appeal no. 170 of 2010

116
BEFORE THE APPELLATE TRIBUNAL FOR ELECTRCITY (APPELLATE JURISDICTION) Appeal No. 170 of 2010 Dated : 6 th May, 2011 Coram; Hon’ble Mr. Rakesh Nath, Technical Member Hon’ble Mr. Justice P.S. Datta, Judicial M`ember In the matter: Madhya Pradesh PowerGeneration Company Ltd, Shakti Bhawan, Vidyut Nagar, Rampur Jabalpur (M.P) 482 008. …Appellant Versus 1. Madhya Pradesh Electricity Regulatory Commission, 5 th floor, Metro Plaza, Shakti Bhawan, Vidyut Nagar, Rampur Jabalpur (M.P) 482 008. 2 Madhya Pradesh Power Trading Company Ltd., Shakti Bhawan, Rampur, Jabalpur- 482 008. 3. Madhya Pradesh Poorv Kshetra Vidyut Vitran Co.Ltd., Shakti Bhawan, Rampur, Jabalpur- 482 008. 4. Madhya Pradesh Madhya Kshetra Vidyut Vitran Co.Ltd., Nishtha Parisar, Govindpura, Bhopal- 462 023. 5. Madhya Pradesh Paschim Kshetra Vidyut Vitran Co.Ltd. GPH Compound, Polo Ground, Indore – 452 002. 1

Upload: truongthien

Post on 01-Jan-2017

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Appeal No. 170 of 2010

BEFORE THE APPELLATE TRIBUNAL FOR ELECTRCITY (APPELLATE JURISDICTION)

Appeal No. 170 of 2010

Dated : 6th May, 2011 Coram; Hon’ble Mr. Rakesh Nath, Technical Member Hon’ble Mr. Justice P.S. Datta, Judicial M`ember In the matter: Madhya Pradesh PowerGeneration Company Ltd, Shakti Bhawan, Vidyut Nagar, Rampur Jabalpur (M.P) 482 008. …Appellant

Versus

1. Madhya Pradesh Electricity Regulatory Commission,

5th floor, Metro Plaza, Shakti Bhawan, Vidyut Nagar, Rampur Jabalpur (M.P) 482 008. 2 Madhya Pradesh Power Trading Company Ltd., Shakti Bhawan, Rampur, Jabalpur- 482 008. 3. Madhya Pradesh Poorv Kshetra Vidyut Vitran Co.Ltd., Shakti Bhawan, Rampur, Jabalpur- 482 008. 4. Madhya Pradesh Madhya Kshetra Vidyut Vitran Co.Ltd., Nishtha Parisar, Govindpura, Bhopal- 462 023. 5. Madhya Pradesh Paschim Kshetra Vidyut Vitran Co.Ltd. GPH Compound, Polo Ground, Indore – 452 002.

1

Page 2: Appeal No. 170 of 2010

6. Madhya Pradesh Power Transmission Co.Ltd., Block No. 3, Shakti Bhawan, Rampur, Jabalpur- 482 008. 7. Madhya Pradesh State Electricity Board, Shakti Bhawan, Vidyut Nagar, Rampur, jabalpur(M.P) 482 008. 8. Rajasthan Rajya Vidyut Prasaran Nigam Ltd., Vidyut Bhawan, Janpath, Jaipur- 302 005. 9. Uttar Pradesh Power Corporation Ltd., 14th floor, Shakti Bhawan Extn., 14, Ashok Marg, Lucknow 226 001. 10. MSEB (Holding Company) & Maharashtra State Transmission Co.Ltd., C-19, E Block, MSETCL, Prakash Ganga, Bandra Kurla Complex, Bandra (East), Mumbai 400 051 Respondent(s)

Counsel for the Appellant : Mr. M.G. Ramachandran Ms. Sneha Venketaramani Ms. Swapna Seshadri Ms. Ranjitha Ramachandran Counsel for the Respondent: Mr. Sanjay Sen No.1 Ms. Shikha Ohri Ms. Surbhi Sharma Mr. Ashok Upadhyay

2

Page 3: Appeal No. 170 of 2010

JUDGMENT

HON’BLE MR. JUSTICE P.S. DATTA, JUDICIAL MEMBER

The appeal presents a pure question of law: whether the

Tribunal can give directions to the Madhya Pradesh Electricity

Regulatory Commission to amend, modify or relax any of the

provision of the Madhya Pradesh Electricity Regulatory

Commission (Terms and Conditions for determination of

Generating Tariff) Regulations, 2009 on the alleged ground

that it has been found impossible for the appellant, a

generating company within the meaning of Section 2 (28) of the

Electricity Act,2003 to reach the benchmarks or the yardstick

fixed by the Commission in its said Regulations, 2009, by virtue

of the provisions contained in the said Regulations conferring

power to the Commission to amend the Regulations.

2. Madhya Pradesh State Electricity Board, following the reforms

in the power sector was bifurcated and restructured as a

result of which the function of power generation has been

vested with the appellant. The function of retail distribution of

power has been vested with the respondent No. 3, 4 and 5,

while the function of transmission of power rests with the

3

Page 4: Appeal No. 170 of 2010

respondent No. 6 ;and respondent No. 2 has been vested with

business of bulk purchase and bulk sale of electricity in the

State of Madhya Pradesh.

3. Respondent No. 8, Rajasthan Rajya Vidyut Prasaran Nigam

Limited, owns 40% share in the Power House -1 of the Satpura

Thermal Power Station at Sarni and 50% share in the Gandhi

Sagar Hydro Station operated by the appellant. The appellant

has 50% share in the Rana Pratap Sagar Hydro Station and

Jawahar Sagar Hydro Station operated by the respondent No.8.

The respondent No.9, Uttar Pradesh Power Corporation Limited

has 50% share in Rajghat Hydro Power Station and the

respondent No. 10 MSEB (Holding Co) & Maharashtra State

Transmission Company Limited has 33% share in the Pench

Hydro Station, both operated by the appellant.

4. To show the details of the generating stations and the age of

each of the stations, the appellant has presented the following

table:

4

Page 5: Appeal No. 170 of 2010

Sl.No. Generating Stations Date of Commission

Age

1. Amarkantak Thermal Power Station , (ATPS) Power House-1

Unit 1: 1.02.1965 Unit 2: 08.02.1965

45 years (retired on 01.04.2009)

2. Amarkantak Thermal Power Station, (ATPS) Power House-I1

Unit 3: 11.09.1977 Unit 4: 31.03.1978

33 years

3. Amarkantak hermal Power Station, (ATPS) Power House-I1I

Unit 5: 10.09.2009

01 year

4. Satpura Thermal Power Station (STPS) Power House-1

Unit 1: 06.10.1967 Unit 2: 21.03.1968 Unit 3: 14.05.1968 Unit 4: 10.07.1968 Unit 5: 21.03.1970

42 years

5.

Satpura Thermal Power Station (STPS) Power House-II

Unit 6: 27.06.1979 Unit 7: 20.09.1980

30 years

5

Page 6: Appeal No. 170 of 2010

6. Satpura Thermal Power

Station (STPS) Power House-III

Unit 8: 25.01.1983 Unit 9: 27.02.1984

27 years

7. Sanjay Gandhi Thermal Power Station (SGTPS), Birsinghpur, Power House-I

Unit 1 26.03.1993 Unit 2: 27.03.1994

17 yars

8. Sanjay Gandhi Thermal Power Station (SGTPS), Birsinghpur, Power House-II

Unit 3: 28.2.1999 Unit 4: 23.11.2008

11 years

9. Sanjay Gandhi Thermal Power Station (SGTPS), Birsinghpur, Power House-III

Unit 5: 28.08.2008

02 years

5. The Commission which is respondent No. 1 herein notified the

generation Tariff Regulations, 2009 as aforesaid on 30th April,

2009 setting out norms relating to various components of tariff

determination including normative annual plant availability

factor, gross station heat rate, specific fuel oil consumption,

auxiliary energy consumption, operation and maintenance

expenses and transit and handling losses for coal in the case of

Thermal Power Generation. Prior to the publication of the

notification as aforesaid, the appellant submitted its comments

on the revised Draft Regulations expressing its difficulties on

6

Page 7: Appeal No. 170 of 2010

the norms proposed for the generating stations on the ground

that they were old and had outlived normal life expectancy.

The appellant was allegedly told by the Commission to file

tariff petition as per the norms approved by the State

Commission in the tariff Regulations and then incorporate the

difficulties faced by the appellant in meeting the norms. Then

the appellant filed a tariff petition being No. 54 of 2009 for

determination of multi year generation tariff for the control

period 2009-2010 to 2011-12. In the said petition the appellant

submitted on the following aspects:

a) Tariff based on the bench marks as approved by the

Commission as per Regulations 2009.

b) Proposed revision of the appellant concerning benchmarks

along with justification

c) Tariff based on the proposed revised benchmarks.

d) Gap analysis of the two sets of tariff elaborated above.

6. In the course of public hearing the appellant reiterated its plea

that the norms set out in the Regulations, 2009 were impossible

7

Page 8: Appeal No. 170 of 2010

to be met with; as such the Commission should relax the

norms by virtue of the power under Regulation 58 of the Tariff

Regulations, 2009. The Commission then is said to had

observed that as regards the relaxation of the norms sought for

by the appellant, it could be considered in a separate petition

which is why the appellant filed a petition being No. 8 of 2010

seeking relaxation of the operating norms like the ones as

mentioned in the preceding paragraph. In that petition the

appellant provided detailed explanation along with supporting

data to demonstrate the requirement for relaxation of the

operating norms. It was contended that all the units of the

appellant except the Sanjay Gandhi Thermal Power Station at

Birsingpur had outlived their design life of 25 years and unless

major renovation and modernization works were undertaken

there could be no improvement in the performance of these

units. The station-wise status of the renovation and

modernization activities and the constraints faced by the

appellant with respect to each of the stations was also

explained.

8

Page 9: Appeal No. 170 of 2010

7. The Commission disposed of the petition No. 8 of 2010 which

was filed by the appellant proposing for the relaxation of the

norms by an order dated 26th May, 2010 which is impugned

herein. By the said order which we shall discuss in the sequel,

the commission rejected the petition.

8. The aforesaid order of the Commission is assailed on the

following grounds:

i) The order is a non-speaking one without dealing with specific

aspects.

ii) The order proceeded on the wrong footing that the

performance of the thermal power station of the appellant was

deteriorating from the previous years and no efforts were made

for improvement of the performance by the appellant.

iii) The Commission failed to consider the reasons given by the

appellant which included that the generating stations were old

and most of them had outlived their lives and there could not

be any improvement except through extensive renovation and

modernization.

9

Page 10: Appeal No. 170 of 2010

iv) The Commission proceeded on the wrong footing that the

appellant was seeking inferior norms during the control period

than the ones which were there in the earlier years.

v) The Commission proceeded on the wrong footing that the

appellant was not showing any commitment for improvement in

the coming years.

vi) The Commission erred in misconstruing the details given and

reaching the conclusion that the appellant was seeking

relaxation even in regard to Sanjay Gandhi Thermal Power

Station which is not quite old. The State Commission has failed

to appreciate the peculiar problem faced by the appellant in the

above station because of non-completion of some of the

facilities of the new plant and the appellant was seeking

relaxation only for the financial year 2009-2010. The Sanjay

Gandhi Thermal Power Station Unit No. 5 for which relaxation

was sought was the first 500 MW plant installed by the

appellant and there was a need for the appellant’s technical

personnel to understand and gain experience for operating

such capacity. The appellant had not sought any relaxation in

respect of the above unit for the financial year 2010-2011

10

Page 11: Appeal No. 170 of 2010

onwards. The conclusion reached by the State Commission in

regard to the said generating unit is, therefore, without

consideration of the relevant facts pleaded by the appellant.

vii) The State Commission erred in not considering the Plant

Availability/Load Factor achieved by the appellant’s generating

units in the past few years, the data of which was provided in

details by the appellant. The State Commission without

considering the actual Plant Availability/Load Factor achieved in

the past years has determined the norms to be achieved by the

appellant’s generating stations which is approximately 20%

higher than the Plant Availability/Load Factor presently

achieved by these generating units. The State Commission

has failed to appreciate that these generating units of the

appellant are extremely old and have since long outlived their

design life. It was impossible for these units to achieve Plant

Availability/Load Factor at par with the new generating units

unless substantial renovation & modernization activities were

undertaken

viii) The State Commission has failed to appreciate that the

auxiliary energy consumption in a thermal power generating

11

Page 12: Appeal No. 170 of 2010

station is more like a fixed consumption. When the machines

are running at lower load, the percentage of auxiliary energy

consumed becomes higher. Some auxiliaries are required to

run even when the machines are shut down. Due to the

ongoing renovation & modernization activities, the higher

consumption of secondary oil is inevitable and an improvement

can be expected only after the renovation & modernization

activities are completed.

ix) The State Commission has failed to appreciate that some

generating units of the appellant are designed with dry bottom

ash disposal system and due to this design constraint, these

units have higher specific oil consumption. For example, in the

case of the Satpura Thermal Power Station Phase 1 (5 x 62.5

MW), the State Commission has approved the specific oil

consumption of the order of 2.5 to 3 ml/kWh whereas, even in

the year of best performance the specific oil consumption of the

unit was 5.80 ml/kWh. Thus, even with the best possible

efforts, it is not possible for the appellant to achieve the target

laid down by the State Commission. Thus, the State

Commission has failed to appreciate the design peculiarities

12

Page 13: Appeal No. 170 of 2010

and the resulting specific oil consumption requirements of these

generating units.

X) The State Commission has failed to appreciate that the

appellant is already applying a system of coal accounting in line

with the system of coal accounting being adopted by other

thermal power stations of both private and public sectors. In

spite of making all possible efforts to minimize the losses, it is

difficult for the appellant to achieve the targets prescribed by

the State Commission for reasons beyond its control

xi) The State Commission has failed to appreciate that losses during

transit and handling of the coal occur due to factors which are

beyond the control of the appellant such as loss of coal

quantity due to fine particles getting blown away due to wind or

washed away during rainy season, spontaneous combustion

causing accumulated heaps of coal to catch fire of their own,

surface moisture getting evaporated due to larger travel

distance and larger exposed surface area and pilferage. The

appellant has adopted the best possible methods to minimize

these losses. It is, however, impossible to completely eliminate

such losses, thereby reducing these losses to an extent

13

Page 14: Appeal No. 170 of 2010

compliant with the prescribed norms. A substantial amount of

the handling and transit losses occur when the coal is under the

control of the other agencies and the appellant cannot have any

role to reduce these losses without interfering with their

working, which is just not possible. The State Commission has,

therefore, erred in not taking these factors into consideration for

relaxing the stringent norms prescribed to reduce the transit

and handling losses of coal

xii) The State Commission erred in observing that with regard to

hydro generating stations, no exemption can be provided to

the appellant from the operating norms prescribed under the

Tariff Regulations. The declared capacity of the generating

unit may be zero, although the units are ready to run, due to

factors beyond the appellant’s control. The appellant,

therefore, is seeking a relaxation of their applicability to the

appellant’s generating units. The appellant had also sought

clarification from the State Commission regarding the

consideration of these constraints while calculating Plant

Availability Factor vide letter dated 20.1.2010. The State

Commission in its response dated 11.3.2010 has not

14

Page 15: Appeal No. 170 of 2010

clarified the above specific issues sought by the appellant,

due to which the appellant again wrote a letter dated

03.04.2010 to which no response has been received from

the State Commission till date.

xiii) The State Commission wrongly proceeded on the basis that

the appellant is proposing revision of norms which are more

relaxed than previous submission made on 27.2.2009 and

particularly for FY 2009-10, and that more relaxation of

norms were sought than the norms specified for FY 2008-09

in the earlier Regulations. The State Commission has

further stated that average of operating parameters achieved

since 2003-04 were proposed while there are instances

when better operating parameters have been achieved,

which have been ignored by MPPGCL. The State

Commission has failed to appreciate that it has proposed

operating norms for the control period on the basis of

average of operating parameters achieved during the last 5

years i.e. upto FY 2007-08. However, when the Tariff

Regulations for control period FY 2010-12 were notified in

April 2009 more recent data was available.

