Appendix 5 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Results of Second Field Survey, February, 2003)

Page 2: Appendix 5 Minutes of Discussions on the Basic Design
Page 3: Appendix 5 Minutes of Discussions on the Basic Design
Page 4: Appendix 5 Minutes of Discussions on the Basic Design
Page 5: Appendix 5 Minutes of Discussions on the Basic Design
Page 6: Appendix 5 Minutes of Discussions on the Basic Design
Page 7: Appendix 5 Minutes of Discussions on the Basic Design
Page 8: Appendix 5 Minutes of Discussions on the Basic Design
Page 9: Appendix 5 Minutes of Discussions on the Basic Design
Page 10: Appendix 5 Minutes of Discussions on the Basic Design
Page 11: Appendix 5 Minutes of Discussions on the Basic Design
Page 12: Appendix 5 Minutes of Discussions on the Basic Design
Page 13: Appendix 5 Minutes of Discussions on the Basic Design
Page 14: Appendix 5 Minutes of Discussions on the Basic Design
Page 15: Appendix 5 Minutes of Discussions on the Basic Design
Page 16: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 6 Letter of MOWRAM regarding Land Acquisition

Page 17: Appendix 5 Minutes of Discussions on the Basic Design
Page 18: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 7 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Explanation on Draft Report, March, 2003)

Page 19: Appendix 5 Minutes of Discussions on the Basic Design
Page 20: Appendix 5 Minutes of Discussions on the Basic Design
Page 21: Appendix 5 Minutes of Discussions on the Basic Design
Page 22: Appendix 5 Minutes of Discussions on the Basic Design
Page 23: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 8 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Commencement of Third Field Survey, June, 2003)

Page 24: Appendix 5 Minutes of Discussions on the Basic Design
Page 25: Appendix 5 Minutes of Discussions on the Basic Design
Page 26: Appendix 5 Minutes of Discussions on the Basic Design
Page 27: Appendix 5 Minutes of Discussions on the Basic Design
Page 28: Appendix 5 Minutes of Discussions on the Basic Design
Page 29: Appendix 5 Minutes of Discussions on the Basic Design
Page 30: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 9 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Results of Third Field Survey, July, 2003)

Page 31: Appendix 5 Minutes of Discussions on the Basic Design
Page 32: Appendix 5 Minutes of Discussions on the Basic Design
Page 33: Appendix 5 Minutes of Discussions on the Basic Design
Page 34: Appendix 5 Minutes of Discussions on the Basic Design
Page 35: Appendix 5 Minutes of Discussions on the Basic Design
Page 36: Appendix 5 Minutes of Discussions on the Basic Design
Page 37: Appendix 5 Minutes of Discussions on the Basic Design
Page 38: Appendix 5 Minutes of Discussions on the Basic Design
Page 39: Appendix 5 Minutes of Discussions on the Basic Design
Page 40: Appendix 5 Minutes of Discussions on the Basic Design
Page 41: Appendix 5 Minutes of Discussions on the Basic Design
Page 42: Appendix 5 Minutes of Discussions on the Basic Design
Page 43: Appendix 5 Minutes of Discussions on the Basic Design
Page 44: Appendix 5 Minutes of Discussions on the Basic Design
Page 45: Appendix 5 Minutes of Discussions on the Basic Design
Page 46: Appendix 5 Minutes of Discussions on the Basic Design
Page 47: Appendix 5 Minutes of Discussions on the Basic Design
Page 48: Appendix 5 Minutes of Discussions on the Basic Design
Page 49: Appendix 5 Minutes of Discussions on the Basic Design
Page 50: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 10 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Results of Forth Field Survey, September, 2004)

Page 51: Appendix 5 Minutes of Discussions on the Basic Design
Page 52: Appendix 5 Minutes of Discussions on the Basic Design
Page 53: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 11 Technical Discussion Record of Steering Committee for the Basic Design

Study on the Project for Rehabilitation of Kandal Stung Irrigation

System in the Kingdom of Cambodia (September, 2004)

Page 54: Appendix 5 Minutes of Discussions on the Basic Design
Page 55: Appendix 5 Minutes of Discussions on the Basic Design
Page 56: Appendix 5 Minutes of Discussions on the Basic Design
Page 57: Appendix 5 Minutes of Discussions on the Basic Design
Page 58: Appendix 5 Minutes of Discussions on the Basic Design
Page 59: Appendix 5 Minutes of Discussions on the Basic Design
Page 60: Appendix 5 Minutes of Discussions on the Basic Design
Page 61: Appendix 5 Minutes of Discussions on the Basic Design
Page 62: Appendix 5 Minutes of Discussions on the Basic Design
Page 63: Appendix 5 Minutes of Discussions on the Basic Design
Page 64: Appendix 5 Minutes of Discussions on the Basic Design
Page 65: Appendix 5 Minutes of Discussions on the Basic Design
Page 66: Appendix 5 Minutes of Discussions on the Basic Design
Page 67: Appendix 5 Minutes of Discussions on the Basic Design
Page 68: Appendix 5 Minutes of Discussions on the Basic Design
Page 69: Appendix 5 Minutes of Discussions on the Basic Design
Page 70: Appendix 5 Minutes of Discussions on the Basic Design
Page 71: Appendix 5 Minutes of Discussions on the Basic Design
Page 72: Appendix 5 Minutes of Discussions on the Basic Design
Page 73: Appendix 5 Minutes of Discussions on the Basic Design
Page 74: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 12 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Alternative Plans of the New Weir Structure, October, 2004)

Page 75: Appendix 5 Minutes of Discussions on the Basic Design
Page 76: Appendix 5 Minutes of Discussions on the Basic Design
Page 77: Appendix 5 Minutes of Discussions on the Basic Design

Appendix 13 Minutes of Discussions on the Basic Design Study on the Project for

Rehabilitation of Kandal Stung Irrigation System in the Kingdom of

Cambodia (Explanation on Draft Report, November, 2004)

Page 78: Appendix 5 Minutes of Discussions on the Basic Design
Page 79: Appendix 5 Minutes of Discussions on the Basic Design
Page 80: Appendix 5 Minutes of Discussions on the Basic Design

5. Cost Estimation Borne by the Recipient Country

Page 81: Appendix 5 Minutes of Discussions on the Basic Design

5. Cost Estimation Borne by the Recipient Country

Required Costs to be born by the Cambodian Side

Description Unit Price (USD) Quantity Amount (USD)

1. Land acquisition m2 1 20,000 20,000

(1) Main canal: 15,000 m2

(2) O&M roads (4 nos): 5,000 m2

2. Investigation and removal of UXOs LS 156,000

3. Banking cost LS 2,700

4. Customs clearance cost LS 1,000

4. Construction and improvement of lateral LS 767,000

and tertiary canals

5. Establishment of O&M office LS 10,500

Total 957,200

Operation and Maintenance Cost

Item Amount (USD)

Personnel cost of O&M office 2,475

O&M cost for O&M office 1,460

O&M cost (average of 30 years) 4,145

Total 8,080