave

T-37

505

Ave

503

La

111 St

109 St

105th St

108 St

510

Ave

513

Ave

105 St

495

Ave

494

Ave

515

Ave

518

La

0 1Miles1:24,000

Map 9") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 24: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

T: 104R: 29S: 2

T: 104R: 28S: 5

T: 104R: 29S: 3

T: 104R: 29S: 1

T: 104R: 28S: 4

T: 104R: 28S: 6

T: 104R: 29S: 13

T: 104R: 28S: 8

T: 104R: 29S: 11

T: 104R: 29S: 12

T: 104R: 29S: 15 T: 104

R: 28S: 17

T: 104R: 29S: 14

T: 104R: 29S: 10 T: 104

R: 28S: 9

T: 104R: 28S: 7

T: 104R: 28S: 18

T: 104R: 28S: 16

P l e a s a n tM o u n d

To w n s h i p

N a s h v i l l eTo w n s h i p

S h e l b yTo w n s h i p

W i n n e b a g oC i t y

To w n s h i p

Blue E

arth R

iver

UV14

UV57

UV40

UV32

UV7

UV1

UV52

UV63

250th St

230th St

495

Ave

505

Ave

510

Ave

320t

h Av

e

100 St

220th St

300t

h Av

e

290t

h Av

e

280t

h S

t

338t

h Av

e

325t

h Av

e

Blue Ear th CountyMar tin County Blue Ear th County

Faribault County

Mar

tin C

ount

yFa

ribau

lt Co

unty

0 1Miles1:24,000

Map 10") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 25: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

T: 104R: 29S: 24

T: 104R: 28S: 19

T: 104R: 28S: 21

T: 104R: 29S: 27

T: 104R: 28S: 30

T: 104R: 28S: 28

T: 104R: 28S: 20

T: 104R: 29S: 25

T: 104R: 29S: 26 T: 104

R: 28S: 29

T: 103R: 29S: 3 T: 103

R: 28S: 4

T: 103R: 28S: 5

T: 103R: 28S: 6

T: 104R: 28S: 33

T: 104R: 29S: 36

T: 103R: 29S: 2

T: 103R: 29S: 1

T: 104R: 29S: 35

T: 104R: 29S: 34 T: 104

R: 28S: 32

T: 104R: 28S: 31

Winnebago

C e n t e rC r e e k

To w n s h i p

N a s h v i l l eTo w n s h i p

Ve r o n aTo w n s h i p

W i n n e b a g oC i t y

To w n s h i p

Elm Creek

Blue Earth

River

Blue Earth River

UV1

UV7

UV12UV44

330t

hAv

e

300t

h Av

e

290t

h Av

e

3 37 t

hAve

215th St

180th St

210th St

280t

h S

t

320t

h Av

e

190th St

280t

h Av

e

Mar

tin C

ount

yFa

ribau

lt Co

unty

0 1Miles1:24,000

Map 11") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 26: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*#*