15

Page 16: Appeal No. 170 of 2010

xiv) The State Commission has wrongly concluded that the vision of

the petitioner is quite contrary to the spirit laid down under

Section 5.3 (f) of Tariff Policy. The State Commission has

failed to appreciate that the Central Commission has also

considered average performance for fixing the target of

Central Generating Stations and norms were fixed below the

average to incentivize the generating units to achieve better

operating parameters. Regarding relaxed norms for FY

2009-10, the appellant has also considered the force

majeure conditions regarding shortage of water in the Tawa

lake of STPS, Sarni. Two sets of policies were prescribed

under this section of Tariff Policy namely one for plant

which is performing at close or above the normative level

and for the other stations which are referred to in sections 5

(h) (ii). The section 5 (h) (ii) is regarding the units where

operations were much below the norms for many previous

years. It was recommended that the initial starting point for

determination of revenue requirement should be recognized

at relaxed level and not at a desired level and suitable

benchmarks study may be conducted to establish desired

16

Page 17: Appeal No. 170 of 2010

performance standard and further, separate studies may be

required for each utility to assess the capital expenditure

necessary to meet necessary service standards. The

appellant had given consent to proposal of the State

Commission for carrying out the independent 3rd party study

for formulation of O & M norms. The study had not been

conducted so far. The appellant has been regularly pursuing

the State Commission for conducting such study to assess

the capability of all plants operated by the Appellant for

providing relaxation.

xv) The State Commission has failed to follow the well settled

principles laid down by this Tribunal in the case of BSES

Rajdhani Power Limited V. Delhi Electricity Regulatory

Commission (2009) ELR APTEL 880; Uttar Pradesh Rajya

Vidyut Utpadan Nigam Limited v. Uttar Pradesh Electricity

Regulatory Commission and Ors. (Appeal No. 129 of 2006)

which deal with the relaxation of norms required to be done in

the context of the old generating stations.

xvI) The State Commission has failed to appreciate that section 5.3

(f) of the Tariff Policy provides that norms should be efficient

17

Page 18: Appeal No. 170 of 2010

related to past performance capable to achieve and also

considering the latest technological advancement, fuel, vintage

of equipment, nature of operation, level of service to be

provided to the consumers.

xvii) The State Commission has not properly construed Section 6 of

the National Tariff Policy. The Policy further clarifies the

requirement under Section 6.2 (2) as under;

“Power Purchase Agreement should ensure adequate bankable

payment security agreements to Generating Companies. In

case of persisting default in spite of the available payment

security mechanisms like letter of credit, escrow of cash flows

etc. the generating companies may sell to other buyers”

Section 6.2 (3) of the National Tariff Policy further states that-

“3. In case of coal based generating stations, the cost of project

will also include reasonable cost of setting up coal washeries,

coal beneficiation system and dry ash handling & disposal

system”

18

Page 19: Appeal No. 170 of 2010

There is inadequate supply of coal by Coal India Limited to the

thermal power stations of the appellant and quality of coal is

also deteriorating year after year. The quality of coal supplied

is inferior to the design requirements of the boiler equipments

resulting in higher Heat Rate and inefficient operation

xviii)The State Commission has failed to appreciate that even the

Central Electricity Regulatory Commission determines the

applicable norms and parameters based on actual performance

of the generating stations and not arbitrarily and unilaterally

without regard to the actual performance in the previous years

9. Accordingly, the prayers are following:

a) “Allow the appeal and set aside the order dated

26.05.2010 passed by the Madhya Pradesh Electricity

Regulatory Commission to the extent challenged in the

present appeal.

b) Pass such other Order(s) and this Tribunal may deem

just and proper”

19

Page 20: Appeal No. 170 of 2010

10. Petition No.8 of 2010 filed by the appellant which is about 388

page petition contains facts and figures station-wise in support

of the prayer for relaxation of norms.

11. Of the ten respondents, it is the State Commission, the

respondent No. 1 alone which has seriously contested the

appeal although no counter affidavit was filed. The respondent

No. 1, of course, filed a written note of submissions in response

to the memorandum of appeal filed by the appellant dealing

with all the points canvassed in the memo of appeal.

12. The contentions of the respondent No.1in response to the

memorandum of appeal are as follows:-

a) Since the Regulations 2009 notified by the State

Commission under Section 61 read with Section 181 of

the Electricity Act, 2003 has the force of law, the State

Commission has to determine the tariff in terms of the

said Regulations and not on the basis of statements

made by the appellant in a petition proposing for

amendment of such regulations.

20

Page 21: Appeal No. 170 of 2010

b) The Commission’s order dated 26th May, 2010 passed in

petition No. 8 of 2010 declining the prayer of the

appellant for amendment of the MYT Regulations,2009

cannot at all be the subject matter of challenge under

Section 111 of the Act.

c) The Tribunal has no authority or jurisdiction to sit on

judgment on the on the legality of the MYT Regulations

which have acquired the status of the law.

d) The appellate power of the Tribunal does not extend to

the examination of vires/ and or the impracticability or

otherwise of the Regulations notified by the Commission,

under Section 111 of the Act. As such, the Tribunal

does not require under the law to ask the Commission to

amend its regulations in the same manner as was

prayed for by the appellant before the Commission.

e) The effect of allowing the present appeal would amount

to holding that the MYT Regulations, 2009 as framed by

the State Commission, which otherwise cannot be set

aside by the Tribunal, shall be amended by the

21

Page 22: Appeal No. 170 of 2010

Commission meaning thereby what cannot be directly

done by the Tribunal is asked to be done indirectly.

f) Factually, in spite of repeated reminders to the appellant

issued by the Commission to come out with a detailed

renovation and modernization plan the appellant failed

to do so and it miserably failed in managing its affairs in

accordance with the directions issued by the

Commission from time to time and in such circumstance,

the appellant’s asking for amendment of the norms and

guidelines by amending the Regulations to suit its

convenience does not deserve commendation.

g) The respondent No. 1 referred to certain decisions of the

Hon’ble Supreme Court in support of its contentions that

whatever is asked for by the appellant in this appeal in

whatever form it be, is not legally permissible for this

Tribunal to do so because to do so would be usurping

the jurisdiction of the power of judicial review which is

available in ultimate analysis with the High Court. It is

contended that the appellate jurisdiction of this Tribunal

which is vested in Section 111 of the Act does not

22

Page 23: Appeal No. 170 of 2010

extend to the jurisdiction of questioning for legality of the

Regulations so as to see whether the norms notified in

the Regulations are possible to reach by the appellant

who has exhibited total failure in coming up to the mark

or standard set up by the Commission. The decisions

are (a) West Bengal Electricity Regulatory Commission

V/s Calcutta Electricity Supply Company Ltd. Reported in

(2002) 8 SCC 715, (b) K.S Venkataraman & Co. Pvt.Ltd.

V/s State of Madras reported in AIR 1966 SC 1089 ,(c )

PTC India Ltd. Vs CERC reported in ( 2010 )4 SCC 603,

(d) Narinder Chand Hemraj Vs Lt. Governor of Union

Territory of Himachal Pradesh reported in (1971) 2 SCC

747, Supreme Court Employees Welfare Association Vs

Union of India & another reported in (1989) 4 SCC 187,

(e) .M.U. Sinai Vs Union of India and Ors (1972) 2 SCR

640, (f) Vinod Seth v/s Devinder Bajaj and another

reported in (2010) 8 SCC 1 (g) Padam Sen v/s State of

UP AIR 1219,and (h) Nain Singh V/s. Koonwarjee

reported in (1970) 1 SCC 735.

13. The pleadings of the parties bring us to the following issues:

23

Page 24: Appeal No. 170 of 2010

a) Is the appeal maintainable in its present form and merit?

b)Whether this Tribunal has jurisdiction to afford relief to the

appellant as was prayed before the Commission under

section 111 of the Electricity Act, 2003?

c)Is the impugned order of the Commission dated 26th May,

2010 passed in petition no. 8of 2010 declining the prayer

of the appellant for amendment of MYT Regulations, 2009

can at all be a subject matter of challenge under Section

111 of the Electricity Act, 2003?

d)Whether the appellate power of the Tribunal can be

extended to the exercise of setting aside MYT

Regulations on the ground of norms set out therein being

impossible to be achieved by the appellant for its

generating station(s)

e)Whether the appellate power of the Tribunal under Section

111 of the Act enables it to direct the Commission to

amend the MYT Regulations?

24

Page 25: Appeal No. 170 of 2010

f) What is the scope and intent of the provisions of the said

Regulations, 2009 dealing with the ‘power to remove

difficulties’(Regulation 57), ‘power to amend’ (Regulation

58) and inherent power of Commission (Regulation 59) in

the context of the exercise of regulatory power to

determine the tariff for the electricity utilities namely the

generating companies?

g) Whether the exercise or non-exercise of powers by the

State Commission under Regulations 57,58 and 59 is

justiceable under Section 111 of the Electricity Act, and if

so, to what extent and in what manner?

h) Whether the State Commission in exercise or non-

exercise of powers under Regulations 57, 58 or 59 is

required to give a reasoned order in support of its

decision?

i) Whether in the facts and circumstance of the case the

appellant has failed on its part to carry out the R&M

activities in terms of the directions issued by the

Commission so much so that such failure led the

25

Page 26: Appeal No. 170 of 2010

appellant to come up before the Commission or before

this Tribunal with prayer for amendment of the

Regulations at a time when the tariff application for

determining the tariff of the appellant is pending for

disposal before the Commission.

14. Though we have framed a number of issues, the pith and

substance of the legal issue is whether this Tribunal has

jurisdiction to enter into the question of validity of the

Regulations. Therefore, we undertake a comprehensive exercise

towards legal examination of the point. The other issue is factual

in this as to whether the norms set up by the Commission are

reasonable in the light of facts and circumstances of the case

and whether the order of the Commission suffers from lack of

reasonableness.

15. Mr. M.G. Ramachandran, learned Counsel for the appellant

relied on a good number of decisions of the Hon’ble Supreme

Court to buttress the point that what is being asked for is not

exactly the amendment of the Regulations by virtue of the

legislative power of the Commission but relaxation of the norms

26

Page 27: Appeal No. 170 of 2010

by virtue of the power already vested in the Commission in

Regulations 57, 58 and 59 of the MYT Regulations, 2009.

Regulation 57 deals with power to remove difficulties, regulation

58 deals with power to amend and regulation 59 deals with

inherent power of the Commission. Mr. Ramachandran argues

that each or either of the powers enumerated above is sufficient

for the Commission to afford complete relief to the appellant and

the Commission having failed to do so, it is open to the appellant

to move this Appellate Tribunal under its appellate jurisdiction to

exercise its appellate power under Section 111 of the Act for

asking the Commission to exercise either of the three powers on

the facts and circumstances of the case and in doing so, the

Tribunal will not be traveling beyond its jurisdiction and will not

be traversing the area of the power of judicial review. Since the

tariff determination is an inquisitorial proceeding and not an

adjudicatory proceeding, the appellant did not commit illegality to

move the Commission to exercise its power and the Commission

having failed to do so, the appellant is within its rights to

approach the Tribunal to appeal against the decision of the

Commission which is verily an appealable one under Section

27

Page 28: Appeal No. 170 of 2010

111 of the Act. Section 61 of the Act in its 9 clauses with one

proviso makes it clear that the generation of the electricity

should be conducted on commercial principles so as to

encourage the competition, efficiency, economical use of

resources, good performance, optimum investments,

safeguarding of consumers’ interest, recovery of cost of

electricity in a reasonable manner. It is argued that the tariff

determination cannot be such as is dehors section 61; or else it

is liable to struck out. The Regulations, 2009 framed by the

Commission is such that norms set out in Regulation 33 of the

said Regulations are not achievable, yet the Commission

declined to amend the norms. In a cost plus basis tariff

determination, the basic concept is that the generating company

is entitled to all costs and expenses reasonably incurred i.e.

incurred by it in a prudent manner plus a reasonable return on its

investment. Thus, unless there is an imprudence or inefficiency

or similar such factors attributable to its working, the generating

companies should get the cost and expenses incurred and in

addition thereto a reasonable return. In other words, the

generating companies cannot be penalized or punished in the

28

Page 29: Appeal No. 170 of 2010

realization through tariff the cost, expense and return to it except

to the extent that any imprudence or inefficiency is attributable to

such generating company. It is contended that it is, however,

well accepted that there cannot be any regulation providing for

various terms and conditions in an absolute manner without the

need to consider exemption, relaxation, deviation, removing

difficulties etc. on an on-going basis. The regulations framed

are for future. The role of the Commission in deciding the tariff is

not adjudicatory in nature, namely, after a dispute having arisen,

the Commission has to decide the dispute on the basis of an

existing rights and obligations of the parties. The Commission

decides on the regulation as applicable during a future period

and, therefore, proceeds on certain assumptions. It is not just

possible to anticipate everything and frame regulations. There

will always be circumstances which may not be envisaged. The

norms and parameters for determination of tariff by the State

Commission are also terms and conditions which cannot be

specified in an absolute manner. There is, therefore, always a

need to exempt or relax or deviate from the terms and

29

Page 30: Appeal No. 170 of 2010

conditions. In this connection, Mr. Ramachandran refers to

the decisions in

1) Uttar Pradesh Power Corporation Limited v/s National

Thermal Power Corporation Ltd & Ors (2009)6SCC 235

2) PTC India Limited V. C.E.R.C. , 2010 (4) SCC 603

3) Premium Granites & Anr. V. State of Tamil Nadu & Ors.

(1994) 2SCC 691

4) Hindustan Paper Corporation Ltd. V. Government of

Kerala (1986) 3 SCC 398

5) Hindustan Steels Ltd. V. A.K. Roy, (1969) 3 SCC 513

6) S.N. Mukhrjee V. Union of India (1990) (4) SCC 594

7) State of Karnatka & Anr. Vs V.R. Vivekanand Swamy

and another case [2008(5)SCC 328]

8) Foulkes- Administrative Law, Eighth edition, pg 217

9) Wet Bengal Electricity Regulatory Commission vs. CESC

Limited (2002) 8 SCC 715

30

Page 31: Appeal No. 170 of 2010

10) Cellular Operators Assn of India v. Union of India (2003

(3) SCC 186)

11) MaharashtraState Power Generation Co. Ltd. V. M.E.R.C.

& Ors. (2010 ELR (APTEL) 0189)

12) NTPC Ltd. V Madhya Pradesh State Electricity Board

2007 ELR APTEL 7

13) BSES Rajdhani Power Ltd. V. Delhi Electricity Regulatory

Commission (2009) ELR APTEL 880

14) Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited V.

Uttar Pradesh Electricity Regulatory Commission and

Ors. (Appeal No. 96 of 2008)

15) Gujarat State Electricity Corporation Ltd. V. Gujarat

Electricity Regulatory Commission and Ors. (Appeal No.

129 of 2006).

Mr. M.G. Ramachandran also referred to treaties of the (a)

Cases and Materials of Indian Administrative Law by M.P.

Jain (1994Edition Volume I page, 117, (b) de Smith’s-

Judicial Review of Administrative Action, 4th Edition, page

31

Page 32: Appeal No. 170 of 2010

285, (c) Bennion on Statutory Interpretation, fifth edition,

Indian reprint, page 90, (d) Hiltaire Barnett-Constitutional

and Administrative Law, first Indian reprint, 1996, page 716

and (e) Bennion on Statutory Interpretation, fifth edition,

Indian reprint, page 142.

