annual+programme+review+2012+ bangladesh+health ......acknowledgements:+...

66
CONSOLIDATED TECHNICAL REPORT ThinkWell @thinkwellglobal www.thinkwellglobal.com Annual Programme Review 2012 Bangladesh Health, Population and Nutrition Sector Development Programme (HPNSDP) Key Findings, Conclusions, and Recommendations October 11, 2012

Upload: others

Post on 23-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

C O N S O L I D A T E D   T E C H N I C A L   R E P O R T    

  ThinkWell     @thinkwellglobal  

www.thinkwellglobal.com  

 

 

Annual  Programme  Review  2012  Bangladesh  Health,  Population  and  Nutrition  Sector  Development  Programme  (HPNSDP)  Key  Findings,  Conclusions,  and  Recommendations  October  11,  2012  

Page 2: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

Acknowledgements:  This  Consolidated  Technical  Report  of  the  findings,  conclusions  and  recommendations  relative  to  the  first  Annual  Programme  Review  of  the  Health,  Population  and  Nutrition  Sector  Development  Programme  has  been  prepared  by  the  team  leader  of  the  Independent  Review  Team  conducting  the  APR.  The  contents,  including  expressed  views,  of  this  report  are  those  of  the  IRT  and  do  not  necessarily  reflect  the  views  of  either  the  Ministry  of  Health  and  Family  Welfare,  the  steward  of  the  Bangladesh  health  sector  or,  those  of  the  Health  Consortium  of  Development  Partners,  who  support  the  MOHFW  in  the  management  of  this  sector-­‐wide  programme.  

On  behalf  of  the  IRT,  we  would  like  thank  the  Senior  Secretary  to  whom  this  report  is  submitted  and  under  whose  auspices  this  APR  took  place.  In  addition,  we  would  like  to  thank  the  Joint  Chief  Planning,  Madame  Niru  Nahar  along  with  her  competent  team,  Dr.  Bushra  Alam  at  the  World  Bank,  and  Ms.  Alana  Albee  representative  of  the  Development  Partners  for  their  support  in  the  conduct  of  this  review.  Special  thanks,  in  particular,  to  Ms.  Shaila  Sharmin  Zaman  at  the  Planning  Wing  and  Ms.  Iffat  Mahmud  at  the  Bank  for  their  patience  and  dedicated  work  in  the  support  of  IRT.    

Authors:  This  report  was  prepared  by  Leslie  Fox,  team  leader  of  the  Independent  Review  Team.    

Recommended  Citation:    Fox,  Leslie.  Annual  Programme  Review  2012:  Volume  I,  Bangladesh  Health,  Population  and  Nutrition  Sector  Development  Programme  (HPNSDP).  October  2012.  Institute  for  Collaborative  Development.    

Page 3: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

A C R O N YM S  

ADP   Annual  Development  Program  

AIDS   Acquired  Immunodeficiency  Syndrome  

AMC   Alternative  Medical  Care  

ANC     Antenatal  Care  

APIR     Annual  Program  Implementation  Report  

APR     Annual  Program  Review  

ARH     Adolescent  Reproductive  Health  

ARI     Acute  Respiratory  Infection  

BCC     Behavior  Change  Communication  

BDHS     Bangladesh  Demographic  and  Health  Survey  

BHE     Bureau  of  Health  Education  

BHFS     Bangladesh  Health  Facility  Survey  

BMMS         Bangladesh  Maternal  Mortality  Survey  

CBHC     Community  Based  Health  Care  

CC     Community  Clinic  

CDC     Communicable  Disease  Control  

CGA     Controller-­‐General  of  Accounts  

CHCP     Community  Health  Care  Provider  

CME     Continued  Medical  Education  

CPR     Contraceptive  Prevalence  Rate  

CSBA     Community  Skilled  Birth  Attendant  

CMSD     Central  Medical  Stores  Department  

DAAR     Disbursement  for  Accelerated  Achievement  of  Results  

DDS   Drugs  and  Dietary  Supplies  

 DDO   Drawing  and  Disbursement  Officer  

DFID   Department  for  International  Development  

DGDA   Department  General  of  Drug  Administration  

   

DGHS   Director  General  of  Health  Services  

 DGFP   Director  General  of  Family  Planning  

DH   District  Hospital  

DMCH   Dhaka  Medical  College  Hospital  

 DOTS     Directly  Observed  Treatment  Short  Course  

 DPA   Direct  Project  Aid  

DSF   Demand  Side  Financing  

DTL   Drug  Testing  Laboratory  

ECNEC   Executive  Committee  of  the  National  Economic  Council  

 

 ECP   Emergency  Contraceptive  Pill  

EDPT   Early  Diagnosis  and  Prompt  Treatment  

 EGV   Equity,  Gender  and  Voice  

EGVNP   Equity,  Gender  and  Voice,  NGO  participation  

 EmOC   Emergency  Obstetric  Care  

EPI     Expanded  Program  of  Immunization  

 EQA   External  Quality  Assessment  

ERD   External  Resource  Division  

ESD   Essential  Service  Delivery    

ESP   Essential  Service  Package  

FeHA   Female  Health  Assistant  

FMAU   Financial  Management  and  Audit  Unit  

FMR   Financial  Monitoring  Report  

FP   Family  Planning  

FPI     Family  Planning  Inspector  

 FSW   Female  Sex  Worker  

FPCST   Family  Planning  Clinical  Supervision  Team  

FWA   Family  Welfare  Assistant  

Page 4: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

FWV   Family  Welfare  Visitor  

FY     Fiscal  Year  

 GOB   Government  of  Bangladesh  

HA   Health  Assistant  

HCWM   Health  Care  Waste  Management  

HEF         Health  Economics  and  Financing  

HEP   Health  Education  and  Promotion  

HEU   Health  Economics  Unit  

 HIS&e-­‐H   Health  Information  System  and  E-­‐Health  

 HIV   Human  Immunodeficiency  Virus  

HNP   Health  Nutrition  and  Population  

HNPSP   Health  Nutrition  and  Population  Sector  Program  

 HPSP   Health  and  Population  Sector  Program  

 HRM   Human  Resource  Management  

HSM   Hospital  Services  Management  

 iBAS   Integrated  Budget  and  Accounting  System  

ICDDR,B   International  Centre  for  Diarrhoeal  Disease  Research,  Bangladesh  

 ICT     Information  and  Communication  Technology  

 IDD   Iodine  Deficiency  Disorder  

 IEC   Information  Education  &  Communication  

IFM   Improved  Financial  Management  

HIS   Improving  Health  Services  

IHT   Institute  of  Health  Technology  

IMCI   Integrated  Management  of  Childhood  Illnesses  

IMED   Implementation  Monitoring  and  Evaluation  Division  

 IMR   Infant  Mortality  Rate  

IPH   Institute  of  Public  Health  

IRT   Independent  Review  Team  

IST   In-­‐Service  Training  

IUD   Intra  Uterine  Device  

IYCF   Infant  &  Young  Child  Feeding  

LAPM   Long  Acting  and  Permanent  Methods  

LCG     Local  Consultative  Group  

 LD     Line  Director  

 LLIN   Long  Lasting  Insecticidal  Net  

LLP   Local  Level  Planning  

LMIS   Logistical  Management  Information  System  

MARP   Most  at  Risk  Population  

MBT   Medical  Biotechnology  

MCWC       Maternal  and  Child  Welfare  Centre  

 MDG   Millennium  Development  Goal  

MDR   Multi-­‐Drug  Resistant  

M&E   Monitoring  &  Evaluation  

MIS   Management  Information  System  

MMR   Maternal  Mortality  Ratio  

MNCAH   Maternal  Neonatal,  Child  and  Adolescent  Health  

 MOF   Ministry  of  Finance  

MOHFW   Ministry  of  Health  and  Family  Welfare  

 MSR   Medical  &  Surgical  Requisites  

MTBF   Medium  Term  Budget  Framework  

NASP   National  AIDS/STD  Program  

NCDC   Non  Communicable  Disease  Control  

NES   Nursing  Education  Services  

NGO   Non-­‐Governmental  Organization  

Page 5: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

NIPORT   National  Institute  of  Population  Research  and  Training  

 NIPSOM   National  Institute  of  Preventive  and  Social  Medicine  

 NNP   National  Nutrition  Project  

NNS   National  Nutrition  Services  

OP     Operational  Plan  

 PA   Project  Aid  

PAD   Project  Appraisal  Document  

PBF   Performance  Based  Financing  

PFD   Physical  Facilities  Development    

PHC   Primary  Health  Care  

 PER   Public  Expenditure  Review  

PIP   Program  Implementation  Plan  

PLMC     Procurement  and  Logistics  Monitoring  Cell  

 PLSM   Procurement,  Logistics  and  Supplies  Management  

PME   Planning,  Monitoring  and  Evaluation  

PMR   Planning,  Monitoring  and  Research  

PPA   Public  Procurement  Act  

PPR   Public  Procurement  Rules  

PPP   Public  Private  Partnership  

PSSM   Procurement,  Storage  and  Supplies  Management  

 PWD   Public  Works  Department  

PW   Planning  Wing  

 RADP   Revised  Annual  Development  Program  

RFP   Request  for  Proposals  

RPA   Reimbursable  Project  Aid  

RFW   Results  Framework  

RRT   Rapid  Response  Team  

SBA   Skilled  Birth  Attendant  

SDAM   Strengthening  of  Drug  Administration  and  Management  

 SHS   Strengthening  Health  Systems  

SOP   Standard  Operating  Procedure  

SRH   Sexual  and  Reproductive  Health  

SWAp   Sector  Wide  Approach  

SWPMM   Sector  Wide  Program  Management  and  Monitoring  

TATR   Thematic  Area  Technical  Report  

TFR   Total  Fertility  Rate  

TRD   Training,  Research  and  Development  

UESD   Utilization  of  Essential  Service  Delivery  

UFPO   Upazila  Family  Planning  Officer  

UHC   Upazila  Health  Complex  

UH&FWC   Upazila  Health  and  Family  Welfare  Clinic  

 UN   United  Nations  

USAID   United  States  Agency  for  International  Development  

WHO   World  Health  Organization  

 WIMS   Warehouse  Inventory  Management  System    

   

   

   

   

   

   

   

   

 

Page 6: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

T A B L E   O F   C O N T E N T S  

Executive  Summary  ........................................................................................................  1  1   Introduction  and  Overview  .......................................................................................  3  

1.1   Programme  Background:  A  Summary  Social  and  Economic  Profile  ....................................  3  1.2   HPNSDP  2011  –  2016  ..........................................................................................................  3  1.3   Context  of  the  APR  2012  and  HPNSDP  ................................................................................  4  1.4   APR  2012  Objectives  and  Deliverables  ................................................................................  4  1.5   APR  2012  Technical  Approach  and  Methodology  ...............................................................  5  1.6   APR  2012  Report  Contents  and  Structure  ...........................................................................  5  

2   Progress  Against  Objectives  and  Main  Findings  of  the  Thematic  Area  Technical  Reports  .....................................................................................................................  6  2.1   Introduction  and  Overview  .................................................................................................  6  2.2   Financial  Management,  with  Planning  and  Budgeting  ........................................................  6  2.3   Procurement  and  Supply  Chain  Management  ....................................................................  8  2.4   Monitoring  &  Evaluation  ...................................................................................................  10  2.5   Disease  Control  (including  human  resources)  ...................................................................  13  2.6   Nutrition  (including  human  resources)  .............................................................................  14  2.7   MNCH  and  Family  Planning  (including  human  resources)  ................................................  16  2.8   Urban  Health  (including  population  and  nutrition)  ..........................................................  18  2.9   IEC  &  Behavior  Change  Communications  ..........................................................................  21  2.10   Overall  Conclusion  and  Recommendations:  Key  Technical  Issues,  Challenges  and  Opportunities  ..............................................................................................................................  23  

3   Overall  Conclusions  and  Recommendations:  Are  Conditions  In  Place  for  a  Successful  Programme  ............................................................................................  26  3.1   Review,  Analysis  and  Updating  of  the  HPNSDP  Results  Framework  .................................  26  3.2   Progress  on  Key  Areas  of  the  Governance  and  Accountability  Action  Plan  ......................  26  3.3   Disbursement  for  Accelerated  Achievement  of  Results  ...................................................  27  3.4   Institutional  Constraints  in  Implementation,  including  Risk  Assessment  Update  ............  27  3.5   Financial  Framework  for  the  Sector,  including  DP  Funding  ..............................................  28  3.6   Team  Leader’s  Thoughts  on  Future  Annual  Programme  Reviews  ....................................  29  3.7   Overall  Conclusions  and  Recommendations  for  the  APR  2012  .........................................  30  

Annex  1  ........................................................................................................................  32  Thematic  Area  Technical  Review  Reports  ...................................................................................  32  

Annex  2  ........................................................................................................................  33  Review  and  Analysis  of  the  Updated  Results  Framework  ...........................................................  33  Additional  Comments  to  HPNSDP  Results  Matrix  Indicators  ......................................................  35  HPNSDP  Results  Matrix  Analysis  .................................................................................................  37  

Annex  3  ........................................................................................................................  43  Governance  and  Accountability  Action  Plan  ...............................................................................  43  Update  on  Governance  and  Accountability  Action  Plan  (GAAP)  .................................................  44  

Page 7: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

Annex  4  ........................................................................................................................  50  DAAR  Analysis  .............................................................................................................................  50  DAAR  Indicators  for  Year  1  (July-­‐December  2011)  ......................................................................  51  Progress  on  2012  DAAR  Indicators  (as  of  September  12,2012)  ..................................................  52  

Annex  5  ........................................................................................................................  54  Team  Leader  Terms  of  Reference  ...............................................................................................  54  

 

 

Page 8: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1  

E X E C U T I V E   S UMMA R Y  

Overview  and  Background  The  Consolidated  Technical  Report  which  follows  this  executive  summary  provides  the  principal  findings,  conclusions  and  recommendations  of  the  Independent  Review  Team  (IRT)  on  the  first  Annual  Programme  Review  (APR)  of  the  Health,  Population  and  Nutrition  Sector  Development  Programme  (HPNSDP)  2011-­‐2016.  The  IRT  was  composed  of  17  members,  eight  international  thematic  area  experts  and  their  national  counterparts,  plus  the  team  leader.  The  IRT  conducted  the  APR  from  September  15,  to  October  5,  2012;  the  team  leader  remained  an  additional  week  to  prepare  this  final  consolidated  technical  report  and  participate  in  the  Policy  Dialogue  which  formed  the  basis  of  APR  2012  Aide  Memoire.    

While  the  32  OPs  were  the  principal  unit  of  analysis  used  by  the  IRT  in  this  APR,  it  was  the  nine  Thematic  Areas  defined  by  the  2012  APR  TORs,  which  provided  the  higher  level  focus  of  the  individual  IRT  member’s  review.  Each  Thematic  Area  team  thus  prepared  and  presented  its  draft  report,  including  principal  findings  and  recommendations,  to  the  concerned  HPNSDP  Task  Group  to  obtain  its  feedback  and  finalize  its  recommendations.  Final  thematic  papers,  with  refined  recommendations,  were  used  to  produce  a  practical  action  plan  by  the  concerned  Task  Group  and  ultimately  to  improve  OP  performance  while  setting  a  baseline  for  the  purpose  of  monitoring  next  year’s  implementation.  

This  first  APR  of  the  third  SWAp  was  focused  largely  on  assessing  whether  the  program  was  on  the  right  track  to  accomplish  its  overall  objectives,  in  terms  of  whether  start-­‐up  measures  (e.g.,  institutional  arrangements,  financial  framework,  monitoring  and  evaluation  systems,  etc.)  were  in  place  and  operational.  The  focus  of  the  APR  2012  was,  therefore,  less  an  assessment  to  determine  whether  the  program  had  achieved  its  overall  objectives  for  year  one,  although  it  did  do  this  too,  than  it  was  a  due  diligence  review  of  the  programme’s  institutional,  financial,  technical  and  management  infrastructure.  

HPNSDP  is  distinguished  from  its  two  predecessors  by  increased  attention  placed  on  several  new  areas,  including  nutrition  mainstreaming,  urban  health  and  gender,  equity,  voice  and  accountability.    Perhaps  one  of  the  most  important  aspects  of  this  third  SWAp  is  the  intense  focus  on  achieving  results,  both  the  at  the  level  of  the  32  operational  plans  (OPs)  which  are  the  building  blocks  of  the  programme,  and  at  the  results  framework  (RFW)  or  strategic  level,  which  defines  the  set  of  high  level  impact  and  outcome  results  to  which  the  OPs  are  intended  to  contribute.    

Each  of  the  Thematic  Area  Technical  Reviews  (TATR)  is  presented  in  summary  below  (Section  2)  and  in  full  in  Volume  II,  Annexures.  Each  of  these  Reviews  provides  principal  findings  both  in  terms  of  achievements  and  challenges,  as  well  as  a  specific  set  of  actionable  recommendations  and  ways  forward.  The  Action  Plan  and  set  of  thirty  recommendations  that  emerged  from  the  Policy  Dialogue  are  based  on  the  TATR  recommendations.  While  space  does  not  permit  a  summary  of  all  nine  Thematic  Areas,  to  the  extent  the  reader  has  time,  a  review  of  the  full  TATR  relative  to  his  or  her  interest  is  a  worthwhile  effort.  

Overall  Conclusions  and  Recommendations  The  review  of  the  eight  Thematic  Areas  by  the  IRT  consultants  shows  that  significant  progress  has  been  made  in  implementation  of  the  HPNSDP  but,  as  would  be  expected,  there  are  a  number  of  programmatic  and  management  issues  that  have  been  identified  which  the  IRT  believes,  if  the  recommendations  are  implemented,  will  lead  to  the  achievement  of  both  Operational  Plan  outputs  as  well  as  contribute  to  the  achievement  of  Results  Framework  outcome  and  impact  level  results.  The  IRT  concludes,  however,  that  the  progress  of  HPNSDP  is  roughly  where  it  should  be  at  the  end  of  the  first  year  of  the  programme,  taking  into  consideration  the  later  than  expected  start  experienced.  Given  the  magnitude  of  the  SWAp,  the  many  stakeholders  involved,  and  the  normal  implementation  hiccups  associated  with  the  commencement  of  most  new  initiatives,  the  IRT  finds  the  initial  delays  understandable.    

Page 9: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2  

Both  the  APIR  and  this  APR  have  identified  the  on-­‐going  crisis  in  human  resources  and  weak  SWAp  monitoring  and  supervision  as  two  of  the  principal  issues  that  will  have  a  likely  impact  on  the  programme’s  successful  achievement  if  not  addressed  immediately;  both  issues  carry-­‐over  from  previous  health  sector  programmes.  In  this  regard,  the  IRT  concludes  that:  

‒ The  Human  Resource  Management  (HRM)  OP  is  best  placed  to  lead  the  Ministry’s  efforts  in  addressing  this  health  sector-­‐wide  constraint.  However,  it  is  currently  understaffed  and  urgently  requires  both  additional  personnel  and  those  with  the  right  mix  of  skills  and  expertise  to  permit  the  OP  to  take  the  lead  in  coordinating  HPNSDP’s  response  to  the  current  and  continuing  HR  crisis.  Furthermore,  when  the  current  workforce  study  being  undertaken  by  the  MOHFW  with  DFID  support  is  completed,  the  HRM  OP,  under  the  guidance  of  the  Senior  Secretary,  and  in  collaboration  with  the  HR  Task  Group,  should  convene  a  sector-­‐wide  workshop  to  develop  individual  Task  Force  HR  action  plans  and  identify  short-­‐term  solutions  while  the  longer-­‐term  reforms  of  the  GOB  across  all  sectors  continues  to  take  hold.  Each  of  the  TATR’s  has  reviewed  HR  issues  in  their  particular  domain  and  made  recommendations  concerning  temporary  measures  that  should  address  the  workforce  constraints  in  the  short-­‐term.  

‒ In  terms  of  improved  monitoring  and  management  of  the  SWAp,  the  SWPMM  OP  through  the  Planning  Wing  plays  a  critical  role,  particularly  in  resource  planning  and  tracking  and  Inter-­‐OP  coordination.  In  this  regard,  the  IRT  singles  out  for  special  attention  the  PMMU,  which  needs  to  urgently  engage  additional  staff  so  that  it  can  support  the  Planning  Wing’s  critical  role  in  independently  monitoring  the  performance  of  Operational  Plan’s,  not  relying  simply  on  LD  reporting.  While  LD  meetings  were  viewed  as  very  useful,  there  appeared  to  be  inadequate  time  to  discuss  inter-­‐OP  coordination  particularly  in  areas  of  overlap  or  cross-­‐cutting  issues  such  as  nutrition,  urban  health,  IEC/BCC,  or  human  resource  needs.  

Several  other  conclusions,  largely  related  to  the  SWAp’s  institutional  arrangements  are  worth  noting:  

‒ Several  new  organizational  entities  or  oversight  tools  were  designed  to  increase  the  financial  and  management  oversight  of  this  SWAp  including,  the  Financial  Management  and  Audit  Unit  (FMAU),  the  PMMU,  the  Procurement  and  Logistics  Monitoring  Cell  (PLMC)  and  Interim  Unaudited  Financial  Report  (IUFR).  Each  of  them  has  shown  initial  effectiveness  during  the  programme’s  start-­‐up  and  this  APR  has  pointed  out  where  additional  support  is  needed  to  make  them  fully  functional  

‒ The  IRT  has  been  particularly  impressed  with  the  governance  structure  of  HPNSDP  and  has  seen  it  in  full  operations  during  the  APR,  from  the  initial  Task  Group  meetings,  to  the  Local  Consultative  Group’s  interactions  through  to  the  Steering  Committee  and  culminating  in  the  Policy  Dialogue.  The  Task  Groups  are  the  key  to  the  technical  success  of  the  programme  and  should  meet  regularly  with  well-­‐articulated  TORs  and  strategies;  the  IRT  encourages  them  to  continue  their  important  work  after  APR.    

While  the  IRT  understands  that  HPNSDP  is  a  limited  SWAp  in  terms  of  whole-­‐of-­‐sector  stakeholder  participation,  each  IRT  expert,  from  his  or  her  own  perspective,  felt  that  there  could  be  greater  coordination  with  and  participation  of  major  health  care  providers  that  are  not  covered  under  the  SWAp,  particularly  NGO  and  private  sector  health  providers.  This  is  particularly  true  since  the  public  sector,  through  the  MOHFW,  covers  only  30  percent  of  health  service  delivery  throughout  the  country,  while  the  remaining  70  percent  is  covered  by  a  combination  of  the  private  sector  and  NGOs,  with  future  projections  placing  the  ratio  of  public  sector  to  private/NGO  sector  coverage  at  10  percent  and  90  percent  respectively.  The  IRT  urges  strong  consideration,  therefore,  for  creating  a  new  cross-­‐sector  service  provider  platform  that  brings  together  current  HPNSDP  stakeholders  with  representatives  of  other  non-­‐member  HPNSDP  organizations,  including  from  the  NGO  and  private  sectors  and,  where  appropriate,  into  the  Task  Group  structure,  to  undertake  joint  planning  and  information  sharing  exercises.  

Page 10: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3  

The  obvious  concern,  recognized  by  all  HPNSDP  stakeholders,  is  the  underfunding  of  the  SWAp.  This  however,  is  meta-­‐level  concern  that  probably  falls  outside  of  the  manageable  interests  of  any  of  the  current  parties  to  address.  The  IRT  would  note  that  the  conditions,  that  is,  the  institutional  arrangements,  systems  and  procedures,  are  for  the  most  part  in  place  to  move  the  Programme  forward  to  the  Mid-­‐term  Review  where  adjustments,  if  necessary,  can  be  made.  This  assumes  that  the  HPNSDP  Steering  Committee  and  the  Policy  Dialogue  accept  the  more  important  of  the  principal  recommendations  that  have  been  made  in  this  report  and  the  full  Thematic  Area  Technical  Review  found  in  Volume  II,  Annexes.        

1 I N T R O D U C T I O N   A N D   O V E R V I EW  

Chapter  1.0  provides  a  brief  summary  of  the  programme  background,  HPNSDP,  2012,  the  APR  2012  context,  objectives  and  methodology,  as  well  as  the  structure  of  this  report.  

1 . 1 P R O G R AMM E   B A C K G R O U N D :   A   S UMMA R Y   S O C I A L   A N D   E C O N OM I C  P R O F I L E  

Over  the  past  25  years,  Bangladesh  has  shown  both  an  acceleration  and  balanced  progress  in  the  country’s  economic  and  social  life,  sometimes  against  a  background  of  difficult  partisan  strife.  Gross  domestic  product  and  per  capita  income  have  increased  significantly  over  the  past  decade,  but  so  too  has  the  cost  of  living.  And,  as  much  of  the  world  knows  from  the  2011  Millennium  Development  Goals’  Report,  Bangladesh’s  progress  in  achieving  MDGs  3,  4  and  5  have  been  nothing  short  of  an  international  success  story.  However,  despite  these  achievements,  it  is  also  fair  to  note  that  nearly  one  third-­‐third  (32  percent)  of  the  population  still  live  below  the  poverty  line  and  about  40  percent  is  underemployed  (BBS  2011).  

In  the  social  sector,  Bangladesh  has  made  remarkable  progress  in  many  areas  during  the  last  decade,  i.e.,  increasing  literacy  and  life  expectancy  at  birth;  sustaining  the  child  immunization  above  90  percent,  which  resulted  in  continued  decline  in  infant  and  child  mortality;  and  achieving  sharp  decline  of  maternal  mortality  ratio  (PIP,  2010).  Furthermore,  since  the  inception  of  the  first  SWAP,  Bangladesh  has  made  impressive  gains  in  health  over  the  past  decade.  According  to  the  DHS,  between  1997  and  2011,  Bangladesh  has  seen  total  fertility  rate  decline  from  3.3  to  2.3,  under-­‐five  mortality  decline  from  116  to  65,  infant  mortality  decline  from  82  to  52,  children’s  vaccination  rate  increase  from  54.1  percent  to  81.9  percent,  ANC  use  increase  from  29  to  51.7,  and  percentage  skilled  deliveries  increase  from  8  percent  to  32  percent.  These  are  unprecedented  gains  that  few  countries  have  ever  made  in  such  a  short  period  of  time.  

