apgtf uk post combustion carbon dioxide capture r&d …...what is post combustion capture (pcc)?...
TRANSCRIPT
APGTF
UK Post Combustion Carbon Dioxide Capture R&D Activities
Hans Jensen February 2008
© Fluor
© Statoil
© Statoil
© IPCC
Contents
The need for CCS
Post Combustion Capture
R&D needs
R&D activities – UK universities, UK industry and Europe / Worldwide
Who’s got the problem?
The problem
Fossil fuels are needed!
– A range of analysis show that fossil fuels is likely to remain a major energy source in 2030
The introduction of renewable energy sources in the energy system will play a large role, but not large enough and soon enough
In several countries nuclear power is currently not an option
What is Post Combustion capture (PCC)? Carbon dioxide is absorbed from the flue gas by a liquid solvent(typically aqueous amine solution)
The solvent is then pumped to a desorber, where it is heated to drive off the CO2. The regenerated solvent is then cooled and reused.
Amine absorption technology has been used in the oil and gas industry for many years. Application to power station flue gas involves new challenges: much greater scale and more difficult chemistry.
Capable of 90%+ CO2 capture
Relatively easy to retrofit to an existing power plant
Possible to test the process on part of the flue gas stream
PCC Impact on Host Power Station
Boiler Steam Turbine Generator
Condenser
5%
boiler losses
1%
feedwaterheating
43.7%
condenser heat
rejection
3.3%
power plant auxiliaries
1%
generator losses
Boiler Steam Turbine Generator
Condenser
5%
boiler losses
1%
feedwaterheating
43.7%
condenser heat
rejection
3.3%
power plant auxiliaries
1%
generator losses
Reduces efficiency from approx. 45% to approx. 35%
Requires about half steam from LP turbine
Energy penalty comprises steam for reboiler 45%, pumps and fans 10% and CO2 compression 45%
Increased capital cost
Substantial land area
Impact on flexibility
High impact means that even incremental improvements can make a big difference
Boiler Steam Turbine Generator
Condenser
5%
boiler losses
1%
feedwaterheating
23.7%
condenser heat
rejection
25.7%
capture plant steam
4.3%
capture plant electric load
3.3%
power plant auxiliaries
1%
generator losses
Capture and
Compression
Boiler Steam Turbine Generator
Condenser
5%
boiler losses
1%
feedwaterheating
23.7%
condenser heat
rejection
25.7%
capture plant steam
4.3%
capture plant electric load
3.3%
power plant auxiliaries
1%
generator losses
Capture and
Compression
Research RequirementsUnderstanding and minimising costs and impact on host plant
Understanding environmental issues (emissions, waste streams)
Understanding process chemistry, corrosion, solvent degradation
Process integration and optimisation
Gas cleaning requirements
Evaluating technologies
Improvement in process technology / reduction in efficiency penalty
Developing modelling capability
Understanding implications for power plant flexibilty, grid code and commercial implications
Understanding Engineering issues for retrofit
Understanding implications for CCGTs
Understanding regulatory and legislative requirements
UK Research Projects (current)
Aberdeen, BGS, Cambridge, Cranfield, Edinburgh, Glasgow, Heriot-Watt, Imperial, Leeds, Manchester, Newcastle, Nottingham, Plymouth Marine Lab, Reading
UK Research Councils’TSEC
All aspects of CO2 capture and storage including PCC
UK Carbon Capture &Storage Consortium Project
RWE npower, BOC Linde, Doosan BabcockLeeds UniversityTSB (UK Govt)Modelling of capture plant integration
Eco-copps
Eon, RWE npower, Doosan Babcock and others
Imperial College, CranfieldUniversity, Cardiff University
BCURA + othersAmines chemistry, corrosion and performance, plant integration, CO2 transport
PhD studentships
RWE npower, PPC (Greece)Leeds, AUTH (Greece), ISFTA (Greece)
EC Research Fund for Coal and Steel
Hybrid / amine oxyfuel process
Ecoscrub
RWE npower, Doosan Babcock, Scottish & Southern Energy, EdF, Scottish Power, Drax Power, Visser Smit Hanab UK
Imperial CollegeTSB (UK Govt)Amine post-combustion capture and test rig
Casscap
Industrial PartnersAcademic Partners
Funding Body
ScopeProject
RWE npower post-combustion capture strategy
FGD/SCR interfaceIntegration with turbinesMass transfer issuesConstruction methodsFull CCS chain (includingcompression)
Scale up capabilityEfficiency optimisation (e.g. heat recovery options)Availability/flexibilityMaterials issuesReliable operating costs
Chemistry of capture solventsEnvironmental issuesEnergy requirementsModelling capability for scale-upOperational capabilityAssess technologies
Phase 2Government funded Demonstrator
Phase 1Pilot plant
Phase 0CTF development
Timescale
Benefits
H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H1H2H12020201920182017201620152014201320122011201020092008