16. Factually, it is submitted that the State Commission has failed

to consider the following aspects which have been pointed out

by the appellant herein in petition No. 8 of 2010 in these

words:-

“3.25. In respect of the units of SGTPS Birsingpur, it is

pertinent to mention that in FY 10 there has been acute

shortage of coal. The units were required to be run on partial

loading. Even the new units of 500 MW as also runs on partial

load on this account. This has resulted in reduction of PLF of

the station in FY 10

3.26 Both the units of PH 1 are also older than 15 years and

have been included by CEA in comprehensive R & M works for

implementation during 12th plan. M/s. NTPC (Consultancy

wing) have been approached for preparation of proposal for R

& M scheme of the Unit 1 & 2 on the similar lines of STPS,

32

Page 33: Appeal No. 170 of 2010

Sarni. HP Heaters of these two units were not functioning

properly. Towards an effort to improve the efficiency of the

units, they have been procured and replaced in one unit in the

AOH of 2009 and the work of other unit shall be taken up in

AOH of 2010.

3.27 Design Probe- The ABL boilers and BHEL Turbine

combination of units have design deficiency compared to BHEL

Boiler/BHEL Turbine. MPPGCL is operating these units best of

its ability. As per CEA performance review for FY 2003 to FY

2007, the performance of 210 MW Unit-1 & 2 of SGTPS is

superior to all India average PUF of ABL Boiler/BHEL Turbine

sets of 200/210 MW capacity, as shown in the table below:-

Year Plant Utilization Factor (PUF) in (%)- ABL / BHEL make

SGTPS Unit No. 1 SGTPS Unit No.2 All India Average

2002-

03 62.64% 62.57% 50.56%

2003-

04 62.55% 62.92% 61.50%

2004-

05 69.60% 63.22% 63.71%

33

Page 34: Appeal No. 170 of 2010

2005-

06 *45.54% 61.77% 65.37%

2006-

07 72.20% 64.34% 63.45%

*The Generator transformer of Unit # 1 failed during this period

resulting in low PUF The comparisons of PUF between

BHEL/BHEL and ABL/BHEL make units as per CEA performance

review for thermal power stations 2006-07 are shown in the table

below:-

Year Plant Utilization Factor (PUF)

BHEL/BHEL ABL/BHEL

2004-05 80.18% 63.71%

2005-06 79.35% 65.37%

2006-07 83.58% 63.45%

34

Page 35: Appeal No. 170 of 2010

The State Commission has failed to consider the above design-

deficiency of the Birsingpur unit and has held that as it is a new

unit, there is no justification of the operating norms for the said

unit.

17. With respect to the hydro generating stations operated by the

appellant, the State Commission has failed to consider the

following aspects with respect to the formula prescribed in the

Tariff Regulations for calculating the availability of these stations,

which have been pointed out by the appellant in Petition No. 8 of

2010 in these words:-

“24. On the basis of the provisions in the clause 38 of the Regulation

2009, the PAFM for preceding three months as certified by SLDC in

respect of all the Hydel Power Stations is as detailed below:-

S.No. Hydro Power Station

Monthly %

MAY(WEF 08.05.09)

June July

CUM.

YEARLY (%)

1. Gandhisagar 59.86 25.46 38.82 40.05

2. Pench 29.17 56.75 92.46 61.99

3. Bargi 69.16 43.30 38.32 48.78

35

Page 36: Appeal No. 170 of 2010

4 Bansagar-1 96.46 66.03 80.92 80.05

5 Banasagar-II 44.75 43.43 47.42 45.26

6 Banasagar-III 72.36 49.20 60.97 60.03

7 Banasagar-IV 0.00 0.00 0.00 0.00

8 Birsingpur 87.50 96.67 100.00 95.29

9 Rajghat 0.00 0.00 8.60 3.14

10. Madhikheda 0.00 0.00 37.82 13.79

25. As the PAFM is linked with DC, we may achieve zero PAFM

even if machine is ready for generation but could not be run due to

any constraints i.e. restriction on release of water for generation

imposed by WRD or in case reservoir level drops below MDDL at

which generation is not possible or nay other constraints imposed

by local/administrative authorities in which units are not allowed to

run due to local “Mela” or any other problems. This is evident from

the above table that Banasagar-IV HPS Jhinna will get no fixed

charges for the period up to July 2009 whereas Rajghat &

Madhikheda HPS will get no fixed charges for the Month May-09

and June-09 because in these months PAFM of these Power

36

Page 37: Appeal No. 170 of 2010

House were zero due to zero DC(no generation was possible due

to reservoir level below MDDL)

26.Further the non-achievement of PAFM shall not be due to poor

performance of plants but due to provisions in respect of

determination of tariff for Hydro Generating Stations. Despite

availability of units / Plants for generation, due to constraints

plants may not achieve normative PAFM & balance 50% fixed cost

shall be recoverable on achieving annual generation equal to

annual design energy. As such despite availability of units / plants

for generation including engagement / availability of staff and all

input required, but due restriction imposed by other agencies on

which MPPGCL has no control, generation from units shall not be

possible and due to zero DC fixed cost shall not be received by

the company”

18. The State Commission is said to have failed to consider the above

aspects and has interpreted the above as a request by the

appellant to issue directions to the local authorities.

.

37

Page 38: Appeal No. 170 of 2010

19. Mr. Sanjay Sen, learned Counsel appearing for the Commission

argued that what Mr. Ramachandran has argued has no legal

sanction behind it, and the question would be whether the Tribunal

has jurisdiction under section 111 of the Act to assume the

jurisdiction to direct the Commission for amendment of the

Regulations, 2009 setting up therein certain norms relating to the

principal generating stations which according to the appellant was

not possible to reach but, which according to the Commission was

verily possible. The alleged impossibility on the part of the

appellant arose due to its impossibility to carry out R& M activities

which the Commission has been insisting on for a number of years

by several meetings with the representatives of the appellant

company and through correspondence which have been set out in

the written note of submissions. In the said scenario, it cannot be

said that the appellant was bonafide in moving the Commission

and from the nature of the application being petition No. 8 of 2010

it would appear that it was argued in unambiguous and clear

words to amend its notified Regulations and bring about the

Regulations to suit its purpose which the Commission refused to

do so holding by a reasoned order that it was not agreeable to

38

Page 39: Appeal No. 170 of 2010

amend the Regulations because the norms set out in the

regulations were such as were not at all impossible to reach at all,

and the appellant inspite of having been directed to extensively

carry out its renovation and modernization works, it failed to do

so. And, when the appellant failed to do so it came of its own with

a petition for amendment of the Regulations. Even the value of the

performance parameters, are inferior to the norms specified in

Regulation, 2009 for FY 2011-12. The Commission asked the

appellant to clarify certain issues which it failed to do so.

Secondly, it is submitted that what is sought for from the Tribunal

is really exercise of the doctrine of judicial review by asking a

direction to the Commission to invoke its power under Regulation

57, 58 and 59 of the MYT Regulations, 2009 when none of these

regulations is at all applicable to mitigate the alleged hardship of

the appellant; and what is really required for the appellant is

amendment of the regulations which the appellant in fact asked

for in petition No. 8 before the Commission and which it again

asked for through this appeal before this Tribunal which cannot

render any relief. Unless the doctrine of judicial review is

exercised which is really non existent either under the statute or

39

Page 40: Appeal No. 170 of 2010

under the Constitution of India, the appellant cannot have any

relief. Therefore, it is submitted that the appeal is not maintainable

under section 111 of Electricity Act, 2003.

20. Having thus recorded the sum total of the submissions of the

learned Counsel for the parties that we proceed to have a critical

appreciation of the issues which can be divided into two parts –

legal and factual ; for the present we will be dwelling upon the

legal issues enumerated above which overlap each other so that

we present herewith a common treatment covering all the legal

issues.

21.Ours is an appellate Tribunal for Electricity set up under Section

110 of the electricity Act,2003 and power and functions of this

Tribunal are dealt with under Section 111 which in essence

provides that it is an appellate authority to examine the orders

passed by adjudicating Officer under the Act(Section 127) or the

orders passed by the Appropriate Commission. The procedure

and power of the Appellate Tribunal are dealt with in Section 120.

The Central Commission and the State Commission pass order

under Part VII of the Act, 2003 which are appealable under section

40

Page 41: Appeal No. 170 of 2010

111 of the Act. There is another power of the Tribunal located in

Section 121 according to which this Tribunal may after hearing the

appropriate Commission or any other party, issue such orders and

instructions or directions from time to time to any appropriate

Commission for the performance of its statutory functions under

the Act. In the present appeal, the appellant has not admittedly

asked the Tribunal to exercise this power. The original Section 121

had given the Chairperson of the Tribunal to examine general

power of superintendence and control over the Commission but

now by amendment the section has been the one which we read

just now.

22. The function of the State Commission will be found in Section 86 of

the Act which we reproduce below:

“86. (1) The State Commission shall discharge the following

functions, namely: -

(a) determine the tariff for generation, supply, transmission and

wheeling of electricity, wholesale, bulk or retail, as the case

may be, within the State:

Providing that where open access has been permitted to a

category of consumers under section 42, the State Commission

41

Page 42: Appeal No. 170 of 2010

shall determine only the wheeling charges and surcharge

thereon, if any, for the said category of consumers;

(b) regulate electricity purchase and procurement process of

distribution licensees including the price at which electricity

shall be procured from the generating companies or licensees

or from other sources through agreements for purchase of

power for distribution and supply within the State;

(c) facilitate intra-state transmission and wheeling of electricity;

(d) issue licences to persons seeking to act as transmission

licensees, distribution licensees and electricity traders with

respect to their operations within the State;

(e) promote congenration and generation of electricity from

renewable sources of energy by providing suitable measures for

connectivity with the grid and sale of electricity to any person,

and also specify, for purchase of electricity from such sources, a

percentage of the total consumption of electricity in the area of a

distribution licensee;

(f) adjudicate upon the disputes between the licensees, and

generating companies and to refer any dispute for arbitration;

(g) levy fee for the purposes of this Act;

42

Page 43: Appeal No. 170 of 2010

(h) specify State Grid Code consistent with the Grid Code specified

under clause (h) of sub-section (1) of section 79;

(i) specify or enforce standards with respect to quality, continuity

and reliability of service by licensees;

(j) fix the trading margin in the intra-State trading of electricity, if

considered, necessary; and

(k) discharge such other functions as may be assigned to it under this

Act.

(2)The State Commission shall advise the State Government on all or

anyof the following matters, namely :-.

(i) promotion of competition, efficiency and economy in activities of

the electricity industry;

(ii) promotion of investment in electricity industry;

(iii) reorganization and restructuring of electricity industry in the State;

(iv) matters concerning generation, transmission , distribution and

trading of electricity or any other matter referred to the State

Commission by that Government.

(3) The State Commission shall ensure transparency while exercising

its powers and discharging its functions.

43

Page 44: Appeal No. 170 of 2010

(4) In discharge of its functions the State Commission shall be guided

by the National Electricity Policy, National Electricity Plan and tariff

policy published under section 3.”

23. In this Connection, we will discuss the provisions of Part IV dealing

with Licensing, Part VII dealing with tariff and Part X dealing with

power and functions of the Commission under this Act.

24. If we analyze different provisions of this Act, which are relatable to

the appropriate Commission it would appear that the regulatory

Commission is a peculiar statutory body having within in itself four

functions, (a) Administrative, (b) Legislative and (c) Judicial and (d)

Advisory . In its administrative jurisdiction, it controls and specifies

the functions of the generating utilities, transmission utilities,

distribution utilities and traders of Electricity. Normally, it does not

have any concern with any individual consumer. Its legislative

function extends to bringing about different types of Regulations

pursuant to the provisions of the Act and to carry out the function

of the Act and its Regulations include determination of terms and

conditions of Tariff Regulations, Conduct of Business Regulation,

MYT Frame Work Regulations, to name a few. It is on the basis of

44

Page 45: Appeal No. 170 of 2010

these Regulations that an appropriate Commission determines

tariff of transmission utilities or of distribution utilities and when it

does so it does exercise quasi -legislative power. Under Section

178 of the Electricity Act, 2003, the Central Electricity Regulatory

Commission is vested with the power to make regulations and

regulations framed by them are required to be laid down before

the Parliament under Section 179 which has authority to make

any modification. Similarly, the State Commission has been

vested with the power to make regulations to carry our the purpose

of the Act under Section 181 and all such regulations made by

the State Commission are required to be laid before each House

of the State Legislature, Unicamral or bicameral as the case may

be. The Regulations framed by the State Commission or the

Central Commission do partake the character of subordinate or

delegate legislation under the law and all such subordinate

legislations have the force of the statutory law Therefore, the

regulations framed by an appropriate Commission are deemed to

be legislative enactments having the approval of Legislature when

it is put to use by notification.

45

Page 46: Appeal No. 170 of 2010

25. So far as the authority of this Tribunal is concerned, its power or

its limitation has been laid down in the most recent decision of the

Supreme Court namely PTC India Ltd. Vs. CERC reported in

(2010) 4 SCC603. This is a five judge bench decision of the

Supreme Court wherein the question arose as to whether this

Tribunal has jurisdiction under Section 111 and 121 to examine

the validity of the regulations. The Hon’ble Supreme Court held

as follows-

‘’93. For the aforesaid reasons, we answer the question raised

in the reference as follows:

The Appellate Tribunal for Electricity has no jurisdiction to

decide the validity of the Regulations framed by the Central

Electricity Regulatory Commission under Section 178 of the

Electricity Act, 2003. The validity of the Regulations may,

however, be challenged by seeking judicial review under Article

226 of the Constitution of India.

94. Our summary of findings and answer to the reference are

with reference to the provisions of the Electricity Act, 2003.

They shall not be construed as a general principle of law to be

46

Page 47: Appeal No. 170 of 2010

applied to Appellate Tribunals vis-à-vis Regulatory

Commissions under other enactments. In particular, we make it

clear that the decision may not be taken as expression of any

view in regard to power of the Securities Appellate Tribunal vis-

à-vis Securities and Exchange Board of India under the

Securities and Exchange Board of India Act, 1992 or with

reference to the Telecom Disputes Settlement and Appellate

Tribunal vis-à-vis Telecom Regulatory Authority of India under

the Telecom Regulatory Authority of India Act, 1997”

26. This decision has also dealt with certain issues which we are

not concerned with. The ratio decidendi of this decision, so far

as the power and functions of the Tribunal is concerned, is very

clear and have been laid down in para 93 and 94 of the

judgment. Therefore, we cannot legitimately do exercise which

is not mandated in Section 111 or 121 of the Act. So far as the

present appeal is concerned, we are faced with the

submissions of the learned Counsel for the appellant that when

a Commission declines to exercise its power to remove

difficulties, or power to relax or when Commission refuses to

exercise its inherent power when exercise of any of such

47

Page 48: Appeal No. 170 of 2010

powers was really necessary, then it is within the domain of this

Tribunal to exercise its power under 111 to direct the

Commission to exercise its any of the powers as enumerated

above so much so that the principles laid down in the National

Tariff Policy, National Electricity Policy and provisions of the

Section 61 of the Act are really honored or they are not

honored in breaches.

27. For better appreciation of the position of law, it is worthwhile to

place on record certain factualities and events in chronological

manner.

28. The First Generation Tariff and Annual Revenue Requirements

for the Financial Year 2005-06 based on the tariff application by

the appellant and the Madhya Pradesh State Electricity Board

was published on 25.01.2006. The multi-year tariff framework

order in respect of the appellant for the FY 2006-07, 2007-08

and 2008-09 was notified on 07.03.2006 on the strength of the

petition of the appellant being petition no. 149 of 2005. In the

Generation Tariff Order for FY 2006-07, the Commission gave

the following directions:-

“The Commission again directs the MPPGCL to carry out

necessary R&M Works for improving the performance of its

generating units. MPPGCL may consider phasing out these

48

Page 49: Appeal No. 170 of 2010

units if it feels that these units have outlived their economic

life and investment in R & M Work may not yield the desired

results. The Company is directed to submits its proposal in

this regard to the Commission with a detailed cost benefit

analysis within three months of this order.”

