appen e - work in progress audit checklist examp
TRANSCRIPT
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
1/9
Work-In-Progress Audit Checklist Example
date
project description
namescompany name
names
Compliance with OBSERVED Items Only
1 Ref. Spec GENERAL YES N/A ACTION RESPONSIBILITYCompletion
Date
A.A policy for Accident/Incident reports and Safety Inspection reports, including
subcontractors in place when necessary.
B. Daily Tool Box Safety Meeting conducted and documented.
C. Other JSA's BEING USED FOR HIGH HAZARD WORK
2 EMERGENCY RESPONSE YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Do contractors know the alarm code for the area they are working in?
B.Do contractors know the location of the nearest safety shower and fire
extinguisher?
C.Do contractors know where the check-off point is in the event of an
emergency?
D. Other
3 OFFICE SAFETY YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Are electrical cords kept out of aisles or walkways?
B. Are electrical cords and equipment in good conditions?
C. Is the paper cutter arm in the safe position? (i.e. not up or open)
AUDIT ACTION ITEMS
Week of:
Proj:
Inspected By:
Contractor:
Owner Proj MGR:
D.Is the work area clear of tripping hazards such as storage boxes, pile of
paper, etc?
E. Are all cabinet drawers closed except when being used and attended?
4 HOUSEKEEPING YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Materials stored in safe and orderly fashion.
B.Inspection performed daily with cleanup of work, fabrication, and personnel
areas.
C.All stairways, walkways, and scaffolds kept clean of tripping hazards and
obstructions.
D. Plant roads free of debris resulting from performance of contractor's work.
E.Safety Equipment in the work area is accessible including Safety Showers/Eye
baths, fire extinguishers, etc.
F. Other
5 PERSONAL PROTECTIVE EQUIPMENT YES N/A ACTION RESPONSIBILITYCompletion
Date
A. 1926.100 Hard hats provided and worn by all employees.
Appendix
E
E - 1
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
2/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
B. 1926.102Eye (including safety glasses) and face protection provided and worn be all
employees when exposed to potential eye or face injury.
C. Chemical goggles provided and carried by all employees.
D. 1926.101Hearing protective devices provided and worn by all employees where noise
levels are excessive
E. Hard toe safety shoes provided and worn by all employees.
F. Proper clothing worn by all employees (sleeved shirts, full length trousers).
G.Jewelry policy adhered to (NO rings or loose/dangling jewelry worn while
performing work).
H.Safety harness and double lanyard with shock absorber and anchor point used
as required.
I. 1926.103Employees using respiratory protective devices have been medically evaluated
and fit tested.
J.1926.103 (c)
(1)
Employees using respiratory protective devices have been thoroughly trained
in their use.
K. 1926.103Respiratory protective devices provided and worn when employees are
exposed to harmful dusts, fumes, gases.
L. Other
6 PORTABLE POWER AND HAND TOOLS YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.302 (b)
(1)
Devices provided and in use on air power tools to prevent from becoming
accidentally disconnected from hose.
B.1926.302 (e)
(1 &11)
Power actuated tools provided with safety shield/guard. Operator has
evidence of special training in their use.
C.1926.301 (b)
(3)
Defective tools/equipment are tagged as unsafe or controls locked in off
position and has been physically removed from job site.
D. 1926.300 (b) All guards in place on power tools.
E.1926.301 (a-
d)Hand tools in good repair.
F. Handles installed on all files.
G. Other
7 SCAFFOLDS YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Inspection / Tagging system in use.
B.
1926. 451 (a)
(3) Competent person supervising all scaffold erection, alteration, moving etc
C.Scaffolds have toe plates, handrails and proper access provided to scaffold
platforms extended 3 feet above guard rails.
D.If handrails do not meet the standard, 100% tie-off is being practiced and an
elevated work checklist has been completed.
E. Other
8 STAIRWAYS AND LADDERS YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.1053
(b) (15 & 16)
Ladders regularly inspected (monthly with tags affixed and destroyed when
found defective.
E - 2
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
3/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
B.1926.1053
(b) (1)Side rails extend 36 inches above landing or provision of grab rails.
C. Tops of all ladders tied off.
D. 1926.1053(b) (4)
Ladders used only for the purpose for which they were designed.