1 . 2 H P N S D P   2 0 1 1   –   2 0 1 6  

The  Health,  Population  and  Nutrition  Sector  Development  Program  (HPNSDP)  2011-­‐2016  is  the  third  five-­‐year  Sector-­‐wide  Approach  (SWAp)  supporting  the  Bangladesh  health  sector.  It  follows  the  Health  and  Population  Sector  Programme  (HPSP,  1998-­‐2003),  and  the  Health,  Nutrition  and  Population  Sector  Programme  (HNPSP)  which  began  in  2003  and  was  completed  in  June  2011.    HPNSDP  was  designed  with  the  full  participation  of  its  principal  stakeholders,  that  is,  the  Ministry  of  Health  and  Family  Welfare  (MOHFW)  and  it  principal  Development  Partners  and,  after  careful  attention  to  the  lessons  learned  from  these  previous  SWAp  experiences  in  Bangladesh.  The  HPNSDP  incorporates  the  broad  themes  of  improving  coverage,  access,  utilization,  governance,  equity,  quality,  and  gaining  efficiency  in  services.  

HPNSDP  has  two  major  components:  The  first  component  on  improving  health  services  aims  at  improving  priority  HNP  services  to  accelerate  the  achievement  of  the  HNP-­‐related  MDGs  and  can  be  divided  into  two  sub-­‐components:  (a)  the  delivery  of  essential  health  services  which  seek  to  improve  reproductive,  adolescent,  maternal,  neonatal,  infant  and  child  health  and  family  planning  (FP),  

Page 11: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4  

nutrition,  communicable  and  non-­‐communicable  diseases;  and  (b)  supporting  the  service  delivery  system  including  primary  health  care  particularly  for  strengthening  the  Upazila  Health  System  (UHS)  and  the  CCs,  as  well  as  hospital  services.  The  second  component  aims  at  strengthening  health  systems  particularly  governance,  stewardship,  health  sector  planning,  human  resources,  health  care  financing,  procurement  and  supply  chain  management,  quality  of  health  care,  and  pharmaceuticals.  

Finally,  it  worth  noting  that  HPNSDP  has  placed  increased  attention  on  several  new  areas  including  nutrition  mainstreaming,  urban  health  and  gender,  equity,  voice  and  accountability.  Perhaps,  one  of  the  most  important  aspects  of  this  third  SWAp,  which  distinguishes  it  from  its  predecessors,  is  the  intense  focus  on  achieving  results,  both  the  at  the  level  of  the  32  operational  plans  (OPs)  which  are  the  building  blocks  of  the  programme,  and  at  the  results  framework  (RFW)  or  strategic  level,  which  defines  the  set  of  high  level  impact  and  outcome  results  to  which  the  OPs  are  intended  to  contribute.  This  managing  for  development  results  focus  has  not  only  permitted  the  programme  to  monitor  and  report  on  results,  but  has  also  established  an  accountability  framework  relative  to  the  performance  of  those  responsible  for  achieving  the  articulated  results.  

1 . 3 C O N T E X T   O F   T H E   A P R   2 0 1 2   A N D   H P N S D P  

The  implementation  of  the  HPNSDP  was  delayed  by  6  months  due  to  delayed  approval  of  Operational  Plans  (OPs).  Consequently,  the  sector  faced  significant  challenges  due  to  delayed  fund  release  and  short  timeframe  in  its  first  year.  Despite  these  challenges,  the  Annual  Program  Implementation  Report  (APIR)  points  to  impressive  progress  made.  

With  these  challenges  in  mind,  this  first  APR  of  the  third  SWAp  was  focused  largely  on  assessing  whether  the  program  was  on  the  right  track  to  accomplish  its  overall  objectives  in  terms  of  whether  start-­‐up  measures  (e.g.,  institutional  arrangements,  financial  framework,  monitoring  and  evaluation  systems,  etc.)  were  in  place  and  operational.  The  focus  of  the  APR  2012  was,  therefore,  less  an  assessment  to  determine  whether  the  program  had  achieved  its  overall  objectives  for  year  one,  although  it  did  do  this  too,  than  it  was  a  due  diligence  review  of  the  programme’s  institutional,  financial,  technical,  and  management  infrastructure.    

1 . 4 A P R   2 0 1 2   O B J E C T I V E S   A N D   D E L I V E R A B L E S  

Annual  Programme  Review  serves  as  a  sector  management  instrument  to  monitor  progress  in  the  implementation  of  the  program  and  to  verify  that  agreed  management  and  policy  issues  have  been  addressed  during  implementation;  in  this  regard,  this  first  APR  of  HPNSDP  is  no  different.  The  Independent  Review  Team,  which  conducted  this  APR,  was  preceded  by  conduct  of  the  APIR,  which  was  prepared  by  the  MOHFW  Planning  Wing;  the  APIR  provides  the  implementation  progress  of  each  of  the  32  operational  plans  during  the  first  year  of  the  HPNSDP.  The  results  of  APIR  analysis  along  with  the  Stakeholder  Analysis  (see  below),  therefore,  serve  as  the  departure  point  and  baseline  data  sources  for  the  2012  APR  IRT  mission.    

Since  this  is  the  first  year  of  the  sector  program,  the  2012  APR  is  the  first  for  HPNSDP.  The  specific  focus  of  the  APR  was  to:    

1 Review  implementation  of  HPNSDP  in  the  light  of  an  up-­‐to-­‐date  results  framework  using  latest  data,  indicators,  and  targets  as  provided  in  the  APIR;  

2 Assess  initial  progress  of  the  program  during  the  first  year;  

3 Review  the  financing  arrangements  and  assess  how  well  the  GOB  and  DP  support  meet  the  priorities  and  requirements  of  the  HPN  sector;    

4 Undertake  analysis  in  eight  thematic  areas  to  set  the  baseline  and  document  the  building  blocks  (operational  plans)  related  to  the  key  health  systems;  identify  issues/challenges  concerning  effective  delivery  of  services;  and  recommend  ways  to  improve  future  implementation.  

Page 12: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5  

The  overall  APR  Terms  of  Reference  (TOR)  called  for  eight  Thematic  Area  Technical  Reviews  (TATR),  which  are  to  be  used  in  fashioning  eight  corresponding  Task  Group  Action  Plans,  based  on  IRT  recommendations;  a  Consolidated  Technical  Report  (this  document)  which  summarizes  the  eight  TATRs,  provides  analyses  of  and  progress  on  other  mandated  reviews  (e.g.,  GAAP,  DAAR,  up-­‐dated  RFW)  and  which  is  used  by  the  Policy  Dialogue  to  prepare  a  final  overall  Action  Plan  which  in  turn  becomes  the  basis  for  the  APR  2012  Aide  Memoire.  

1 . 5 A P R   2 0 1 2   T E C H N I C A L   A P P R O A C H   A N D  M E T H O D O L O G Y  

The  IRT  team  used  a  methodology  that  was  similar  to  the  previous  APRs  under  the  two  previous  sector  programmes.  The  MOHFW  Planning  Wing  and  World  Bank  led  the  preparations  for  the  APR.  An  initial  inception  visit  was  made  by  the  team  leader  in  August  2012  to  develop  a  work  program  (see,  Team  Leader’s  Inception  Report  APR  2012,  Annex  7),  obtain  background  documentation,  become  familiar  with  the  Bangladeshi  context,  and  meet  HSPSDP  stakeholders.    

The  APR  review  was  conducted  by  a  17  member  IRT  (eight  international  thematic  area  experts  and  their  national  counterparts  plus  the  TL)  from  September  15,  to  October  5,  2012;  the  team  leader  remained  an  additional  week  to  prepare  the  final  consolidated  report  and  participate  in  the  Policy  Dialogue  which  formed  the  basis  of  APR  2012  Aide  Memoire.  In  addition  to  a  review  of  the  significant  documentation  on  the  HPNSDP  and  its  predecessors,  the  IRT  received  a  briefing  from  concerned  officers  in  the  MOHFW,  particularly  the  Planning  Wing,  and  the  APIR  consultants  who  supported  the  PW  in  this  year’s  implementation  review.  The  IRT  met  with  a  broad  range  of  stakeholders,  including  various  levels  of  MOHFW,  Line  Directors,  DPs,  NGOs,  and  other  Ministries  through  a  combination  of  individual  and  group  interviews  (see,  individual  Thematic  Area  Technical  Reviews  for  list  of  interviewees).  Field  visits  by  the  IRT  were  made  to  Pabna,  Syhlet,  Chittagong,  and  Dhaka  City,  with  participation  by  MOHFW  and  DP  members  who  served  as  resource  persons  to  the  IRT.  In  each  District  various  Upazilas  were  visited  and  interviews  were  made  with  the  civil  surgeon,  deputy  directors,  and  other  health  staff  at  all  levels  of  the  service  delivery  system  (District  Hospital,  MCWC,  UHC,  Union  Health  and  Family  Welfare  Centers  and  Community  Clinics).    

While  the  32  OPs  were  the  principal  unit  of  analysis  used  by  the  IRT  in  this  APR,  it  was  the  nine  Thematic  Areas1,  defined  by  the  2012  APR  TORs,  which  provided  the  higher  level  focus  of  the  individual  IRT  member’s  review.  Each  thematic  area  team  thus  prepared  and  presented  their  draft  reports,  including  principal  findings  and  recommendations  to  the  concerned  HPNSDP  Task  Group  to  obtain  its  feedback  and  guide  its  recommendations.  Based  on  this  feedback,  final  thematic  papers  with  refined  recommendations  were  prepared,  to  produce  a  practical  action  plans  by  the  concerned  Task  Group  and  intended  to  improve  OP  performance  while  setting  a  baseline  for  the  purpose  of  monitoring  next  year’s  implementation.  

1 . 6 A P R   2 0 1 2   R E P O R T   C O N T E N T S   A N D   S T R U C T U R E  

The  report  has  two  chapters  following  this  introduction,  which  respond  to  the  requirements  of  the  overall  2012  APR  Terms  of  Reference  (annex  5):  Chapter  2.0,  which  provides  an  analysis  of  the  progress  of  the  HPNSDP  against  planned  objectives  and  main  findings;  and,  Chapter  3.0  which  provides  an  overall  conclusions  focusing  on  the  effectiveness  of  start-­‐up  measures  and  presents  the  principal  analysis  called  for  in  the  TORs,  including  GAAP  progress,  DAAR  indicators,  Up-­‐dated  Results  Framework,  the  financial  framework  for  the  sector,  and  institutional  constraints  in  implementation  including  updates  required  on  the  Risk  Assessment.  

                                                                                                                         1 The  nine  thematic  areas  are:  (i)  Gender,  Equity,  Voice  and  Accountability,  (ii)  Monitoring  and  Evaluation,  (iii)  Procurement  and  Supply  Chain  Management,  (iv)  Financial  management  with  Planning  and  Budgeting,  (v)  MNCH  and  Family  Planning,  (vi)  Nutrition,  (vii)  Disease  Control,  (vii)  Urban  Health,  and  (xi)  IEC  and  Behavior  Change  Communications  

Page 13: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  6  

2 P R O G R E S S   A G A I N S T   O B J E C T I V E S   A N D  M A I N   F I N D I N G S   O F   T H E  T H EM A T I C   A R E A   T E C H N I C A L   R E P O R T S  

2 . 1 I N T R O D U C T I O N   A N D   O V E R V I EW  

The  IRT  reviewed  32  operational  plans  as  part  of  its  assessment  of  the  eight  Thematic  Areas  that  composed  this  year’s  Annual  Programme  Review.  Each  of  the  following  eight  sections  provides  a  summary  of  the  principal  findings,  challenges  and  recommendations  from  the  concerned  IRT  technical  reviewer.    It  should  be  noted  that  the  ninth  Thematic  Area,  Gender,  Equity,  Voice  and  Accountability  (GEVA)  was  not  reviewed  this  year.  Rather,  the  HPNSDP  Steering  Committee  felt  that  the  Stakeholder  Consultation  would  suffice  to  address  GEVA  issues  while  serving  the  needs  of  the  IRT.  Issues  related  to  human  Resources  were  a  principal  crosscutting  issue  addressed  by  and  reported  on  in  each  of  the  eight  Thematic  Area  Technical  Reviews.  In  addition  to  the  assessment  of  progress  against  objectives  for  each  of  these  technical  reviews,  this  chapter  also  includes  the  key  technical  issues  for  each  thematic  area  to  be  discussed  during  the  policy  dialogue.    The  following  eight  sections  provide  the  executive  summary  and  recommendations  from  each  Technical  Review  that  is  “suitable  from  the  technical  reviews  that  will  inform  the  Aide  Memoire  for  the  overall  APR.”  

2 . 2 F I N A N C I A L   M A N A G EM E N T ,   W I T H   P L A N N I N G   A N D   B U D G E T I N G  

Planning,  budgeting,  and  financial  management  are  key  ingredients  to  achieving  the  overall  objectives  of  the  HPNSDP.  The  health  sector  is  challenged  by  historic  institutional  attributes  of  the  Bangladesh  public  sector,  such  as  the  complex  civil  service  structure  and  centralized  planning  system.  The  plurality  of  financing  mechanisms  by  development  partners  further  complicates  effective  planning  and  financial  management.  Despite  these  challenges,  the  sector  has  made  many  improvements  over  the  years  and  has  worked  creatively  to  overcome  structural  complexities  with  innovations  such  as  local  level  planning  and  outsourcing  human  resources.  Overall,  the  HPNSDP  is  on  the  right  track,  as  evidenced  by  the  marked  improvement  in  health  indicators  and  increasing  willingness  by  development  partners  to  use  government  systems  for  financing.    

Results  and  Achievements  Since  the  last  APR  in  2009,  the  MOHFW  has  made  significant  progress.  The  sector  program  has  attracted  increased  resources  from  DPs  into  the  RPA  pooled  fund,  reflecting  the  high  degree  of  confidence  in  the  country  public  financial  management  system  by  international  community.  The  empowerment  of  the  Financial  Management  and  Audit  Wing  (FMA  Wing)  to  oversee  all  financial  functions  for  both  the  revenue  and  development  budget  (under  the  Joint  Secretary  of  Finance)  is  a  welcome  step  towards  harmonization.  The  MOHFW  is  on  track  to  outsource  critically  needed  financial  management  and  audit  staff  on  a  temporary  basis  to  support  the  FMAU  and  line  directors,  thereby  mitigating  a  major  concern  in  previous  APRs.  Internal  audit  has  been  strengthened.  According  to  APIR  2012,  financial  management  and  audit  trainings  have  occurred  at  all  levels  of  the  system,  which  has  greatly  contributed  in  improving  overall  financial  management,  reducing  financial  irregularities  and  consequently  audit  objections.  Though  much  work  is  still  needed,  the  development  of  the  ADP  Monitoring  System  has  proven  to  be  a  powerful  financial  management  tool  for  the  MOHFW.  Finally,  the  quality  and  timeliness  of  financial  management  reporting  has  improved,  facilitating  on-­‐time  reimbursement  by  DPs.    

Challenges  and  constraints  Several  challenges  in  resource  planning,  budgeting,  and  financial  management  still  confront  the  health  sector.  Our  key  areas  of  concern  are:  

1 The  HPNSDP  is  not  on  track  to  be  financed  by  the  amounts  set  forth  in  the  PIP.  Although  overall  HPNSDP  spending  for  the  FY  2011-­‐2012  stood  at  87  percent  against  the  allocated  the  Revised  Annual  Development  Plan  (RADP),  only  about  60  percent  of  the  OP  provision  for  2011-­‐12  was  allocated  in  the  RADP  of  the  same  year  and  the  actual  utilization  stood  at  53  percent  of  the  OP  

Page 14: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  7  

provision.  The  ADP  allocation  in  2012-­‐2013  indicates  further  decline  in  the  trend,  as  only  58.5  percent  of  the  OP  provision  has  been  allocated  for  the  year.  In  2011-­‐2012,  overall  budget  execution  was  87  percent,  though  in  some  OPs  it  is  below  50  percent.  Bottlenecks  to  budget  execution  include  delays  in  the  release  of  fund,  shortage  of  trained  FM  staff,  and  inadequate  delegated  financial  power  of  Line  Directors  (LDs).  The  recent  revision  of  the  fund  release  procedure  by  the  MOF  restricting  the  authority  of  the  line  ministries  to  release  more  than  one  quarter  of  the  fund  at  a  time  without  the  approval  of  the  MOF  will  further  slowdown  the  process  of  fund  release  and  consequently  the  utilization  of  ADP  allocation.    

2 Systems  for  comprehensive  resource  planning  and  tracking  do  not  exist.  As  previous  APRs  have  pointed  out,  Bangladesh  has  had  a  historic  disconnect  between  the  development  and  non-­‐development  budgets  in  health,  which  still  exists  today.  The  Planning  Wing  (PW)  is  responsible  for  the  preparation  of  the  development  budget,  with  almost  no  interaction  with  the  FMAU,  which  prepares  the  non-­‐development  budget.  This  lack  of  coordination  has  led  to  sub-­‐optimal  resource  allocation.  

Further  to  this  historic  phenomenon,  the  assessment  team  was  also  concerned  about  the  lack  of  systematic  planning  and  coordination  of  Direct  Project  Aid  (DPA)  and  parallel  funds.  Systems  for  ensuring  that  development  partners  coordinate  their  efforts  through  joint  work  planning  and  honor  their  aid  commitments  were  not  evident.  Systematic  expenditure  tracking  for  DPA  and  parallel  funds  was  also  not  evident,  thus  it  was  not  possible  to  clearly  ascertain  the  sources  of  all  financing  supporting  the  HPNSDP  and  the  priorities  financed  from  those  sources  within  the  HPNSDP.  Finally,  a  joint  systematic  review  process,  in  which  all  SWAp  partners  jointly  evaluate  resource  utilization  by  each  partner,  was  also  not  evident.    

3 Lack  of  human  resources  in  health  finance  and  financial  management  is  a  major  impediment.  The  outsourcing  of  financial  management  and  audit  staff  should  help  relieve  these  constraints  in  financial  management,  however  planning  for  permanent  staffing  is  needed  once  this  stop  gap  measure  ends.  The  organogram  of  the  Financial  Management  and  Audit  Unit  (FMAU)  appears  to  have  too  many  support  staff  and  not  enough  technical  staff.  The  Health  Economics  Unit  (HEU)  still  faces  serious  human  resource  capacity  constraints,  especially  in  light  of  the  critical  work  ahead.  Staff  reposting  and  technical  knowledge  in  health  economics  and  finance  were  described  as  the  most  pressing  human  resource  issues.    

4 Resource  allocation  is  not  based  on  need.  Development  budget  is  prepared  on  the  basis  of  multiyear  plan  (OPs).  Allocations  are  often  made  without  making  field  level  needs  assessment  on  annual  basis.  Cost  centers  at  the  field  level  have  virtually  no  participation  in  budget  preparation.  As  a  result,  the  budget  is  often  not  need-­‐based  causing  under-­‐allocation  in  certain  priority  areas  as  well  as  over-­‐allocation  of  resource  in  certain  activities.  Local  Level  Planning  (LLP)  attempted  to  resolve  this,  and  strong  progress  was  made  in  training  and  the  preparation  of  LLP  plans  nationwide.  Unfortunately,  despite  the  Project  Appraisal  Document  (PAD)  and  Programme  Implementation  Plan  (PIP)  recommendations,  the  LLP  plans  were  still  not  linked  to  budget  allocation,  thus  very  little  practical  impact  of  LLP  is  evident.  

Principal  Recommendations    1 Ensure  adequate  resource  allocation  and  efficient  utilization  to  achieve  HPNSDP  results.  A  joint  

review  by  GOB  and  DPs  should  be  undertaken  immediately  to  analyze  the  growing  trend  of  underfunding  OP  provisions  of  PIP.  In  addition,  discussions  with  the  finance  division  must  be  held  to  relax  the  newly-­‐imposed  quarterly  fund  release  for  RPA.  Other  actions  include  more  aggressive  monitoring  by  planning  wing  for  budget  execution  by  OPs  and  improved  performance  of  MOHFW  in  clearing  procurements  for  World  Bank  approval.  Finally,  joint  OP  planning  with  districts  can  help  allay  Civil  Surgeon  (CS)  and  Deputy  Director,  Family  Planning  (DDFP)  concerns  of  underfunding  while  improving  OP  spending.  

Page 15: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  8  

2 Implement  comprehensive  resource  planning  and  tracking  system.  A  comprehensive  picture  of  all  planned  and  expended  finances  in  the  HPNSDP  is  critically  needed  to  ensure  strong  planning  and  sector  management.  Building  from  the  unified  workplan  developed  in  previous  years,  an  online  system  should  be  developed  that  accounts  for  planned  and  expended  budgets  from  all  sources  of  financing  of  the  HPNSDP:  non-­‐development,  development,  DPA,  Reimbursable  Project  Aid  (RPA),  and  parallel  funds  that  support  HPNSDP.  An  expert  team  should  be  constituted  to  assess  current  resource  planning  tools,  develop  joint  annual  work  plan  classifications,  and  develop  a  blue  print  and  action  plan.  

3 Increase  human  resource  capacity  in  health  financing  and  financial  management  in  the  health  sector.    An  immediate  review  of  the  current  staffing  structure  of  FMAU  is  needed,  with  an  eye  towards  revising  the  organogram  to  increase  professional  posts  and  reduce  support  staff.  Also,  a  review  of  human  resource  needs  to  accomplish  objectives  in  health  economics  OP  should  be  undertaken,  and  a  strategy  to  fill  human  resource  gaps  should  be  developed.  This  strategy  should  be  jointly  developed  with  DPs  (including  parallel  funders),  who  can  help  close  the  technical  manpower  gap.  

4 Link  local  level  planning  with  fund  allocation.  LLP  is  a  powerful  mechanism  to  ensure  need-­‐based  resource  allocation.  However,  without  concrete  steps  to  mainstream  LLP  into  the  national  budgeting  process,  the  initiative  will  not  succeed.  Financial  mechanisms  to  operationalize  LLP  must  be  put  in  place.  Financial  management  procedures  must  be  developed  for  LLP  administration.  Legal,  administrative,  and  procedural  actions  to  enable  the  delegation  of  financial  and  administrative  authority  should  be  completed.  The  PAD  and  PIP  outline  the  necessary  actions,  however,  little  progress  has  been  made.  An  expert  team  should  be  constituted  to  develop  a  phased  action  plan  for  operationalizing  these  steps.  

2 . 3 P R O C U R EM E N T   A N D   S U P P L Y   C H A I N   M A N A G EM E N T  

The  basic  configuration  of  the  public  procurement  system  followed  by  the  MOHFW  has  not  changed  over  the  past  years.  In  the  current  (third)  health,  population  and  nutrition  sector  program,  there  are  four  main  procuring  entities  at  the  national  level.  The  Procurement,  Storage  and  Supplies  Management  (PSSM)  of  Directorate  General  Health  Services  (DGHS)  and  Procurement,  Logistics  and  Supplies  Management  (PLSM)  of  the  Directorate  General  Family  Planning  (DGFP)  are  using  reimbursable  project  aid  mainly  for  goods  and  non-­‐consulting  services.  The  HED/MOHFW  and  the  PWD  (the  specialized  health  wing  of  the  Ministry  of  Housing  and  Public  Works)  both  mainly  operate  using  GOB  development  and  revenue  budget.    

The  IRT,  in  this  technical  review,  looked  at  the  operational  plans  of  PSSM,  PLSM,  Physical  Facilities  Development  (PFD)  and  Strengthening  of  Drug  Administration  and  (SDAM).  

Line  directors,  the  tertiary  hospitals  and  the  civil  surgeons  do  limited  procurement  of  goods  using  mainly  GOB  development  and  revenue  budget.  

The  MOHFW  through  PFD  and  PLMC  provide  technical  support  for  the  procurement  of  consulting  services.  

After  a  long  delay  the  PLMC  has  been  formally  constituted  under  PFD  (August  2012)  to  ensure  coordination  and  technical  support  to  the  procuring  entities.  

Results  and  achievements  A  first  strategic  planning  workshop  to  strengthen  procurement  management  and  monitoring  was  held  in  December  2011.  An  initial  draft  strategic  plan  was  produced.  

Although  there  is  no  written  “public  procurement  improvement  plan”  as  such,  different  elements  such  as  capacity  building,  the  development  of  e-­‐tools,  improved  communication  and  coordination  

Page 16: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  9  

are  together  gradually  helping  to  develop  a  sound  strategy,  which  is  starting  to  produce  positive  outcomes.  

The  multi-­‐layered  training  approach  (5-­‐day  training,  3-­‐week  training,  CIPS  training,  etc.)  allows  for  targeting  the  beneficiaries.  It  not  only  allows  for  improving  the  general  procurement  understanding  amongst  civil  servants  but  also  allows  for  developing  specialized  procurement  capacity.  

In  general,  the  number  of  civil  servants  that  have  been  trained  in  procurement  has  increased  significantly  and  there  seems  to  be  a  better  understanding  of  procurement  principles  and  procedures  throughout  the  sector,  horizontally  and  vertically.  

The  managerial  procurement  capacity  in  the  major  procuring  entities  has  also  improved  as  evidenced  by  lack  of  stock  out  of  items,  reduction  of  procurement  lead-­‐time,  and  improved  communication  and  data  management,  especially  in  the  family  planning  sub-­‐sector.  

The  commitment  of  the  government  to  procurement  efficiency,  transparency,  and  accountability  is  clear.  This  includes  introducing  electronic  web  based  tools  in  procurement  and  supply  processes  improving  coordination  and  management  of  the  procurement  plans,  as  well  as  for  the  monitoring  of  the  procurement  and  supply  chain  processes.  It  is  expected  with  fair  amount  of  confidence  that  if  the  current  pace  of  development  is  maintained,  it  will  have  a  significant  effect  on  the  reduction  of  lead  times  and  system  wastage  in  the  coming  years.  

The  introduction  of  regular  routine  meetings  between  the  major  procuring  entities  and  the  Line  Directors  to  discuss  and  review  procurement  plans,  procurement  packages,  procurement  progress,  and  distribution  plans  is  another  major  step  that  will  likely  result  in  increased  efficiency  and  reduced  lead  time  and  complaints.  

The  creation  of  the  PLMC  is  an  important  step  towards  reinforcing  both  the  coordination  and  the  monitoring  role  of  the  MOHFW,  as  well  as  its  regulatory  function.  

Constraints  and  challenges  The  currently  available  storage  space  at  the  national  level  and,  in  some  cases,  at  the  regional  or  district  level  is  no  longer  sufficient  to  deal  with  either  the  current  volumes  (quantity)  or  to  ensure  the  quality  drug  management.  