29. The Commission paid a visit to Satpura Thermal Power Station

at Sarni and made a report which was forwarded to the

appellants. In the said report dated 30.05.2007 the

Commission inter alia made the following observations:-

“The Commission directs that Company shall file a

comprehensive proposal for R& M of the STPS as per the

Commission’s guidelines for capital expenditure. The

Commission has also noted that power house –I has been

performing quite satisfactorily even though it has completed

more than 37 years of its operation. The Commission directs to

prepare a need based action plan for renovation of this power

house. The Commission has also taken stock of breakdown

and failures in the power station. The Company should file a

detailed analysis of various breakdowns and the remedial

measures undertaken to bring down the avoidable number of

incidence in future********. The Commission directed MPPGCL

to file a detailed report on the performance of the units before

and after AOH/COH. “

49

Page 50: Appeal No. 170 of 2010

30. Then on 01.09.2007 the Commission wrote a letter to the

appellant stating inter alia that the compliance report of the

appellant was scrutinized and the Commission directs the

appellant to file a comprehensive compliance report on the

directions of the Commission originally given along with views of

the Commission on the status of the compliance report by

30.09.2007. The direction was that the proposal for R & M of

the STPS would relate to capital expenditure. Then on

11.10.2007 the Commission wrote a letter to the appellant noting

inter alia that the Company had not yet submitted any proposal

for R & M of their own thermal power stations for the appraisal of

the Commission and the Commission’s view was that no R & M

proposal had been submitted to the Commission for appraisal till

date. On 30.11.2007 the Commission again wrote to the

appellant on this subject reiterating virtually what was reapeted in

the letter dated 11.10.2007. On 22.01.2008 the Commission

again wrote regarding the status of the compliance report of

Satpura TPS informing that instructions were issued by the

Commission to send the compliance report by 15.01.2008 but till

date the same could not be received and compliance might be

expedited. Then, on 18.03.2008 the Commission wrote to the

appellant that direction-wise comprehensive impact analysis

report should be submitted by 31.03.2008. Meanwhile, some

NTPC Officers called on the appellant at Jabalpur and visited the

plant and submitted a detailed report comprising

recommendations and the Commission directed the appellant

that the action plan on such recommendations should be

50

Page 51: Appeal No. 170 of 2010

submitted by 24.03.2008. Then on 16.05.2008 the Commission

convened a meeting with the officers of the appellant concerning

renovation and modernisation of the thermal power stations at

Satpura and Amarkantak. On 30.05.2008 the Commission wrote

to the appellant to say that a compliance report might be

submitted towards implementation of the recommendations by

M/s. A.F. Ferguson, Action Plan made by M/s. Deolittle Touche

Tohmatsu India Pvt. Ltd., by 15.07.2008. On 03.08.2009 the

Commission wrote to the appellant on Review of Consolidated

Annual Regulatory Compliance Report of MPPGCL for FY 2008-

09 and directed that since no further progress could be observed,

the appellant should submit a detailed report along with time

bound programme for implementing the system. The

Commission also lamented that the appellant was not serious for

developing data based management and management

information system. On 03.09.2008 the Commission wrote to

the appellant to say that true up petition was filed, audited

accounts were submitted, details of the R & M carried out during

the preceding year but R & M scheme should be made a part of

the plan of R & M in respect of the thermal power stations of MP.

On 26.02.2009 the Commission on the subject of filing R & M

proposal and energy audit report by the Company for thermal

power stations of the appellant stated that it was once again

stressed the need for R & M works but the appellant did not file

any proposal under capital expenditure guidelines. Thus, the

Commission drew up a suo motu proceedings being 07 of 2009

directing the appellant to appear in person or through

51

Page 52: Appeal No. 170 of 2010

authorized representative in default whereof further action would

be contemplated under the Act. Meanwhile, on 11.11.2008 the

Commission published draft regulation for terms and conditions

for determination of Generation Tariff for the FY 2009-10 to FY

2011-12 on multi year tariff principle basis. On 03.12.2008 the

appellant submitted its comments and suggestions on the draft

regulations. On 11.12.2009 the Commission published a

revised draft of the tariff regulations inviting further comments

and suggestions and on 22.02.2009 and 20.03.2009 the

appellant submitted its comments and suggestions on the

revised draft regulations notified by the State Commission. On

04.03.2009 public hearing was conducted, the appellant

appeared and apprised the Commission about the present

status. On 09.03.2009 the Commission sought for additional

information which the appellant is said to have complied with on

20.03.2009. At the other side hearing on the suo motu petition

being 07 of 2009 took place before the Commission on

25.03.2009 and the Commission passed an order on 15.04.2009

in the matter of filing of R & M proposal and directed that (a) R

& M needs of thermal power stations must be identified within

three months (b) comprehensive project report with detailed cost

benefit analysis be prepared within six months (c) the funding

possibility for R & M projects should be explored (d) necessary

approvals from different agencies might be obtained (e)

specifications/draft NIT parallel for above activities be prepared,

(f) approval as per regulations notified by the Commission should

be obtained and (g) better O & M practices as prevailing in

52

Page 53: Appeal No. 170 of 2010

NTPC be adopted. On 30.04.2009 the Commission notified the

M P Electricity Regulatory Commission (Terms and Conditions

for determination of Generation Tariff) Regulations, 2009. On

08.05.2009 the said Regulation was notified in the Government

gazette after final approval. On 02.06.2009 the Commission

notified its order dated 19.05.2009 concerning approval of capital

expenditure towards R & M scheme for STPS Sarni. In this order,

the Commission directed the appellant to submit a report within a

month on 9 points which were put in seriatim at paragraph 10 of

the said order. The questions were very specific and direct. On

03.08.2009 the Commission reviewed the matter and gave

certain directions to carry out R & M in thermal power stations.

On 27.08.2009 a meeting was held between the Commission

and the appellant wherein the appellant expressed its difficulty in

submitting its tariff petition in accordance with the norms

prescribed in the notified regulations. But the Commission

directed the appellant to file the tariff petition in accordance with

the norms prescribed in the tariff regulations. Accordingly, on

28.08.2009 the appellant filed its tariff petition being no. 54 of

2009 in accordance with the tariff regulations for determination of

multi year generating tariff for the period FY 2009-10, 2010-11

and 2011-12. On 05.01.2010 the State Commission held a

public hearing in respect of the petition No. 54 of 2009 wherein

the appellant requested for relaxation of the operating norms

prescribed in the tariff regulations. It is the case of the appellant

that the Commission suggested that a separate petition for

relaxation of the norms might be filed and accordingly on

53

Page 54: Appeal No. 170 of 2010

20.01.2010 the appellant filed a petition requesting the

Commission to clarify certain issues regarding fixed charges and

calculation of plant availability factor in respect of hydro

generating units. It is alleged that the Commission did not give

any clarifications for which the appellant again wrote a letter on

03.04. 2010 requesting for clarifications. However, on

25.01.2010 the appellant filed petition no. 08 of 2010 seeking for

relaxation of the operating norms as prescribed in the tariff

regulations. On 16.02.2010 the appellant filed a petition

requesting the Commission to hear both the petitions, namely, 54

of 2009 and 08 of 2010 in a comprehensive manner but the

Commission is alleged to have declined the request. Then came

the impugned order dated 26.05.2010.

31. The above is a brief narration as to how the matter relating to R &

M works and the correspondences between the parties on the

subject went on. According to the Commission, despite

directions from the Commission from time to time the appellant

was lethargic and did not carry out the scheme, while according

to the appellant, as is now canvassed before us, the generating

stations were quite old ones and the appellant faced difficulties in

implementing the scheme.

32. Let us now have a look as to what was actually prayed for before

the Commission by filing the petition no. 08 of 2010. It is a

detailed petition, self-evident and prayers were as follows:-

54

Page 55: Appeal No. 170 of 2010

“1Consequent to the implementation of power sector reforms in

the State whereunder amongst others, the activities of

generation, transmission, distribution and retail supply of

electricity carried out by MPSEB have been restructured and

transferred to the six successor corporate entities, the function

of power generation has been vested with MPPGCL. The MP

Tradeco has been vested with the responsibility of Power

trading and MPPGCL is required to sell its entire generation to

MP Tradeco at a rate determined by Hon’ble MPERC.

ii. In view of the above, the petitioner respectfully prays that

Hon’ble Commission may kindly:-

(a) Amend the norms specified in Regulations 2009 [RG- 26 (1)

of 2009] and consider the same as proposed in the para 1 to

36 above.

(b) Condone any inadvertent omissions/errors/short comings

and permit the applicant to add/change/modify/alter this filing

and make further submissions as may be required at later

stages.

(c) Pass such orders as Hon’ble MPERC may deem fit and

proper and necessary in the facts and circumstances of the

case to grant relief to petitioner.”

55

Page 56: Appeal No. 170 of 2010

33. To judge as to whether the Commission was justified in

rejecting the petition of the appellant praying for amendment of

the notified Regulations it is most appropriate to quote the

findings of the Commission which are as follows:-

“13.0 Regarding the prayer made by the petitioner for

amendment of the norms specified in the regulation, the

Commission is of the view that the regulations are issued

exercising legislative functions of the Commission of the

Commission given to it under the act and there is no provision

for review. Even otherwise also the petitioner could not satisfy

the Commission on merit warranting further “ In view of the

above, the Commission has observed the following

-

i)The performance of the thermal power stations of MPPGCL

have been deteriorating since past years and no sincere

efforts seem to have been made to arrest such deterioration

what to speak of improvement.

ii)The petitioner has sought relaxation in norms for 2009-10

which are even inferior to the norms for FY 2008-09

prescribed by the Commission in the Regulations for the

earlier control period i.e. FY 2007to FY 2009. It is strange to

note that the petitioner is seeking inferior norms than what

he had in the earlier years. This request is not at all the

spirit of the Electricity Act,2003 and the Tariff Policy notified

by the Government of India.

56

Page 57: Appeal No. 170 of 2010

iii) The petitioner has totally relied on its past trend rather than

showing a commitment for improvement in the coming years.

This contention of the petitioner is not tenable since it would

be against the reform process and will burden the

consumers with the cost of the inefficiency at at the

generating end.

iv)The petitioner has also sought relaxation in the operating

norms for the new unit i e., SGTPS 500 MW Birsinghpur

commissioned recently on 28.08.2008 . While the petitioner

has been citing lack of renovation& Modernization of old

units as the main reason for poor performance , the

petitioner’s inability to operate a new unit at the desired and

nationally acceptable level of performance shows that the

problem is much deep and se vere than what has been

made out. Merely showing helplessness and seeking

relaxation is not going to solve the deep rooted problem.

v) On going through the complete petition , it is observed that

the petitioner is seeking relaxation in norms, notified through

a regulation that too far for all the years of the years of the

control period and for all the thermal and hydel generating

units including the new capacities. The complete reading of

the petition indicates that the petition is seeking amendment

to the Regulation 2009 notified by the Commission on 08-

05-2009. The Commission does not find any event or reason

57

Page 58: Appeal No. 170 of 2010

which justifies the prayer on merit of this case with adequate

grounds based on occurrences a between the notification of

the regulation and the filing of the petition for relaxation of

operating norms action.

14.0. In view of the above findings, the Commission is of the

view that the petition in not maintainable hence stands

dispose d off.”

34. The above order which is under appeal before us is said to be

non-speaking one as being without any reason and in support of

such contention as this, a decision of the Hon’ble Supreme

Court has been referred to us which we shall place in our

judgement to test the validity of the submission at the appropriate

place.

35. For the present it is necessary for us to study the different

provisions of the Tariff Regulations,2009 in respect of which

amendment is sought for. The Regulations,2009 consists of five

chapters covering 59 regulations of which we quote some of

them as could be seen hereunder for better appreciation of the

case. Mr. Ramchandran submits that he is quite conscious that

this Tribunal does not have the power of judicial review so that

before us he is not challenging the Regulation, nor is he asking

for amendment of the Regulations from the Tribunal; what he is

asking for his client is a direction to the Commission in order that

the Commission may relax the norms /modify the norms to suit

58

Page 59: Appeal No. 170 of 2010

the suitability of the appellant in exercise of the power of the

Commission to i)relax, or ii)re move difficulties ,or iii)apply

inherent power .Before we examine the issue we read the

relevant provisions of the Tariff Regulations,2009.

“1.3 These Regulations shall come in force with immediate

effect from the date of their publication in the Official Gazette of

the Government of Madhya Pradesh and unless reviewed

earlier or extended by the Commission, shall remain in force for

a period upto March 2012 from the date of commencement.

Provided that where a Project, including a part thereof, has

been declared under commercial operation before the date of

commencement of these Regulations and whose Tariff has not

been finally determined by the Commission till that date, Tariff

in respect of such Project or such part thereof, as the case may

be, for the period ending 31.3.2009 shall be determined in

accordance with the Madhya Pradesh Electricity Regulatory

Commission (Terms and Conditions for Determination of

Generation Tariff) Regulations, 2005.

2. Scope and extent of application

2.1 These Regulations shall apply in all cases of determination

of Generation Tariff under Section 62 of the Electricity Act,

2003 for supply of electricity to a Distribution Licensee, but shall

not apply where Tariff has been determined through the

59

Page 60: Appeal No. 170 of 2010

transparent process of bidding in accordance with the

guidelines issued by the Central Government as per the

provisions of Section 63 of the Electricity Act, 2003.

3. Norms of Operation to be threshold norms

3.1 For removal of doubts, it is clarified that the norms of

operation specified under these Regulations are the threshold

norms and this shall not preclude the Generating Company and

Beneficiaries from agreeing to improved norms of operation and

in such case the improved norms shall be applicable for

determination of Tariff.

6. Principles for Tariff determination

6.1. The Commission, while specifying the terms and conditions

for the determination of Tariff under these Regulations, is

guided by the principles contained in Section 61 of the Act.

6.2. These Regulations intend to encourage Generating

Company to operate on sound commercial principles. The

return on equity allowable to Generating Company shall depend

upon its performance relative to the benchmark levels of the

operating parameters fixed by the Commission. Only prudent

capital expenditure shall be considered for inclusion in the

asset base.

60

Page 61: Appeal No. 170 of 2010

6.3. The Multi-Year Tariff Principles adopted in these

Regulations seek to promote competition, adoption of

commercial principles, efficient working of the Generating

Company and are based on the Central Electricity Regulatory

Commission (CERC)’s principles. The operating and cost

parameters for the Tariff period have been prescribed after duly

considering the past performance, performance of similarly

placed Units, fuel, vintage of equipments, nature of operation

and capability of achievement in view of past performance for

many years. The allowable Tariffs shall be determined in

accordance with these norms. The Generating Company is

allowed to retain most of the savings as a reward for

performance better than those prescribed in these Regulations.

This is expected to incentivise the Generating Company for

efficient performance and economical use of resources. The

Beneficiaries shall also benefit from the efficient performance

and economical use of resources by the Generating Company

through lowering of Tariffs and improvement in availability and

Plant Load Factor of generating stations.

6.4. Only those investments and capital expenditure that are in

accordance with the guidelines framed by the Commission in

this regard shall be allowed to be recovered through Tariff.

This shall ensure prudent investments by the Generating

Company.

61

Page 62: Appeal No. 170 of 2010

6.5. The terms and conditions prescribed in these Regulations

are for conventional energy sources.

16. CERC’s Principles

16.1. The Commission, while framing these Regulations has

been guided by the principles and methodologies specified by

the Central Commission (CERC) in its Notification dated

19.01.2009 on terms and conditions of Tariff Regulation, 2009

effective from 1.04.2009.