E.
1926.1053
(b) (20, 21 &
22)
Employees ascending/descending ladders while facing it with at least one
hand holding the ladder and not carrying any loads.
F.When there is possible exposure to an electrical hazard, wooden or fiberglass
ladders are used. (Wooden ladders must be treated.)
G.1926.1053
(b) (9)Area clear around top and bottom of ladder.
H.1926.1053
(b) (5)
Ladder on proper angle (horizontal distance from the top support to the foot
of the ladder is about one quarter of working length.
I.Employees using step ladders are standing so that their waists are below the
top of the ladder.
J. Other
9 ABRASIVE BLASTING YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Proper PPE worn by all personnel involved in blasting operation.
B. Dust accumulation kept to a minimum.
C. Area around equipment being cleaned is barricaded-off.
D. Other.
10 HIGH PRESSURE WATER BLASTING YES N/A ACTION RESPONSIBILITYCompletion
Date
A.Is the area around the equipment to be cleaned, roped-off for a distance of 30
feet?
Are all ersonnel wearin ro er ersonal rotective e ui ment for h dro-
B. blasting work? (minimum of hard hat, safety shoes, goggles, face shield, and
hearing protection)
C.Are hoses, fittings, lances, and nozzles inspected and pressure tested before
each use?
D.Has hydro-blasting equipment been provided with a dump valve which will
immediately reduce system pressure when release by operator?
E. Has hydro-blasting equipment been lift pressurizers and equipment?
11 WELDING, CUTTING AND BRAZING YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.353 (e)
(2)Proper PPE provided, in good condition and being used.
B. 1926.350 (h) All oxygen and acetylene gauges in working condition.
C. 1926.350 (h) All oxygen and acetylene hoses in good condition.
D.1910.252 (a)
(5) (b)Back flow preventers in use.
E.1926.350 (g)
(3)Torches lighted by friction lighters or other approved device.
F.1926.350 (g)
(3)
Oxygen and acetylene hoses properly located so as to avoid a tripping hazard
and potential damage to the hoses.
E - 3
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
4/9
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
5/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
F.1910.252 (a)
(2) (iv) (c)
At least 20 ft. or noncombustible barrier at least 5 ft. high separates oxygen
cylinders from fuel gas.
G. Other
14 FIRE PROTECTION & PREVENTION YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Do contractors know the location of the fire alarm system?
B. Is smoking practiced only in designated areas?
C. Are all fire extinguishers provided by the contractor inspected monthly?
D. Other
15 STEEL ERECTION YES N/A ACTION RESPONSIBILITYCompletion
Date
A. 100% fall protection implemented when fall potential greater than 6 feet.
B. Training provided for all employees using 100% fall protection equipment.
C.1926.750 (b)
(1) (iii)
On levels with flooring/handrails, or 1/2 inch wire rope or equivalent installed
around the perimeter approximately 42 inches high.
D.1926.750 (b)
(1) (iii)Tools and material hoisted/lowered in suitable containers.
E.Working personnel straddling beams when traveling from the point to another
(A.N.S.I. A10.13-1978 (8) (8.3)
F. Other
16 CONCRETE, CONCRETE FORMS AND SHORING YES N/A ACTION RESPONSIBILITYCompletion
Date
A. 1926.701 (b) Protruding reinforcing steel guarded to eliminate impalement hazard.
B.1926.701 (e)
(1)Employees not working under concrete buckets while buckets are elevated orlowered into position.
C.1926.701 (e)
(2)
Elevated concrete buckets routed so that NO employee is exposed to the
possibility of a falling bucket.
D.1926.706 (f)
(2)
Employees wearing safety harness when 6 feet or more above adjacent work
surfaces.
E.1926.706 (a)
(1-5)A limited access zone established for construction of masonry walls.
F. PPE is being used to eliminate routine skin contact with fresh poured concrete.
G. Other
17 HAZARDOUS WORK PERMITS YES N/A ACTION RESPONSIBILITY CompletionDate
A.
A hot work permit obtained for all welding burning, cutting, torch heating,
grinding, or similar operations using an electric arc or open flame, or any
other flame or spark-producing operation.
B.Adequate fire watch is provided with proper extinguishing agent for the type
of hot work being performed.
