WHY DOES THE SAFETY REQUIREMENT EXIST?

“We’ve always done it that way?”

How was the requirement validated?

What were the circumstances at the time?

Is the requirement still relevant (effective) in today’s environment?

Page 3: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

SHACKLE FOR CRITICAL LIFT APPLICATION

  AFSPCMAN 91-710 ASME B30.26

Initial Proof 2 x Rated Load 2 X Rated Load*

Post Proof Inspection Volumetric & NDE Visual

Periodic (annual) Proof 2 x Rated Load Not Required

Periodic (annual) Inspection

NDE(Dye Penetrant)

(Magnetic Particle) Visual

FAST FORWARD TO TODAY

Facility Cost ⇒ $110K annualUser Mission Cost ⇒ $ 34K per mission

TOTAL COST ON Eastern Range = ~$1M per year

Page 4: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

BUT IS IT MORE SAFE?

Page 5: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

US NAVY – high number of accidents◦ Causes: Uncertainty in the load

High corrosion environmentNo Consensus standard for

design◦ Solution: Annual 2 x rated load test

OSHA in its infancy

US Air Force Range◦ Adopt 2 x RL in ESMC (1984)

Page 6: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

1970 2000

Weak OSHA Strong OSHA

Inconsistent Design FOS Consensus FOS

Various materials Specific Materials

2 x rated test solution 2 x rated test solution

WHAT DOES ASME SAY ABOUT 2 x RL TESTING?

Do not recommend exceeding 42% yield strength or fatigue may occur (ASME B30.20 interpretation)

Page 7: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

Does annual 2 x RL proof increase safety?

Are Magnetic Particle or Dye Penetrate inspections required to find critical flaws?

Page 8: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

10 Fatigue Rated shackles failed in fatigue when subject to 2 x RL

BUST

E

D

Page 9: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

Failed @ 2.87 x RL Failed @ 1.28 x RL

Failed @ 1.87 x RL Failed @ 2.28 x RLBUST

E

D

Page 10: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

Chance of improperly tested Change of damage during installation Change of damage during installation

Page 11: Anthony Underhill 321-730-6269 anthony.underhill@mantech.com capt_underhill@yahoo.com

REVISIT YOUR SAFETY REQUIREMENTS

REVALIDATE THEY ARE FULLFILLING THEIR INTENDED PURPOSE

◦ YES – ENFORCE THEM◦ NO – CHANGE THEM