18. Renovation and Modernisation

18.1. The Generating Company, for meeting the expenditure on

Renovation and Modernization (R&M) for the purpose of

extension of life beyond the Useful life of the generating station

or a Unit thereof, shall make an application before the

Commission for approval of the proposal with a Detailed Project

Report giving complete scope, justification, cost benefit

analysis, estimated life extension from a reference date,

financial package, phasing of expenditure, schedule of

completion, reference price level, estimated completion cost

including foreign exchange component, if any, consent of

Beneficiaries and any other information considered to be

relevant by the Generating Company:

62

Page 63: Appeal No. 170 of 2010

18.2. Where the Generating Company makes an application for

approval of R&M proposal, the approval shall be granted after

due consideration of reasonableness of the cost estimates,

financing plan, schedule of completion, interest during

construction, use of efficient technology, cost-benefit analysis,

and such other factors as may be considered relevant by the

Commission.

18.3. Any expenditure actually incurred or projected to be

incurred as admitted by the Commission after prudent check

based on the estimates of Renovation and Modernization

expenditure and life extension, and after writing off the original

amount of the replaced assets and deducting the accumulated

depreciation already recovered from the Original Project Cost,

shall form the basis for determination of Tariff.

18.4. The Generating Company in case of thermal generating

station, may, in its discretion, avail of a special allowance either

for a Unit or a group of Units as compensation for meeting the

requirement of expenses including Renovation and

Modernisation beyond the Useful life of the generating station

or a Unit thereof, and in such an event revision of the capital

cost shall not be considered and the applicable operational

norms shall not be relaxed but the special allowance shall be

included in the annual fixed cost :

63

Page 64: Appeal No. 170 of 2010

Provided further that the option once exercised shall be final and

shall not be allowed to be changed. Provided also that such

option shall not be available for a generating station for which

Renovation and Modernization has been undertaken and the

expenditure has been admitted by the Commission before

commencement of these Regulations, or for a generating station

or Unit which is in a depleted condition or operating under

relaxed operational and performance norms. An appropriate

reduction in NAPAF (Normative Annual Plant Availability Factor)

of such a generating Unit whose R&M proposal is approved by

the Commission as per Regulation 18.1, shall be considered by

the Commission for the Year in which R&M of Unit is undertaken.

However, the operational norms for such generating Unit shall be

reviewed by the Commission keeping in view the objectives of

R&M works. The Generating Company shall file the expected

improvement in norms in its DPR of R&M and the envisaged

improvement in operational norms shall be applicable for that

particular generating Unit after completion of R&M works.

18.5. A Generating Company on opting for alternative option in

Regulation 18.4 of this Regulation shall be allowed special

allowance @ Rs. 5 lakh/MW/Year in 2009-10 and thereafter

escalated @ 5.72 % every Year during the Tariff period in 2009-

12, Unit-wise from the next financial Year from the respective

date of the completion of Useful life with reference to the COD of

respective Units of generating station.

64

Page 65: Appeal No. 170 of 2010

Provided that in respect of a Unit in commercial operation for

more than 25 Years as on 1.4.2009, this allowance shall be

admissible from the Year 2009-10.

56. Deviation from norms.

56.1. Tariff for sale of electricity by the Generating Company may

also be determined in deviation of the norms specified in these

Regulations subject to the conditions that-

(a) The levelised Tariff over the Useful life of the Project , calculated

based on the discounting factor as notified by the CERC from

time to time for the Projects under Section 63 of the Act, on the

basis of the norms in deviation does not exceed the levelised

Tariff calculated on the basis of the norms specified in these

Regulations; and

(b) Any deviation shall come into effect only after approval by the

Commission, for which an application shall be made by the

Generating Company.

57. Power to remove difficulties

57.1. If any difficulty arises in giving effect to any of the

provisions of these Regulations, the Commission may, by

general or special order, do or undertake or direct the Generating

65

Page 66: Appeal No. 170 of 2010

Company to do or undertake things, which in the opinion of the

Commission are necessary or expedient for the purpose of

removing the difficulties.

58. Power to Amend

58.1. The Commission may, at any time add, vary, alter, modify

or amend any provisions of these Regulations.

59. Repeal and Savings

59.1. The Regulations namely “Madhya Pradesh Electricity

Regulatory Commission (Terms and Conditions for determination

of Generation Tariff), Regulations, 2005 (G-26 of 2005)”

published vide Notification No.2932/MPERC/2005 in the Gazette

dated 23/12/2005 and read with all amendments thereto, as

applicable to the subject matter of these Regulations is hereby

superseded.

59.2. Nothing in these Regulations shall be deemed to limit or

otherwise affect the inherent powers of the Commission to make

such orders as may be necessary for ends of justice to meet or

to prevent abuses of the process of the Commission.

59.3. Nothing in these Regulations shall bar the Commission

from adopting, in conformity with the provisions of the Act, a

66

Page 67: Appeal No. 170 of 2010

procedure, which is at variance with any of the provisions of this

Regulation, if the Commission, in view of the special

circumstances of a matter or class of matters and for reasons to

be recorded in writing, deems it necessary or expedient for

dealing with such a matter or class of matters.

59.4. Nothing in these Regulations shall, expressly or impliedly,

bar the Commission dealing with any matter or exercising any

power under the Act for which no Regulations have been framed,

and the Commission may deal with such matters, powers and

functions in a manner it thinks fit.”

36. Now we quote some of the provisions of the Act dealing with

Tariff in Part VII which will be relevant for our purpose.

“61. The Appropriate Commission shall, subject to the

provisions of this Act, specify the terms and conditions for the

determination of tariff, and in doing so, shall be guided by the

following, namely:-

(a) the principles and methodologies specified by the Central

Commission for determination of the tariff applicable to

generating companies and transmission licensees;

(b) the generation, transmission, distribution and supply of

electricity are conducted on commercial principles;

67

Page 68: Appeal No. 170 of 2010

(c) the factors which would encourage competition, efficiency,

economical use of the resources, good performance and

optimum investments;

(d) safeguarding of consumers' interest and at the same time,

recovery of the cost of electricity in a reasonable manner;

(e) the principles rewarding efficiency in performance;

(f) multi year tariff principles;

(g) that the tariff progressively reflects the cost of supply of

electricity and also, reduces and eliminates cross-subsidies

within the period to be specified by the Appropriate

Commission;

(h) the promotion of co-generation and generation of electricity

from renewable sources of energy;

(i) the National Electricity Policy and tariff policy:

Provided that the terms and conditions for determination of

tariff under the Electricity (Supply) Act, 1948, the Electricity

Regulatory Commission Act, 1998 and the enactments

specified in the Schedule as they stood immediately before

the appointed date, shall continue to apply for a period of

one year or until the terms and conditions for tariff are

specified under this section, whichever is earlier.

Determination of Tariff.

68

Page 69: Appeal No. 170 of 2010

Determination of tariff by bidding process.

62. (1) The Appropriate Commission shall determine the tariff in

accordance with provisions of this Act for –

(a) supply of electricity by a generating company to a distribution

licensee:

Provided that the Appropriate Commission may, in case of

shortage of supply of electricity, fix the minimum and maximum

ceiling of tariff for sale or purchase of electricity in pursuance of

an agreement, entered into between a generating company and

a licensee or between licensees, for a period not exceeding one

year to ensure reasonable prices of electricity;

(b) transmission of electricity ;

(c) wheeling of electricity;

(d) retail sale of electricity.

Provided that in case of distribution of electricity in the same area

by two or more distribution licensees, the Appropriate

Commission may, for promoting competition among distribution

licensees, fix only maximum ceiling of tariff for retail sale of

electricity.

(2) The Appropriate Commission may require a licensee or a

generating company to furnish separate details, as may be

specified in respect of generation, transmission and

distribution for determination of tariff.

69

Page 70: Appeal No. 170 of 2010

(3) The Appropriate Commission shall not, while determining the

tariff under this Act, show undue preference to any

consumer of electricity but may differentiate according to the

consumer's load factor, power factor, voltage, total

consumption of electricity during any specified period or the

time at which the supply is required or the geographical

position of any area, the nature of supply and the purpose

for which the supply is required.

(4) No tariff or part of any tariff may ordinarily be amended more

frequently than once in any financial year, except in respect

of any changes expressly permitted under the terms of any

fuel surcharge formula as may be specified.

(5) The Commission may require a licensee or a generating

company to comply with such procedures as may be

specified for calculating the expected revenues from the tariff

and charges which he or it is permitted to recover.

(6) If any licensee or a generating company recovers a price or

charge exceeding the tariff determined under this section,

the excess amount shall be recoverable by the person who

has paid such price or charge along with interest equivalent

to the bank rate without prejudice to any other liability

incurred by the licensee.

70

Page 71: Appeal No. 170 of 2010

63. Notwithstanding anything contained in section 62, the

Appropriate Commission shall adopt the tariff if such tariff

has been determined through transparent process of bidding

in accordance with the guidelines issued by the Central

Government.

Procedure for tariff order.

64. (1) An application for determination of tariff under section

62 shall be made by a generating company or licensee in

such manner and accompanied by such fee, as may be

determined by regulations.

(2) Every applicant shall publish the application, in such

abridged form and manner, as may be specified by the

Appropriate Commission.

(3) The Appropriate Commission shall, within one hundred and

twenty days from receipt of an application under sub-

section (1) and after considering all suggestions and

objections received from the public,-

(a) issue a tariff order accepting the application with such

modifications or such conditions as may be specified in that

order;

(b) reject the application for reasons to be recorded in

writing if such application is not in accordance with the

71

Page 72: Appeal No. 170 of 2010

provisions of this Act and the rules and regulations

made thereunder or the provisions of any other law for

the time being in force:

Provided that an applicant shall be given a reasonable

opportunity of being heard before rejecting his

application.

(4) The Appropriate Commission shall, within seven days

of making the order, send a copy of the order to the

Appropriate Government, the Authority, and the

concerned licensees and to the person concerned.

(5) Notwithstanding anything contained in Part X, the tariff

for any inter-State supply, transmission or wheeling of

electricity, as the case may be, involving the territories of

two States may, upon application made to it by the

parties intending to undertake such supply, transmission

or wheeling, be determined under this section by the

State Commission having jurisdiction in respect of the

licensee who intends to distribute electricity and make

payment therefor:

(6) A tariff order shall, unless amended or revoked, shall

continue to be in force for such period as may be

specified in the tariff order.”

72

Page 73: Appeal No. 170 of 2010

37. We have quoted some of the provisions of the Regulations of the

State Commission and that of the Act. The Commission is a

creature of the statute and apart from the provisions of the Act

we have quoted, some other provisions of the Act are there

which are located in Part –IV, Part-V and Part-VI of the Act. Part

–IV deals with the licensing, Part –V deals with transmission and

Part-VI deals with distribution of electricity. Generation,

transmission, distribution and trading are the four components of

the electrical system under the Act. If we look at Section 86

which occurs in Part-X of the Act, we can easily find that this

Section which governs the other provisions of the Act so far as

the State Commission is concerned is a conglomeration of

administrative, legislative, judicial and advisory power of the

State Commission. These four jurisdictions are vested with the

Commission which exercises its powers under any of the

jurisdictions in terms of the statute. Following the reforms in the

electricity sector, there has been induction of the private sector in

the electricity business and in terms of the Act, either the Central

Government or the State Government can no longer be identified

with any utilities. Section 108 is a provision giving power to the

State Government to give any direction only in the matter of

policy and that too involving public interest to the Commission,

save which the Commission is statutorily an independent body

vested with the aforesaid jurisdictions, and so far as the Tribunal

is concerned it has jurisdiction to hear appeal against the order of

the Commission that is passed primarily under Part VII of the

Act. The Tribunal vis-à-vis the Commission has no legislative

73

Page 74: Appeal No. 170 of 2010

relation to perform. Basically, it exercises judicial function and

that apart there is a provision in Section 121 that gives power to

the Tribunal to issue such orders, instructions or directions to any

appropriate Commission for the performance of its statutory

functions under the Act. Be it noted here that this power is

different from appellate power which is vested in Section 111.

38. We could not be in agreement with Mr. Ramachandran that it is

not a case of direction to the Commission to bring about an

amendment of the notified regulations but it is simply a case

asking the Commission by the Tribunal to relax the norms. It

has to be made clear that it is not a case where we have been

asked to adjudicate upon a tariff determination order in respect of

the generating stations of the appellant for any particular financial

year. So far no tariff order has yet been passed by the

Commission. The tariff application is pending before the

Commission for hearing and disposal, it being application no. 54

of 2009. During the pendency of the tariff determination

application the appellant filed petition no. 08 of 2010 praying for

amendment of the notified Regulations on the ground that the

norms set out in the Regulations were on the part of the

appellant being impossible to reach and that petition has been

disposed of by the Commission through a rejection order on the

grounds which we have set out above. Therefore, before us

there is no concrete case for adjudication in respect of tariff for

the appellant; the Commission has notified its Regulations

dealing with how to determine tariff and a set of parameters has

74

Page 75: Appeal No. 170 of 2010

been laid down in respect of the generating stations of the

appellant and we are asked by the appellant to examine whether

the norms fixed by the Commission in the tariff Regulations by

virtue of the legislative power of the Commission were pragmatic

or otherwise so that the Commission could be asked to modify

the regulations in order that the norms may be relaxed to the

advantage of the appellant. We ask ourselves: what is meant

when we say that the Commission should be asked only to

modify the norms ? The relaxation of norms or modification

thereof to the advantage of the appellant irrespective of the

question whether such relaxation or modification would or would

not be justified is possible only when the notified Regulation is

again notified by bringing about an amendment thereof.

Unquestionably, the Commission has power to amend, modify,

rescind or repeal regulation in the same manner as the Central

legislature or State legislature derives its authority from the

Constitution to enact a law, to modify or amend, or rescind or

repeal; and any of these functions falls within the legislative

jurisdiction of the Commission. Therefore, what we are really

asked to do is to direct the Commission to bring out the

amendment of the regulation. When we ask the Commission to

amend its regulations it virtually implies that the regulations

framed by it is deficient, short of achieving its purpose and

defeats the objectives of the Act, the national tariff policy and the

national electricity policy. We do not apprehend that when we

say so nobody will say that we are not exercising the power of

judicial review the very existence of which with the Tribunal has

75

Page 76: Appeal No. 170 of 2010

been negated by the decision of the Hon’ble Suprene Court in

the PTC case which we have already noted and which really is

not there in the Act or the Constitution. We cannot conceive of

the source of the power of judicial review in the statute since the

power is a constitutional power that enables a judicial authority

to examine the validity of a legislation or a delegated legislation.

39. Be that as it may, let us examine as to which of the sources of

power, namely, a) power to remove difficulties, b) power to relax

norms, c) exercise of inherent powers and d) power to amend

the regulations apart from the power of Judicial Review will be of

aid to the appellant and in which particular circumstance. Mr.

Ramachandran has taken us to a good number of decisions

which we shall now consider. He has referred to Utter Pradesh

Power Corporation Limited Vs. National Thermal Power

Corporation of India Limited and others reported in (2009) 6 SCC

235. One important observation made at paragraph 56 of the

judgment is that:

“It is now a well settled principle of law that a subordinate

legislation validly made becomes a part of the Act and should be

read as such.”

It has been held that power to regulate may include the power to

grant or refuse to grant a licence, a power to tax or exempt from

taxation, a power to increase tariff or a power to decrease the

tariff having relied on the decision in Hotel & Restaurant

76

Page 77: Appeal No. 170 of 2010

Association Vs. Star India Pvt. Ltd., (2006) 13 SCC 753, it was

held the jurisdiction was not only to fix tariff but also laying down

terms and conditions for providing services . In this decision it

was held at paragraph 66 that the jurisdiction of the Appellate

Tribunal is wide, it being an expert Tribunal, and it can interfere

with the finding of the Commission both on fact as also on law. If

we have correctly understood the submission of Mr.