C.Confined Space Entry Permit obtained for all work in closed or confined
spaces.
E - 5
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
6/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
D.Line entry procedure followed for all entries into pipelines and process
equipment and has been returned to the control room at the end of work.
E. When appropriate, an elevated check list was completed.
F.All rotating or moving equipment, valve or any other potential energy source
locked out and tagged before work begins.
G.Personal locks being used have discrete identification of the individual it
belongs to.
H. Other
18 ELECTRICAL SAFETY YES N/A ACTION RESPONSIBILITYCompletion
Date
A. 1926.404 (b)Ground fault circuit interrupters AND Assured Equipment Grounding Conductor
Program in use to protect employees from electrical shock.
B.
1926.416 (e)
(1) All tools and cords inspected for good physical condition.
C.1926.405 (a)
(2) (ii) (G)
Portable electric lighting used in wet and or conductive locations is 12 Volts or
less, 120 volt lights used if protected by GFCI.
D.1926.416 (e)
(2)Electrical cords are properly suspended. (not suspended by wire or nails)
E.Other Because of the environment NO trees are available on this site, cords
are managed.
19 HOT TAPPING YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Have all necessary permits been issued?
B.
Have the hot-tapping equipment operators been trained, qualified,and
certified for the equipment?C. Has the welder been certified to weld the hot tap nozzles?
D. Is the proper welding machine being used? (i.e. electrical)
E. Does safety equipment conform to what is listed on the Hot Tap Permit?
20 TRENCHING AND EXCAVATION YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.651 (j)
(2)
Excavated material effectively stored and retained at least 2 feet or more from
edge of excavation.
B. 1926.651 (f)Substantial stop logs or barricades installed when mobile equipment working
adjacent to excavation.
C. 1926.652 (a)Excavations and trenches over 4 feet in depth shored to standard, laid back tostable slopes or provided with other equivalent protection where hazard of
moving ground exists.
D.1926.651 (c)
(2)
Excavations and trenches less than 4 feet in depth examined daily by a
competent person for indication of potential cave-in.
E.1926.651 (c)
(2)
Excavations and trenches 4 feet deep or more are provided with ladders
located so that NO more than 25 feet of lateral travel is required for egress.
F.Confined space entry permit issued if excavations and trenches are 4 feet
deep or greater.
E - 6
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
7/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
G.
Employees in excavations or trenches greater than 4 feet in depth equipped
with safety harness and standby person present as per confined space entry
permit.
Other
21 FLOOR AND WALL OPENINGS/BARRICADES YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1910.23 (a)
(9)
All floor openings wider than 1 inch protected by a secure cover to prevent
tools or materials from falling through.
B.1926.500 (b)
(8)
All floor holes into which persons can accidentally walk guarded by standard
railing and toe board or a secured cover. Floor hole covers must be clearly
marked or tagged Do Not Remove Floor Hole Cover.
C.1926.500
(d) (1)Every open-sided floor or platform guarded by standard railing with toeboard.
D.Necessary actions taken to identify and mark off danger zones created by the
work. Barricade system in place to control entry into the danger zone.
E. Other
22 DEMOLITION AND DISMANTLING YES N/A ACTION
A.Has and engineering survey been made and documented by a competent
person?
B. Have all applicable permits been issued?
C. Have you observed material properly transferred to lower levels?
D.Have safe walkways been provided to reach any point without walking on
exposed beams?
E. Are employee entrances protected by sidewalk sheds, canopies, or both?
F.Have floor openings been provided with necessary protection to prevent
equipment from running over the edges of upper floors?
G.
Have all openings in floors not used as material drops, been covered over with
material substantial eNOugh to support the weight of any load that might be
imposed?
23 HAZARD COMMUNICATION YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.59 (e)
(1)
Contractor has written hazard communication program developed,
implemented and maintained at the work place.
B.1926.59 (e)
(l) (i)
Employees informed of the availability of program, including required list(s) of
hazardous chemicals, and Material Safety Data Sheets required.
C.1926.59 (f)
(5) (i) (ii)
Each contractor of hazardous chemicals is labeled, tagged, or marked with
identity of hazardous chemicals inside and shows hazard warnings for
employee protection.
D.1926.59 (h)
(1)
Employees provided with information and training on hazardous chemicals in
their work area at initial assignment and when a new hazard is introduced into
their work area.