#*

#*

#* #*#*

#*

#*

#*

#*#*

#*

#*

#*

#*

#*

#*

#*

#*#* #*#*#*#*#*#*#*#*#*#*#*#*#*#*#*#*

#*#*#*

#*#*#*#*

#*#*#*

#*

#*

#*#*

#*

#*

#*

#*

#*

#*#*

#*

#*

T: 108R: 27S: 17

T: 108R: 27S: 18

T: 108R: 28S: 14 T: 108

R: 27S: 15

T: 108R: 27S: 20

T: 108R: 27S: 22

T: 108R: 27S: 16

T: 108R: 28S: 23

T: 108R: 27S: 19

T: 108R: 28S: 24

T: 108R: 28S: 13

T: 108R: 27S: 21

T: 108R: 27S: 29

T: 108R: 27S: 30

T: 108R: 28S: 25

T: 108R: 27S: 27

T: 108R: 27S: 28

T: 108R: 28S: 26

Blue Ear th

CountyNicollet

CountyNorth

Mankato

Mankato

B e l g r a d eTo w n s h i p

J u d s o nTo w n s h i p

S o u t h B e n dTo w n s h i p

Le Sueur River

Minneopa Creek

Blue Earth River

Minnesota River

%,B

%,C

%,E

O A VeeMemorial

WMA

!(4

!(8!(7

!(5

!(1

!(2

UV69

UV50

UV34

UV11

UV90

UV41

UV33

"̄³68

"̄³66

"̄³60

535

Ave

Foothill Rd

Marie La

207 Military Rd

7th St

Mar

quet

te A

ve

Lookout Dr

Forest La

Clarion St

T-48

4

Judson Bottom Rd

Clay C

t

Alle

n Av

e

T-736

547

Ave

Gooseberry

La

3rd St

Grant Dr

Marvin Blvd

Bluf

f St

Cliff

Ct

551

Ave

T-207

6th St

T-492

Dakota La

204 St

Horses hoe

La

Tow

er B

lvd

539

La

Sunrise Dr

528

Ave

200th St

208 St

204 La

208 La

Reno St

216 St

203 St

513

Ave

Garland

La

Dale Way

Pint

ail S

t

IvyLa

549

Ave

Cliff

Dr

Oak

Ter

5th St

549t

h Av

e

Fernwood

La

Badger La

T-359

Royal Rd

T-287

Haw

keye

La

T-189

£¤169

0 1Miles1:24,000

Map 12") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28

Page 27: APPENDIX A Route Permit Application Completeness Checklist...Appendix B Subd. 3b Within 30 days of receiving a project notice, local units of government may request the applicant to

#*

#*

#*

#*

#*

#* #*

#*

T: 107R: 27S: 16

T: 107R: 28S: 13

T: 107R: 27S: 18

T: 107R: 27S: 15

T: 107R: 27S: 17

T: 107R: 27S: 14

T: 107R: 27S: 8

T: 107R: 27S: 11

T: 107R: 27S: 10

T: 107R: 27S: 7

T: 107R: 27S: 9

T: 107R: 28S: 12

T: 107R: 27S: 6

T: 107R: 27S: 4

T: 107R: 27S: 5

T: 108R: 28S: 36

T: 107R: 27S: 2

T: 107R: 28S: 1

T: 107R: 27S: 3

T: 108R: 27S: 32

T: 108R: 27S: 35

T: 108R: 27S: 33

T: 108R: 27S: 34

T: 108R: 27S: 31

G a r d e n C i t yTo w n s h i p

J u d s o nTo w n s h i p

R a p i d a nTo w n s h i p

S o u t h B e n dTo w n s h i p

Watonwan

River

Maple River

Blue Earth River

Maple

River

Le Sueur River

Blue E

arth R

iver

%,E

UV9

UV33

UV34

UV90

"̄³66

T-631

T-636

T-63

7

195 St

194 StRidge Dr

195th La

Huffy La

Finc

h R

d

184 St

198th La

544Ave

522n

dAv

e

548

La

192 St

195 La

185 La

540

La

199th La

543

La

193 St

192 La

181 St

194 La

Galena

La

181 La

198 St

185 St

Hardwood

Rd

198 La 549t

h Av

e

Indi

anLa

keRd

Red

Ridge

Rd

T-641

Sunset

Vlg

564 La

Hickory La

IvywoodLa

561Ave

£¤169

0 1Miles1:24,000

Map 13") Substation#* Residence within 500 feet

Proposed Route

Proposed AlignmentPurple Route AlignmentGreen Route Alignment

Red Route AlignmentBlue Route AlignmentAlternative Segments

Existing Transmission69 kV115 kV

161 kV345 kV

Wildlife Management AreaWaterfowl Production AreaSite of High Biodiversity Significance

Native Plant CommunityNWI WetlandsStream%,

1 inch equals 2,000 feet

4

3 2 1

5

12 20

6

13 21

7

14 22

8

15 23

9

16 24

10

17 25

11

18 26

30

19 27

29 28