Ramachandran, it would appear that he seeks to stretch to the

point that because of being it an expert Tribunal having appellate

jurisdiction it can direct the Commission to relax the norms, to

amend the Regulations or make an order directing the

Commission to remove the difficulties; and according to Mr.

Ramachandran power to remove difficulties vested with the

Government in a statute is not the same thing as power to

remove difficulties vested in a Commission. To our reasoning,

the appellate jurisdiction of the Tribunal is only exercisable in

terms of the statute that created the Tribunal. Certainly as a first

appellate forum it can examine facts as also the law. The

exercise of the function of the appellate Authority must be within

the domain of the law which has been engrafted in Section 111of

the Act. It is not deniable that the Commission has manifold

powers, namely, administrative, supervisory, legislative and

adjudicatory but each power, according to us, must be exercised

at appropriate field; simply because a Commission has many

powers, it cannot be said that while exercising one power it

oversteps its limit in that power and assumes another jurisdiction.

This was what has been exactly said in WB Electricity

77

Page 78: Appeal No. 170 of 2010

Regulatory Commission Vs. CERC reported in (2002) 8 SCC 715

which has also been relied on by Mr. Ramachandran. In this

case, the High Court while hearing appeal in its appellate

jurisdiction vested in the statute, since repealed, exercised the

writ jurisdictional power under Article 226 which was deprecated

by the Hon’ble Supreme Court. What we want to emphasise is

that this Tribunal would exercise power only to the extent as is

conferred on it. There is no difference with Mr. Ramchandran’s

submission that while determining the tariff, the Commission has

to bear in mind the principles laid down in Section 61 and that the

tariff has to be determined on cost plus basis so that a

reasonable return on investment enures to the investors. In this

connection Mr. Ramachandran argued that there cannot be any

regulation providing for various terms and conditions in absolute

manner without exercising discretion like exemption, relaxation,

deviation, removing difficulties etc. Since the power to exercise

all these things or any of them is there in the regulations itself,

we are nobody to question the legitimacy of such provisions

therein.

40. Mr. Ramachandran took us to the recent judgment of the

Hon’ble Supreme Court, namely, PTC India Ltd. Vs. CERC

reported in (2010) 4 SCC 603 . We have earlier noted that one

of the issues which the Hon’ble Supreme Court was invited to

address to was whether Section 121 of the Electricity Act gives

power to the Tribunal to examine validity of a regulation and the

Hon’ble Court had said it can be examined by Judicial Review

78

Page 79: Appeal No. 170 of 2010

under Article 226 of the Constitution. Mr. Ramachandran does

not dispute this proposition of law and does not ask us to

exercise any such power which is really not there. Now,

importantly from paragraph 25 onwards of the judgment, the

Hon’ble Supreme Court has observed that the Commission has

many jurisdictions, legislative, advisory, quasi-judicial as vested

in different provisions of the Act. At paragraph 49 of the

judgment, their Lordships have said that decision making and

regulation making functions are both assigned to CERC and

price fixation exercise is really legislative in character unless by

the terms of a particular statute it is made quasi-judicial as in the

case of tariff fixation under Section 62 which is appellable under

Section 111 although Section 61 is an enabling provision for the

framing of regulations by the Commission. At para 52 of the

judgment, their Lordships have observed that a distinction must

be made between delegation of legislative function and

investment of discretion to exercise a particular discretionary

power by a statute. The ruling in this PTC case has been so far

as the instant appeal is concerned is not purely a matter of

academic interest but also decisive.

41. Mr. Ramachandran then took us to the decision in Premium

Granites & Anr. V. State of Tamil Nadu & Ors. (1994) 2 SCC 691,

it was a case where the main question was whether Rule 39 of

the Mineral Concessional Rules is legal and valid. It was struck

down by the Madras High Court, while the Hon’ble Supreme

Court upheld the vires of the rules saying that it does not offend

79

Page 80: Appeal No. 170 of 2010

the Act or the Constitution. This Rule 39 dealt with power of

relaxation which has been a matter of concern for the client of

Mr. Ramachandran. Their Lordships held at paragraphs 48, 49,

50 and 51 that power of relaxation as was there in Rule 39 has to

be exercised for mineral development and in public interest after

recording reasons therefor and such exercise of power must

exhibit reasonableness of State action. It was further held that it

is not the domain of the Court to embark upon uncharted ocean

of public policy in an exercise to consider whether the particular

public policy is wise or a better policy can be achieved and such

exercise must be left to the discretion of the executive and the

legislative authorities as the case may be. (Emphasis ours)

According to Mr. Ramachandran, we must ask the Commission

to exercise such power in its legislative jurisdiction because what

was basically prayed before the Commission was to relax the

norms by amendment of the regulations. There cannot be any

second proposition to the proposition of law as laid down by the

Hon’ble Supreme Court. The question whether we would have

legitimacy to ask the Commission to amend the regulation is

exactly the question before us. To our mind this decision does

not help the appellant. If the discretion to relax is not arbitrary, it

cannot be read down. If the discretion is based on reason and

objectivity while refusing to relax the norm yet keeping in mind

the objectives of the Act and the National Tariff Policy then it is

not for the Tribunal to interfere with the discretion and ask the

Commission in exercise of academic pursuit without before us

any order determining tariff application and to substitute the

80

Page 81: Appeal No. 170 of 2010

Tribunal’s reason to be the reason of the Commission. This to

our mind is not the ratio decidendi of the decision, on the

contrary the Hon’ble Court held that the Court must not embark

upon the public policy.

42. Mr. Ramachandran then took us to the case of Hindustan Paper

Corporation Limited Vs. Government of Kerala ( 19860 3 SCC

398. This was a case where the question was whether the

power of exemption under Section 6 of Kerala Forest Produce

(Fixation of Selling Price) Act 1976 was ultra vires or not. The

Kerala High Court held it was invalid, but the Hon’ble Supreme

Court ruled in favour of validity. Here it has been observed in

paragraph 9 of the decision that it is well recognized and

constitutionally accepted legislative practice to incorporate

provision conferring the powers of exemption on the Government

in such statutes and such exemption has to be in public interest.

It is not a case before us as to whether the Commission can

exercise any power of exemption nor we are called upon to

examine whether such exemption was rightly granted or not. Be

it noted here that the exemption talked of by the Hon’ble

Supreme Court in the instant case or the relaxation talked of in

the Premium Granite case is exemption or relaxation vested in

the Government but here in the instant appeal before us such

relaxation is asked for to be exercised by the Commission in its

legislative jurisdiction.

81

Page 82: Appeal No. 170 of 2010

43. Now Mr. Ramachandran says that in the treatise of the learned

author Mr. M.P. Jain in Cases and Materials on India

Administrative Law – 1994 Edition volume 1, Page 117, there is a

deliberation on removal of difficulty clause. This clause is better

known as Henry VIII clause the necessity of which arises to

remove the difficulties which were not foreseen at the time of

passing the Act, and it is left to the executive to remove any

such. Mr Ramchandran lays emphasis to the sentence where it

has been observed that “ At times, ‘removal of difficulty’ clause

may empower the Government to amend the parent Act or any

other Act with a view to bring the parent Act into full operation .”

It is hardly deniable that a tariff regulations must contain power to

remove the difficulties, to relax, to amend the regulations, to

obviate from the norms and to exercise inherent power if the

facts and circumstances justify exercise any such power.

44 Next we were shown the decision in Hindusthan Steels Ltd. Vs

A.K.Roy, (1969)3 SCC 513 which according to us is totally out

context because whether an Industrial Tribunal while dealing with

a case of termination of an employee from an industrial concern

has power to direct reinstatement or order for compensation, and

the Hon’ble Supreme Court ruled that such discretion can be

exercised by the Tribunal judicially.

45. The principle governing the use of discretion was again

considered in de Smith’ Judicial Review of Administrative

Action,4th. Edition, page285 where it has been observed that the

82

Page 83: Appeal No. 170 of 2010

authority in which a discretion is vested can be compelled to

exercise that discretion, but not to exercise it in any particular

manner, and in general a discretion must be exercised only by

the authority to which it is committed.

46. In support of the argument that the Commission while rejecting

the petition for amendment of the Regulations so as to suit the

convenience of the appellant has not assigned any reason for

such rejection Mr. Ramchandran has relied on the authority in S.N.

Mukherjee Vs. Union of India reported in (1990 ) 4 SCC 594 where

it has been held that an administrative authority while exercising

quasi-judicial function must record reason for its decision so that it

could be understood that the Authority has given due

consideration to the points in controversy and that to show clarity

and avoid arbitrariness. We must observe that whether in

ultimate terms we accept the appeal or not, we cannot say that the

order impugned is without any reason. Reasons have been given

which are well understood and it can never be alleged that the

order lacks transparency and objectivity, no matter whether one

agrees to it or not. It is not the requirement of law, as this

decision has held, that as in a Court of law the reason should be

elaborate. Therefore, this decision is of no avail to Mr.

Ramachandra’s client.

47. In State of Karnataka & Anr. Vs. R. Vivekanand Swamy and

Another 2008 (5) SCC 328 the question was of relaxation by the

Government of the medical reimbursement rules in contravention

83

Page 84: Appeal No. 170 of 2010

of which a Government employee got himself treated in a hospital

of his own choice which the regulations did not permit but the

Government relaxed the rule to mitigate the exigencies of

circumstances. This decision is of no avail to any of the parties

here. The rider was that such discretion to deviate from the rules

must not be arbitrary.

48.. Mr. Ramchandran rightly submits that if an Authority which is

vested with a discretion does not exercise the discretion, it would

amount to fettering discretion or fettering jurisdiction in support of

which he relies on Foulke’s – Administrative Law, Eighth Edition,

Pg. 217 and Bennion on Statutory Interpretation, Fifth

Edition, Indian reprint Pg. 90. The bottom-line is that if power of

discretion is there, it may be exercised and such exercise must be

judiciously done meaning thereby that power may not be refused

when exercise of such power is warranted.

49. While elaborating this above argument, Mr. Ramachandran refers

to 115 of the Civil Procedure Code, 1908 dealing with revision.

We fail to understand how Section 115 which has drastically been

amended does have any level playing field in the circumstances.

It is the cardinal principle of law that if the Court refuses to

exercise jurisdiction vested in it the Court having power of revision

has to revise the order or when the Court exercises jurisdiction not

vested in it, then also equally the power of revision lies. We are

quite conscious of this position. Now in this connection Mr.

Ramachandran takes us to WBERC Vs. CESC Ltd. (2002) 8 SCC

84

Page 85: Appeal No. 170 of 2010

715 where at paragraph 102 of the judgment it was observed that

the Hon’ble Supreme Court felt the necessity of having an expert

body to act like a Tribunal to examine the orders of the

Commission since the matter is technical. This observation of the

Hon’ble Supreme Court has inspired Mr. Ramachandran to say

that the appellate power under Section 111 is no less wider than

the power of judicial review which is exercised under Article 226 of

the Constitution. Respectfully to the learned counsel, we are

unable to concede to this position because in this case itself the

Supreme Court took exception to the manner in which the Calcutta

High Court exercised the power of writ jurisdiction while hearing

appeal under Section 27 of the Electricity Regulatory Commission

Act, 1998. It was observed that the appellate power and the

power of judicial review are distinct. It is important to remember

here that in this decision we have been reminded by the Supreme

Court that there is weighty authority for the proposition that a

Tribunal which is a creature of a statute cannot question the vires

of the provisions under which it functions and quoting the decision

of Dhulabhai Vs. State of M.P. AIR 1969 SC 78 it was held that

challenge to the provisions of a particular act as ultra vires cannot

be brought before the Tribunal constituted under that Act and even

the High Court cannot go into that question on a revision or

reference from the decision of the Tribunals.

50. Mr. Ramachandran himself has cited Hilaire Barnett – Constitutional

and Administrative Law, first Indian reprint, 1996, Pg. 716 wherein

it was observed that judicial review is distinguishable from an

85

Page 86: Appeal No. 170 of 2010

appeal against a decision. An appeal is made both on the law

and the facts, while judicial review by contrast is concerned with

the manner in which the decision maker has applied the relevant

rules. It has been observed in this book that judicial review

derives from the courts inherent powers to keep decision making

bodies within the bounds of their powers, and to provide remedies

for abuse of power, and its purpose is not to substitute a decision

of the Court for the decision of the administrative body.

51. Again, the learned author Bennion in his treatise on Statutory

Interpretation, 5th Edition, Indian Reprint, Pg. 142 writes that the

distinction between original and appellate jurisdiction is an

important one, while in the former the enforcement agency gives a

decision upon hearing the counsel, while in the latter the body has

to carefully consider the reasons and if it involves an improper

exercise of discretion the appellate body may substitute its own

view. In a word, appellate jurisdiction is a statutory jurisdiction

which is competent to examine both fact and the law but which will

not normally interfere with the exercise of the judges discretion

except, however, on the grounds of law.

52. In Cellular Operators Association of India and Others Vs. Union of

India and Others reported in (2003) 3 Supreme Court Cases 186

the scope and power of the Telecom Regulatory Authority of India

was considered. Mr. Ramachandran interprets this judgment to

say that the Appellate Tribunal for Electricity which is as expert

body as the Appellate Tribunal under Telecom Regulatory

86

Page 87: Appeal No. 170 of 2010

Authority of India Act, 1997 can exercise so much of power to

make any order while examining legality, propriety or correctness

of a decision or order or direction of a Commission and in that way

it surpasses the power of judicial review. This Tribunal is a

creature of statute as other Tribunals are. Each functions in its

own orbit as defined in the Act creating it. In the Telecom

Regulatory Appellate Tribunal, there is Section 15 according to

which power of that appellate Tribunal has been found by the

Hon’ble Supreme Court to be quite wide as has been indicated in

the statute itself and the decisions of the Supreme Court dealing

with the power of Court exercising appellate power or original

power will have no application for limiting the jurisdiction of the

appellate Tribunal under that Act. But one Hon’ble Judge writing

separate opinion while concurring observed that when jurisdiction

upon a Court or Tribunal is conferred by statute the same has to

be construed in terms thereof and not otherwise, while the power

of Judicial Review of the Supreme Court as also the High Court

stand on a different footing.

53. Now, Mr. Ramachandran refers to five decisions of this Tribunal,

namely, Maharashtra State Power Generation Co. Ltd. Vs.

Maharashtra Electricity Regulator Commission & Ors. (2010 ELR

(APTEL) 0189, NTPC Ltd. S. Madhya Pradesh State Electricity

Board 2007 ELR APTEL 7, BSES Rajdhani Power Ltd. Vs. Delhi

Electricity Regulatory Commission (2009) ELR APTEL 880, Uttar

Pradesh Rajya Vidut Utpadan Nigam Ltd. Vs. Uttar Pradesh

Electricity Regulatory Commission and Ors. (Appeal No. 96 of

87

Page 88: Appeal No. 170 of 2010

2008) and Gujarat State Electricity Corporation Ltd. Vs. Gujarat

Electricity Regulatory Commission and Ors. (Appeal No. 129 of

2006). In the Maharashtra case, the appellant submitted its

application for approval of ARR and tariff petition for FY 2005-06

and 2006-07. The Commission passed an order determining the

tariff under the tariff regulation and an appeal was preferred

against that order. In course of hearing and disposal, this

Tribunal felt the necessity of an independent study to consider the

operating parameters observing that the Commission has power to

revise the parameters by amending the tariff regulations. Nothing

more was done in that case. The Tribunal did not make any order

directing the Commission to amend the regulations. It simply

directed an exercise of study to examine the feasibility of coming

down from the norms. To our understanding, this decision does

not lay down any proposition of law and the questions we are

confronted with were not posed thereat, and here it is a case

where we are not hearing any appeal against any order

determining tariff; we are called upon to hear an appeal against

alleged insufficiency, incorrectness of the regulations themselves

on the ground that the norms set down there should be amended.