Although  investments  in  medical  equipment  are  large  and  system  wastage  is  significant,  very  little  has  been  done  to  develop  and  maintain  a  national  level  medical  equipment  database.  

The  introduction  of  routine  procurement  and  supply  audits  (internal  or  external)  has  not  yet  begun  nor  have  all  procurement  agents  produced  procurement  risk  mitigation  plans.  

All  line  directorates  have  a  designated  procurement  correspondent  and  the  procuring  entities  all  have  focal  points  but  not  all  relevant  staff  has  been  trained  yet.  

The  existing  system  can’t  always  ensure  that  the  staff  and  equipment  necessary  for  functioning  of  facilities  is  available  immediately  after  their  construction.  

The  limited  administrative  and  financial  authority  at  divisional  and  district  level  has  a  negative  impact  on  their  ability  to  render  the  health  system  more  efficient  and  cost  effective.  

Conclusions  and  recommendations  The  overall  strategy  to  reinforce  the  procurement  and  supply  management  that  was  started  in  the  previous  sector  program  has  produced  results.  The  MOHFW  (Development  &Monitoring  and  Evaluation  /  ME)  has  continued  and  initiated  a  number  of  activities  (capacity  building,  e-­‐tools)  that,  if  sustained,  could  produce  transparent,  efficient,  and  effective  procurement  and  supply  systems  by  the  end  of  this  sector  program.  More  attention  can,  and  should,  be  given  to  the  downstream  supply  management.  There  are,  however,  still  a  number  of  issues  that  have  to  be  addressed  in  the  short  term,  including  the  following:  

Page 17: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 0  

1 All  the  different  elements  that  together  constitute  the  procurement  and  supply  strategy  should  be  institutionally  linked  through  the  PLMC,  whose  own  institutional  linkages,  and  working  relationships  both  vertically  and  horizontally  should  be  further  examined  and  defined.  A  standards  operation  procedures  manual  should  be  developed  for  PLMC.  

2 A  critical  mass  of  procurement  specialists  has  not  yet  been  reached  and  the  MOHFW  should  continue  to  invest  in  training.  

3 It  is  strongly  recommended  that  health  sector  e-­‐procurement  be  undertaken  through  electronic  government  procurement  (e-­‐GP)  and  not  by  using  a  specific  MOHFW  procurement  site.  The  MOHFW  through  the  PLMC  should  continue  working  with  the  CPTU  with  an  objective  to  start  using  e-­‐GP  within  the  current  fiscal  year.  

4 The  preparation  of  the  annual  procurement  plans  should  start  simultaneously  with  the  annual  development  plan  in  April  before  the  start  of  the  new  fiscal  year.  

5 An  in-­‐depth  study  should  be  commissioned  with  subject  specialists  to  look  into  solving  the  space  shortage  of  storage,  taking  into  account  possible  construction,  as  well  as  reconfiguration  of  the  existing  storage  and  supply  system.  

6 Standardization  and  definition  processes  should  be  reinforced  (medical  equipment,  tables  of  equipment,  standard  tender  documents)  and  a  national  level  web  based  medical  equipment  database  should  be  established  as  soon  as  possible  and  administered  either  by  the  PLMC  or  the  Central  Medical  Stores  Department  (CMSD).  

2 . 4 MON I T O R I N G   &   E V A L U A T I O N  

This  summary  reports  the  findings  of  the  thematic  area:  Monitoring  and  Evaluation.  The  objective  of  the  M&E  thematic  review  is  to  highlight  health  systems  issues  and  challenges  in  monitoring  HPNSDP  outcomes  and  outputs  at  both  the  RFW  and  OP  levels  and  to  make  recommendations  for  strategies,  implementation,  and  financing  for  the  remainder  of  the  program.  The  base  of  this  analysis  is  the  review  of  the  operational  plans  of  the  Sector  Wide  Program  Management  &  Monitoring  (SWPMM),  of  the  Programme  Monitoring  and  Evaluation  (PME-­‐)  FP,  Management  information  Systems  (MIS)-­‐FP,  HIS/eHealth,  PM&R,  the  APIR  of  the  Programme  Management  and  Monitoring  Unit  (PMMU),  and  various  web-­‐based  Health  Information  Systems  (HIS).      

Main  Analysis  and  Findings:  SWPMM  and  the  PMMU  

The  SWPMM  became  operational  in  July  2011  with  the  general  objective  of  improving  the  performance  of  HPN  sector  through  appropriate  planning,  budgeting,  and  monitoring  for  coordination  and  efficient  utilization  of  resources.  SWPMM  has  four  components:  1)  Planning  and  budgeting;  2)  Monitoring  and  Evaluation;  3)  Governance  and  Stewardship  and  4)  Coordination  and  Collaboration.  In  regards  to  improving  monitoring  and  evaluation,  SWPMM  has  established  the  Program  Management  and  Monitoring  Unit  (PMMU).  SWPMM  drafted  a  strategic  M&E  Framework  and  Action  Plan  in  2008/2009  which  was  intended  to  address  overall  coordination  of  M&E  between  OPs  to  improve  HPNSDP  monitoring.  It  has,  however,  not  been  approved  and  thus  leaves  no  guiding  framework  for  SWPMM  M&E  tasks.  

The  PMMU,  which  became  operational  at  the  beginning  2012,  is  replacing  the  former  MEU  (Monitoring  and  Evaluation  Unit  under  the  HNPSP).  PMMU’s  main  objective  is  to  manage  and  monitor  the  implementation  process  of  the  HPNSDP.  The  PMMU  produced  the  first  APIR  in  September  2012.  This  document  was  used  as  the  main  source  for  the  IRT  (Independent  Review  Team)  to  evaluate  progress  of  HPNSDP  32  OPs  and  their  corresponding  indicators  (316,  around  10  for  each  OP).    

Page 18: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 1  

The  316  indicators  have  been  collected  using  templates  to  be  filled  by  32  Line  Directors  (yearly)  in  a  self-­‐evaluation  procedure  to  assess  OPs  progress  of  the  HPNSDP.    Comparing  the  status  quo  and  relating  them  to  the  target  indicators  for  the  mid-­‐term  evaluation  (in  2013),  and  adjusting  the  mid-­‐term  targets  to  the  current  FY  (2011-­‐2012),  produced  the  achievement  rate  of  all  316  indicators.  

The  IRT  has  reviewed  indicators  of  all  OPs  and  found  them  to  be  of  mixed  quality  with  the  results  found  in  each  of  the  other  seven  TATRs  as  well  as  those  reviewed  for  this  Thematic  Area  (see  Annex  1  and  discussion  in  the  following  full  report).    The  various  IRT  Thematic  Area  teams  have  noted  problems  with  OP  indicators,  including  the  lack  of  baselines,  unclear  targets  and/or  ambitious  targets,  and  sometimes  confusing  recording  of  achievements.  The  great  majority  of  OP  indicators  are  quantitative  and  largely  measure  numbers,  whether  of  people  trained,  items  procured  and  distributed  or  materials  developed.  These  are  considered  output  or  process  indicators  and  are  supposed  to  link  upwards  to  the  HPNSDP  Results  Framework  (RFW).    

The  M&E  Team  recognizes  that  this  is  the  first  time  under  any  of  the  SWAps  that  such  a  rigorous  undertaking  has  been  related  to  managing  for  development  results.  While  the  32  OP  have  made  significant  progress  as  noted  in  the  APIR,  the  M&E  Team  believes  that  there  is  an  opportunity  to  move  the  process  forward  by:  1)  revising  many  of  the  indicators  found  in  all  the  OPs,  including  this  one;  and  2)  developing  an  intermediary  set  of  results  and  corresponding  indicators  for  OP  performance  management  purposes  between  the  current  set  of  output  indicators  found  in  the  OPs  and  the  outcome  and  impact  results  found  in  the  RFW  and  based  on  the  log-­‐frames  found  in  each  OP.      

A  brief  review  of  the  current  health  information  systems  was  conducted  in  order  to  assess  if  data  and  reports  from  various  sources  are  reliable,  available  and  may  function  as  a  tool  for  the  M&E  tasks.  Data  on  urban  health  services  and  NGO/private  provider  service  are  currently  not  complete,  and  data  on  project  implementation  and  activities  (ADP  and  OP)  are  still  processed  in  stand-­‐alone  systems.  Routine  reports  are  not  yet  tailored  to  the  identified  needs.  Both  HIS  &  eHealth  and  MIS/FP  directorates  initiated  web-­‐based  applications  for  data-­‐entry,  transmission,  storage,  and  retrieval.    The  MOHFW  health  information  system  still  experiences  some  duplication  of  data-­‐collection  and  parallel  reporting  structures.  The  Data  Warehouse  project  (DMIS)  needs  a  thorough  review  to  test  for  functionality  and  better  integration  into  MOHFW  organizational  structure.  There  is  also  an  urgent  need  to  determine  whether  the  technical  assistance,  which  has  been  provided  to  the  MOHFW  in  the  establishment  of  the  data  warehouse,  has  been  effective  in  this  regard  and  what  the  intentions  are  by  the  technical  provider  (GiZ)  in  terms  of  its  future  support  to  the  Ministry.  Finally,  the  M&E  Team  notes  that  hiring  and  retaining  human  resources  for  both  HIS/e-­‐Health  and  MIS-­‐FP  continues  to  be  a  challenge,  as  the  GOB’s  low  salary  scale  remains  unattractive  for  high  level  IT  experts.  

Conclusions  and  Recommendations:    1 The  IRT  recommends  that.  in  addition  to  the  revision  of  the  current  set  of  indicators  in  each  OP  

that  are  used  to  measure  OP  progress  including  those  reviewed  under  this  Thematic  Area,  an  additional  number  of  intermediary  result  level  indicators  based  on  OP  Log-­‐frames  be  incorporated  into  OP  performance  monitoring  system.  Specifically,  each  OP  should  review  the  Output  and  Purpose  level  indicators  in  the  OP  log-­‐frames  that  are  more  results  oriented  than  the  input/output/process  indicators  currently  used  to  track  progress  of  the  OPs.  In  this  regard,  the  IRT  recommends  that  a  results-­‐based  management  specialist  provide  technical  support  to  the  OP  teams  undertaking  these  important  exercises  (short-­‐term  activity,  2012-­‐2013).  

2 Full  development  of  the  M&E  Strategy  from  the  existing  M&E  Framework  should  be  completed  and  approved  as  soon  as  possible.  As  part  of  this  strategy  development  it  is  recommended  that  an  analysis  of  the  implementation  effectiveness  of  the  existing  roles  and  responsibilities  of  the  concerned  units  within  MOHFW,  i.e.,  SWPMM,  PMMU,  Planning,  Monitoring  and  Research  (PMR),  Planning,  Monitoring  and  Evaluation  of  Family  Planning  (PME-­‐FP),  with  Management,  Monitoring  and  Reporting  functions  should  be  conducted.    This  would  include,  as  per  the  TORs,  

Page 19: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 2  

the  relationship  between  the  PMMU  and  the  Line  Directors  in  terms  of  monitoring  and  oversight  of  OP  progress  (short-­‐term  activity,  2012-­‐2013).  

3 It  is  recommended  that  the  PMMU  begin  the  process  of  taking  on  the  independent  role  for  the  PW  of  monitoring  MOHFW  results  progress  at  both  the  OP  and  RFW  levels  through  periodic  progress  reports,  including  OP  indicator  performance  reporting  that  are  discussed  at  the  monthly  LD  meetings  with  concerned  DG  heads,  are  forwarded  to  the  PMMU  for  information  and  consolidation.  This  will  likely  require  targeted  TA  from  an  RBM  expert,  but  should  be  able  to  be  completed  by  the  MTR  (short-­‐  to  medium  term).  

4 It  is  further  recommended  that  the  PW  undertake  a  review  and  analysis  of  the  existing  MIS  system  to  incorporate  OP  reporting  and  analysis  to  ensure  more  regular  OP  performance  monitoring.  ADP  and  expenditure  data  need  to  be  available  in  real-­‐time  and  accessible  by  authorized  stakeholders.  This  activity  should  be  accomplished  before  the  midterm  review.  (Mid-­‐term,  MTR).  

5 It  is  recommended  that  the  M&E  TG  review  and  determine  whether  the  DMIS  initiative  is  fulfilling  the  function  for  which  it  was  designed.  This  activity  should  take  into  consideration  WHO’s  policy  recommendation  creating  interoperable  information  systems  and  a  common  data-­‐warehouse.  This  should  include  an  analysis  of  whether  the  current  TA  provider  is  providing  the  right  quantity  and  quality  support  required  to  fully  operationalize  and  sustain  the  DMIS.  In  the  event  that  this  assessment  leads  to  the  continuation  of  the  DMIS,  the  data-­‐ware-­‐house  system’s  technical  support  should  be  integrated  to  the  HIS/eHealth  (short-­‐term  activity).  As  per  one  of  the  recommendations  that  came  out  of  a  review  of  the  draft  M&E  report,  the  analysis  should  determine  whether  HRIS  can  be  integrated  into  current  configuration  (short-­‐term,  2012-­‐2013).  

6 It  is  recommended  that  the  PMMU  utilize  existing  IT  infrastructure  at  the  MOHFW,  specifically  that  HIS/E-­‐health  should  develop  data  banks  that  generate  reports  based  on  PMMU  specification  in  order  to  support  PMMU  responsibilities  in  this  area  (mid-­‐term,  MTR).  

7 Consistent  with  the  PIP  and  the  SWPMM  OP,  the  IRT  concludes  that  the  PMMU  is  best  placed  to  support  the  Planning  Wing’s  responsibility  to  monitor,  analyse,  and  report  on  the  performance  of  the  32  OPs  and  progress  of  the  RFW.  It  is  the  IRT’s  recommendation,  therefore,  that  the  PMMU  will  require  additional  staff  with  expertise  in  performance  management  and  managing  for  development  results;  and,  an  implementation  plan  that  clearly  lays  out  priorities  and  the  activities,  timelines,  benchmarks  and  individual  PMMU  member  responsibilities  to  ensure  this  most  important  PW  function  is  achieved.  It  is  hoped  that  a  concerned  DP(s)  would  support  this  recommendation  (short-­‐term  activity).  

8 Consistent  with  WHO  Health  Metrics  Network  recommendation,  the  MOHFW  should  consider  bringing  in  technical  support  to  begin  the  process  of  developing  a  draft  on  Health  Information  Policy.  The  policy  needs  to  address  data  security,  data  validity,  reporting  obligations  of  non-­‐MOHFW  government  health  services,  the  private-­‐  and  NGO  sector  (long-­‐term,  2016).  

9 To  further  improve  the  process  of  data  collection  at  facility  level,  consider  an  assessment  of  data  collection  and  reporting  functions  at  the  Upazila  level  and  above  to  determine  if  efficiencies  (reduce  multiple  redundant  data  collection  forms)  can  be  improved  (mid-­‐term  activity).  

10 A  study  is  recommended  to  examine  the  rationale  for  creating  a  Central  IT  Information  Unit,  preferably  headed  by  the  HIS/eHealth,  to  be  attached  directly  to  the  Secretary  of  Health,  in  order  to  establish  one  entity  responsible  for  data  processing,  software  design,  reporting,  and  interoperability  of  all  MOHFW  information  systems  (long-­‐term,  2016).    

Page 20: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 3  

2 . 5 D I S E A S E   C O N T R O L   ( I N C L U D I N G   H UM A N   R E S O U R C E S )  

The  HPNSDP  contains  five  OPs  directly  related  to  disease  control.  Three  OPs,  i.e.,  communicable  disease  control,  National  AIDS/STD  Program  and  Tuberculosis  (CDC,  NASP,  TB&LC)  deal  with  communicable  diseases  and  two  OPs,  i.e.,  non-­‐communicable  Disease  Control  and  National  Eye  Care  (NCDC,  NEC)  with  non-­‐communicable  diseases.  Considerable  success  has  been  made  in  managing  communicable  diseases  through  well  run  vertical  programmes  which  have  attracted  both  pool  and  parallel  DP  support  and  extensive  technical  assistance.  Leprosy  has  almost  been  eliminated  from  the  country;  TB  and  malaria  have  strong  control  programmes  in  place  although  the  burden  of  disease  remains  high;  and  the  country  has  responded  well  to  emerging  threats  such  as  avian  influenza,  pandemic  H1N1  and  nipah  virus;  the  prevalence  of  Human  Immune-­‐Virus  (HIV)  in  Most  at  Risk  Population  (MARPs)  remains  under  1  percent.    

Success  in  controlling  communicable  and  vaccine  preventable  diseases,  reductions  in  maternal  and  neonatal  mortality  combined  with  sustained  economic  growth  (the  number  living  in  poverty  has  reduced  from  49  percent  in  2000  to  31  percent  in  2010),  rapid  urbanization,  reduced  fertility,  and  increased  life  expectancy  are  all  contributing  to  a  major  change  in  the  epidemiology  of  disease.  NCDs  now  account  for  52  percent  of  deaths,  up  from  44  percent  in  2002;  diabetes  prevalence  is  about  7  percent  and  Bangladesh  will  be  among  the  top  ten  countries  in  the  world  by  the  number  of  people  living  with  diabetes  in  2025  –  just  as  it  is  now  for  TB.  

Although  most  people  seek  outpatient  care  from  private  providers  and  the  non-­‐formal  sector,  the  majority  of  inpatient  care  still  occurs  in  public  facilities.  Significant  progress  and  investment  has  been  made  in  upgrading  facilities  but  less  progress  has  been  made  in  addressing  the  more  fundamental  issue  of  staff  numbers,  location  and  skill  mix.  In  particular,  the  lack  of  nurses  and  midwives  remains  a  critical  issue.  

Results  and  Achievements  Good  progress  has  been  made  in  malaria  control  with  an  impressive  reduction  in  mortality  from  0.0034/1000  to  0.0022/1000  and  67  percent  coverage  of  households  with  LLIN;  a  TB  drug  resistance  survey  has  been  completed,  treatment  guidelines  written,  and  Multi-­‐Drug  Resistant  (MDR-­‐)TB  enrollment  started  outside  Dhaka;  PEP  for  rabies  is  now  available  in  64  districts;  progress  is  being  made  in  the  treatment  of  kala-­‐azar;  and  the  national  response  to  pandemic  H1N1  and  avian  influenza  was  rapid,  flexible  and  coordinated;  targets  for  cataract  surgery  for  2014  have  already  been  achieved.  A  national  strategy  for  NCDs  has  been  developed  and  a  national  strategic  plan  for  HIV/AIDS  is  also  in  place.  However,  implementation  in  both  these  programmes  is  weak.  

Recruitment  was  static  from  2008-­‐2010  but  since  then  over  2000  nurses  and  3000  doctors  have  been  recruited.  A  direct  entry  midwifery  programme  has  been  established  that  aims  to  train  3000  midwives  by  2015  –  a  recommendation  from  the  last  APR.  Drug  supply  has  improved  at  hospitals  with  stock-­‐outs  no  longer  a  major  problem  and  the  use  of  web-­‐based  systems  has  significantly  improved  the  quality  and  timeliness  of  reporting  from  district  and  sub-­‐district  levels.  

Challenges  and  Constraints  A  number  of  challenges  exist.  The  key  areas  of  concern  are:      

1 The  NASP  used  only  41  percent  of  PA  funds  during  the  FY2011-­‐12.  The  Global  Fund  for  AIDS,  TB  and  Malaria  (GFATM)  programme,  United  States  Agency  for  International  Development  (USAID)  HIV  Prevention  Programme,  and  NASP  OP  are  complementary  and  all  are  needed  to  implement  the  national  strategic  plan.  The  provision  of  Anti-­‐retroviral  therapies  (ARTs)  (from  November  2012),  VCT  (from  September  2013)  and  national  sero-­‐surveillance  lie  with  the  NASP.  The  delay  in  the  release  of  funds  means  that  implementation  in  these  and  other  areas  has  been  delayed,  creating  significant  problems  on  the  ground  and  risks  for  the  future.    

2 The  number  of  nurses  and  midwives  being  trained  and  recruited  remains  too  low.  Despite  clear  political  support  and  an  ambitious  OP  the  key  issues  remain  unaddressed  and  the  capacity  of  the  

Page 21: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 4  

Director  of  Nursing  Services  (DNS)  to  deliver  the  OP  is  limited  largely  by  factors  beyond  its  control.  The  bottlenecks  in  the  recruitment  and  promotion  of  nurses  remain;  a  full  director  of  nursing  has  not  been  appointed  since  1992;  and  the  number  and  quality  of  training  facilities  and,  more  importantly,  trainers  is  low.  

3 Implementation  in  the  area  of  NCDs  is  weak  and  uncoordinated.    The  NCD  strategy  rightly  focuses  on  screening  and  prevention  to  be  delivered  via  existing  hospitals  and  clinics.  However  implementation  to  date  is  weak  and  the  ability  of  already  busy  and  understaffed  units  to  manage  this  is  unclear;  only  limited  use  has  been  made  of  the  many  national  institutes  in  this  field.    

Principal  Recommendations    1 Conduct  a  mid-­‐term  review  of  the  national  strategic  plan  for  HIV/AIDS  in  early  2013.  This  

should  be  planned  now  using  money  allocated  from  the  OP  or  other  sources,  independently  led,  and  engage  stakeholders  in  the  field.  The  outputs  should  include  necessary  revisions  to  the  OP  and  budget  to  address  the  key  areas  of  concern.  

2 Remove  the  bottlenecks  in  nursing  recruitment  and  promotion  and  build  capacity  within  the  DNS.  Multiple  sets  of  rules  govern  nursing  recruitment  and  promotion  and  these  are  both  complex  and  confusing.  A  new  set  of  rules  has  been  drafted  and  priority  should  be  given  to  approving  and  implementing  this.  The  DNS  needs  strengthening  if  it  is  to  deliver  the  OP.  Appointing  a  full  director  of  nursing  for  the  first  time  since  1992  would  give  a  clear  signal  of  strong  commitment  in  this  area.  

3 Move  from  strategy  to  implementation  in  NCDs.  The  current  plan  is  to  use  hospitals  and  clinics  to  screen  for  diabetes  and  hypertension.  Far  more  capacity  and  interest  exists  at  the  community  clinics  and  screening  should  be  based  here.  The  expertise  of  national  institutes  such  as  NICVD  and  BIRDEM  should  be  used  to  develop  and  implement  simple,  low-­‐cost,  and  locally  appropriate  treatment  guidelines  and  also  to  monitor  their  use.  Focus  should  be  given  to  other  NCDs.  The  biggest  area  of  concern  is  drowning.  This  is  the  leading  cause  of  death  in  children  aged  1-­‐5  years  and  proven  interventions  exist  in  Bangladesh  

2 . 6 N U T R I T I O N   ( I N C L U D I N G   H UM A N   R E S O U R C E S )  

Results  and  Achievements  There  has  been  progress  in  the  reduction  of  stunting  and  underweight  in  children  under  five.  At  the  current  rate  of  progress  (from  41  percent  to  36  percent  in  the  period  2007-­‐2011),  Bangladesh  will  most  likely  attain  MDG  1  of  33  percent  underweight  by  2015.  It  will  be  much  more  difficult  to  reach  the  stunting  target  of  38  percent  given  current  progress  (from  43  percent  to  41  percent  in  the  period  2007-­‐2011).  Gains  in  exclusive  breastfeeding  rates  are  unlikely  to  result  in  substantial  reduction  in  stunting  unless  appropriate  infant  and  young  child  feeding  practices  (diet  diversity  and  frequent  feeding)  improve  substantially.  Only  30  percent  of  the  mothers  in  the  highest  wealth  quintile  and  23  percent  of  the  mothers  who  completed  secondary  education  or  higher  apply  at  least  three  of  the  recommended  Infant  &  Young  Child  Feeding  (IYCF)  practices.  Only  one  in  ten  mothers  in  the  lowest  wealth  quintile  and/or  not  having  attained  any  education  adequately  feeds  their  children.    

An  estimated  17  percent  of  all  children  under  five  suffer  from  acute  malnutrition.  That  is  some  2.5  million  children,  of  whom  half  a  million  suffer  from  severe  acute  malnutrition.  In  addition,  more  than  one  in  five  babies  (22  percent)  weigh  less  than  2,500  gram  at  birth  (Low  Birth  Rate  /  LBW).  Both  impact  negatively  on  under  five  and  neonatal  mortality,  because  low  birth  weight  babies  are  ten  to  twenty  times  more  likely  to  die  than  babies  of  normal  weight,  while  the  odds  of  severely  malnourished  children  dying  are  eight  times  as  high  as  those  of  well-­‐nourished  children.    

Levels  of  anaemia  among  women  and  children  are  very  high  (ranging  from  35  percent  to  70  percent).  Iron  deficiency  anaemia  is  estimated  to  cause  2.5  percent  drop  in  adult  wages  and  8  percent  loss  in  gross  domestic  production.      

Page 22: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 5  

Mainstreaming  nutrition  is  one  of  the  HPNSDP  priorities.  This  should  (eventually)  result  in  a  country-­‐wide  comprehensive  system  of  nutrition  services  delivery.  The  National  Nutrition  Service  (NNS)  OP  aims  to  improve  the  nutritional  status  of  women  and  children  and  has  formulated  targets  for  five  nutrition  outcomes.  If  these  are  achieved,  Bangladesh  will  be  well  on  the  way  to  reducing  under-­‐nutrition.  The  OP  has  prioritized  ten  activities/components,  progress  of  which  is  monitored  through  12  output/process  indicators.  During  the  first  year  of  implementation,  nine  of  these  (75  percent)  outputs  were  achieved.  One  of  the  outputs  not  achieved  is  the  development  of  the  nutrition  information  system  and  merging  thereof  with  the  current  HIS.  NSS  has  started  developing  this,  but  even  in  the  best  of  circumstances  this  takes  several  years  to  achieve.  The  output  in  terms  of  capacity  development  is  very  substantial  in  terms  of  health  staff  trained  at  all  levels,  particularly  considering  that  NSS  has  only  been  fully  functional  since  early  2012.    Whether  training  translates  into  improved  nutritional  services  is  difficult  to  assess  in  the  absence  of  nutrition  data  in  the  routine  HIS.    Moreover,  the  NNS  is  highly  dependent  on  health  staff  under  other  directorates  including  Hospital  Services  Management  (HSM),  Maternal,  Neonatal,  Child  and  Adolescent  Health  (MNCAH),  Maternal,  Child,  Reproductive  and  Adolescent  Health  (MC-­‐RAH),  Community  Based  Health  Care  (CBHC),  and  UPHCP  for  the  delivery  of  nutrition  services.        