CCS tested and commercially available for 2020
Storage
2014 20102008Operation
Transport
Constraints
Phase 0
Capture
Phase 2Phase 1Issue
Test ProgrammeFeatures
8m column height0.07 MWe (50 kg/h CO2)SO2 and NOX pre-treatmentMultiple solvent sampling locationsProvision for corrosion coupons and alternative material test sitesTrace gas injectionContinuous analysis
Test programmeMEA reference tests with heat and material balances and parametric studiesAlternative solvents e.g. MDEA, hindered amines and blendsValidation of baseline process economics and assessment of plant flexibilityTests on different flue gases and fuels including biomass
Aberthaw pilot facility (2010)Key role in capability development
– building operational experience– assisting in technical decisions for
demonstration and in troubleshooting plant in early years
Evaluating issues requiring longer operation and larger scale
– Long-term degradation of solvent
– Materials and corrosion
– Scale-up
– CO2 Purity and implications for compression
– Performance on a real power station
UK Government Competition
Competition launched by BERR in November 2007
Aims to be first large scale coal power station CCS scheme in the world
Post combustion capture
300-400 MWe (will accept staged approach)
15 year project
Operational by 2014
Three consortia under consideration
Some PCC Pilot Plant Projects
Cato pilot Plant (2008)
ENEL /ENI pilot Plant – Brindisi(2009)
European CO2 Test Centre (Mongstad)
NiederaussemPilot Plant (2009)
Didcot test rig (2008) Esbjerg Pilot Plant
(2006)
BerlinAmsterdam
Karlshamn
HeydenWilhelmshaven
London
7 MWel2009
5.5 MWel2009/10
7 MWel2009/10
<1 MWel2009
3,0 MWel2008
0.5 MWelMay 2008
w. Electrabel 1 MWel, 2009
Maasvlakte
Kopenhagen
Phase I of E.ON’s broad programme to develop2nd generation post combustion capture with world market leaders ongoing
� R&D CCS-budget with a commitment of about 100 Million €
UK Government CCS Competition entry
Kingsnorth
CCS - View from Industry: E.ON 19th September 2008 E.ON UK Seite 15
CESAR Project
EU FP7 funded project
19 partners including power companies, OEMs, research organisations and universities
Builds on findings of Castor project – will use the Castor Esbjerg pilot plant to test novel amines
Aims to reduce cost of capture below 15 euro / tonne
Looking at novel solvents, membrane processes and environmental performance
International Academic Links
University of TexasResearch programme into all aspects of post combustion capture including energy efficiency, amine degradation, analytical techniques
Supported by a number of industrial partners including UK utilities
Pilot plant offers opportunity to test different amines
University of ReginaInternational Test Centre supports a range of research activities including degradation, materials performance, EOR
ITC houses an amine pilot plant and University runs the Boundary Dam Pilot plant where CO2 capture using the MEA process is tested on real coal flue gas
Supported by a wide range of international companies including UK utilitiies
Links with Technology Providers
In September 2008, Doosan Babcock signed an agreement with HTC Purenergy of Canada to license the company’s technology for post-combustion capture of CO2 and will take advantage of the series of demonstration projects in which HTC Purenergy are involved.
Other UK companies have been sponsoring research projects internationally
Continuing dialogue between UK power companies and international technology providers such as Fluor, MHI, HTC, Cansolv etc
Research Requirements
LimitedUnderstanding regulatory and legislative requirements
( )Understanding implications for CCGTs
Limited -site specificUnderstanding Engineering issues for retrofit
Understanding implications for power plant flexibilty, grid code and commercial
Developing modelling capability
Improvement in process technology / reduction in efficiency penalty
Evaluating technologies
Gas cleaning requirements
Site specific research needed
Process integration and optimisation
Understanding process chemistry, corrosion, solvent degradation
Understanding environmental issues (emissions, waste streams)
Understanding and minimising costs and impact on host plant
Conclusions
Coal is likely to be a necessary part of the fuel mix needed for power generation at least until 2030 and action is required from industry to address GHG emissions
A range of capture options is available for fossil-fired plant but all require further R&D investment and assessment
Transportation of CO2 is possible by on-shore or off-shore pipe line or by specially adapted tankers
CO2 storage is possible but a number of technical and legal obstacles need to be overcome
CCS needs to be recognised in the EU ETS to encourage development