In the NTPC case it was observed at page 293 which is the ratio

decidendi of the case that regulation 13 of the CERC Terms and

Conditions of Tariff Regulations, 2004 empowers the Commission

to vary the provisions of the regulations on its own motion or on an

application made before it as power to relax is there with the

Commission. Notably, in the two cases observations were made

in course of hearing and disposal of the appeals that arose out of

88

Page 89: Appeal No. 170 of 2010

orders determining tariff which is not the case with us. In BSES

Rajdhani case, the Tribunal held that the Commission has right to

reconsider the target that has been set and if necessary they may

amend regulation. In Uttar Pradesh Rajya Vidyut Utpadan Ltd

case upon factual analysis direction was made to the Commission

by this Tribunal to re-determine the parameters for the year 2006-

07 and 2007-08 and to undertake study for renovation and

modernisation of older plants. In Gujrat State Electricity

Regulation case, the Tribunal made certain directions to modify

the generation tariff on certain points set out in the body of the

judgment. None of the decisions of this Tribunal which have

been relied upon by the appellant does render any real assistance

to us because in each of the cases the Tribunal felt while hearing

appeal on determination of tariff, which we are not doing, that the

Commission may in consideration of facts and circumstances of

each particular case may go on re-determine tariff after varying

different parameters by undertaking study. In none of the cases

this Tribunal directed any of the Commissions to amend the

regulations so as to suit the parameters of the Generating

Companies.

54. Having studied the decisions relied on by Mr. Ramachandran, we

are to consider whether we should ask the Commission to

exercise the power of removal of difficulties, or to relax or to

amend the regulation or to exercise inherent powers of the

Commission. At the cost of repetition it has to be observed that in

the peculiar situation in which we are beset with if we ask the

89

Page 90: Appeal No. 170 of 2010

Commission to exercise the power of removal of difficulty, or to

relax, or to exercise inherent power, we would be directing the

Commission indirectly which we cannot do directly that it should

amend its regulation. What we cannot ask the Commission to do

directly, we cannot ask to do indirectly and it is the place now to

see that as to under what circumstances and in which jurisdictions

the power to remove difficulties or to power to relax or to exercise

inherent jurisdiction can be exercised. The question is whether the

power to remove difficulties can be exercisable in legislative

jurisdiction or the power to relax or the power to exercise the

inherent power to do justice can be exercised in the legislative

jurisdiction. Importantly, what the appellant desires is an order of

the Tribunal so that the Commission in its legislative jurisdiction

exercises legislative power to amend its regulations which power

definitely is there with the Commission, of course.

55. We fail to be in agreement with Mr. Ramachandran when he says

that power to remove difficulties as is ordinarily available in statute

enacted by Parliament is not the same power as the power to

remove difficulties as is there in a regulation available to the

Commission. But Mr. Ramachandran is right when he says that

such power is vested in the Commission to remove anomalies and

difficulties. To our understanding, the exercise to remove

difficulties cannot have different connotation in different statutes or

distinguishable between statute and regulation. If we closely read

Regulation 57 of the MYT Regulations, 2009 we find that power to

remove difficulties which is given to the Commission is basically an

administrative power not a legislative power which the

90

Page 91: Appeal No. 170 of 2010

Commission may by general or special order do or undertake or

direct a generating Company to do or undertake things which the

Commission find necessary for the purpose of removing the

difficulty. This power is exercisable only to ensure that the Act is

implemented and it is in furtherance of the Act that the power to

remove difficulties is conferred. It is only to give effect to the

provisions of the regulations that this power is exercised. It has

been rightly argued by Mr. Sanjay Sen, learned Advocate for the

Commission that the power to remove difficulty does not

contemplate removal of hardship that may arise as a result of

giving effect to the regulation. The decision in M.U.Sinai Vs

Union of India (1975) 2 SCR 640 is pertinent. In this decision it

has been held that in order to obviate the necessity of approaching

the legislature for removal of every difficulty encountered in the

enforcement of statute, the legislature some times thinks it

expedient to invest the executive with a very limited power to make

minor adaptations and peripheral adjustments in the statute for

making its implementation effective without touching its substance.

It has been observed that :

“The existence or arising of a difficulty is the sine qua non for the

exercise of power. If this condition precedent is not satisfied as

an objective fact, the power under this clause cannot be invoked

at all. Again, the “difficulty” contemplated by the clause must be

a difficulty arising in giving effect to the provisions of the Act and

not a difficulty arising aliunde, or an extraneous difficulty.

Further, the Central Government can exercise the power under

the clause only to the extent it is necessary for applying or giving

91

Page 92: Appeal No. 170 of 2010

effect to the Act etc., and no further. It may slightly tinker with

the Act to round off angularities, and smoothen the joints or

remove minor obscurities to make it workable, but it cannot

change, disfigure or do violence to the basic structure and

primary features of the Act. In no case, can it, under the guise of

removing a difficulty change the scheme and essential

provisions of the Act ”.

56. lf it is a legislative function to remove difficulty like amending

regulation, no direction can be passed by the Tribunal to the

delegated Authority to exercise legislative power. Mr Sanjay Sen,

learned counsel for the Commission takes us to the words of

regulation 57.1 to submit that the power to remove difficulties

which lies with the Commission is exercisable only to give effect

to the provision of the Regulations . Now to direct the generating

company to do or undertake things or itself to do or undertake

by general or special order implies that this power to remove

difficulties is intended to be exercised from the administrative

domain of the Commission instead of exercising the legislative

jurisdiction. Mr. Sen relies on M.U. Sinai V/s Union of India,

(1975) 2 SCR 640 which we have already discussed. It is

submitted by Mr. Sen that before the Commission the appellant

did not rely on this power to remove difficulty clause, what was

prayed for before the Commission was amendment of the

Regulations. It is submitted that no direction can be passed by a

Tribunal to the delegated authority to exercise legislative power

92

Page 93: Appeal No. 170 of 2010

57. Mr. Sen relied on the West Bengal Regulatory Commission Vs

CESC (ibid) to argue that the question of vires cannot be argued

before the Tribunal. He refers to the decision of the Honb’le

Supreme Court in Raleigh Investment Co. Ltd. Vs Governor

General in Council reported in ILR(1944)1 Cal 34 , United Motors

(India) Ltd. Vs State of Bombay reported in (1953) 55 ,Bomb. LR

246, M.S.M.M. V/s. Meyyappa Chettiar V. ITO reported in II

(1964)54 ITR I51(Mad) & K.S. Venkatraman & Co. (P) Ltd. Vs

State of Madras(ibid) where it has been held that there is

weighty authority for the proposition that a Tribunal which is

creature of a Statute cannot question the vires of the provisions

under which it functions. Mr. Sen refers to one of our decisions

in Navyeli Lignite Corporation Ltd. Vs Tamil Nadu Electricity

Board and Ors. Where we have observed as follows

“9. In view of the aforesaid decision of the Supreme Court, which

is directly on the point, we have no hesitation in holding that the

Regulations framed under Sections 61 & 178 of the Electricity

Act 2003, are in the nature of subordinate legislation and we

have no jurisdiction to examine the validity of the Regulations in

exercise of our appellate jurisdiction under Section 111 of the Act

of 2003. Even, under section 121, which confers on the Tribunal

supervisory jurisdiction over the Commission, we cannot

93

Page 94: Appeal No. 170 of 2010

examine the validity of the Regulations framed by the

Commission, as we can only issue orders, instructions or

directions to the Commission for the performance of its statutory

functions under the Act. It is not a case, where the Commission

has failed to perform its statutory functions. At this stage we may

also refer to the submission of Mr. Reddy that Regulation 16(i)

(c) of the Regulations applies to the appellant alone and

therefore the same cannot be in the nature of subordinate

legislation. It needs to be noted that Sub Clauses (a), (b) and (c)

of Sub Regulation (i) of Regulation 16 apply to various entities.

Regulation 16(i) (c) undoubtedly applies to the appellant alone

but this is in view of the special nature of the generating unit

established by the appellant. It is well settled that a legislation

can be framed for a single unit, entity or a person. The same

principle would apply to the framing of subordinate legislation in

respect of a single unit or entity or body, provided it can be

distinguished from others on the basis of its peculiar or distinctive

features. In any event we are bound by the decision of the

Supreme Court rendered in the West Bengal Electricity Board

case (Supra) as it directly deals with the nature of the

94

Page 95: Appeal No. 170 of 2010

Regulations notified by the Regulatory Commission in exercise of

its power conferred by Section 58 of the Electricity Regulatory

Commissions Act, 1998, a provision similar to sections 68 and

178 of The Electricity Act, 2003. None of the other decisions

cited at the bar deal with the Regulations framed under the

provisions of the Act of 1998 or the Act of 2003.

.Accordingly, on the first point we hold that the Regulations

framed under Electricity Act 2003, are in the nature of

subordinate legislation and on second point we hold that the

challenge to their validity falls outside the purview of the

Tribunal.”

58. Thus, Mr. Sen submits that since the regulations have the force

of a statute the appellate Court cannot go into the validity of the

regulations. In this connection, Mr. Sen also relied on the

decision in PTC India Ltd. Vs CERC (ibid) which we have

discussed earlier.

59. As regards the regulation 56 dealing with deviation from norms it

is submitted by Mr. Sen that regulation 56 and 56.1 of the MYT

Regulations, 2009 permit deviation from norms only under

95

Page 96: Appeal No. 170 of 2010

certain specific circumstances which have been elaborated in the

said provisions. We are in agreement with Mr. Sen that the

deviation from the norms contemplated under the MYT

Regulations, 2009 is only in relation to approval of Tariff under

Section 63 of the Act and the MYT Regulations, 2009 does not

conceive of deviation on any other ground apart from what have

been expressly provided for in the said regulations. We are

simply to observe that if in course of determination of tariff

pursuant to the application filed by the appellant the Commission

would think that the deviation from the norms was necessary

within the parameters as laid down in the regulations it can very

well do so, but for us in course of the present appeal in its

present form and prayer it is quite impossible that this regulation

56 can at all be invoked.

60. As regards power to amend which is given in regulation 58 it is

not deniable that the Commission undoubtedly has that power.

Section 21 of the General Clauses Act clearly provides that

power to issue notification, orders, rules, bye-laws includes a

power exercisable in the same manner to add or amend or vary

96

Page 97: Appeal No. 170 of 2010

or rescind. The question is whether we should direct the

Commission to exercise that power. It is not that we are hearing

and disposing of an application for determination of tariff because

such application is yet to be disposed of according to the Tariff

Regulations. What we are asked to do is to direct the

Commission to relax the norms in the MYT Regulations, 2009. It

is not that we are asked to direct the Commission to relax a

particular norms in exigencies of circumstances of a particular

case because in that case the Commission has the power to

deviate from the norms subject to the conditions stipulated in the

Regulations. To direct the Commission to deviate the norms for

particular generating station or stations of the appellant we mean

that such direction is possible so far as the Commission is

concerned to implement only by amendment of the MYT

Regulations. To repeat, it is not a case of prayer for deviation

from norms in a particular situation while keeping the legislation

in tact. Before we are prepared to direct the Commission to

deviate from the norms and that too by amendment of the

Regulations we would be required to observe that the norms or

parameters set out in the Regulations are unjust or improper or

97

Page 98: Appeal No. 170 of 2010

illegal so much so that amendment is necessary, which means

that we are travelling beyond our jurisdiction in asking the

legislature to bring about a regulation with amendment so as to

suit the need of the appellant. We are constrained to hold that by

going that path is none else the path of the judicial review

because we are to hold first that the law is deficient, unjust or

unlawful. In this connection, we may refer to the decision in

Narinder Chand Hemraj Vs Lt. Governor- Administrator of the

Union Territory of Himachal Pradesh reported in (1972) 1 SCR

940 wherein it was observed as follows:

“What the appellant really wants is a mandate e from the Court

to the Competent Authority to delete the concerned entry from

the schedule A and include the same in Schedule B. We shall

not go into the question whether the Government of Himachal

Pradesh on its own authority was competent to make the

alteration in question or not. We shall assume for our present

purpose that it had such a power. The power to impose a tax is

undoubtedly is a legislative power. That power can be exercised

by the legislature directly or subject to certain conditions, the

legislator may delegate that power to some other authority. But

98

Page 99: Appeal No. 170 of 2010

the exercise of that power whether by the legislature or by its

delegate is an exercise of legislative power. The fact that the

power was delegated to the executive does not convert that

power into an executive or administrative power. No Court can

issue a mandate to a legislature to enact a particular law.

Similarly, no Court can direct a sub-ordinate legislative body to

enact or not to enact a law which it may be competent to enact.

No Court can give a direction to Government to refrain from

enforcing a provision of law.

61. Similarly in Supreme Court Employees Welfare Association &

Ors. v/s Union of India reported in (1989) 4 SCC 187 the same

principle was reiterated in these words “There can be no doubt

that no Court can direct a legislature to enact a particular law.”

Similarly, when a executive Authority exercises a legislative

power by way of subordinate legislation pursuant to the

delegated authority of a legislature, such executive authority

cannot be asked to enact a law which he has been empowered

to do under the delegated legislative authority. On the same

principle it is impossible for the Tribunal to direct the sub

99

Page 100: Appeal No. 170 of 2010

ordinate legislative body to amend a subordinate legislation

under Section 111 of the Electricity Act. As we said earlier, what

we could not do directly we could not do indirectly.

62. With regard to exercise of inherent power which we have noticed

in regulation 59.2 it can fairly be stated that this inherent power

which is akin to Section 151 of the Civil Procedure Code is

exercisable only in adjudicatory jurisdiction, not in legislative

jurisdiction. The law is very clear on the subject. In Vinod Seth

v/s Devinder Bajaj & Anr. (2010) 8 SCC 1 the Hon’ble Supreme

Court refers to the decision in Padam Sen Vs. State of U.P.

reported in AIR 1961 SC 218, Manohar Lal Chopra vs Seth Hira

Lal reported in AIR 1962 SC 527, Nain Singh Vs Koonwarjee

reported in (1970) 1 SC 732 and held that Section 151 is

intended to apply where the Code does not cover any particular

procedural aspect, and interest of justice requires the exercise of

power to cover a particular situation. Section 151 is not a

provision of law conferring power to grant any substantive relief.

This power is exercisable not with reference to any matter duly

covered by a statute, nor any such order under inherent

100

Page 101: Appeal No. 170 of 2010

jurisdiction can be passed contrary to the provision of the law.

When the law is silent and adjudicatory process demands that a

particular order is necessary to prevent the abuse of the Court

then and then only Court’s inherent jurisdiction expressed in

Section 151 can be invoked. This is the essence of the decisions

quoted above and we find that regulation 59.2 has been drafted

exactly in line with Section 151 of the CPC.

63. It is very well settled that a delegated legislation is open to the

scrutiny of a Court on two grounds, namely a) it violates the

provisions of the Constitution and b) it violates the provisions of

the enabling Act. In the case of alleged violation of the enabling

Act the ground may include not only the cases of violation of the

substantive provision of the Act but also the cases of violation of

the mandatory procedure prescribed. It is Mr. Ramachandran’s

argument that the power of judicial review is not at all required in

as much as what is prayed for is simply deviation from norms as

contained in chapter III , Regulation 33, 34 , 35 and 36 of

Madhya Pradesh Electricity Regulatory Commission(Terms and

Conditions of generation Tariff)(Revision-I) Regulations, 2009

101

Page 102: Appeal No. 170 of 2010

(RG-26 I) of 2009), and if the Tribunal find that having regard to

the age of the generating units deviation from norm is required

then it may direct the Commission to do so by amendment. Mr.