Conclusions  and  Recommendations  Policy  level  

1 In  pursuance  of  article  18  (A)  of  the  constitution  (Improvement  of  the  Nutrition  of  the  people  and  public  health)  the  Government  of  Bangladesh  developed  a  Nutrition  Policy  aimed  at  improving  the  nutrition  status  with  a  particular  focus  on  women,  children  and  vulnerable  groups  and  reducing  severe  malnutrition  through  food  safety,  security,  supply,  and  nutrition  education.  The  National  Food  and  Nutrition  Policy  was  formulated  in  1997;  this  policy  was  split  into  two  parts  in  2006  when  the  section  on  Food  Policy  was  updated.  There  is  a  need  to  update  the  National  Nutrition  Policy.      

2 The  need  for  multi-­‐sectoral  coordination  to  improve  nutrition  has  been  recognized;  development  partners  and  several  ministries,  including  the  Ministries  of  Agriculture,  of  Livestock  and  Fisheries,  of  Education,  Food  and  Disaster  Management,  Industries  are  represented  in  the  Nutrition  Steering  Committee  under  the  lead  of  the  MOHFW.  The  effectiveness  of  the  Steering  committee  could  be  further  improved  by  preparing  subjects  in  smaller  forums  consisting  of  primary  stakeholders,  for  decisions  on  programmatic  collaboration.      

3 Because  for  most  activities  NNS  depends  on  other  services  for  actual  service  delivery,  all  relevant  services  should  include  in  their  OPs,  nutrition  outcomes  and  –  where  they  are  responsible  for  the  actual  service  delivery  –  outputs,  indicators  and  activities,  and  made  accountable  for  their  achievement.  When  adjusting  the  current  OPs,  this  should  be  a  priority.  Inclusion  of  nutrition  indicators  makes  visible  that  mainstreaming  nutrition  needs  a  concerted  effort  and  that  the  ultimate  desired  outcome  of  mainstreaming  is  integration.      

4 Steps  need  to  be  taken  to  implement  the  decision  of  the  Honourable  Prime  Minister  (as  per  Her  letter  of  8th  March  2011)  to  appoint  a  nutritionist  in  all  hospitals  (district  hospitals  and  UHC).  

Programme  level  

1 NNS  has  elaborated  both  a  comprehensive  strategy  and  a  plan  of  action  for  training  health  service  providers.  In  order  to  successfully  mainstream  nutrition  within  the  regular  health  services,  capacity  building  of  a  very  substantial  number  of  staff  at  all  levels  is  required.  This  cannot  realistically  be  achieved  by  NNS  alone.  Therefore,  nutrition  should  be  integrated  in  all  in-­‐service  and  pre-­‐service  conducted  by  DGHS  and  DGFP  training,  and,  under  the  leadership  of  MOHFW,  included  in  all  medical  (training)  institutions.      

2 Capacity  at  CC  level,  consisting  of  three  staff  working  part  time  (translated  in  two  full  time  equivalent  posts),  is  limited  in  view  of  the  (many)  activities  as  well  as  the  increasing  population,  

Page 23: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 6  

making  it  very  challenging  to  adequately  provide  services  including  home-­‐visits.  In  view  of  the  need  to  increase  nutrition  services  in  particular  at  CC  level,  it  is  recommended  to  incorporate  more  nutrition  workers  for  quick  fulfillment  of  the  HR  gap,  and  gradually  incorporate  them  in  the  revenue.  In  hard  to  reach  areas,  collaboration  with  NGO’s  using  the  NGO  partnership  model  should  be  pursued.      

3 Reducing  the  prevalence  of  anaemia  by  one  third  in  women  in  reproductive  age  and  children  is  unlikely  to  succeed  in  view  of  the  high  needs  and  a  food  consumption  pattern  low  in  iron,  unless  a  concerted  multi-­‐sectoral  effort  is  made.  The  latter  should  include  fortification  of  rice.  MOHFW  services  should  scale  up  supplementation  of  iron/folic  to  include  all  females  of  reproductive  age  and  children  under  five.      

Operational  level  

1 The  NNS  OP  prioritises  growth  monitoring  and  promotion  (GMP),  but  lacks  output  indicators  specifically  related  to  GMP.  It  is  recommended  to  include  an  output  indicator  for  GMP  when  the  OP  is  revised.  Health  workers,  in  particular  at  CC  level,  need  to  be  prioritized  for  capacity  building  in  GMP.    Monitoring  of  weight  (and  in  a  second  phase  height)  should  go  hand  in  hand  with  both  individual  and  group  counselling  on  IYCF  including  EBF  and  the  use  of  iodised  salt,  with  a  view  to  raise  awareness  on  adequate  nutrition  as  (one  of  the)  crucial  determinant(s)  of  children’s  healthy  growth.          

2 Ongoing  mass  media  campaigns  to  improve  IYCF  practices,  complementing  facility  based  and  community  based  nutrition  education,  should  be  intensified  and  research  on  the  impact  and  modalities  of  mass  campaigns  on  exclusive  breastfeeding  should  be  conducted  to  inform  the  ongoing  campaign  on  IYFC  as  well  as  other  mass  campaigns.  IEC  and  BBC  need  to  be  strengthened.      

3 Treatment  of  children  suffering  from  severe  acute  malnutrition  in  nutritional  rehabilitation  units  in  hospitals  and  priority  UHCs  needs  to  be  effectuated.  To  this  end  the  following  is  recommended:  (1)  scale-­‐up  training  in  management  and  control  of  severe  acute  malnutrition;  (2)  accelerate  the  distribution  of  measuring  equipment  and;  (3)  ensure  availability  of  F-­‐75  and  F-­‐100  (to  be  imported  as  an  interim  measure,  with  permission  from  MOHFW).  Without  easy  to  prepare  F-­‐75  and  F-­‐100  formula,  treatment  of  the  severely  malnourished  within  the  regular  health  services  is  simply  not  feasible.    

4 The  sheer  effort  of  mainstreaming  nutrition  warrants  a  step-­‐by-­‐step  approach  (as  already  foreseen  for  such  activities  like  inclusion  of  nutrition  data  in  the  HMIS  and  management  of  severe  acute  malnutrition).  It  is  better  to  proceed  systematically,  and  more  slowly,  and  adjusting  interventions  when  needed,  than  jeopardising  the  effectiveness  of  nutrition  activities.  

2 . 7 MN C H   A N D   F AM I L Y   P L A N N I N G   ( I N C L U D I N G   H UM A N   R E S O U R C E S )  

Bangladesh  over  the  past  decade  has  registered  dynamic  changes  in  the  social  and  economic  sectors.  Recent  national  surveys  (BDHS  and  BMMS)  report  remarkable  progress  on  a  good  number  of  health,  family  planning  and  MDG  indicators,  which  are  on  track  to  achieve  targets  by  2015.  Contributions  from  the  public,  private,  and  GOB  partnership  with  the  Development  Partners  (DPs)  and  NGO  community  must  be  appreciated.  Other  indicators  are  progressing  relatively  well  but  will  require  some  level  of  acceleration,  in  terms  of  increased  efforts,  investment,  planning  specific  health  interventions,  and  removing  health  care  delivery  system  bottlenecks  by  thinking  outside  the  box.  

Results  and  Achievements  Despite  impressive  gains  in  maternal,  neonatal,  and  child  health  indicators,  provision  of  services  in  government  health  facilities  remains  a  major  challenge.  The  provision  of  EmOC  at  UHC  level  is  limited  and  the  ones  already  in  place  are  not  functioning  24/7  as  expected,  mainly  due  to  HRH  issues  like  vacancies  against  sanctioned  positions.  The  pair  of  gynaecologist  and  anaesthetist  is  not  always  

Page 24: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 7  

functional  in  the  only  Upazila  visited  during  the  IRT  visit.  It  would  be  important  to  have  a  more  comprehensive  analysis  of  the  status  in  all  Upazilas  where  the  pair  should  be.  The  Demand-­‐Side  Financing  (DSF)  is  a  laudable  initiative  and  needs  to  be  examined  within  the  framework  of  equity  and  targeting  to  address  the  urban/rural  and  rich/poor  disparities.  

At  the  community  clinic  levels,  the  Female  Welfare  Assistant  (FWA),  Health  Assistant  (HA),  Community  Health  Care  Provider  (CHCP)  and  those  who  qualified  to  become  Community  Skilled  Birth  Attendants  (CSBAs)  have  the  tremendous  potential  to  make  significant  contributions  to  further  improving  the  health  status  of  the  people  and  improving  a  good  number  of  MDG  indicators.  However,  their  work  must  be  coordinated  and  guided  within  the  process  of  developing  a  yearly  Local  Level  Plan.  The  work  and  potential  of  CSBAs  are  important  but  extremely  limited  at  the  present  time  and  must  be  scaled  up  to  the  national  level  in  the  shortest  possible  timeframe.  Efforts  to  meet  the  commitment  of  Honourable  Prime  Minister  at  UN  General  Assembly  to  train  and  deploy  3,000  Midwives  is  critical  in  enhancing  the  facility  and  skilled  deliveries  and  given  that  an  estimated  21,154  midwives2  will  be  needed  to  cover  Bangladesh’s  population  of  150  million  people.  

The  family  planning  related  OPs  have  made  progress  but  it  is  not  clear  whether  they  will  achieve  the  shift  from  temporary  to  long  acting  and  permanent  methods.  Again  effective  partnership  with  the  private  and  NGO  sectors  would  help  to  achieve  them.  The  Family  Planning  Field  Service  Delivery  (FPFSD)  needs  to  revise  its  baseline  data  and  set  new  targets.  

Challenges  and  Constraints  The  public  sector  faces  some  key  and,  at  the  same  time,  chronic  challenges.  By  and  large,  the  quantity  and  quality  of  human  resources  is  the  principal  sector  challenge,  followed  closely  by  limited  programme  monitoring  and  supervision.  The  human  resource  challenge  is  complex  and  a  sustainable  solution  difficult  to  develop  and  achieve  for  it  deals  with  major  policy  issues  such  as  decentralization  and  civil  service  reform.  Health  sector  HR  development  and  management  plan  to  deal  with  employment,  rational  deployment,  retention,  and  incentives  to  personnel  posted  to  rural  and  less  attractive  duty  stations  must  be  in  place.  Some  concrete  suggestions  are  made  in  the  consolidated  2012  APR  Report.  The  challenge  is  for  the  MOHFW  to  take  this  as  the  highest  system  priority  and  set  clear  deadlines  and  benchmarks  that  can  be  monitored  by  development  partners  and  allocate  sufficient  funds  from  either  or  both  development  and  revenue  budgets.  

As  far  as  institutional  performance  appraisal  is  concerned,  there  are  already  some  elements  of  it  in  place  such  as  the  monitoring  of  OP  implementation  by  process  indicators,  as  well  as  the  indicators  to  monitor  the  Disbursement  for  Accelerated  Achievement  of  Results  (DAAR)  and  the  Governance  and  Accountability  Action  Plan  (GAAP).  The  challenge  will  be  the  regular  use  of  the  information  generated  by  normal  administrative  records  for  management  purposes.    

Local  Level  Planning  is  popular  amongst  most  of  the  OPs  but  shows  limited  coverage  because  it  is  partly  implemented,  monitored,  and  supervised.  However,  the  resource  backed  LLPs  developed  in  Joint  GOB-­‐UN  and  NGO  MNH  Initiatives  in  29  districts  with  proper  financial  support  are  very  encouraging.  Good  practice  and  lessons  learned  could  be  applied  to  the  implementation  of  LLP  in  most  OPs.    

Local  Level  Planning  at  the  community  clinic  level  would  address  some  issues  of  decentralisation  and  more  importantly  it  has  the  unique  potential  to  encourage  functional  integration  of  health  and  family  service  providers  under  the  ownership  of  the  Community  Clinic  staff  to  ensure  reasonable  levels  of  leadership  and  accountability.  If  good  coverage  is  achieved,  it  will  contribute  to  making  further  progress  in  achieving  the  process  and  impact  indicators  not  only  in  the  OPs  but  also  with  the  HPNSDP  Results  Matrix  indicators.  

                                                                                                                         2     One  midwife  for  approximately  175  annual  births  in  the  context  of  Bangladesh  with  150  million  people  (WHO).  

Page 25: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 8  

None  the  four  OPs  reviewed  as  part  of  the  MNCH-­‐FP  Thematic  Area  assessment  considers  programme  information  communication  or  behaviour  change  communication  as  priorities.  The  OP  communication  priorities  are  set  by  the  IEM  and  BCC  Operational  Plan  and  there  is  no  evidence  the  health  services  and  family  planning  OP  LDs  had  participated  in  defining  behaviour  change  priorities  and  therefore  communication  strategic  priorities  to  help  the  OP  to  achieve  its  programme  objectives  for  the  communication  component  is  part  and  parcel  of  programme  management.  

Principal  Recommendation  Short  Term  

‒ Human  resources:  Institutionalize  short-­‐term  emergency  measures  such  as  task  shifting,  local  recruitment,  contracting,  partnership  with  NGOs.  

‒ Ensure  DGHS  and  DGFP  functional  integration  by  enhancing  LLP  at  community  clinic  level,  in  addition  to  Upazila  and  District.  

‒ Implement  the  Neonatal  Health  Strategy  focused  to  activities  at  community  level.  ‒ Midwifery  training  and  deployment  at  DH  and  UHCs  should  be  given  priority.    ‒ The  training  and  deployment  of  CSBA  must  be  accelerated  and  proper  supervision,  monitoring  

and  mentoring.  ‒ Strengthening  FP  activities  especially  at  the  low  performing  and  HTR  areas  enhance  CPR  and  

reduction  of  TFR.  ‒ Accelerate  to  reach  20  percent  share  of  long  acting  and  permanent  methods  (LAPM)  by  involving    

OB-­‐GYNAE  specialists  at  MCH,  DH,  and  private  facilities  through  orientation,  supply  of  logistics.  Increasing  IEC  activities  at  all  level,  supportive  supervision  and  monitoring,  fixing  monthly  target  for  field  workers.  

‒ Strengthen  IEC  to  support  the  delivery  of  key  health  and  family  planning  services,  focused  on  improving  facility  deliveries,  community  essential  newborn  care  and  LAPM.  

‒ Expand  both  C-­‐  IMCI  and  F-­‐  IMCI,  training  of  service  providers  on  newborn  care,  and  supply  of  drugs  and  logistics.  HBB  may  be  very  effective.  

‒ Some  OPs  could  be  revised  to  ensure  quality  and  relevance  of  indicators  to  measure  implementation  progress  over  the  next  year.  It  is  recommended  to  include  at  least  one  nutrition  related  indicator.  

Medium  Term  

‒ Developing  a  Human  Resources  Development  Plan  with  proper  demographic  projections,  recruitment,  and  reallocation  of  staff.  

‒ Developing  and  regularly  updating  the  Human  Resource  Information  System.  ‒ Based  on  field  experience  already  available  in  the  country,  develop  a  TQM  Procedures  and  

Manual  to  be  used  by  public,  private  sectors,  and  NGOs  

Long  Term  

‒ Develop  an  accreditation  system  and  enhance  capacity  at  the  pre-­‐service  training  institutions  to  fulfil  workforce  needs.  

‒ Address  major  policy  issues  such  as  civil  service  reform  and  decentralization.  

2 . 8 U R B A N   H E A L T H   ( I N C L U D I N G   P O P U L A T I O N   A N D   N U T R I T I O N )  

Last  year’s  national  census  reported  that  out  of  a  population  of  more  than  150  million,  approximately  30  percent  live  in  one  of  the  rapidly  expanding  cities  and  towns  (as  opposed  to  2  percent  about  a  century  ago).  It  is  believed  that  this  urban  population  will  be  increasing  by  6  percent  a  year  as  millions  of  people  leave  rural  areas  in  search  of  work.    

It  is  obvious  that  this  anticipated  situation  will  have  a  great  impact  on  all  sectors  in  society,  be  it  agriculture,  industry,  water,  infrastructure,  housing,  as  well  as  on  the  ‘health,  population  and  nutrition’  sector.  Even  in  the  likely  event  of  continued  economic  growth,  which  usually  has  multiple  

Page 26: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  1 9  

positive  effects  on  a  country’s  health  status,  it  remains  to  be  seen  whether  future  public  service  budgets  will  be  sufficient  to  meet  the  growing  demand  for  badly  needed  basic  facilities  in  urban  areas,  like  education,  water,  electricity,  housing,  nutrition,  health,  as  well  as  for  effective  health  promotion  activities.  Should  these  enormous  challenges  not  be  met,  the  majority  of  the  population  (with  the  poor  in  particular)  will  end  up  being  exposed  to  increasing  social  and  health  risks,  the  nature  of  which  will  be  alarming  for  society.  

Results  and  Achievements  Available  studies  and  policy  documents  (such  as  the  DHS,  Urban  Health  Survey  of  2006,  the  6Th  FYP,  2011  National  Urban  Health  Sector,  the  Urban  Health  Strategy  and  recent  Stakeholder  Consultation)  confirm  that  health  services  in  most  urban  areas  are  inadequate,  both  qualitatively  and  quantitatively.  It  is  estimated  that  approximately  40  percent  of  the  urban  poor  (approximately  17  million  people)  are  currently  not  covered  by  primary  health  care.  With  the  costs  of  health  services  and  citizen’s  demand  for  them  rising  on  the  one  hand  and  a  limited  capacity  to  pay  on  the  other,  this  will  inevitably  lead  to  a  decrease  in  access  to  quality  urban  health  care.    

By  incorporating  urban  health  in  the  2011-­‐2016  HPNSDP  and  making  it  a  thematic  area,  the  MOHFW  has  made  a  commendable  first  step  in  recognizing  the  structural  nature  of  the  problem  and  all  future  challenges  going  with  it.  It  is  encouraging  to  note  that  there  is  also  increasing  realization  within  the  MOHFW  and  MOLGRD  that  ultimately  health  services  in  urban  areas  will  have  to  be  funded,  organized,  and  managed  differently.    

However,  many  of  the  rather  ambitious  plans  anticipated  under  the  2011-­‐2016  HPNSDP  towards  developing  a  more  rational  and  service  delivery  system  (i.e.  mapping  exercise),  addressing  existing  overlap  and  fragmentation  in  service  delivery  (i.e.  development  of  referral  guidelines),  rationalizing  the  service  delivery  system  (i.e.  strengthening  public  private  partnerships),  and  building  up  a  solid  PHC  health  infrastructure  at  urban  level  (i.e.  resource  plan)  are  still  in  their  infancy  and  need  further  strengthening  as  a  matter  of  urgency.    

Under  component  3  of  the  2011  “Essential  Service  Delivery”  (ESD)  Operational  Plan  of  Directorate  General  of  Health  Services  /  GHS),  the  following  objectives/targets  were  to  be  achieved  in  2011/2012:  (a)  provide  PHC  services  to  the  urban  population,  (b)  ensure  proper  utilization  of  resources  for  urban  primary  health  care  activities,  (c)  provide  PHC  services  to  the  urban  poor,  (d)  ensure  strong  coordination  between  MOLGRDC  and  the  MOHFW,  (f)  define  an  adequate  referral  system  between  the  various  urban  health  dispensaries  (Government  Outdoor  Dispensaries,  GODs)  and  the  second  and  third  level  hospitals,  and  (g)  explore  feasibility  of  introducing  General  Physician  System.  As  discussed  in  the  concluding  section  of  this  chapter,  MOHFW’s  principal  role  in  urban  health  is  as  “steward”,  providing  commodity  and  technical  support  where  required  and  policy  guidance  and  good  practice  to  the  principal  service  providers.  

The  FPFSD  OP  under  DGFP  included  some  activities  aimed  at  strengthening  FP  services  in  urban  slum  and  (a)  registering  couples,  (b)  domiciliary  and  door  to  door  distribution,  (c)  counseling  and  motivation,  (d)  establishing  referral  linkages  between  urban  slum  and  FP  service  centers,  (e)  arranging  FP  package  programs,  and  (e)  orientation  and  coordination  meeting.  Little  progress  in  these  areas  is  reported  in  the  2012  APIR  of  the  latter  two  OPs  on  urban  health.    

Challenges  and  Constraints  Assessing  progress  to  date  of  the  ESD  and  FPFSD  OP’s  against  2011/2012  targets,  results  are  somewhat  disappointing.  Apart  from  some  training,  orientation  workshops,  and  seminars,  the  2012  APIR  does  not  show  much  evidence  that  the  core  issues  pertaining  to  urban  health,  have  been  properly  and  fully  addressed.    

Underachievement  is  due  to  a  variety  of  reasons:  

‒ Short-­‐term  (operational)  targets  have  not  been  properly  derived  from  earlier  agreed  conceptual  framework,    

Page 27: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 0  

‒ And  activities  are  not  worked  out  in  an  effective  way  and  defined  as  the  drivers  of  outputs.    

Furthermore,  it  looks  as  though  DGHS  and  DGFP  are  not  in  the  best  position  to  perform  most  of  the  activities  planned  for,  since  these  are  related  to  the  mandate,  role  and  functions  of  the  line  Ministries.    

Nonetheless,  experienced  weaknesses  during  the  first  year  of  implementation,  there  is  good  potential  for  building  up  a  first  level  of  care  system  in  urban  areas  along  with  the  MOLGRD.  The  results  from  previous  (policy)  studies  and  project  ‘lessons  learnt’  within  the  NGO  sector  could  be  used  to  this  effect.  At  the  same  time,  an  increasing  number  of  DP’s  has  expressed  interest  to  provide  targeted  technical  and  financial  assistance  in  such  process.    

The  report  also  argues  that  improved  partnership  between  the  MOHFW  and  the  MOLGRD,  as  well  as  between  the  public  and  private  /NGO  sector  is  indeed  required  to  yield  better  results.      

Considering  the  variety  of  (institutional,  administrative,  organizational  and  managerial)  issues  which  need  addressing  under  the  Programme,  it  is  recommended  to  adopt  a  step-­‐by-­‐step  approach  and  deal  with  identified  challenges  more  systematically,  rather  than  spreading  out  existing  capacity  too  thinly.  

A  series  of  actionable  recommendations  are  made  for  the  MOHFW  to  consider  for  future  policy  development  and  planning  purposes.  For  each  of  the  OP’s,  specific  activities  are  listed,  some  of  which  could  be  implemented  shortly,  while  others  will  be  more  time-­‐consuming.  

Recommendations     Lead  OP   Priority   Comments    

Agreeing  on  clear  strategy,  responsibilities,  and  management  structures  between  MOHFW  and  MOLGRD  

SWPMM   Short-­‐term     Senior  management  of  MOHFW  to  initiate  the  process    

Developing  policies,  plans  and  guidelines  for  linking  PHC  services  in  urban  areas  with  clean  water,  housing,  sanitation,  and  environmental  pollution  etc.    

SWPMM   Medium-­‐term    

In  consultation  with  other  line  Ministries    

Revitalizing  Joint  Urban  Health  Technical  Committee  to  ensure  that  strategic  issues  pertaining  to  urban  health  be  adequately  translated  in  policies  and  plans    

SWPMM   Short-­‐term     Strong  involvement  of  MOLGRD/  City  Corporation,  LD  of  ESD  and  FP/FSD  desired    

Urban  Health  Task  Force  between  MOHFP,  MOLGRD  and  DP’s  to  periodically  discuss  and  review  for  urban  health  policies,  plans,  and  resource  strategies    

SWPMM   Short-­‐term    

Define  the  principles  and  modalities  of  ‘outsourcing’  PHC  services  from  large  to  small  municipalities  with  a  clear  accreditation  mechanism  

SWPMM    Short-­‐term   In  coordination  with  MOLGRD,  City  Corporations  and  relevant  NGO’s    

Prepare  an  national  urban  health  coverage  plan     SWPMM    Medium-­‐term    

In  coordination  with  MOLGRD/  City  Corporations    

Recruit  the  services  of  a  consultant  to  facilitate  the  process  of  policy  development  and  mainstreaming  urban  health  in  the  core  activities  of  the  MOHFW  and  MOLGRD    

SWPMM   Short-­‐term      

Strengthen  referral  system  between  urban  PHC  centers  and  secondary/tertiary  health  centers  

ESD   Medium-­‐term    

In  coordination  with  MOLGRD,  City  Corporations,  relevant  DP’s  and  NGO’s  

Page 28: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 1  

 

2 . 9 I E C   &   B E H A V I O R   C H A N G E   C OMMUN I C A T I O N S  

The  review  of  information,  education,  and  communication  (IEC)  and  behaviour  change  communication  (BCC)  products  and  processes  in  HNPSDP  involved  an  assessment  of  a  very  wide  range  of  materials  and  observation  of  communication  activities.  The  IRT  members  studied  strategy  documents  and  implementation  reports;  visited  a  number  of  NGOs  and  media  agencies  active  in  IEC  and  BCC;  interviewed  a  number  of  key  informants  from  inside  and  outside  the  Ministry  of  Health  and  Family  Welfare  (MOHFW);  and  made  a  field  trip  to  Pabna  District.              

The  focus  was  on  two  operational  plans  (OPs):  Health  Education  and  Promotion  (HEP)  of  the  DGHS  and  the  Information,  Education  and  Communication  (IEC)  of  the  DGFP.  The  key  objectives  of  the  review  were  to  assess  achievements  made  during  the  first  year  of  HPNSDP  operations,  identify  opportunities  and  challenges,  and  make  recommendations  for  possible  improvements  in  IEC/BCC  strategies  and  activities  –  which  would  enhance  the  achievements  of  all  the  programme’s  health  and  family  planning  service  delivery  objectives.    

Achievements  and  Results  Bangladesh’s  successes  in  family  planning  programmes  have  resulted  in  a  dramatic  reduction  in  fertility  and  its  service  delivery  strategies  have  made  its  health  indicators  on  a  par  with  or  better  than  its  South  Asian  neighbours.  The  IRT  believes  these  achievements  are,  to  a  significant  degree,  due  to  the  design  and  development  of  IEC  materials.  