More confidence is needed with CCS so risks can be better understood, the regulatory regime is smoothed and requirements for new plant are understood
Public acceptability is a critical issue
Visit us on our web-site:
www.rwe.com RWE Group Research & Development
RWE Forschung & EntwicklungResearch & Development
Contact me: [email protected]
Back up slides
ECO-Scrub ConceptSeveral potential benefits
– potential for net reduction of operating cost due to increased capture efficiency (opex)
– potential for slight reduction in size of post-combustion capture plant (capex)
– reduced-cost retrofit option or potential for savings in new plant through advanced combustion optimisation and reduced boiler size
– may also be able to reduce size of SCR plant
– no issues with air in-leakage
Project39 month project funded by EC Research Fund for Coal and Steel, co-ordinated by RWE npower in collaboration with three universities, two research institutes and three utilities from five EU member statesEnhanced combustion with oxygen and scrubbing
– either no recirculation or partial recirculation of flue gas with replacement of some air by oxygen
• reduces volume of flue gas• enhances CO2 concentration of flue gas
Referencecase
Retrofit Case(post-
combustion)
RetrofitCase
(oxyfuel)
RetrofitCase
(ECOS-Scrub)
Gross electric power MWe 330.67 299.44 357.44 312.19
Gross electrical efficiency % 42.45 38.44 45.89 40.08
Net electric power MWe 304.15 243.43 258.62 248.24
Net electrical efficiency % 39.05 31.25 33.20 31.87
Pumps (electric) MWe 18.15 18.87 20.16 19.27
CO2 compressors (electric) MWe - 21.24 21.24 21.23
Fans and compressors (electric) MWe 8.37 15.9 57.42 23.35
Reboiler duty MWth - 268 - 256.85
O2 in secondary air % vol. 21 21 95 30
Referencecase
Retrofit Case(post-
combustion)
RetrofitCase
(oxyfuel)
RetrofitCase
(ECOS-Scrub)
Gross electric power MWe 330.67 299.44 357.44 312.19
Gross electrical efficiency % 42.45 38.44 45.89 40.08
Referencecase
Retrofit Case(post-
combustion)
RetrofitCase
(oxyfuel)
RetrofitCase
(ECOS-Scrub)
Gross electric power MWe 330.67 299.44 357.44 312.19
Gross electrical efficiency % 42.45 38.44 45.89 40.08
Net electric power MWe 304.15 243.43 258.62 248.24
Net electrical efficiency % 39.05 31.25 33.20 31.87
Pumps (electric) MWe
Net electric power MWe 304.15 243.43 258.62 248.24
Net electrical efficiency % 39.05 31.25 33.20 31.87
Pumps (electric) MWe 18.15 18.87 20.16 19.27
CO2 compressors (electric) MWe - 21.24 21.24 21.23
Fans and compressors (electric) MWe 8.37 15.9 57.42 23.35
18.15 18.87 20.16 19.27
CO2 compressors (electric) MWe - 21.24 21.24 21.23
Fans and compressors (electric) MWe 8.37 15.9 57.42 23.35
Reboiler duty MWth - 268 - 256.85
O2 in secondary air % vol. 21 21 95 30Data courtesy of CERTH/ISFTA, National Technical University of Athens
Output of simulations for a lignite-fired power plant
Post-combustion capture at Didcot
Testing different flue gas compositions.Parametric tests of solvent loading and desorption temperature and pressure.Alternative solvents e.g. MDEA, hindered aminesValidation of baseline process economics and assessment of plant flexibility
SpecificationTreat 33% of 0.5 MW CTF flue gasCarbon dioxide removal using MEA of 1 tonne per day (>85%)SO2 and NOX pre-treatment
Test programmeComparison of energy requirements for range of solventsCompatibility with bio-mass
Multiple solvent sampling locationsProvision for corrosion and alternate material test sites
Overview of oxyfuel programme
Desktop Studies
Regulation issues – CO2 purity limits for oxyfuel
Pre-investment issues compared with post-combustion capture
Required footprint for retrofit (e.g. air separation unit)
Safety Fuel Issues
Process Development
OptimisationAir leakage
Optimum recycle ratio
Air heater design
Optimisation of mixing strategy (where to add oxygen (PA/SA/TA or overfire air etc.)
Gas recirculation
Oil burner operation on oxyfuel
Flexibility - start-up/shutdown limited by air separation unit so cold-start on air
CTF StudiesSelection of coals (optimise purchasing)
Use of biomass
Furnace slagging
Furnace Corrosion
Fouling
NOX chemistry not well understood)
Heavy metal recycling and ash composition
Safety handling and storage of O2 and CO2
Flame detection issues (higher moisture and CO2 may affect UV and IR absorption)
Safety of mixing oxygen/CO2
Flame stability
Safe switch-over the oxyfuel combustion
Safety of staff with CO2 / and flue gas leaks
Purging for safetyBurner design
Carbon burnout
Heat transfer (radiative/convective properties)
Schematic of CTF
Amine Test Rig Process Flow Diagram
What is an Amine?
Ammonia (NH3) in which one or more hydrogen atoms have been replaced by organic groups.
Monoethanolamine
MEA or 2-aminoethanol C2H7NO or NH2.CH2.CH2OH
OHHN
H
Methyldiethanolamine (MDEA)
CH3
NHO
OH