Sen for the Respondent No.1 seriously disputes the submission

contending that it has far reaching consequences. Now,

howsoever simplistic the argument of Mr. Ramachandran

appears to be, it has cascading effect in this that in that case

the Tribunal which is mandated to hear appeal only under

Section 111 of the Act and in relation to a particular regulation

either of the Central Commission or State Commission has to

direct that since the regulation fails to achieve the objective of the

Act amendment of the regulation is called and direction has to be

given. In fact, Mr. Ramachandran commenced his argument with

the submission that the aforesaid Regulation, 2009 has not been

framed and enacted in compliance with the provisions of the Act,

particularly Section 61 thereof and accordingly it offends the Act.

The learned Counsel for the appellant brought to our notice a

decision of this Tribunal in appeal No. 36 of 2008 wherein this

Tribunal held as follows:

102

Page 103: Appeal No. 170 of 2010

“There is however, no bar on the Commission reconsidering the target and amend the regulation, if necessary. The target for MYT period needs to be set on the basis of losses at the beginning of the MYT period and not on the basis of the loss level on the date of privatization when the policy target period began. The consequences of failure or success in reaching the loss reduction target have already been borne by the licensee. Hence, reference to the initial level of loss at the time of privatization is not necessary. The Commission may itself consider the plea of any amendment in the target set in this regard in case the appellant makes out a case. There fore we direct that the appellant may make an appropriate representation to the Commission in this regard within one month hereof and that if a representation is so made the Commission shall dispose it in two months”

64. This decision was not passed on an appeal wherein challenge

was made to a regulation concerned. The Tribunal was

appropriately hearing an appeal under Section 111 of the Act. The

Tribunal did not give any direction to the Commission to consider

an amendment in positive term. Liberty was given to the appellant

to make a representation and in that case the Commission was

directed to dispose it in two months. Here an appeal has

purportedly been filed before us under Section 111 but the

substance is a challenge to the regulation on the ground that the

norms set out in that regulation was such as would defeat the

object of the Act and hence the Tribunal should direct the

Commission to bring about an amendment.

103

Page 104: Appeal No. 170 of 2010

65. Thus, to summarize our reasoning, power to remove difficulties is

a power given to the executive in order that the provisions of the Act

may be given effect to. The Executive may exercise such power by

executive order or in some cases they exercise legislative function

to bring about minor adjustments so that implementation of the Act

may be smoothened. Here in regulation 57 it is an express

language that the Commission may by general or special order itself

do or undertake or direct a generating company to do or undertake

things for the purpose of removing the difficulties. This provision in

the context of an express provision in regulate in 58 giving the

Commission power to amend is not attracted here.

66. In view of the decisions cited in the preceding paragraphs, we find

that this appeal fails to be an appeal under Section 111 of the Act.

The prayer in substance in this appeal has been one to give a

command to the Commission to effect amendment of the regulation

on the ground of alleged defects therein impairing the fulfilment of

the object of the Act which we are unable to subscribe to in as

much as to do so would entail in travelling beyond our jurisdiction.

104

Page 105: Appeal No. 170 of 2010

While saying so, we do not say that the Commission at no point of

time can exercise the powers conferred on it under regulation 56,

57, 58 and 59 in appropriate cases.

67. So far as regulation 56 is concerned, it appears that this regulation

is not so wide and generic that the Commission can deviate from

the norms as it would like to in any manner in appropriate case.

Moreover this regulation can be exercised in course of

determination of tariff of a generating company without bringing

about an amendment.

68. Inherent jurisdiction as found in regulation 59.2 and 59.3 cannot

be exercised in legislative domain. We repeat to say that in

course of determination of tariff the Commission may exercise its

inherent power in order to prevent the abuse of the process of the

Commission and to give complete justice in any given matter.

69. If we consider the factualities, we find that the appellant has

questioned the Commission’s wisdom in not considering the

paragraph No. 3.25, 3.26, 3.27, 24, 25 and 26 of the petition No. 8 of

105

Page 106: Appeal No. 170 of 2010

2010 reproduced from pages 38 to 43. The essence of the

contentions in the aforesaid paragraphs of the petition No. 8 of 2010

is that ( a) at SGTPS at Birsingpur FY 2009-10 there was partial load

shedding and acute shortage of coal ( b) the units of PH 1 are more

than 15 years old and placed under comprehensive R&M works,(c)

the ABL boilers and BHEL Turbine combination of units have design

deficiency compared to BHEL boiler/BHEL Turbine and the

performance of the two units of SGTTPS is superior to all India

average PUF of ABL boiler/BHEL Turbine sets of 200/210 MW

capacity, (d) as PAFM is linked to DC only zero result would be

achieved because of restrictions on release of water for generation

imposed by WRD, (e) non achievement of PAFM was due to the

provisions in respect of determination of tariff for hydro generating

stations. It is argued that the Commission has not dealt with this

situation.

70. It is important that we should give a look to what the Commission has

said. The Commission’s order is dated 26th May, 2010 impugned

herein. At the outset we are constrained to say that the argument

that the order is not a speaking one has to remain far from being

established. The Commission has noted (i) reasons for poor

106

Page 107: Appeal No. 170 of 2010

performance (ii) status of R&M work in all three thermal power

stations (iii) difficulties experienced in respect of the thermal power

stations by the appellant in FY 2009-10 for the reasons recorded by

the appellant (iv) the proposals of the appellant (v) the picture of the

operating norms prescribed for FY 2008-09 in earlier Regulation and

the relaxation being sought by the appellant for new control period at

two different stages station-wise in respect of the items covering

gross station heat rate, specific fuel oil consumption, auxiliary energy

consumption, (vi) appellant’s proposal for relaxation of norms also for

transit and handling losses of hydro power stations on the grounds as

mentioned in seriatim and then (vii)the Commission’s observations

which can be seen at para 33 of this judgment and we restrain from

repeating the same once again.

71. One may in his wisdom agree or disagree with the findings of the

Commission, but it cannot be said that the Commission’s detailed

order is without any reason. The Commission has assigned cogent

reasons for not agreeing to the appellant’s prayer for amendment of

the regulations. We in this Appellate Forum are mandated to hear

appeals under Section 111 of the Act and must not substitute our

107

Page 108: Appeal No. 170 of 2010

Jurisdiction to say that the Commission’s order for refusal to effect

amendment was justified. The norms set out in chapter III of the

Regulations are not so impractical, imprudent, absurd, manifestly

wrong and shockingly high and speculative that warrants interference

even if it is considered that this appeal under Section 111 against an

order of the Commission refusing to bring about an amendment is

absolutely justified. Again, to ask the Commission to make

amendment of the regulation would imply: (a) such direction is

possible in law in this appeal presented in the present form (b) the

regulations are not in keeping with the provisions of the Act and (c ) it

is quite permissible for this Tribunal to make such order, which to our

understanding is impermissible for the reasons we have set out

hereinabove. While observing so, we do not observe at the moment

that the Commission is powerless to do so. The Commission has

power to relax or deviate from the norms, but for the purpose of

deviating from the norms, they by virtue of regulation 58 can amend

the norms set out in Regulation 56 so that the norms are brought

down at a level comfortable to the appellant’s power plants. Mr.

Ramachandran has submitted that the norms of operation as laid

down in Regulation 33 are quite unusual inasmuch as they are

108

Page 109: Appeal No. 170 of 2010

specific power plants oriented and that is why the appellant made an

application for amendment of Regulation 33. Mr. Sen for the

Commission has submitted that as the appellant company is the

Government Company vested with the function of generation of

electricity and this company has number of power plants, the norms

had to be made different according to the age of the power plant.

The norms for the old generating stations have not been the same for

the new ones and this is for the convenience of the appellant and no

exception or challenge can be made to Regulation 33 of the

Regulations, 2009 only because of certain norms having been made

specific station-oriented. It has been submitted by Mr. Sen that the

Central Electricity Regulatory Commission does not make uniform

norms in the Regulations and they mention specifically the stations

which are not as young as the other ones established in recent times.

Having heard learned counsels for the parties, we do not think that

the Commission’s Regulation 33 can be taken exception to because

of specification of norms station-wise. In this connection, our

attention has again been invited by the learned counsel for the

Commission to the decision of this Tribunal in Neyveli Lignite

109

Page 110: Appeal No. 170 of 2010

Corporation Ltd. Vs. Tamil Nadu Electricity Board and others ( Appeal

Nos. 114 and 115 of 2005). This Tribunal has held as follows:

“At this stage we may also refer to the submission of Mr. Reddy that Regulation 16(i) (c) of the Regulations applies to the appellant alone and therefore the same cannot be in the nature of subordinate legislation. It needs to be noted that Sub Clauses (a), (b) and (c) of Sub Regulation (i) of Regulation 16 apply to various entities. Regulation 16(i) (c) undoubtedly applies to the appellant alone but this is in view of the special nature of the generating unit established by the appellant. It is well settled that a legislation can be framed for a single unit, entity or a person. The same principle would apply to the framing of subordinate legislation in respect of a single unit or entity or body, provided it can be distinguished from others on the basis of its peculiar or distinctive features. In any event we are bound by the decision of the Supreme Court rendered in the West Bengal Electricity Board case (Supra) as it directly deals with the nature of the Regulations notified by the Regulatory Commission in exercise of its power conferred by Section 58 of the Electricity Regulatory Commissions Act, 1998, a provision similar to sections 68 and 178 of The Electricity Act, 2003. None of the other decisions cited at the bar deal with the Regulations framed under the provisions of the Act of 1998 or the Act of 2003. Accordingly, on the first point we hold that the Regulations framed under Electricity Act 2003, are in the nature of subordinate legislation and on second point we hold that the challenge to their validity falls outside the purview of the Tribunal. Accordingly, the point raised by Mr. Ramachandran has been set at rest so far as this Tribunal is concerned.”

72. It has been submitted by Mr. Sen that it is incorrect to say that the

Commission advised the appellant to file tariff petition incorporating

the difficulties in meeting the norms set out by the Commission, on

the contrary, the appellant on its own filed the MYT petition. Our

110

Page 111: Appeal No. 170 of 2010

attention has been drawn to the letter dated 08.09.2009 wherein the

Commission communicated to the appellant as follows:

“MPPGCL submitted that the company is facing difficulties in complying with the operational norms notified in the MYT Regulation, 2009. MPPCL requested for a review of benchmark set by the Commission in MYT Regulation, looking to the conditions of machines. The Commission expressed its displeasure and observed that this reason for delay in filing MYPT petition was not convincing. Since the norms under Regulations are notified tariff petition is to be filed accordingly. However, the norms fixed by the Commission are almost similar to the norms fixed by the CERC for the same vintage of power station.”(Emphasis ours)

73.The Commission in its MYT order for FY 2009-10 to FY 2011-12

dated 03.03.2010 has observed that the appellant in its petition

sought for revision in the bench marks/norms specified in the

Regulations, 2009 notified on 8th Mary, 2009 and also filed a tariff

proposal based on the norms proposed by the appellant. The

Commission conveyed to the appellant that since it was only in the

recent past that after a prolonged public hearing norms were set out it

was not possible to revise the norms. Then, the appellant filed a

petition being no. 8 of 2010 specifically praying for relaxation of

norms and in the preceding paragraphs we have found the reasons of

the Commission in rejecting the petition. It is commented by Mr. Sen

that appellant sought revision in norms which were more relaxed than

its previous submission made on 27.02.2009 as comments to the

draft regulation and further the appellant was seeking more relaxed

norms for FY 2009-10, than the norms specified for FY 2008-09 in the

111

Page 112: Appeal No. 170 of 2010

Regulation for the earlier control period based on which the MYT

order for the control period 2006-07 to2008-09 as also the true up

orders for FY 2006-07 were issued. These submissions are borne by

the record and could not be disputed. The commission’s impugned

order testifies to this position. It has been submitted by Mr. Sen that

the appellant considered the average of the operating parameters

actually achieved since FY 2003-04 when there are instances of the

appellant achieving better operating parameters in between the years

and the approach of the appellant was not in conformity with what the

tariff policy provides for in Section 5.3 which we quote below:

“Suitable performance norms of operations together with

incentives and disincentives would need be evolved along with

appropriate arrangement for sharing the gains of efficient

operations with the consumers. Except for the cases referred

to in para 5.3 (h) (2), the operating parameters in tariff should

be at “Normative levels” only and not at “Lower of normative

and actual”.

The policy further runs thus:

“This is essential to encourage better operating performance. The norms should be efficient, relatable to past performance, capable of achievement and progressively reflecting increased efficiencies and may also take into consideration the latest technological advancements, fuel, vintage of equipments, nature of operations, level of service to the provided to consumers etc.”.

112

Page 113: Appeal No. 170 of 2010

74. It has further been submitted that the appellant sought relaxation in

operating norms even for the new capacity i.e. SGTPS 500 MW

Birsinhpur unit commissioned on 28.08.2008 although Mr.

Ramachandran claims that such relaxation was not sought for the FY

2010-11 although relaxation was sought for so as to facilitate the

appellant technical personnel to understand and gain experience for

operating such capacity.

75. Our attention has been drawn to the table given by the respondent

no.1 to show how the appellant on 27.02.2009 proposed benchmarks

for FY 2008-09 and onwards in the petition no. 08 of 2010 praying for

relaxation of norms again downgraded the norms. This is why the

Commission observed in para 12 of the order that the appellant

sought relaxation in norm for FY 2009-10 which are even inferior to

the norms for FY 2008-09 prescribed by the Commission in the

Regulations for the earlier control period i.e. FY 2007-09 and the

appellant was seeking inferior norms than what he had in the earlier

years. In these circumstances, we are unable to say that factually

also the Commission’s finding cannot said to be without reason and

that reasons advanced by the Commission on objectivity of facts

should not be substituted by our view, if any.

76. Having thus found out the factual situation we are to observe that any

amount of impression that the Commission was not realistic in its

approach must be dispelled and that it had consistently insisted upon

the appellant to carry out renovation and modernization activities

113

Page 114: Appeal No. 170 of 2010

which the Commission lamented that the appellant did not seriously

pursue for.

77. We have so far covered all the issues in a comprehensive manner

and summarize our reasons as below:

(a) The appeal is not maintainable in its present form.

(b) To direct the Commission to effect an amendment of the

regulation would entail encroaching upon the power of

Judicial Review which we do not have.

(c) The impugned order of the Commission dated 26th May,

2010 cannot be the subject-matter of challenge in an

appeal under Section 111 of the Electricity Act.

(d) Regulation 57 dealing with power to remove difficulties is

inappropriate and cannot be taken as resort to for

downgrading the benchmarks.

(e) Regulation 56 as it is there in the regulation does not

entitle the Commission to come down from the norms and

it is only when regulation 58 is exercised to amend

regulation 56 that the Commission may in its wisdom

lower down the norms and benchmarks.

(f) Regulations 59.2 and 59.3 of Regulation 59 are

exercisable in adjudicatory process, not in legislative

jurisdiction.

(g) The Commission’s impugned order does not suffer from

lack of reason and objectivity of facts.

114

Page 115: Appeal No. 170 of 2010

(h) While holding the above, we also hold that it is always

open to the Commission, if they would like, to undertake

any study of norms even after the rejection of the prayer

for amendment so as to consider the feasibility or

otherwise of bringing out an amendment of the

Regulations in course of the determination of the tariff

application. We also hold that within the present

parameters of Regulation 56 the Commission can

deviate from the norms if it so wishes and deems fit. We

also hold that the Commission is at liberty if it would

deem proper to amend Regulation 56 on the strength of

Regulation 58 so as to widen its power to deviate. We

further hold that the Commission in course of

determination of tariff may exercise any of the powers as

is available to it in a suitable situation in their respective

jurisdiction. Since the prayer for amendment has been

refused by a reasoned order, we are not in a position to

say that we must intervene so as to compel the

Commission to pass an amended notified Regulations.

115

Page 116: Appeal No. 170 of 2010

78. Subject to what we have held in penultimate paragraph, the

appeal fails and is dismissed but without costs.

(Justice P.S. Datta) (Rakesh Nath) Judicial Member Technical Member Dated: 6th May, 2011 Reportable/Non-reportable PK/RKT

116