Both  OPs  reviewed  by  the  IRT  are  broadly  on  track  to  achieve  their  targets,  as  shown  in  the  2012  Annual  Programme  Implementation  Report  (APIR).  The  IRT  notes  that  the  range  of  output  indicators  of  both  OPs  contribute  to  the  achievement  of  service  delivery  outcomes  arrayed  in  the  programme’s  Results  Matrix.  However,  the  output  indicators  could  be  made  more  precise  by  defining  the  content  of  materials  to  be  produced  or  the  nature  of  the  activities  to  be  conducted  –  and  the  target  groups.        

The  IRT  has  reviewed  a  very  wide  range  of  materials:  posters,  flipcharts,  flash  cards,  leaflets,  TV  and  radio  drama  series  and  ‘infomercials’,  and  videos  for  use  in  the  extensive  network  of  health  facilities  across  the  country.  The  team  has  also  considered  the  use  of  mobile  phones  and  websites  in  the  promotion  of  health  education  and  the  training  of  front-­‐line  health  workers.  There  is,  then,  a  rich  array  of  available  IEC  materials  covering  all  the  priority  topics  of  the  HPNSDP  and  leading  towards  the  achievement  of  indicators  concerned  with  increased  utilization  of  essential  HPN  services  and  improved  awareness  of  healthy  behaviours.  

Many  of  these  print  and  electronic  materials  have  been  designed  and  disseminated  in  collaboration  with  social  marketing  NGOs,  media  houses,  private  companies,  and  often  funded  by  development  

Ensure  provision  of  communicable  disease  services    

CDC   Short-­‐term     In  consultation  with  MOLGRD    

Define  performance  and  output  indicators  related  to  urban  health  services  

ESD  and  FP/FSD  

Short-­‐term      

Update  urban  health  survey     TRD/NIPORT   Short-­‐term      

Conduct  operational  research  on  best  practices  for  outsourcing  urban  PHC  services  to  NGO  sector  with  a  view  to  developing  a  generic  model  for  use  by  City  Corporations  

TRD  and  Planning  DGHS  

   

Provide  support  to  City  Corporations  in  local  mapping  and  preparation/  use  of  urban  health  development  plans,  in  consultation  with  all  providers    

SWPMM   Short-­‐term     In  coordination  with  City  Corporations  and  MOLGRD    

Conduct  operational  research  on  alternative  financing  mechanism  

SWPMM   Medium-­‐term    

 

Page 29: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 2  

partners.  In  this  regard,  the  IRT  finds  that  the  regulating  and  coordinating  functions  of  the  MOHFW,  through  its  Technical  Committee  (in  order  to  ensure  consistency  of  health  messages  and  avoid  overlaps)  have  been  carried  out  effectively  and  without  cramping  creativity.  There  are,  though,  concerns  expressed  about  the  sometimes  slowness  of  the  approval  process.  But  if  there  is  a  key  problem,  it  is  not  to  do  with  the  availability  or  quality  of  IEC  materials  –  it  is  more  to  do  with  their  use.  From  observation  of  health  education  sessions  in  health  facilities  in  Pabna  District,  from  confirming  reports  from  key  informants,  we  conclude  that  most  teaching  –  or  even  counselling  –  is  conducted  in  a  transmittal  and  directive,  as  opposed  to  participatory  manner.  Moreover,  the  settings  for  these  health  education  sessions  are  not  conducive  for  interactive  and  discussion-­‐based  communication.  The  IRT  submits  that  behaviour  change  is  usually  the  result  of  more  complex  and,  even,  challenging  communication  modes,  such  as  force  field  analysis,  positive  deviance,  and  the  confrontational  approaches  used  in  community-­‐led  total  sanitation  (CLTS)  that  was  pioneered  in  Bangladesh.  It  is  in  the  main  in  relation  to  this  crucial  issue  that  the  IRT  has  made  a  number  of  recommendations  concerned  with  strengthening  the  BCC  initiatives  under  the  HPNSDP.  

Principal  Recommendations    1 When  approving  IEC  materials  the  MOHFW’s  Technical  Committee  should  develop  and  apply  a  

set  of  criteria  for  appraising  the  design  and  production  qualities  of  submitted  materials.  This  is  in  addition  to  what  they  are  doing  now:  that  is,  ensuring  that  the  health  care  and  family  planning  messages  are  consistent,  overlaps  are  avoided,  and  the  content  is  in  keeping  with  the  values  and  practices  of  Bangladeshi  culture.  (Short-­‐term)  

2 Though  the  IRT  recognises  the  complexity  and  sensitivity  involved  in  appraising  some  IEC  materials  –  particularly  with  scripts  of  TV  or  radio  drama  series  –  nevertheless,  mindful  of  the  production  deadlines  and  funding  conditionalities  that  production  houses  are  faced  with,  it  is  suggested  that  the  Technical  Committee  should  consider  ways  of  completing  its  work  as  expeditiously  as  possible  –  even  building  in  a  ‘no  objection’  clause  that,  if  a  review  is  not  completed  within  a  period  of,  say,  two  months  the  submission  would  be  considered  approved.  (Short-­‐term)  

3 The  IRT  recommends  that  an  intensive  module  should  be  designed  for  those  expected  to  train  both  health  facility  staff  and  front-­‐line  family  welfare  assistants  and  family  welfare  visitors.  Such  a  module  should  contain  a  toolkit  of  experiential  and  interactive  facilitation  and  counselling  methods.  It  should  last  at  least  two  weeks  and  should  allow  sufficient  opportunity  for  the  participants  to  practise  the  BCC  skills.  Ideally,  the  module  should  include  follow-­‐up  sessions  during  which  the  participants  could  raise  issues  encountered  in  their  own  training  and  supervision  activities.  Finally,  refresher  workshops  should  be  planned  for  at  suitable  intervals  –  further  opportunities  for  reflection  on  challenges  encountered  and  lessons  learnt.  (Medium-­‐term)    

4 The  proposed  BCC  module  should  include  advice  on  how  to  use  videos  as  trigger  material  for  discussion  of  key  health  issues,  whether  in  health  facility  or  community  settings.  (Medium-­‐term)    

5 Concerning  the  mobile  vans  of  the  MOHFW,  the  IRT  suggest  that  they  could  be  turned  into  ‘caravans’  or  road  shows,  involving  a  broader  range  of  performances.  It  would  increase  their  appeal  and  deepen  their  educational  impact  if,  along  with  playing  recorded  music  and  videos,  they  could  promote  performances  of  live  street  theatre  and  songs  in  local  dialects  –  using,  whenever  possible,  local  popular  artists.  (Medium-­‐term)    

6 Part  of  the  emerging  health  strategy  should  be  to  engage  with  community  and  religious  leaders  in  order  to  inform  them  about  key  health-­‐related  initiatives  and  make  them  allies  in  such  campaigns  as  those  related  to  girls’  education,  early  marriage,  dowry,  and  violence  against  women  –  by  involving  them  in  campaigns  and  including  them  in  TV  and  radio  drama  or  infomercials.  (Short-­‐term)  

Page 30: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 3  

7 The  BHE  and  IEM  units  should  be  ready  to  engage  with  those  health  education  NGOs  and  media  agencies  that  are  willing  to  experiment  with  multi-­‐media  programmes  and  packages  (using  TV,  websites,  mobile  phones  and  newspapers)  that  have  a  potential  for  scaling  up  through  the  extensive  infrastructure  and  widespread  personnel  of  the  MOHFW.  (Medium-­‐term)    

In  order  more  effectively  to  link  the  work  of  the  BHE  and  IEM  units  with  IEC  and  BCC  initiatives  being  taken  outside  the  MOHFW  –  and  to  assist  other  OPs  of  the  HPNSDP  in  availing  IEC  materials  and  BCC  approaches  –  it  would  be  of  great  benefit  to  both  units  if  they  had  IEC/BCC  advisors,  who  could  work  across  the  OPs  when  designing  their  communication  strategies  and  activities.  (Short-­‐term)  

2 . 1 0 O V E R A L L   C O N C L U S I O N   A N D   R E C OMM E N D A T I O N S :   K E Y   T E C H N I C A L  I S S U E S ,   C H A L L E N G E S   A N D   O P P O R T U N I T I E S  

The  review  of  the  eight  Thematic  Areas  by  the  IRT  consultants  shows  that  significant  progress  has  been  made  in  implementation  of  the  HPNSDP  but,  as  would  be  expected,  there  are  a  number  of  programmatic  and  management  issues  that  have  been  identified  which  the  IRT  believes,  if  the  recommendations  are  implemented,  will  lead  to  the  achievement  of  both  Operational  Plan  outputs  as  well  as  contribute  to  the  achievement  of  Results  Framework  outcome  and  impact  level  results.  In  addition  to  the  key  issues  raised  each  of  the  Thematic  Area  Technical  Reviews  noted  above,  this  concluding  chapter  also  raises  several  overarching  issues  related  this  first  Annual  Programme  Review  under  the  new  SWAp,  including  the  two  new  HPNSDP  components,  Urban  Health  and  Nutrition,  as  well  the  focus  on  managing  for  development  results.    Finally,  while  this  year’s  APR  substituted  the  Stakeholder  Consultation  for  a  formal  review  of  the  Gender,  Equity,  Voice  and  Accountability  (GEVA)  thematic  area,  the  Team  Leader  undertook  a  limited  review  in  collaboration  of  the  GEVA  Task  Group  and  provides  a  brief  summary  of  the  analysis  and  principal  findings  and  recommendations  below.  

Urban  Health  Urban  health  was  singled  out  for  special  attention  for  a  number  of  reasons  under  HPNSDP,  including  both  moral  and  practical  ones.    Moral,  in  the  sense  that  the  significant  numbers  of  the  poor  are  increasingly  found  in  urban  centers  and  particularly  urban  slums  and  that,  as  the  principal  Ministry  responsible  for  health  care  and  services,  the  poor  in  urban  slums  need  to  be  continued  and  focused  assistance,  particularly  given  the  equity  focus  of  the  new  SWAp;  and,  practical,  in  the  sense  that  many  of  the  principal  HPNSDP  RFW  national  level  impact  results  (NMR,  stunting)  are  being  brought  down  by  the  low  health  indicators  of  the  urban  poor  requiring  renewed  targeting.    

The  Ministry  of  Health  and  Family  Welfare  recognizes  that  its  principal  role  in  urban  health  is  to  act  as  the  Government  of  Bangladesh’s  principal  steward  as  it  does  in  all  such  health  sector  wide  initiatives;  and,  as  a  critical  partner,  along-­‐side  the  Ministry  of  Local  Government  and  Rural  Development,  in  the  governance  of  urban  health  activities.  MOLGRD  is  responsible  for  primary  health  care  delivery  services  to  urban  inhabitants,  including  slum  dwellers  and  does  this  largely  through  NGOs  with  the  support  of  development  partners,  often  outside  of  SWAp  boundaries.  This  is  the  reality,  and  the  responsibility,  therefore,  of  the  Ministry  is  not  as  an  implementer  of  PHC  services,  but  rather  as  a  facilitator  and  provider  of  technical  support  to  concerned  City  Corporations,  including  good  practice,  commodities  (family  planning)  and  technical  assistance  and  training  on  the  one  hand,  while  ensuring  overall  sector  policy  guidance,  standards  and  norms  on  the  other.  

The  IRT  has  noted  a  number  of  key  issues,  but  the  two  of  the  more  important  are:  1)  the  need  for  MOHFW  to  take  a  proactive  role  in  reinvigorating  the  multi-­‐sectoral  forum  of  concerned  health  service  providers  in  urban  areas;  and  (2)  establish  written  guidance  on  the  MOHFW’s  role  in  urban  health  for  the  OPs  and  ensure  that  they  up-­‐date  their  individual  strategies  to  reflect  their  role  in  urban  health,  including  one  or  more  indicators  to  measure  this  role.  

Nutrition  Mainstreaming  Nutrition  has  gone  from  a  discrete  programme,  often  unrelated  to  other  health  activities  and  surely  not  given  the  highest  priority  in  earlier  SWAps,  to  a  major  new  component  of  the  HPNSDP  through  

Page 31: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 4  

its  mainstreaming  of  activities  in  relevant  Operational  Plans  under  both  the  Director  Generals  of  Health  Services  and  Family  Planning.  The  IRT  has  found  that  good  progress  is  being  made  in  this  mainstreaming  effort  and  that  the  National  Nutrition  Service  has  taken  the  lead  in  promoting  both  the  importance  of  nutrition  in  service  delivery  activities  across  the  HPNSDP,  and  coordinating  with  other  OPs  to  ensure  that  they  assess  and  undertake  their  activities  in  such  a  way  that  nutrition  is  taken  as  a  priority  alongside  their  normal  activities.  In  addition  to  the  recommendations  noted  above  under  the  Nutrition  Thematic  Area  Technical  Review,  the  IRT  would  like  to  emphasize  the  following  here:  

‒ The  NNS  is  a  relatively  new  service  and  requires  strengthening,  including  additional  staff  with  the  right  mix  of  skills  and  their  ongoing  in-­‐service  and  specialized  training.  This  includes  the  LD  and  concerned  staff,  as  well  as  frontline  workers  from  the  Upazila  to  Community  Center  levels.  

‒ Secondly,  it  is  critical  that  each  concerned  OP  not  only  add  indicators  to  reflect  the  nutrition  outputs  that  they  will  now  promote  as  a  normal  part  of  their  activities,  but  also  better  understand  how  to  integrate  and  mainstream  nutrition  interventions  into  their  respective  OP  strategies.  The  IRT’s  recommendation  in  this  regard  is  a  major  strategic  planning  effort  for  concerned  OPs  to  think  through  what  they  will  do  to  promote  nutrition,  how  they  will  do  it,  both  technical  approach  and  methodology,  and  most  importantly  with  whom  in  terms  of  both  coordinated  activities  with  other  OPs  but  also  with  NGOs  and  the  private  sector.  

Monitoring  and  Evaluation:  Managing  for  Development  Results  The  IRT  noted  with  interest  the  significant  emphasis  that  SWAp  documentation,  from  the  PIP  to  relevant  Task  Group  TORs  and  Operational  Plans,  placed  on  the  importance  of  managing  for  development  results.  In  the  review  of  the  M&E  Thematic  Area,  the  team  highlighted  the  critical  role  that  the  Planning  Wing  plays  in  ensuring  that  results  at  both  the  RFW  and  OP  levels  are  achieved,  as  well  as  promoting  a  performance-­‐based  and  accountability  framework  among  the  OPs.  The  concerned  IRT  M&E  Thematic  Area  Review  did  raise  several  issues  including:  1)  the  weak  link  between  the  OP  outputs  and  RFW  results  that  indicated  the  possibility  that  while  OP  indicators  could  be  achieved,  there  was  no  necessary  conclusion  that  this  would  ensure  that  concerned  RFW  results  were  achieved;  2)  the  APIR  is  based  on  self-­‐reporting  of  OPs  and  is  thus,  not  an  independent  review  of  OP  implementation;  and  3)  the  PMMU  is  best  placed  to  support  the  PW’s  responsibility  in  the  management,  monitoring,  and  reporting  on  OP  and  RFW  results  but  lacks  the  human  resources,  both  in  numbers  and  expertise  to  fulfill  this  key  function.  The  IRT,  thus,  posed  three  principal  recommendations  to  address  these  key  issues:  

1 Develop  two  to  three  “intermediary  results”  for  each  OP  based  on  the  relevant  log-­‐frame  purpose  level  result,  that  bridge  the  weak  link  found  between  the  OP  and  the  RFW;    

2 The  APIR  should  be  based  on  an  independently  monitored  review  based  on  of  OP  results-­‐reporting  to  the  PMMU  in  its  role  as  PW/MOHFW  oversight  body,  including  existing  indicators  and  new  intermediary  results’  indicators;  and,  

3 Strengthening  the  PMMU,  including  adequate  number  and  expertise  level  of  its  staff,  to  undertake  this  independent  oversight  role  for  the  PW/MOHFW.  

Gender,  Equity,  Voice  and  Accountability  (GEVA)  Thematic  Area  GEVA  was  the  ninth  Thematic  Area  to  have  been  reviewed  by  the  IRT.  However,  the  decision  was  made  by  the  HPNSDP  to  not  conduct  a  full  review  this  year,  rather  viewing  the  Stakeholder  Consultation  as  an  adequate  vehicle  to  assess  GEVA  progress  and  thus  contribute  to  the  2012  APR  review.  The  Team  Leader  reviewed  the  draft  Stakeholder  Consultation  and  found  it  inadequate  either  to  the  needs  of  the  GEVA  Task  Group  or  as  an  independent  assessment  of  stakeholder  views  that  would  feed  into  the  IRT’s  work  by  providing  a  means  to  triangulate  the  findings  of  the  APIR  and  IRT  member  individual  analyses.  The  following  brief  discussion  provides  the  TL’s  analysis  of  GEVA  thematic  area  in  two  parts:  (a)  stakeholder  consultation  and  (b)  GEVA  going  forward.  

Page 32: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 5  

Stakeholder  Consultation  (ShC)  

The  ShC  provided  little  if  any  discussion,  whether  findings  or  analysis,  of  gender,  equity,  or  accountability.    It  did  of  course  provide  a  voice  for  concerned  HPNSDP  stakeholders,  but  not  on  issues  that  were  of  use  to  either  the  IRT  or  GEVA.  The  conclusion  is  that,  as  currently  constituted,  the  ShC  has  very  little  relevance  to  either  GEVA  or  future  APRs.  The  IRT  recommendation  in  this  regard  is  the  following:  

‒ The  purpose  of  the  ShC  needs  to  be  rethought  including  whether  one  is  needed  at  all.    If  it  is  needed  then  a  relevant  methodology  needs  to  be  developed.  It  is  recommended  that  GEVA  review  this  issue  and  bring  it  forward  to  the  HPNSDP  SC.    If  a  decision  is  made  to  go  forward  with  a  ShC  in  the  future,  competitive  bidding  process  should  be  used  to  choose  an  organization  to  develop  such  methodology.  

GEVA  Going  Forward  

The  brief  review  and  analysis  of  GEVA  TG  indicates  that  its  mandate  is  far  too  broad;  anyone  of  these  areas  (e.g.,  gender,  equity,  voice  and  accountability)  could  easily  take  up  the  efforts  of  a  Task  Group,  let  alone  all  four.  Additional  findings  that  are  relevant  to  all  four  GEVA  thematic  interests  include:  

‒ Gender  considerations,  including  analysis  and  strategies,  are  largely  absent  from  all  OPs  and  the  RFW,  as  are  indicators  to  measure  gender  equality;  

‒ An  equity-­‐focused  approach  has  not  been  translated  into  most  OP  strategies  and  there  are  few  indicators  or  disaggregations  to  measure  an  equity-­‐focused  approach;  

‒ There  has  been  mixed  effectiveness  of  Community  Clinic  Management  Group  in  the  planning,  management,  and  oversight,  etc.  of  community  clinics  (CCs);  and,  

‒ There  has  been  little  NGO–private  sector  participation  in  SWAp  forums,  particularly  where  joint  planning  takes  place.  

It  is  the  TL’s  conclusion  that  GEVA  TG  has  a  critical  role  to  play  in  moving  HPNSDP  forward  and  with  the  greatest  potential  pay-­‐off  among  any  of  the  Task  Groups  in  promoting  the  achievement  of  HPNSDP  results  at  OP  and  by  extension  the  RFW  level.  To  seize  this  opportunity  GEVA  needs  to  become  more  focused  and  proactive.  Specifically,  it  is  recommended  that:  

‒ At  a  minimum,  gender  and  equity  should  be  disaggregated  for  all  relevant  OP  and  RFW  indicators;  ‒ Develop  GEVA  TG  strategy,  which  focuses  on  the  community  level  where  gender,  equity,  and  

voice  issues  play  out;  ‒ Conduct  a  gender  assessment  of  HPNSDP  and  integrate  the  results  into  GEVA  and  OP  strategies;  ‒ Conduct  a  bottleneck  analysis  of  inequity  drivers  in  HPNSDP  and  integrate  the  results  into  GEVA  

and  OP  strategies;  ‒ Conduct  an  in-­‐depth  assessment  of  the  community  clinic  management  groups’  role  in  CC  

planning,  oversight,  etc.,  and  integrate  results  into  GEVA  and  OP  strategies;  ‒ Engage  a  gender  specialist  under  SWPMM  to  provide  Technical  Assistance  to  OPs;  ‒ Create  a  forum  or  use  existing  Steering  committee  as  a  means  for  NGOs  and  the  private  sector  to  

participate  in  overall  SWAp  planning  and  integrate  representatives  into  Task  Groups;  and,  ‒ In  the  next  APR  conduct  a  GEVA  Thematic  Area  review.  

Overall  IRT  Conclusion  on  Progress  Against  Objectives  In  conclusion,  the  IRT  feels  that  the  Thematic  Areas  are  poised  to  improve  their  ability  to  contribute  to  HPNSDP  objectives  through  the  adoption  and  implementation  of  the  principal  recommendations  made  in  the  individual  Thematic  Area  Technical  Reviews.  The  above  noted  key  issues  were  fully  discussed  with  concerned  HPNSDP  stakeholders  and  it  is  our  view  that  the  majority  of  the  IRT’s  recommendations  will  be  addressed.  

Page 33: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 6  

3 O V E R A L L   C O N C L U S I O N S   A N D   R E C OMM EN D A T I O N S :   A R E   C O N D I T I O N S  I N   P L A C E   F O R   A   S U C C E S S F U L   P R O G R AMM E  

In  this  concluding  chapter,  the  IRT  addresses  four  of  the  principal  requirements  of  the  overall  APR  2012  Terms  of  Reference,  that  is,  the  review  and  analyses  of  (a)  the  Updated  Results  Framework;  (b)  the  Governance  and  Accountability  Action  Plan;  (c)  the  Disbursement  for  Accelerated  Achievement  of  Results;  and  (d)  Updates  on  the  Risk  Assessment.  In  addition,  a  discussion  of  institutional  constraints  in  implementation,  including  any  updates  to  the  Risk  Assessment  are  provided,  and  a  financial  Framework  for  the  sector  including  DP  funding.  The  chapter  concludes  by  assessing  the  second  principal  APR  requirement:  do  start-­‐up  measures  implemented  to  date  ensure  the  successful  implementation  of  SWAp  activities  over  the  remaining  four  years  of  the  programme?  

3 . 1 R E V I EW ,   A N A L Y S I S   A N D   U P D A T I N G   O F   T H E   H P N S D P   R E S U L T S  F R AM EWO R K  

The  HPNSDP  Result  Matrix  presents  the  indicators  that  were  defined  in  the  Project  Investment  Plan  for  use  in  measuring  progress  against  the  results  articulate  for  the  HPNSDP,  the  targets  of  which  are  expected  to  be  completed  no  later  than  the  end  of  the  SWAp  in  2016.  The  RFW  also  presents  the  baseline  data  and  the  expected  targets  to  be  achieved  by  2016.  

Annex  3,  provides  the  complete  review  and  analysis  of  each  RFW  indicator.  In  undertaking  this  review,  the  IRT  took  the  updated  RFW  found  in  the  2012  Annual  Programme  Implementation  Review  and  applied  an  Annual  Indicator  Change  Rate  (AICR)  methodology  to  determine  whether  or  not  the  concerned  indicators  were  on  track  or  required  acceleration.  We  provide,  in  our  analysis  of  the  indicators  requiring  additional  acceleration,  why  that  is  the  case.  We  note  the  following  principal  findings:  

‒ Two  of  eight  (one-­‐quarter)  goals  or  impact  level  indicators,  that  is,  NMR  and  stunting,  require  acceleration;  

‒ Eleven  of  33  (one-­‐third)  outcome  indicators  require  acceleration  if  they  are  to  meet  the  2016  targets  set  out  for  them  

‒ Three  indicators  have  already  been  achieved  by  the  end  of  the  first  APR.  Consideration  should  be  given  to  reviewing  these  indicators  and  determining  whether  the  targets  were  set  too  low.  

As  a  general  recommendation,  concerned  Task  Groups  should  review  the  IRT  findings  and  analysis  to  determine  how  they  will  go  forward  in  achieving  the  targets  established  by  the  PIP.  

3 . 2 P R O G R E S S   O N   K E Y   A R E A S   O F   T H E   G O V E R N A N C E   A N D  A C C O U N T A B I L I T Y   A C T I O N   P L A N  

As  the  PAD  notes,  the  GAAP  outlines  the  governance  and  accountability  risks  and  mitigation  actions  to  ensure  the  success  of  key  aspects  of  the  project  which  may  otherwise  be  adversely  impacted  by  these  risks.  The  GAAP  has  recommendations  in  support  of  improving  financial  management,  strengthening  weak  internal  controls,  improving  procurement  management,  and  strengthening  the  M&E  capacity.            

Annex  four  contains  the  complete  analysis  of  the  GAAP.  The  IRT  has  reviewed  all  21  of  the  GAAP  Key  Objectives,  including  MOHFW  updates,  and  has  provided  specific  comments  on  each  of  them.  As  a  general  conclusion,  the  IRT  can  say  that  the  majority  of  Key  Objectives  are  on  track  but  that  addressing  the  specific  recommendations  made  in  the  GAAP  analysis  will  ensure  that  they  will  be  met  as  intended  and  thus  promote  the  achievement  of  results  both  at  the  OP  and  RFW  levels.  We  make  the  following  overall  observations  concerning  GAAP  Key  Objective  performance:  

‒ The  principal  area  of  concern  is  one  that  has  been  recognized  in  previous  APRs  and  which  was  again  highlighted  in  the  individual  Thematic  Area  Technical  Reviews  conducted  by  individual  IRT  members,  that  is,  the  problem  of  ensuring  an  adequate  number  of  health  force  workers,  with  the  

Page 34: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 7  

right  mix  of  skills,  in  the  posts  where  they  are  most  needed.  This  includes  the  issues  of  frequent  transfers,  as  well  as  the  non-­‐filling  of  sanctioned  posts.  

‒ As  we  discuss  below,  there  has  been  both  an  issue  with  the  timely  release  of  funds  as  well  as  the  overall  lower  than  planned  allocation  of  funds  to  the  OPs  as  planned  in  the  PIP.  