E.
E - 7
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
8/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
24 ASBESTOS ABATEMENT YES N/A ACTION RESPONSIBILITYCompletion
Date
A.
Does contractor have written program for protection of all contractor
employees and location personnel from exposure to asbestos?
B.Does contractor require asbestos related medical examinations and
evaluations?
C. Does contractor hold asbestos related training?
D. Is contractor disposing of asbestos properly?
25 LEAD EXPOSURE YES N/A ACTION RESPONSIBILITYCompletion
Date
A.Does contractor have written program for protection of all contractor
employees and location personnel from exposure to lead?
B. Does contractor require lead related medical examinations and evaluations?
C. Does contractor hold lead related training?
D.Is contractor using the appropriate personal protective equipment when
exposed to lead?
26 VEHICLE SAFETY YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Vehicle in good repair (tires, brakes, windshield, etc.)
B. Seat belts worn by all operators and passengers.
C. Back up alarm on vehicle when rear view is obstructed.
D. Other
27 CRANES AND HOISTING EQUIPMENT YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.550 (a)
(2)Rated capacity posted on all lifting, hoisting equipment clearly visible to theoperator.
B.1926.550 (a)
(4)Illustration of crane signals posted at the job site.
C.1926.550 (a)
(6)
Annual inspection made of crane hoisting machinery and record kept of dates
and results.
D.1926.550 (a)
(5)
Competent person designated to inspect equipment prior to and during use, to
ensure a safe operating condition.
E.1926.550 (a)
(9)
Accessible areas within the swing radius are barricaded to prevent an
employee from being struck.
F.1926.550
(15) (i-ii)
NO part of crane or its load closer than 10 ft. energized electrical lines.
G. Load Chart and Boom angle indication is readily visible to the operator.
H. Other
28 PILE DRIVING YES N/A ACTION RESPONSIBILITYCompletion
Date
A.Are stop blocks provided for the leads to prevent the hammer from being
raised against the head block?
B.Are guards in place across the top of the head block to prevent the cable from
jumping out of the sheaves?
C.Are engineers and winchmen accepting signals only from a designated
signalman?
E - 8
-
7/28/2019 Appen E - Work in Progress Audit Checklist Examp
9/9
Work-In-Progress Audit Checklist Example
Compliance with OBSERVED Items Only AUDIT ACTION ITEMS
D. Are all employees kept clear when piling is being hoisted into the leads?
29 MOBILE/POWERED CONSTRUCTION EQUIPMENT YES N/A ACTION RESPONSIBILITYCompletion
Date
A. 1926.602(a)(9)(i).
Bi-directional equipment equipped with a horn?
B.1926.602
(c)(l)(i)Rated capacity posted on all lift trucks, stackers, etc?
C. Fire extinguisher available on all mobile/powered equipment.
D. Refueling takes place while the engine is not running.
E. Other
30 WASTE MANAGEMENT YES N/A ACTION RESPONSIBILITYCompletion
Date
A.Identify, treat, store, and handle waste consistent with EPA and state
regulations.
B. Waste generated on location is disposed of as approved by the CMR.
C.Employees working where hazardous waste is present have been properly
trained and certified per 29 CFR 1910.120
31 GROUND & SERVICE WATER PROTECTION YES N/A ACTION RESPONSIBILITYCompletion
Date
A. Measures have been taken to prevent spills and releases.
B. Contractor has a written plan to contain and clean up any spill.
32 OCCUPATIONAL MEDICINE YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.50 (d)
(2)First aid kit well stocked and available on job site.
B. Person on job site adequately trained and current qualification to render firstaid.
.
33 EXTENSIBLE AND ARTICULATING BOOM PLATFORMS YES N/A ACTION RESPONSIBILITYCompletion
Date
A.1926.556 (b)
(2) (ii)Only authorized persons operating aerial lift.
B.1926.556 (b)
(2) (iv)
Employees standing firmly on floor of basket not climbing or sitting on edge of
basket or using planks or ladders for a work position.
C.Work platform/basket of lift free of all trash, debris, and unnecessary tools
and material.
D.
1926. 556 (b)
(2) (v) Safety harness with lanyard worn and attached to boom or basket.E. Other
E - 9