3 . 3 D I S B U R S EM E N T   F O R   A C C E L E R A T E D   A C H I E V EM E N T   O F   R E S U L T S  

To  accelerate  progress  on  key  areas  of  the  HPNSDP,  the  development  of  a  DAAR  modality  was  put  into  place.  On  an  annual  basis,  GOB  and  DPs  jointly  agree  on  key  priorities  and  indicators.  These  indicators  are  then  linked  to  incentive  payments  based  on  achievement.  On  a  regular  basis,  the  Local  Consultative  Group  meets  to  review  progress.  Annex  5  contains  the  complete  analysis  of  the  DAAR  indicators  

In  2011,  three  DAAR  indicators  on  (1)  Maternal  health/health  system-­‐Human  Resources,  (2)  Maternal  health/FP/child  health,  and  (3)  Nutrition  were  achieved  fully  and  two  indicators  on  Health  systems-­‐budgeting  and  planning  and  Fiduciary  were  achieved  partially.  This  resulted  in  a  disbursement  of  US$  7.16  million  from  the  DAAR  fund.  The  APR  team  believes  that  the  DAAR  indicators  chosen  were  appropriate  and  feasible.  The  MOHFW  clearly  has  the  capacity  to  implement  these  indicators.    

In  2012,  good  progress  has  already  been  made  on  the  selected  indicators.  The  GOB  feels  that  they  are  able  to  achieve  most  of  the  DAAR  targets  fully.  Our  discussion  with  DPs  also  indicates  that  there  is  comfort  in  the  capacity  of  the  MOH  to  achieve  the  2012  targets.  

Overall,  it  appears  that  the  DAAR  indicator  system  incentivizes  the  acceleration  of  progress  in  key  areas.  The  targets  chosen  thus  far  are  feasible  and  the  MOHFW  has  the  capacity  to  achieve  them.  The  verification  of  some  targets  should  receive  continued  attention.      

3 . 4 I N S T I T U T I O N A L   C O N S T R A I N T S   I N   I M P L EM E N T A T I O N ,   I N C L U D I N G  R I S K   A S S E S SM E N T   U P D A T E  

The  IRT  has  reviewed  the  Operational  Risk  Assessment  Framework  (ORAF)  in  which  the  main  risks  identified  included:  (a)  inherent  weaknesses  in  financial  management,  procurement  and  monitoring  and  evaluation;  (b)  high  rates  of  absenteeism  of  health  professionals;  (c)  shortage  of  drugs  and  equipment;  (d)  frequent  transfers  of  staff  in  MOHFW;  and  (e)  weak  governance  and  accountability  framework.  Our  review  of  the  ORAF  around  these  issues  is  as  follows:  

In  most  cases,  the  risks  remain  as  they  were  noted  in  the  PAD  and  the  IRT  has  commented  on  many  of  them  in  the  individual  Thematic  Area  Technical  Report.  It  is  our  conclusion,  that  there  has  been  no  increase  in  the  risk  in  any  of  the  ORAF  risk  categories  and  that  the  risk  mitigation  actions  remain  appropriate.  The  one  area  that  the  IRT  does  feel  additional  actions  need  to  be  taken  concerns  the  overall  monitoring  and  evaluation  of  the  HPNSDP.  We  have  noted,  in  the  M&E  report,  that  the  current  method  of  monitoring  outputs  in  the  OPs  relies  on  the  self-­‐reporting  of  the  OP  Line  Directors.  The  findings  of  the  APIR  are  also  dependent  on  this  self-­‐reporting.  The  IRT  does  not  think  this  is  adequate  and  has  recommended  that  a  strengthened  the  Programme  Management  and  Monitoring  Unit,  set  up  under  the  Planning  Wing  of  the  MOHFW,  is  the  proper  entity  within  the  Ministry  to  develop  an  “independent”  monitoring  and  management  system  that  provides  oversight  of  OP  performance  and  progress.  The  Planning  Wing  has  taken  this  recommendation  under  advisement  and  we  believe  it  will  be  a  key  action  that  will  improve  results  reporting  to  the  concerned  HPNSDP  stakeholders.  

As  an  overall  comment,  the  IRT  notes  that  the  Planning  Wing  of  the  MOHFW,  through  the  Sector-­‐wide  Programme  Management  and  Monitoring  Operational  Plan,  has  been  doing  a  very  effective  job  in  undertaking  the  four  principal  responsibilities,  including  M&E,  under  its  jurisdiction,  with  a  minimum  of  staff  to  accomplish  them.  The  IRT  believes  that  for  the  SWAp  to  be  successful,  the  

Page 35: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 8  

Planning  Wing  could  use  additional  staff  particularly  in  the  area  of  planning,  budgeting  and  in  the  PMMU  as  noted  in  the  M&E  report  and  Key  Issues  noted  in  Chapter  2.0,  above.  

3 . 5 F I N A N C I A L   F R AM EWO R K   F O R   T H E   S E C T O R ,   I N C L U D I N G   D P   F U N D I N G  

The  IRT  has  reviewed  Financial  Framework  for  the  sector  including  DP  funding.  The  IRT’s  overall  finding  is  that  there  is  serious  resource  gap  to  fulfill  HPNSDP  requirements  as  found  in  the  Project  Investment  Plan.  Several  of  the  more  important  specific  findings  related  to  the  framework  include:  

‒ There  were  late  fund  releases  because  of  initial  delays  in  the  approval  of  the  PIP  and  OPs;  ‒ Only  60  percent  of  overall  OP  provisions  for  2011/2012  were  allocated  in  the  Revised  Annual  

Development  Plan  (RADP),  which  is  understandable  since  there  was  a  delay  in  the  start-­‐up  of  programme  implementation;  

‒ The  principal  short-­‐fall  in  funding  has  been  in  the  development  budget;  ‒ The  actual  utilization  by  OPs  during  2011/2012  implementation  was  less  than  53  percent,  which  

again  is  understandable  considering  the  six  month  delay  in  HPNSDP  start-­‐up  and  OP  implementation;  and,  

‒ The  trend  in  underfunding  HPNSDP  as  per  the  PIP  has  continued  in  year  two  with  only  58.5  percent  of  OP  provision  for  2012/2013  in  the  ADP.    

  OP  provision  for  the  entire  program  

OP  provision  for  2011-­‐12  

RADP  allocation  for  2011-­‐12  

%  of  OP  provision  

%  of  RADP  provision  

%  of  OP  provision  

Total   22176   3786   2270   60   87.7   52.6  

GOB   87603   1325   790   60   94.9   56  

PA   13573   2461   1480   0   16.4   50  

 

The  IRT’s  conclusion  is  that  the  short-­‐fall  in  PIP  indicative  funding  will  necessitate:  1)  a  more  efficient  planning  and  tracking  of  available  resources;  2)  additional  resources  being  committed  to  HPNSDP  as  previewed  in  the  PIP;  and  3)  both  more  efficient  planning  and  additional  resources  committed.    Specifically,  we  conclude:  

‒ Transparency  in  DPA  and  parallel  funding  allocations  and  reporting  must  improve;  ‒ Transparency  in  NGO/INGO  financing  and  reporting  must  improve;  ‒ The  alignment  of  development  and  non-­‐development  budgets  is  needed;    ‒ The  IRT  strongly  recommends  that  resource  tracking  and  reporting  must  be  a  systematic  and  

routine  part  of  annual  sector  management,  not  ad  hoc  activities  conducted  every  few  years.  

Concerning  DP  Funding,  the  following  table  shows  actual  DP  self-­‐reported  Allocations  and  Disbursements.  What  we  can  say  is  that  these  disbursements  and  allocations  differ  from  those  figures  PIP  and  could  have  implications  for  the  future  funding  of  the  HPNSDP.  

Development  Partner  Self-­‐Reported  Allocation  and  Disbursements  

Donor   Fiscal  Year  Pool  Allocation  

Pool  Disbursement  

DPA  Allocation  

DPA  Disbursement  

Off-­‐budget  Allocation  

Off-­‐budget  Disbursements   Notes  

World  Bank  IDA  Credit   July-­‐Jun   $358,9000,00   $92,000,00   $0   $0   $0   $0    

Netherlands   Jan-­‐Dec   $5,126,000   $0   $0   $0   $4,485,250   $3,422,246    

Ausaid   July-­‐Jun   $8,029,000   $8,029,000   $0   $0   $15,488,200   $15,488,200    

UNICEF   Jan-­‐Dec   $0   $0   $10,848,963   $3,646,963   $1,836,424   $1,836,424    

WHO   Jan-­‐Dec   $0   $0   $7,400,000   $5,300,000   $250,000   $200,000    

CIDA   Apr-­‐March   $0   $0   $9,794,295   $9,794,295   Incomplete   $3,327,847    

Page 36: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  2 9  

JICA   Apr-­‐March   $64,512,000   $10,099,200   $0   $0   $0   $0  In  kind  not  reported  

SIDA   Jan-­‐Dec   $12,160,000   $12,160,000   $228,000   $0   $3,617,600   Incomplete    

DFID   Apr-­‐March   $40,312,500   $40,312,500   $11,287,500   $10,465,125   $322,500   $262,838    

USAID   Oct-­‐Sept   $8,000,000   $8,000,000   $0   $0   $53,483,000   $53,483,000    

GIZ   Jan-­‐Dec   $0   $0   $0   $0   $0   $0   In  kind  only  

KFW   No  response  

UNDP   No  response    

UNAIDS   Jan-­‐Dec   $0   $0   $0   $0   $320,722   $242,415    

Total     $497,039,500   $170,600,700   $39,558,758   $29,206,383   $79,803,696   $78,262,969    

 

3 . 6 T E AM   L E A D E R ’ S   T H O U G H T S   O N   F U T U R E   A N N U A L   P R O G R AMM E  R E V I EW S  

Having  now  completed  this  first  APR  for  GOB  and  Development  Partners,  it  is  hard  not  to  come  away  without  some  thoughts  on  the  process  and  how  it  might  be  done  better  in  the  future.  

The  principal  issue  to  consider  is  whether  APRs  need  to  be  conducted  every  year?  There  are  pros  and  cons  to  consider  in  this  regard:  

There  is  nothing  like  a  review  (or  evaluation,  assessment,  etc.)  to  focus  everyone’s  mind  on  the  subject  at  hand.  This  is  probably  one  of  the  most  important  reasons  to  conduct  an  APR  annually.  It  is  as  much  about  the  process,  or  the  journey,  as  it  is  about  the  outcome,  or  arriving  at  a  planned  destination.  APRs  bring  all  the  concerned  stakeholders  together  to  participate  in  what  is  essentially  a  joint  problem  solving  exercise,  and  this  is  a  healthy  thing.  The  IRT  acts  as  both  facilitator  and  catalyst  on  behalf  of  the  stakeholders.  Furthermore,  reviews  are  an  opportunity  for  the  different  parties  to  send  messages  to  each  other  via  the  independent  reviewers  who  are  hopefully  skilled  enough  in  being  able  to  discern  those  messages  about  which  something  can  be  done,  or  at  least  to  present  them  in  such  a  way  as  they  can  be  more  readily  accepted  by  the  intended  recipient.  Many  messages  were  sent  via  the  IRT  and  perhaps  a  few  were  received  positively.  

Is  there  a  need  for  a  16  person  IRT  every  year?  The  answer  from  this  TL’s  perspective  is  no,  it  seems  unnecessary  and  should  rather  be  determined  by  the  function  that  a  given  APR  is  expected  to  fulfill.  

Is  three  weeks  for  the  Thematic  Area  experts  enough  time  to  conduct  the  APR?  With  better  planning  –  having  scheduled  meetings  for  the  first  week  prior  to  the  IRT’s  arrival  –  more  logistics  support  (see  below),  three  weeks  is  adequate  to  do  reasonably  in-­‐depth  analysis  of  a  given  Thematic  Area.  

Is  it  necessary  to  review  all  nine  thematic  areas  every  year?  Again,  the  answer  would  be  no.  As  noted  in  the  overall  recommendation  below,  it  may  be  necessary  to  review  each  thematic  area  every  other  year,  but  this  would  really  depend  on  whether  all  nine  thematic  areas  merit  such  a  full  review.  It  is  rather  suggested  that  in  years  two  and  four  (the  out  years),  for  instance,  that  three-­‐to-­‐five  specific  topics  such  as  health  insurance  or  local  level  planning  be  taken  up  as  operations  research  efforts  to  address  specific  problems  encountered  in  implementation  during  the  preceding  year(s);  or,  pick  two  or  three  thematic  areas  and  do  in-­‐depth  reviews  on  them.  

Is  it  necessary  to  pair  national  and  international  experts?  Most  definitively,  yes.  National  team  members  bring  local  knowledge  and  context  that  even  international  experts  with  long-­‐term  Bangladesh  experience  do  not  possess.  And,  in  some  cases,  they  are  also  able  to  open  doors  that  an  international  member  simply  cannot.  International  team  members’  principal  value  is  bringing  internationals  good  practice  and  policy  in  their  areas  of  thematic  expertise,  which  when  applied  with  good  analysis  can  sometimes  lead  to  interesting  insights  and  recommendations.  One  recommendation  would  be,  however,  to  mix  the  background  of  national  consultants  so  that  there  

Page 37: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 0  

are  more  members  with  an  NGO  and  private  sector  experience,  in  addition  to  those  with  previous  MOHFW  experience.  Similarly,  it  might  be  useful  to  engage  international  consultants  who  may  have  less  years  of  experience  but  who  may  have  more  relevant  and  timely  experience  and  a  record  of  innovative  and  practical  thinking  and  problem  solving.  

Consider  (strongly)  a  counterpart  for  the  team  leader  and  a  dedicated  logistics  /  administrative  person.  This  would  be  a  mental  health  kindness  for  the  next  team  leader  not  to  mention  permitting  her  or  him  to  more  effectively  use  her  or  his  time  for  substantive  rather  than  process  tasks.  Sixteen  consultants,  each  with  his  or  her  own  individual  TOR  (and  personal)  requirements  (and  idiosyncrasies)  cannot  be  coordinated  or  effectively  directed  without  significant  time  and  effort  being  expended.  Placing  a  bulletin  board  up  on  a  wall  and  expecting  the  rationale  and  effective  use  of  time  and  four  or  five  vehicles  by  16  consultants  is  unrealistic;  having  a  logistics  person  for  the  first  two  weeks  would  make  a  world  of  difference  in  the  way  the  team  and  team  leader  function.    And,  there  is  no  reason  to  believe  that  the  TL  is  any  more  omniscient  concerning  the  socio-­‐cultural  dynamics  of  Bangladesh  than  any  other  international  team  member;  having  the  counsel  of  an  experienced  and  professional  Bangladesh  counterpart  would  help  to  avoid  the  inevitable  contretemps  that  working  in  a  highly  sensitive  and  cross-­‐cultural  setting  is  certainly  a  small  price  to  pay  given  the  potential  damage  to  the  review  that  a  poorly  handled  situation  can  cause.  

Overall  Recommendation  Full  reviews  should  take  place  in  year  1  to  set  the  SWAp  baseline  and  make  sure  that  all  conditions  are  in  place  for  the  successful  conduct  of  the  next  two  years  of  the  programme;  in  year  3,  the  MTR  fulfills  the  APR  function  in  which  an  assessment  of  actual  against  planned  results  achieved  is  undertaken;  and,  finally,  in  year  5  to  evaluate  the  actual  impact  of  the  SWAp  in  terms  of  outcomes  and  impacts.    

3 . 7 O V E R A L L   C O N C L U S I O N S   A N D   R E C OMM E N D A T I O N S   F O R   T H E   A P R  2 0 1 2  

The  IRT  concludes  that  the  progress  of  HPNSDP  is  roughly  where  it  should  be  at  the  end  of  the  first  year  of  the  programme,  taking  into  consideration  the  late  start  experienced;  given  the  magnitude  of  the  SWAp,  the  many  stakeholders  involved,  and  the  normal  hiccups  associated  with  the  commencement  of  most  new  initiatives,  the  IRT  finds  the  initial  delays  understandable.    

Both  the  APIR  and  this  APR  have  identified  the  on-­‐going  crisis  in  human  resources  and  weak  SWAp  monitoring  and  supervision  as  two  of  the  principal  issues  that  will  have  a  likely  impact  on  the  programme’s  successful  achievement  if  not  addressed  immediately;  both  issues  carry-­‐over  from  previous  health  sector  programmes.  In  this  regard,  the  IRT  concludes  that:  

‒ The  Human  Resource  Management  (HRM)  OP  is  best  placed  to  lead  the  Ministry’s  efforts  in  addressing  this  health  sector-­‐wide  problem.  However,  it  currently  understaffed  and  urgently  requires  both  additional  personnel  and  those  with  the  right  mix  of  skills  and  expertise  to  permit  the  OP  take  the  lead  in  coordinating  HPNSDP’s  response  to  the  current  and  continuing  HR  crisis.    Furthermore,  when  the  current  workforce  study  being  undertaken  by  the  MOHFW  with  DFID  support  is  completed,  HRM  OP,  under  the  guidance  of  Senior  Secretary,  and  in  collaboration  with  the  HR  Task  Group,  should  convene  a  sector-­‐wide  workshop  to  identify  short-­‐term  solutions  while  the  longer-­‐term  reforms  of  the  GOB  across  all  sectors  continues  to  take  hold.  Each  of  the  TATR’s  has  reviewed  HR  issues  in  their  particular  domain  and  made  recommendations  concerning  temporary  measures  that  should  address  the  workforce  constraints  in  the  short-­‐term.  

‒ In  terms  of  improved  monitoring  and  management  of  the  SWAp,  the  SWPMM  OP  through  the  Planning  Wing  plays  a  critical  role,  particularly  in  resource  planning  and  tracking  and  Inter-­‐OP  coordination.  In  this  regard,  the  IRT  singles  out  for  special  attention  the  PMMU,  which  needs  to  urgently  engage  additional  staff  so  that  it  can  support  the  Planning  Wing’s  critical  role  in  independently  monitoring  the  performance  of  Operational  Plan’s,  not  relying  simply  on  LD  

Page 38: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 1  

reporting.  While  LD  meetings  were  viewed  as  very  useful,  there  appeared  to  be  inadequate  time  to  discuss  inter-­‐OP  coordination  particularly  in  areas  of  overlap  or  cross-­‐cutting  issues  such  as  nutrition,  urban  health,  IEC/BCC,  or  human  resource  needs.  

Several  other  conclusions,  largely  related  to  the  SWAp’s  institutional  arrangements  are  worth  noting:  

‒ Several  new  organizational  entities  or  oversight  tools  were  designed  to  increase  the  financial  and  management  oversight  of  this  SWAp  including,  the  Financial  Management  and  Audit  Unit  (FMAU),  the  PMMU,  the  Procurement  and  Logistics  Monitoring  Cell  (PLMC),  and  Interim  Unaudited  Financial  Report  (IUFR).  Each  of  them  has  shown  initial  effectiveness  during  the  programme’s  start-­‐up  and  this  APR  has  pointed  out  where  additional  support  is  needed  to  make  them  fully  functional  

‒ The  IRT  has  been  particularly  impressed  with  the  governance  structure  of  HPNSDP  and  has  seen  it  in  full  operations  during  the  APR,  from  the  initial  Task  Group  meetings,  to  the  Local  Consultative  Group’s  interactions  through  to  the  Steering  Committee  and  culminating  in  the  Policy  Dialogue.  The  Task  Groups  are  the  key  to  the  technical  success  of  the  programme  and  should  meet  regularly  with  well-­‐articulated  TORs  and  strategies;  the  IRT  encourages  them  to  continue  their  important  work  after  APR.    

While  the  IRT  understands  that  HPNSDP  is  a  limited  SWAP  in  terms  of  whole  of  sector  stakeholder  participation,  each  IRT  expert,  from  his  or  her  own  perspective,  felt  that  there  could  be  greater  coordination  with  and  participation  of  major  health  care  providers  that  are  not  covered  under  the  SWAp,  particularly  NGO  and  private  sector  health  providers.  This  is  particularly  true  since  the  public  sector,  through  the  MOHFW,  covers  only  30  percent  of  health  service  delivery  throughout  the  country,  while  the  remaining  70  percent  is  covered  by  a  combination  of  the  private  sector  and  NGOs,  with  future  projections  placing  the  ratio  of  public  sector  to  private/NGO  sector  coverage  at  10  percent  and  90  percent  respectively.  The  IRT  urges  strong  consideration,  therefore,  for  creating  a  new  cross-­‐sector  service  provider  platform  that  brings  together  current  HPNSDP  stakeholders  with  representatives  of  other  non-­‐member  HPNSDP  organizations,  including  from  the  NGO  and  private  sectors  and,  where  appropriate,  into  the  Task  Group  structure,  to  undertake  joint  planning  and  information  sharing  exercises  

The  obvious  concern,  recognized  by  all  HPNSDP  stakeholders,  is  the  underfunding  of  the  SWAp.    This  however,  is  meta-­‐level  concern  that  probably  falls  outside  of  the  manageable  interests  of  any  of  the  current  parties  to  address.    The  IRT  would  note  that  the  conditions,  that  is,  the  institutional  arrangements,  systems  and  procedures,  are  for  the  most  part  in  place  to  move  the  Programme  forward  to  the  Mid-­‐term  Review  where  adjustments,  if  necessary  can  be  made.  This  assumes  that  the  HPNSDP  Steering  Committee  and  the  Policy  Dialogue  accept  the  more  important  of  the  principal  recommendations  that  have  been  made  in  this  report  and  the  full  Thematic  Area  Technical  Review  found  in  Volume  II,  Annexes.    

 

 

 

 

Page 39: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 2  

A N N E X   1  

T H EM A T I C   A R E A   T E C H N I C A L   R E V I EW   R E P O R T S  

Nine  Thematic  Areas  under  APR  2012  Review  

1 Gender,  Equity,  Voice  and  Accountability  (No  formal  review)  

2 Monitoring  and  Evaluation  

3 Procurement  and  Supply  Chain  Management  

4 Financial  management  with  Planning  and  Budgeting    

5 MNCH  and  Family  Planning  (including  human  resources)  

6 Nutrition  (including  human  resources)  

7 Disease  Control  (including  human  resources)  

8 Urban  Health  (including  population  and  nutrition)  

9 IEC  &  Behavior  Change  Communications  (BCC)  

Human  Resources  was  a  principal  crosscutting  issue  addressed  by  each  of  the  8  Thematic  Area  Technical  Reviews.  

Page 40: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 3  

A N N E X   2    

R E V I EW   A N D   A N A L Y S I S   O F   T H E   U P D A T E D   R E S U L T S   F R AM EWO R K    

Introduction  The  overall  APR  2012  IRT  TORs  called  for  a  review,  analysis,  and  updating  of  the  HPNSDP  Results  Framework.  The  following  analysis  looks  at  each  of  the  41  results  and  corresponding  indicators  in  the  RFW  to  determine  whether  they  are  on  track  or  not  for  completion  by  2016.  The  IRT  uses  the  updated  data  found  in  the  APIR  to  perform  its  analysis  using  the  Annual  Indicator  Change  Rate  methodology  discussed  below.  Table  2.B,  below,  provides  the  overall  analysis  of  each  result.  

Methodology  The  Annual  Indicator  Change  Rate  (AICR)  is  a  calculation  of  historical  progress  made  in  the  indicator  from  the  baseline  data  to  the  latest  data  available  and  divided  by  the  number  of  years  it  took  to  achieve  them  which  yields  an  estimate  of  average  progress  in  one  year.  Assuming  that  indicators  will  make  progress  at  the  same  historical  pace,  it  is  possible  to  calculate  the  progress  it  is  expected  in  the  remaining  years  of  the  plan,  in  this  case  2016.  

Example:  Infant  Mortality  Rate  

Target  for  2016:  31  

Baseline:  52,  BDHS  2007    

Latest  available  data:  43,  BDHS  2011    Number  of  years  between  base  line  (2007)  and  latest  available  data  (2011):  4  years.  AICR:  52-­‐43/4=  2.25  per  year  

Number  of  Years  between  latest  available  data,  in  this  case  between  2011  and  2016:  5  years.    Based  on  the  AICR  and  the  number  of  years  between  2011  and  2016,  a  projection  is  made  on  what  the  indicator  will  look  like  in  5-­‐years  time:  AICR  x  5  years.    2.25  x  5  =  11.25  in  five  years.    The  next  step  is  to  subtract  the  projected  reduction  of  5  years  from  the  latest  available  data:  43-­‐11.25  =31.75  or  round  to  32.    Final  calculation:  comparison  between  target  to  be  achieved  in  2016  (31)  and  projected  figure  (32).  Both  are  very  close  and  therefore  it  considered  to  be  on  track.  

The  Analysis:  Health,  Population  and  Nutrition  Sector  Development  Plan  (HPNSDP)-­‐  2012-­‐2016    Component  1:  Service  Delivery  Improved.  

‒ Result  1.1.  Increased  utilization  of  essential  HPN  services.  ‒ Result  1.2.  Improved  equity  in  essential  HPN  service  utilization.  ‒ Result  1.3.  Improved  awareness  of  healthy  behaviour.  ‒ Result  1.4.  Improved  PHC  CC  systems.  

Component  2:  Strengthen  Health  Systems  

Page 41: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 4  

‒ Result  2.1.  Strengthened  planning  and  budgeting  procedures.  ‒ Result  2.2.  Strengthened  monitoring  and  evaluation  systems.  ‒ Result  2.3.  Improved  human  resource  planning,  development,  and  management.  ‒ Result  2.4.  Strengthened  quality  assurance  and  supervision  systems.  ‒ Result  2.5.  Sustainable  and  responsive  procurement  and  logistic  system.  ‒ Result  2.6.    Improved  infrastructure  and  maintenance.  ‒ Result  2.7.    Sector  management  and  legal  framework.  ‒ Result  2.8.    Decentralization  through  LLP  Procedure.  ‒ Result  2.9.    SWAP  and  improved  DP  coordination  (delivering  on  the  Paris  Declaration).  ‒ Result  2.10.  Strengthened  financial  management  systems  (funding  and  reporting).  

The  HPNSDP  Result  Matrix  presents  the  indicators  it  will  be  used  to  measure  progress  against  the  results  listed  above.  It  also  presents  the  baseline  data  and  the  expected  targets  to  be  achieved  by  2016.  

Assuming  that  progress  will  continue  at  the  same  historical  pace  (progress  between  baseline  and  latest  available  update),  it  is  possible  to  mathematically  estimate  whether  achieving  the  indicator  by  2016  is  realistic  and  on  track  or  not.  

Using  the  average  Annual  Indicator  Change  Rate  (AICR)  achieved  from  the  baseline  data  to  the  latest  data  available  and  divided  by  the  number  of  years  it  took  to  achieve  them  will  yield  an  estimate  of  average  progress  in  one  year.  Assuming  that  indicators  will  make  progress  at  the  same  historical  pace,  it  is  possible  to  project  the  indicator  by  2016  and  then  compare  this  figure  with  the  Results  Matrix  targets.  

Based  on  the  IACR,  the  Results  Matrix  indicators  were  examined  to  determine  whether  they  are  on  track  to  achieve  the  desired  target  by  2016,  recommend  some  level  of  acceleration  or  revision  of  indicators.    

It  has  therefore  been  found  that  17  (45)  %  indicators  are  on  track  and  13  (34)  %  are  not.  Some  level  of  acceleration  will  be  required.  Five  (13%)  indicators  will  need  to  be  revised  and  3  (8%)  will  need  new  targets  as  current  target  has  already  been  met  by  2010/11.  

Page 42: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 5  

A D D I T I O N A L   C OMM E N T S   T O   H P N S D P   R E S U L T S   M A T R I X  I N D I C A T O R S  

SI  #   Indicator   Status   Comments  

GI  3     Neonatal  mortality  rate  (NMR)  

Acceleration  Required.  

Acceleration  should  be  possible  for  all  the  policies  and  the  National  Neonatal  Health  Strategy  are  in  place.  The  gradual  removal  of  HRs,  particularly  at  the  community  level,  HAs,  FWAs,  CHCP,  and  CSBAs  and  strengthening  field  supervision  and  monitoring  will  need  to  be  addressed.  

GI  6     Prevalence  of  stunting  among  under-­‐5  children    

Acceleration  Required  

Interventions  in  the  health  sector  are  generally  weak  to  address  chronic  malnutrition.  Strong  multi  sectorial  coordination  will  be  required  to  address  issues  of  food  production,  food  price,  fertilizer  subsidies,  cash  transfer  to  the  poor.  

1.1.1.     %  of  delivery  by  skilled  birth  attendant      

Acceleration  Required  

This  will  require  a  full  scale  training  of  CSBAs  and  FWA  to  increase  number  of  home  deliveries  assisted  by  a  trained  health  worker.  At  present  is  very  modest  4.4%.  However,  the  raining  curricula,  the  trainers  had  been  trainers  and  country  is  ready  to  scale  up  to  nationally  agreed  coverage  (1  CSBA/FWA:  population  ration)  It  will  also  require  adequate  funding  from  development,  revenue  or  both  budgets.  

1.1.2.     Antenatal  care  coverage  (at  least  4  visits)      

Acceleration  Required  

This  is  very  ambitious  target.  Considering  that  most  services  are  available,  reaching  the  target  will  require  an  aggressive  communication  campaign  to  encourage  mothers  to  come  forward  to  ANC  services,  particularly  in  the  last  trimester.  However,  one  must  take  into  consideration  the  additional  demand  for  services  when  the  health  sector  key  bottleneck  is  availability  of  human  resources.  

1.1.3.     Postnatal  care  within  48  hours  (at  least  1  visit)  

Acceleration  Required  

As  above.  

1.1.4.     Contraceptive  prevalence  rate  (CPR)    

Acceleration  Required  

The  historical  annual  change  rate  was  rather  small  albeit  the  APIR  reported  a  number  of  indicators  as  “achieved”.  However,  this  might  not  be  enough  to  ensure  the  achievement  of  the  HPNSDP  Results  Matrix  indicator.  Extra  effort  and  investment  must  be  made  and  consider  going  beyond  the  OP  annual  target  if  not  revise  them.  

1.1.7.     %  of  under-­‐5  children  with  pneumonia  receiving  antibiotics    

Change  of  target  for  2016  

The  Results  Matrix  has  already  been  met  as  reported  by  BDHS,  2011.  The  new  target  should  be  to  increase  the  proportion  of  5-­‐children  with  pneumonia  receiving  antibiotics  to  at  least  80%.  

1.1.8.     %  of  children  (6-­‐59  months)  receiving  Vit-­‐A  supplementation  in  the  last  6  months    

Acceleration  Required    

Acceleration  is  required  based  on  the  mathematical  model  of  projection.  However,  it  is  felt  that  from  latest  Vit  A  campaigns  have  been  reflected  in  the  latest  BDHS.  

1.1.9.     TB  case  detection  rate      

Modest  target  set   PA  change  of  indicator  is  proposed  to  “TB  notification  Rate  since  the  denominator  is  uncertain  for  TB  case  detection  rate.  

1.3.2.     %  of  children  6-­‐23  months  fed  with  appropriate  IYCF16  practices    

Acceleration  Required  

This  indicator,  based  on  past  performance  has  been  deteriorating  and  it  requires  careful  examination  of  causes.  It  will  require  properly  managed  nutrition  interventions  supported  with  adequate  communication  and  mass  media  efforts.  

1.2.2.     Use  of  modern  contraceptives  in  low  performing  areas    

Acceleration  Required  

Sylhet  requires  acceleration.    

Page 43: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 6  

1.2.3.     #  of  Upazilas  with  women  targeted  by  improved  voucher  scheme14  for  having  institutional  deliveries    

Change  of  target  for  2016    

The  Results  Matrix  has  already  been  met  as  reported  by  BDHS,  2011.  The  new  target  should  be  at  least  65  Upazilas.  

1.3.1.     Rate  of  exclusive  breastfeeding  in  infants  up  to  6  months    

Change  of  target  for  2016  

The  Results  Matrix  has  already  been  met  as  reported  by  BDHS,  2011.  The  new  target  should  be  at  lest  75%  

1.3.2.     %  of  children  6-­‐23  months  fed  with  appropriate  IYCF16  practices    

Acceleration  Required  

All  policies  and  strategies  are  in  place.  

1.4.1.     #  of  Community  Clinics  (CC)  with  increasing  number  of  service  contacts  over  time    

Close  monitoring  is  required.  

Data  is  not  available  to  project  indicator  in  2016.  

1.4.2.     %  of  upgraded  union-­‐level  facilities  able  to  provide  basic  EmOC  services18    

This  indictor  actually  decreased  between  2007  and  2011  

Very  optimistic  target  given  the  HR  constraint.  However,  policies  and  strategies  are  in  place.  

2.1.1.     %  of  MOHFW  budget  allocated  to  Upazila  level  or  below    

This  indictor  actually  decreased  between  2007  and  2011  

No  comments.  

2.3.1.     Proportion  of  service  provider  positions  functionally  vacant  at  district  level  and  below,  by  category    

Acceleration  is  required.  

Key  indicators.  It  will  require  policies  and  short,  medium,  and  long  term  strategies  

2.3.3.     Number  of  comprehensive  EmOC  facilities  with  functional  24/7  services  covering  all  districts    

No  assessment  is  possible  due  to  different  sources  of  data.  

Important  indicator  and  should  be  measured  as  proportion  of  districts  with  functional  24/7  CEmOC  services  

2.5.1.     %  of  health  facilities,  by  type,  without  stock-­‐outs  of  essential  medicines  at  a  given  point  in  time    

Modest  target.   Consider  new  target  to  achieve  at  least  85%  of  health  facilities  by  type  without  essential  medicine  stock  outs.  

2.5.2.     %  of  facilities  without  stock-­‐outs  of  contraceptives  at  a  given  point  in  time    

Acceleration  required.  

See  recommendation  of  the  Procurement  review  team.  

2.8.1.     #  of  Districts/Upazilas  having  functional  LLP  procedures      

No  assessment  is  possible  with  data  available.  

This  is  key  indicator  particularly  for  Community  level  clinics  and  target  should  be  100%  by  2016.  

2.9.1.     #  of  non-­‐pool  DPs  submitting  quarterly  expenditure  reports    

Target  is  100%   This  is  fundamental  principle  of  SWAp  and  should  be  achieve  long  before  2016.  

 

Page 44: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

 

37  

H P N S D P   R E S U L T S   M A T R I X   A N A L Y S I S  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

Goal:  Ensure  quality  and  equitable  health  care  for  all  citizens  of  Bangladesh.  

GI  1     Infant  mortality  rate  (IMR)     BDHS,  every  3  yrs     52,  BDHS  2007     43,  BDHS  2011     31   2.25   32   OK  

GI  2     Under  5  mortality  rate     BDHS,  every  3  yrs     65,  BDHS  2007     53,  BDHS  2011     48   3.0   38   OK  

GI  3     Neonatal  mortality  rate  (NMR)    

BDHS,  every  3  yrs     37,  BDHS  2007     32,  BDHS  2011     21   1.25   26   Acceleration  required  

GI  4     Maternal  mortality  ratio  (MMR)    

BMMS,  every  5  yrs     194,  BMMS  2010     194,  BMMS  2010     <143   14.22   137   OK  

GI  5     Total  fertility  rate  (TFR)     BDHS,  every  3  yrs     2.7,  BDHS  2007     2.3,  BDHS  2011     2.00   0.1   1.80   OK  

GI  6     Prevalence  of  stunting  among  under-­‐5  children    

BDHS,  every  3  yrs     43.2%,  BDHS  2007     41.3%,  BDHS  2011     38%   0.48   38.90   Acceleration  required  

GI  7     Prevalence  of  underweight  among  under-­‐5  children    

BDHS,  every  3  yrs     41%,  BDHS  2007     36.4%,  BDHS  2011     33%   1.15   30.70   OK    

GI  8     Prevalence  of  HIV  in  MARP     Sero-­‐Surveillance  (SS),  every  2  yrs    

<1%,  SS  2007     <1%  (0.7%),  SS  2011  (9th  round)    

<1%   <1   <1   OK  

Program  Development  Objective:  Increase  availability  and  utilization  of  user-­‐centered,  effective,  efficient,  equitable,  affordable  and  accessible  quality  HPN  services.    Strategic  Objective:  To  improve  access  to  and  utilization  of  essential  health,  population  and  nutrition  services,  particularly  by  the  poor.    

Component  1:  Service  delivery  improved  

Result  1.1:  Increase  utilization  of  essential  HPN  services  

1.1.1.     %  of  delivery  by  skilled  birth  attendant    

BDHS,  every  3  yrs     26.%,  UESD  2010  18%,  BDHS  2007    

31.7%,  BDHS  2011     50%   3.43   48.80   Acceleration  required  

1.1.2.     Antenatal  care  coverage  (at  least  4  visits)    

BDHS,  every  3  yrs     19.9%,  UESD  2010  20.6%,  BDHS  2007    

25.5%,  BDHS  2011     50%   1.23   31.63   Acceleration  required  

1.1.3.     Postnatal  care  within  48  hours  (at  least  1  visit)    

BDHS,  every  3  yrs     20.9%,  UESD  2010  18.5%,  BDHS  2007    

27.1%,  BDHS  2011     50%   2.15   38.85   Acceleration  required  

1.1.4.     Contraceptive  prevalence  rate  (CPR)    

BDHS,  every  3  yrs     61.7%,  UESD  2010  55.8%,  BDHS  2007    

61.2%,  BDHS  2011     72%   1.35   61.2   Acceleration  required  

1.1.5.     Unmet  need  for  FP     BDHS,  every  3  yrs     17.1%.  BDHS  2007     11.7%,  BDHS  2011     9.0%   1.35   4.95   OK  

Page 45: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 8  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

1.1.6.     Measles  immunization  coverage  by  12  months    

CES,  annual     82.4%,  CES  2009     87.5%,  BDHS  2011     90%   2.55   100   OK  

1.1.7.     %  of  under-­‐5  children  with  pneumonia  receiving  antibiotics    

BDHS,  every  3  yrs     38.0%,  UESD  2010  37.1%,  BDHS  200711    

71.4%,  BDHS  2011     50%   8.58     Target  for  2016  already  met  on  2011.  Revise  target  

1.1.8.     %  of  children  (6-­‐59  months)  receiving  Vit-­‐A  supplementation  in  the  last  6  months    

BDHS,  every  3  yrs     82.6%,  UESD  2010  88.3%,  BDHS  200712    

59.5%,  BDHS  2011     90%   Decreased  and  needs  to  increase  by  6.1%  per  

year  

  Acceleration  required  

1.1.9.     TB  case  detection  rate     NT  Program,  annual     74%,  NTP  2009     70.5%,  NTP  2010     75%   Decreased  and  needs  to  increase  by  1%  per  

year  

  Modest  Target  It  is  also  Proposed  change  indicator  to  notification  rate  due  to  uncertainty  over  denominator  

Result  1.2:  Improve  equity  in  essential  HPN  service  utilization  (MDGs  1,4,5  and  6)  

1.2.1.     Proportion  of  births  in  health  facilities  by  wealth  quintiles    

BDHS,  every  3  yrs     Q1:Q5  =  8.0:59.5,  UESD  2010  Q1:Q5*  =  4.4:43.4,  BDHS  200713    

Q1:Q5  =  9.9:59.8,    BDHS  2011    

Q1:Q5  =  <1:4   1:13  (2004)  1:8      (2007)  1:6      (2011)  

1:4   OK  

1.2.2.     Use  of  modern  contraceptives  in  low  performing  areas    

BDHS,  every  3  yrs     Syl:  35.7%,  Ctg:  46.8%,  UESD  2010  Syl:  24.7%,  Ctg:  38.2%,  BDHS  2007    

Sylhet:  35.2%    Chittagong:  44.5%,    BDHS  2011    

Sylhet  &  Chittagong:  

50.0%  

Syl:  2.63    

Ctg:  1.58  

Syl:  48.4    

Ctg:  52.4  

Sylhet:  Acceleration  required  

1.2.3.     #  of  Upazilas  with  women  targeted  by  improved  voucher  scheme14  for  having  institutional  deliveries    

DSF  Monitoring  Reports,  annual    

31  DSF  Upazilas  (+9  universal),  DSF  Monitoring  Report  2010    

53  Upazilas  (7  MNH  upazilas),  DSF  Monitoring  Cell  2012    

50  DSF  Upazilas15  

11     Target  for  2016  already  met  on  2011.  Revise  target  

Result  1.3:  Improved  awareness  of  healthy  behavior  (MDG  1,4,5)  

1.3.1.     Rate  of  exclusive  breastfeeding  in  infants  up  to  6  months    

BDHS,  every  3  yrs     43.0%,  BDHS  2007     63.5%,  BDHS  2011     50%       Target  for  2016  already  met  on  2011.  Revise  target  

Page 46: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  3 9  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

1.3.2.     %  of  children  6-­‐23  months  fed  with  appropriate  IYCF16  practices    

BDHS,  every  3  yrs     41.5%,  BDHS  2007     20.9%,  BDHS  2011     52%   Decreased  and  needs  to  increase  by  6.2%  per  

year  

  Acceleration  required  

Result  1.4:  Improved  PHC-­‐CC  systems  

1.4.1.     #  of  Community  Clinics  (CC)  with  increasing  number  of  service  contacts  over  time    

CC  Project/  MIS/MOHFW,  annual    

Registers  and  forms  supplied  to  CCs  in  June  201217    

NA     13,500       Close  monitoring  required  

1.4.2.     %  of  upgraded  union-­‐level  facilities  able  to  provide  basic  EmOC  services18    

Health  Facility  Survey  (BHFS),  every  2  yrs    

15.5%19,  BHFS  2009     4.3%20,  BHFS  2011     50%   Decreased  and  needs  to  increase  by  9.1%  per  

year  

  Acceleration  required  

Component  2:  Strengthened  Health  Systems  

Result  2.1:  Strengthened  planning  and  budgeting  procedures  

2.1.1.     %  of  MOHFW  budget  allocated  to  Upazila  level  or  below    

Public  expenditure  review,  annual    

52%,  PER  2006/2007    

47%,  PER  2008/2009    

60%   Decreased  and  needs  to  increase  by  2.6%  per  

year  

  Acceleration  required  

2.1.2.     %  of  annual  work  plans  with  budgets  submitted  by  LDs  by  defined  time  period  (July/Aug)    

Administrative  records  from  the  Planning  Wing,  annual    

NA21     100%,  Planning  Wing  2012    

100%  (target  by  2013)  

    OK  

Result  2.2:  Strengthened  monitoring  and  evaluation  systems  

2.2.1.     MIS  reports  on  service    delivery  published  and  disseminated22  annually  

HIS  &  eHealth  and  MIS-­‐FP,  annual  

NA23     Both  Directorates  have  published  but  not  disseminated  

100%       OK    

Page 47: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 0  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

2.2.2.     Performance  report  of  OPs  reviewed  with  policy  makers,  MOHFW,  Directorates  and  DPs,  six  months  and  annually24    

Planning  Wing,  six  monthly  (Jul-­‐Dec-­‐>Feb),  (Jul-­‐Jun-­‐>Aug)    

NA     100%  (FY  2011-­‐12  annual  performance25  will  be  disseminated  under  APIR  2012),  Planning  Wing  2012    

100%  (achieved  by  

2013)  

    OK  

Result  2.3:  Improved  human  resources  –  planning,  development  and  management    

2.3.1.     Proportion  of  service  provider  positions  functionally  vacant  at  district  level  and  below,  by  category    

DGHS/DGFP  MIS,  annual  BHFS,  every  2  yrs    

Physicians:  45.7%;  Nurses:  24.7%;  FWV/SACMO/MA:  16.9%,  BHFS  2009    

Physicians26:  46.1%,    Nurses:  19.59%,    FWV/SACMO/MA:  21.2%,  BHFS  2011    

Physicians:  22.8%;  Nurses:  15.0%;  

FWV/SACMO/MA:  8.5%27  

Physicians:  vacancy  rate  increased  Nurses:  annual  

reduction  4.06%  

Physicians:  vacancy  rate  needs  to  

decrease  by  4.7%  

Nurses:  will  achieve  15.53  

vacancy  rate.  

Acceleration  required  

2.3.2.     #  of  additional  providers  trained  in  midwifery  at  Upazila  health  facilities    

HRD/MOHFW,  annual    

NA     115     3,000       OK  

2.3.3.     Number  of  comprehensive  EmOC  facilities  with  functional  24/7  services  covering  all  districts    

MIS/EOC  BHFS,  every  2  yrs    

132,  MIS/DGHS  2009    

8528,  MNCAH  LD,  2012    

204  (DGHS  Voice  of  MIS  Feb,  2009)  

    Important  indicator  and  should  be  measured  as  proportion  of  districts  with  functional  24/7  CEmOC  services  

Result  2.4:  Strengthened  quality  assurance  and  supervision  systems    

2.4.1.     Case  fatality  rate  among  admitted  children  with  pneumonia  in  Upazila  health  complex    

DGHS  MIS,  annual     8%,29  Health  Bulletin  2009    

NA  (Proper  data  source  is  being  identified)    

6.2%30       OK  

Result  2.5:  Sustainable  and  responsive  procurement  and  logistic  system    

Page 48: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 1  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

2.5.1.     %  of  health  facilities,  by  type,  without  stock-­‐outs  of  essential  medicines  at  a  given  point  in  time    

BHFS,  every  2  yrs     66.1%,31  BHFS  2009     74%,  BHFS  2011     75%       Modest  target  

2.5.2.     %  of  facilities  without  stock-­‐outs  of  contraceptives  at  a  given  point  in  time    

BHFS,  every  2  yrs     58.1%,32  BHFS  2009     55.1%,  BHFS  2011     70%   1.5   63   Acceleration  required  

Result  2.6:  Improved  infrastructure  and  maintenance    

2.6.1.     %  of  facilities  (excluding  CCs)  having  separate,  improved  toilets  for  female  clients      

BHFS,  every  2  yrs     5%,  BHFS  2009     44.5%,  BHFS  2011     75%   19.75   100   Remarkable  progress  in  two  years  

Sl  #     Performance  Indicator     Means  of  Verification  &  Timing    

Baseline    &  Source    

Update    2012    

Target  2016          

Result  2.7:  Sector  management  and  legal  framework    

2.7.1.     Regulatory  framework  for  accreditation  of  health  facilities  including  hospitals  (both  in  the  public  and  private  sectors)  reviewed  and  updated33    

MOHFW     1982  Regulatory  Act     Accreditation  of  public  hospitals  is  under  process,  HSM  OP  2012    

Reviewed  (by  2012)  

    OK  

Result  2.8:  Decentralization  through  LLP  procedures    

2.8.1.     #  of  Districts/Upazilas  having  functional  LLP  procedures    

Respective  agencies,  annual    

NA     07  districts  (including  14  pilot  upazilas)    

Piloting  completed  

and  reviewed  for  scale-­‐up.  

    This  is  key  indicator  particularly  for  Community  level  clinics  and  target  should  be  100%  by  2016  

Page 49: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 2  

SI  #   Performance  Indicator   Means  of  Verification  &  Timing  

Baseline  &  Source  

Update  2012  

Target  2016   Annual  Rate  (AR)  

Projection  to  2016  

Status/  On  track  /acceleration  

Result  2.9:  SWAp  and  improved  DP  coordination  (deliver  on  the  Paris  Declaration)    

2.9.1.     #  of  non-­‐pool  DPs  submitting  quarterly  expenditure  reports    

Planning  Wing    FMAU    

Irregular     1  out  of  15  (only  USAID)    

100%       Key  to  achieve  100%  within  the  SWAp  framework.  

Result  2.10:  Strengthened  Financial  Management  Systems  (funding  and  reporting)    

2.10.1.     %  of  project  aid  fund  (e.g.  development  budget)  disbursed  annually  and  quarterly    

FMAU     79.4%,34  FMAU  2009/2010    

60%  (FY  2011-­‐12),  APIR  201235    

100%  (by  2013)  

    OK  

2.10.2.     %  of  OPs  with  spending  >80%  of  ADP  allocation  (annually)    

FMAU/  Planning  Wing    

44.7%,36  FMAU  2003-­‐2011    

59.4%  (with  80%  or  more);    50%  (with  >80%),  Planning  Wing  2012    

100%*  (by  2013)  *Target  set  as  100%  to  ensure  

efficient  fund  utilization  

    OK  

2.10.3.     %  of  serious  audit  objections  settled  within  the  last  12  months    

FMAU     7%,  FMAU  2007/200837    

39%,  FMAU  201238     >80%       OK      

 

Page 50: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 3  4 3  

A N N E X   3    

G O V E R N A N C E   A N D   A C C O U N T A B I L I T Y   A C T I O N   P L A N  

As  the  PAD  notes,  the  GAAP  outlines  the  governance  and  accountability  risks  and  mitigation  actions  to  ensure  the  success  of  key  aspects  of  the  Project,  which  may  otherwise  be  adversely  impacted  by  these  risks.  The  GAAP  has  recommendations  in  support  of  improving  financial  management,  strengthening  weak  internal  controls,  improving  procurement  management,  and  strengthening  the  M&E  capacity.            

This  annex  contains  the  complete  analysis  of  the  GAAP.  The  IRT  has  reviewed  all  21  of  the  GAAP  Key  Objectives,  including  MOHFW  updates,  and  provided  specific  comments  on  each  of  them.  As  a  general  conclusion,  the  IRT  can  say  that  the  majority  of  Key  objectives  are  on  track  but  that  addressing  the  specific  recommendations  made  in  the  GAAP  analysis  will  ensure  that  they  will  be  met  as  intended  and  thus  promote  the  achievement  of  results  both  at  the  OP  and  RFW  levels.  We  make  the  following  overall  observations  concerning  GAAP  Key  Objective  Performance.  

‒ The  principal  area  of  concern  is  one  that  has  been  recognized  in  previous  APRs  and  which  was  again  highlighted  in  the  individual  Thematic  Area  Technical  Reviews  conducted  by  individual  Team  members,  that  is,  the  problem  of  ensuring  an  adequate  number  of  health  force  workers,  in  with  the  right  mix  of  skills  and  in  the  posts  where  they  are  most  needed.  This  includes  the  issues  of  frequent  transfers,  as  well  as  the  non-­‐filling  of  sanctioned  posts.  

‒ As  we  discuss  below,  there  has  been  both  an  issues  with  the  timely  release  of  funds  as  well  as  the  overall  lower  than  planned  allocation  of  funds  to  the  OPs  as  noted  in  the  PIP.  

Page 51: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 4  

U P D A T E   O N   G O V E R N A N C E   A N D   A C C O U N T A B I L I T Y   A C T I O N   P L A N   ( G A A P )  

Draft  IRT  Review:  02/10/2012  

Bangladesh  Health  Sector  Development  Project  (HSDP)    Error!  Unknown  document  property  name.  Governance  and  Accountability  Action  Plan  Date:  April  19,  2011  [Updated  on  22  September  2012]    

Key  Objectives   Key  Activities   Responsible  Agencies  

Key  Indicators   Reporting  Frequency/  Timeframe  

Expected  Results   MOHFW  Update  2012  

APR  2012  Comments  

1.    Sector  Governance/Enabling  Environment      

1.1  Multi-­‐year  perspective  in  fiscal  planning,  expenditure  policy  and  budgeting  

• Synchronize  OPs  with  MTBF  using  MTBF  resource  envelopes.  

 • Three  months  prior  to  the  

start  of  each  related  fiscal  year,  MOHFW  will  share  the  proposed  ADP  with  the  co-­‐financiers  for  review  to  support  the  OPs  for  the  following  fiscal  year.      

 • Predictability  in  the  

availability  of  funds.  

MOHFW,  MOF   • Rolling/Forward  budget  prepared  for  the  Program.    

• Synchronized  budget  between  MTBF,  OP  and  ADPs.  

       • Pooled  funding  

partners  to  provide  indicative  commitments  by  January  31  of  each  year.  

Annually  [CHANGE  TO:  Revision  of  OPs  for  synchronization  will  take  place  during  MTR]    Annually            Annually  

Budget  allocated  based  on  MTBF.  Predictability  of  DPs  funds  for  the  sector  

Yearly  allocation  of  OPs  synchronized  with  MTBF  projection  (but  the  ADP  allocation  deviated).    Shared  with  DPs.            Pool  Fund  partners  provided  indicative  commitments  for  FY  2011-­‐12.  Commitment  for  FY12-­‐13  will  require  to  be  obtained  soon.  

This  is  an  important  objective.  IRT  believes  that  single  work  plan  that  includes  DPA  and  parallel  funds  is  also  needed  to  understand  overall  resource  envelope.  

1.2  Public  access  to  key  fiscal  information:  Implementation  of  transparency  and  disclosure  measures  

• Ensure  regular  public  disclosure  activities  through  website  (and  appropriate  media  (e.g.  the  Strategic  Plan  and  budget,  procurement  advertisement,  EOI,  RFP,  Survey  and  Evaluation  reports).  

MOHFW,  DGHS,  DGFP,  CMSD,  HED  

• There  is  sufficient  flow  of  information  for  stakeholders    

• Website  is  active  

Once/  Continuous   Listed    information  related  to  HPNSDP  implementation  is  kept  in  the  public  domain  by  adhering  to  the  Right  to  Information  Act  2009  

Program  documents,  MIS/Survey  reports  available  from  the  following  websites:  HIS-­‐DGHS,  MIS-­‐DGFP,  MOHFW  Health  budgets  available  in  MOF  website  EOI/RFP  published  in  various  portals  like  DG  Market,  UN  and  CPTU  websites.  

Appears  to  be  on  track.  

2.    Stakeholder    

Page 52: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 5  

2.1  Ensuring  stakeholder  consultation/social  audit    

• Adequate  budget  provision  for  stakeholder  consultation/  during  APR  in  the  OPs  

 • Community  planning  and  

management  mechanisms  such  as  Community  Clinics  will  ensure  the  representation  and  participation  of  Community  representatives  

 • Clients’  Charter  of  Rights  

(CCR)  and  duties  will  be  displayed  in  the  health  facilities.  

MOHFW/  HEU   • Stakeholder’s  consultation  done  during  APR  

 • A  local  level  

accountability  mechanism  will  be  developed  in  participation  with  community  people  and  local  NGOs  

 • Citizen’s  Charter  

for  health  service  delivery  displayed.      

Annually  Progress  reviewed  during  APR    

Results  are  independently  evaluated  and  corrective  actions  taken  for  any  reported  deficiencies    Mainstreamed  voice  and  accountability  mechanisms  into  the  governance  and  stewardship  functions  of  the  overall  program.    

Stakeholder  Consultation  for  APR  2012  completed  on  time      HIS  &  eHealth  initiated  feedback  system  using  mobile  phones;  CC  Management  Support  Groups  established  with  NGOs/organizations  (e.g.  Eminence,  Plan  BD,  StC,  CARE,  JICA,  GAVI).      Citizen  Charter  displayed  in  all  health  facilities;  Hospital  Management  Committee  in  place.  

IRT  validates  the  Stakeholder  consultation  was  completed.    Whether  it  is  relevant  to  the  needs  of  the  APR  as  conducted  is  another  question.  See  APR    The  CC  offer  tremendous  potential  for  community  participation.    IRT’s  review  indicates  that  effective  participation  is  mixed  …  IRT  recommends  close  monitoring  of  this  initiative      While  the  Charters  are  not  binding,  they  do  provide  a  moral  tie  between  the  service  provider  and  clients  assuming  they  are  posted.    The  IRT  members  did  see  several  on  their  field  visits  to  three  Divisions  and  Dhaka    

3.    Implementation  Capacity/Institutional  Capacity      

3.1  Ensuring  adequate  capacity  development  of  institutions  and  human  resources  strengthening  to  effective  implementation  of  HPNSDP    

• Annual  workplans  and  budgets  to  incorporate  capacity  development  initiatives  for  different  levels  of  staff  

 

MOHFW  and  all  key  institutions  at  central,  division,  district  and  local  levels  engaged  in  health  service  delivery  .  

• Budget  execution  of  the  planned  activities.  

Annually  during  APR   Improved  implementation  capacity  and  progress  towards  the  results.  

APIR  found  overall  progress  satisfactory  (65%  of  the  OP  indicators  achieved  target  in  FY  2011-­‐12)  

While  the  APIR  notes  65  percent  of  OP  indicators  achieved  their  targets,  this  is  not  a  good  measure  for  the  Key  Objective  which  is  targeted  to  HR  and  institutional  capacity.    HRM  OP  for  instance  is  not  meeting  and  is  not  likely  to  achieve  its  results  if  it  continues  as  is.      APIR  as  well  as  all  IRT  Thematic  Reviews  have  raised  the  problem  of  HR  issues  as  one  of  the  principal  if  not  principal  constraint  to  achieving  RFW  results.    Furthermore,  it  is  the  team’s  view  that  too  much  emphasis  may  be  given  to  training  as  an  activity  and  output  …  the  link  with  RFW  results  and  OP  training  outputs  is  not  always  a  given  in  an  RBM  framework.    See  IRT  recommendation  

Page 53: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 6  

3.2  Ensuring  adequate  number  and  diversity  of  health  workforce  as  per  norms  set  by  MOHFW  

• Annual  Development  Program  preparation  and  approvals.  

     

MOHFW,  DGHS,  DGFP  

• Diversity  of  staff  increased  

       

Annually  during  APR   Effective  utilization  of    the  health  workforce  

ADP  prepared  and  approved  on  time      Substantial  augmentation  took  place  at  community  level  workforce,  e.g.  CHCP,  FWV,  FWA,  HA,  nurse-­‐midwives.    Diversity  is  being  promoted  by  MOHFW  (e.g.  NASP,  TB-­‐LP,  Community  Clinic,  FP).  

The  IRT  would  prefer  to  keep  the  second  activity  and  an  additional  indicator  that  measures  vacancy  rates  and  transfer  rates.  As  the  APIR  and  the  IRT’s  analysis  shows,  HR  is  still  in  crisis  in  Bangladesh  and  is  one  of  the  principal  constraints  to  achieving  indicator  targets  in  a  significant  number  of  OPs    Having  said  that  we  also  acknowledge  that  vacancy  rates  of  sanctioned  positions  have  improved  from  SWAp  to  SWAp.  

3.3  Improving  quality  of  health  services  

• Updating  of  the  standard  operating  procedures  and  clinical  protocols.    

• Conduct  client  and  provider  satisfaction  survey  every  two  years.  

MOHFW,  DPS   • Improvement  in  satisfaction  of  clients  and  providers    

Every  two  years,  HFS   Improved  quality  of  health  services.    

SOP  update  in  progress      Health  Facility  Survey  collects  info  on  client  and  provider  satisfaction  in  every  two  years  

No  change  proposed.    

4.    Financial  Management      

4.1  Adequate  and  timely  financial  management  at  central,  district  and  health  facility  level  

• Customize  and  expand  iBAS  for  timely  preparation  and  submission  of  quarterly  FM  reports  covering  sector  accounts.  

MOHFW/  MOF   • Quarterly  reports  of  adequate  quality  and  coverage  submitted  for  smooth  disbursement  of  funds  to  the  program.  

IUFRs  on  quarterly  basis      

Financial  statements  of  HNPSDP  prepared  through  the  iBAS    

iBAS  connectivity  established  with  FMAU.  

IRT  believes  that  customization  of  IBAS  is  not  the  appropriate  strategy.  IBAS  is  a  government-­‐wide  accounting  system,  the  reporting  needs  should  come  from  a  financial  management  system.  IRT  recommends  building  upon  the  ADP  Monitoring  tool  for  reporting  requirements.  

4.2  Timely  fund  execution  

• Conduct  regular  review  of  ADP  implementation.    

MOHFW/MOF   • Ensure  disbursement  of  Q1  funds  for  the  health  sector.  

By  August  of  each  FY      

Efficient  expenditure  Management  

Done  on  monthly  basis.   IRT  believes  this  is  a  key  objective,  given  the  underfunding  of  the  HPNSDP  vis-­‐à-­‐vis  the  PIP.    

4.3  Improve  the  quality  of  asset  management  

• Install  inventory  software  for  fixed  assets  

MOHFW/All  Directorate  

• At  least  piloted  in  one  tertiary  hospital.  

By  June  2012   Safeguard  assets  and  Inventory  

Propose  to  delete   The  IRT  believes  this  Key  Objective  should  be  maintained  and  not  deleted  as  it  responds  to  real  problems  that  exist  in  the  program  at  all  levels.  A  national  level  database  for  medical  equipment  over  a  certain  value  should  be  installed  and  maintained.  Two  previous  databases  were  already  developed  but  never  used.  This  is  not  inventory  software  (all  fixed  assets  are  in  the  inventory  software  of  CMSD)  but  asset  management  software.  

Page 54: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 7  

4.4  Establish  effective  Internal  Audit    

• Outsourced  audit  firm  to  carry  out  internal  audit    

 • Develop  in-­‐house  capacity  

to  carry  out  internal  audit  function  and  phased  out  the  outsourced  internal  audit  function.  

MOHFW/  FMAU  

• Provision  for  adequate  budget  and  initiate  the  procurement  process.    

 • Identified  qualified  

staff  and  developed  capacity  (including  report  writing  skill)  to  carry  out  internal  audit.  

By  April    2011        From  July  2011  

Safeguard  of  resources.      Capacity  developed  to  conduct  in-­‐house  internal  audit.  

Firm  outsourcing  is  at  EOI  stage.      Training  on  FM  and  auditing  going  on  by  FMAU.    

IRT  believes  this  is  on  track.    FMAU  is  suffering  from  lack  of  human  resources,  and  will  therefore  rely  on  outsourced  internal  audit  until  this  gap  can  be  filled.  

4.5  External  Audit:  Scope,  nature  and  follow-­‐up  

• Strengthening  Audit  Committee  

 • Develop  an  Audit  Strategy  

outlining  the  coverage,  focus  of  audit  and  steps  for  effective  and  timely  follow  up  on  audit  observations.  

MOHFW/FMAU,C&AG  and  PAC  

• Co-­‐opt  member  from  MOF  and  CGA  and  organize  meeting  at  regular  intervals    

• Timely  resolution  of  audit  observations.  

July  2011          December  2011      

Pending  audit  observations  settled  in  a  timely  manner.  

Audit  monitoring  system  already  in  place.      To  be  initiated  

IRT  believes  this  is  important,  especially  in  light  of  unresolved  audit  objections  raised  by  FAPAD.  

4.6    Adequate  Funds  ensured  for  operation  and  maintenance  of  medical  equipment  and  hospital  buildings  

• Adequate  budget  provision  kept  for    Operation  and    Maintenance  (O&M  )for  maintenance  of  medical  equipments,  and  hospital  buildings  

MOHFW,     • Optimum  uses  of  equipment  and  facilities  for  improved  service  delivery.  

Annual            

Adequate  funds  ensured  for  O&M  

Budget  provision  for  O&M  falls  under  revenue  budget.    The  budget  is  being  increased  every  year.  

International  medical  equipment  studies  budget  annually  between  7  and  15%  of  purchase  price  for  maintenance  of  larger  medical  equipment.  Study  should  be  done  here  and  budget  should  be  linked  to  study  outcomes.  

4.7  Improving  institutional  strengthening  of  the  MOHFW  in  collaboration  with  SPEMP    

• Identify  focal  person  for    establishing  coordination  with  the  SPEMP    

 

MOHFW/DPs   • iBAS  customized  to  capture  financial  date  of  expenditure.  

Continuous   MOHFW’s  capacity  developed  in  expenditure  management  and  in  the  area  of  fiduciary  oversight.    

Focal  person  identified  (JS-­‐FMA)  

IRT  witnesses  excellent  collaboration  between  these  two  important  partners  

5.    Procurement        

5.1  Establishment  of  PLMC  at  the  beginning  of  the  program    

• Adequate  budget  provision  kept  in  the  OP  for  PLMC  

 • Initiate  the  procurement  

process  to  hire  consultants  for  the  entire  project  life.  

MOHFW   • Consultants  are  hired  by  December  2011  

   • PLMC  functional    

PLMC  in  place  by  December  2011      

All  contracts  approved    within  timeline  given  in  PPR  Improvement  in  quality  of  procurement  process  and  documents  and  the  capacity  developed    

PLMC  formally  established      Hiring  of  consultants  ongoing  

PLMC  established  26  August  2012.  Not  fully  operational  yet.  May  take  another  6  months  before  they  can  fully  assume  their  role  as  described  in  their  terms  of  reference.  

Page 55: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 8  

5.2  TA  provided  for  procurement  consultants  for  the  procuring  agencies.  

• Individual  procurement  consultants  assigned  to  CMSD  and  DGFP,  either  through  Bank  financing  or  parallel  TA  from  other  DPs  

MOHFW   • All  documents  show  improvement  in  quality  of  bidding  documents,  evaluation  reports  and  complaint  handling  

 

Comprehensive  review  during  each  APR    

Contracts  are  awarded  within  the  initial  bid  validity  period.    

Propose  to  delete  as  the  PLMC  will  take  care  of  these  activities  

PLMC  will  indeed  give  technical  support  to  the  procuring  entities.  IRT  would  suggest,  however,  that  this  indicator  remains  for  another  year  and  be  reviewed  again  in  2013  APR  as  not  all  e-­‐management  tools  or  standards  have  been  developed.  

5.3  Introduce  E-­‐GP  at  major  3  procuring  entities  (CMSD,  DGFP  and  HED)  

• Piloting  e-­‐GP  for  CMSD,  DGFP  and  HED  in  collaboration  with  CPTU  

• Make  necessary  resources  and  logistics  available  for  e-­‐GP  implementation  

MOHFW/CPTU   • At  least  one  contract  per  agency  procured  through  e-­‐GP  in  2nd  year  of  the  project  (2012-­‐13)  

Progress  to  be  reviewed  during  APR  

More  competition  in  HED  contracts;  Lower  bid  prices  for  CMSD  and  DGFP  contracts  

Propose  to  delete  as  the  eGP  established  in  MOF  will  take  care  of  these  activities  

Indicator  should  remain  as  e-­‐GP  has  not  yet  been  done  nor  are  the  discussions  with  CPTU  to  access  the  GOB  e-­‐GP  web  portal  in  an  advanced  stage.  Availability  of  resources  and  logistics  remains  the  responsibility  of  the  MOHFW.  

5.4  Procurement  Audit  

• Provision  for  adequate  budget  and  initiate  the  procurement  process  

 • Outsourced  audit  firm  to  

carry  out  procurement    audit    

   

MOHFW/JS  (Dev  &  ME)  

• Audit  performed  and  report  disseminated    

 

By  April    2012  (contract  out  auditors  for  the  first  2  years)    By  April  2014  (contract  out  auditors  for  the  remainder  3  years)  

Improved  procurement  management.  

Budget  available  and  firm  contracting  initiated  

No  procurement  audits  have  been  done  to  our  knowledge  but  we  may  be  incorrect.  Will  follow  up  with  JS.  I  do  not  think  that  the  expected  result  of  an  audit  can  be  improved  procurement  management.  However,  if  the  audit  report  is  followed  by  the  development  of  a  procurement  risk  mitigation  plan  and  this  is  applied,  it  may  improve.  

5.5  Introduce  Framework  contract  

• Framework  contracts  for  pharmaceuticals,  medical  supplies,  contraceptives  and  repeated  commodities    

MOHFW   • No  repetitive  procurement  for  off  shelf  goods.    

By  July  2012    No  stock  out  of  consumables  or  non-­‐technical  goods  and  reduce  the  number  of  procurement  transaction.  

Agreement  for  framework  contract  is  being  developed  

Agreed.  Effort  is  made  to  make  the  framework  contract  eligible  for  GOB  and  all  DPs.  Better  to  take  more  time  than  to  rush  in  to  it  as  the  final  document  may  be  used  for  years  to  come.  

6.    Environmental  and  Social  (including  safeguards)      

6.1  Improving  and  expanding  Health  Care  Waste  Management  

• Procurement  of  equipment  and  accessories  relating  to  health  care  waste  management  (HCWM)  done  on  time  and  supplied  to  all  facilities.  

 • HCWM  activities  at  the  

upazila  levels  rolled  out  in  phases    

• Training  provided  to  all  staff  dealing  with  HCWM      

LD-­‐IHSM  and  LD-­‐ESD  

• HCWM  activities  regularly  monitored  and  annual  reviews  undertaken  to  measure  implementation  progress    

 

Continuous   Environmental  degradation  due  to  health  care  waste  prevented.    

Will  be  initiated  from  FY  2012-­‐13  

The  APR  2013  should  confirm  that  the  key  objective  has  been  initiated    

Page 56: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  4 9  

6.2  Ensure  compliance  of  safeguard  policies  relating  to  resettlement  and  land  issues  

• All  civil  works  are  screened  to  identify  possible  social  safeguard  issues      

• Any  issues  arising  out  of  the  civil  works  are  mitigated  as  per  the  guidelines  set  out  in  the  Social  Management  Framework.  

HED  and  PWD   • People  affected  by  the  civil  works  are  compensated  appropriately.  

Continuous   Issues  relating  to  land  acquisition  and  resettlement  minimized/  mitigated    

Civil  works  adhere  to  GOB’s  safeguard  policies      No  safeguard  issue  triggered    

To  date  this  has  not  been  a  major  issue  as  there  has  been  no  major  construction  that  would  trigger  the  safeguard,  e.g.,  a  resettlement  action  plan.    The  problem  does  play  out  however  with  real  consequences  for  the  achievement  of  results  throughout  the  OPs  as  relates  to  the  land  that  is  donated  by  communities  for  the  construction  of  CCs.    The  land  is  often  far  from  population  centers  and  thus  inaccessible  by  the  majority  of  the  population;  the  IRT  witnessed  several  newly  constructed  CCS  that  were  either  abandoned  or  underutilized  

6.3  Specific  needs  of  the  tribal/ethnic  people  are    addressed  appropriately  

• Recommendations  and  activities  outlined  in  the  Tribal  Health,  Nutrition  and  Population  Plan  implemented  

MOHFW  (LD-­‐ESD)  

• Implementation  progress  reviewed  at  least  annually  by  the  GOB  Task  Force  

Continuous   Ensuring  equitable  access  of  tribal/ethnic  people  to  HNP  services  without  compromising  their  cultural/  traditional  norms  

4  workshops  on  tribal  health  conducted  at  national  and  regional  levels.  

The  IRT  has  reviewed  the  THNNP  and  found  it  to  be  relevant  and  a  good  guide  for  going  forward.    We  however  have  some  concern  that  the  implementation  of  the  Plan  will  not  be  given  the  priority  it  deserves,  in  much  the  same  way  that  the  Team  sees  issues  of  gender,  equity,  voice  and  accountability  given  secondary  status  in  HPNSDP  implementation.    The  IRT  recommends  that  the  GEVA  Task  Group  place  the  monitoring  of  this  Key  objective  on  its  agenda  

 

 

Page 57: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 0  

5 0  

A N N E X   4  

D A A R   A N A L Y S I S  

To  accelerate  progress  on  key  areas  of  the  HPNSDP,  the  development  of  a  DAAR  modality  was  put  into  place.  On  an  annual  basis,  GOB  and  DPs  jointly  agree  on  key  priorities  and  indicators.  These  indicators  are  then  linked  to  incentive  payments  based  on  achievement.  On  a  regular  basis,  the  LCG  meets  to  review  progress.    

In  2011,  three  DAAR  indicators  for  2011  on  Maternal  health/  health  system-­‐Human  Resources,  Maternal  health/FP/child  health,  and  Nutrition  were  achieved  fully  and  two    indicators  on  Health  systems-­‐budgeting  and  planning  and  Fiduciary  were  achieved  partially.  This  resulted  in  a  disbursement  of  US$  7.16  million.  The  APR  team  believes  that  the  DAAR  indicators  chosen  were  appropriate  and  feasible.  The  MOH  clearly  has  the  capacity  to  implement  these  indicators.    

In  2012,  good  progress  has  already  been  made  on  the  selected  indicators.  The  GOB  feels  that  they  are  able  to  achieve  most  of  the  DAAR  targets  fully.  Our  discussion  with  DPs  also  indicate  that  there  is  comfort  in  the  capacity  of  the  MOH  to  achieve  the  2012  targets.  

Overall,  it  appears  that  the  DAAR  indicator  system  incentivizes  the  acceleration  of  progress  in  key  areas.  The  targets  chosen  thus  far  are  feasible,  and  the  MOHFW  has  the  capacity  to  achieve  them.  The  verification  of  some  targets  should  receive  continued  attention.      

Page 58: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 1  

5 1  

D A A R   I N D I C A T O R S   F O R   Y E A R   1   ( J U L Y -­‐ D E C EM B E R   2 0 1 1 )  

Sl.  No.   Priority    areas   Year    1   Inputs  

1.   Maternal  health  /  health  system  (HUMAN  RESOURCES)  

Obgyn  and  anesthetist  pair  present  in  2  pre-­‐identified  Upazila  health  complexes  in  5  low  performing  districts  with  high  maternal  mortality  rates.  

1. Selection  of  low  performing  districts  &  Upazilas.  

2. Trained  service  providers  (for  each  Upazila  :  2  doctors  in  obs.,  2  doctors  in  anesthesia  &  3  nurses  in  EOC  )  

2.   Maternal  health  /FP/  Child  health  

Availability  of  12  pre-­‐identified  obstetric  drugs  and  semi  permanent  FP  methods  in  2  Upazila  health  complexes/FP  facilities  in  5  low  performing  districts  with  high  rate  of  maternal  and  child  mortality.  

1. Selection  of  low  performing  districts  &  Upazilas.  

2. Identification  of  essential  drugs  by  competent  committee  in  consultation  with  OGSB.  

3. Need  assessment  of  identification  of  essential  drugs  on  the  basis  of  case  load  and  treatment  load.  

4. Placement  of  demand  and  procurement  of  identified  amount  of  drugs/  contraceptives  

5. Supply  according  to  need.  

3.   Health  systems  (budgeting  and  planning)  

Resource  allocation  formula  for  the  non-­‐salary  recurrent  budget  is  adopted  to  be  applied  to  the  FY2012-­‐13  budget.  

1. Sharing  Draft  Resource  Allocation  formula  with  key  stakeholders.  

2. Conduct  workshop  to  discuss  and  reach  consensus  among  key  stakeholders  on  the  resource  Allocation  formula  developed  by  HEU.  

3. Organize  TOT  training  and  provide  training  to  relevant  staff  of  the  selected  cost  centers  and  budget  personnel  at  directorates  on  applying  the  formula.  

4.   Nutrition   Nutrition  Implementation  Coordination  Committee  headed  by  the  DGHS  is  established  and  at  least  2  meetings  are  held  to  monitor  nutrition  activities  in  the  concerned  LD  (PHC,  MNCH,  IPHN,  and  Community  Clinics)  &  relevant  stakeholders.    

1. Formation  of  steering  committee  headed  by  Secretary,  MOHFW  with  TOR.  

2. Formation  of  Nutrition  Implementation  Coordination  Committee  headed  by  DGHS  with  TOR  especially  focusing  the  mainstreaming  of  nutrition.  

3. Approached  by  MOHFW  issuing  a  GO  circulated  to  concern  LDs,  DPs  &  others.  

4. Committee  would  be  reflected  in  NNS  OP.  

5.   Fiduciary   GOB  iBAS  adapted  to  meet  health  sector  financial  reporting  requirements.  

1. Identify  whether  the  reporting  options  are  available  from  GoB  iBAS  system.    

2. Identify  the  difference  between  the  transactions  recorded  in  iBAS  system  and  in  the  Line  Directors  record,  which  is  supposed  to  be  addressed  through  regular  reconciliation  process.  

Page 59: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 2  

P R O G R E S S   O N   2 0 1 2   D A A R   I N D I C A T O R S   ( A S   O F   S E P T EM B E R   1 2 , 2 0 1 2 )  

Priority  Areas   DAAR  Indicators  2012   Implementation  Responsibility   Progress  

1. Financial  Management  

a)    Financial  management  support  in  place  in  FMAU  and  selected  LDs.  

b)    iBAS  connectivity  established  with  FMAU.  

 FMA  Wing,  MOHFW  

‒ Recruitment  of  a  Firm  is  under  process.    Request  for  Proposal  (RFP)  has  been  distributed  among  short  listed  firms.  The  deadline  for  submission  of  RFP  is  16  September  2012.  

‒ iBAS  connectivity  has  been  established  with  FMAU.  

2. Procurement   a)    Staffed  and  functioning  Procurement,  Logistics  And  Monitoring  Cell  (PLMC).  

b)    Procurement  Web  Portal  is  ready  for  trial.  

 Dev.&  ME  Wing,  MOHFW  

‒ PLMC  was  established  on  26  August  2012  ‒ Trial  of  procurement  Portal  has  been  done.    

3. Monitoring  and  Evaluation  

Establishment  of  PMMU  (with  6  fully  assigned  staff),  and  Annual  Program  Implementation  Report  (APIR)  completed  on  time  to  feed  into  APR.  

 

 Planning  Wing,  MOHFW  

‒ PMMU  was  established  on  14  December  2011  (vide  notification  no.  45.184.136.00.00.27.2011-­‐112).  

‒ Since  establishment,  2  Programme  Management  Officers  (PMO)  are  working  at  PMMU.  Operational  support  to  PMMU  is  being  provided  through  ICDDR,B  with  funding  of  Sector-­‐Wide  Program  Monitoring  &  Management  (SWPMM)  Operational  Plan.  Staffing  of  PMMU  with  3  Senior  Assistant  Chief/Assistant  Chiefs  and  1  Deputy  Chief  was  made  in  September  2012.    

‒ Dissemination  of  APIR  with  Line  Directors  was  held  on  12  September  2012  with  Senior  Secretary,  MOHFW  in  the  chair.    

4. Human  Resources  &  Supplies  

A  pair  of  Obgyn  and  Anesthetist,  and  3  nurses  trained  in  EOC  present  in  10  UHCs  in  5  new  low  performing  districts  on  the  basis  of  maternal  health  and  child  mortality.  

LD  (MNCAH),  DGHS;  Director  (Admin),  DGHS;  Director,  DNS;  and  Administration  Wing,  MOHFW.  

[10 upazilas in 5 new districts (Madaripur : Shibchar, Rajoir; Netrokona: Kolmakanda, Kendua; Cox’s Bazar: Teknaf, Chokoria; Narail: Kalia, Lohagora; Habiganj: Baniachong, Ajmeriganj) were selected in July 2012 and the responsible parties were informed accordingly.]  ‒ Posting progress of a pair  of  Obgyn  and  Anesthetist may be seen

in Annex-A.  ‒ Posting of nurses trained in EOC  in  10  UHCs  in  5  new  low  

performing  districts is under process.  

Page 60: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 3  

5. Nutrition    

a)    Rollout  plan  for  SAM  is  finalized  and  approved    b)  Bi-­‐monthly  NICC  meetings  and  quarterly  SC  meetings  taking  place  

LD  (NNS),  DGHS;  and PH&WHO  Wing,  MOHFW.  

‒ Rollout  plan  for  SAM  is  Finalized  and  approved  and  is  now  at  implementation  phase  (Progress  of  SAM  activity  is  detailed  in  Annex-B)  

‒ NICC  was formed  in  December,  2011  and  from  January  three  meetings  took  place.  

‒ Three  SC  meetings  took  place  after  formation  of  the Steering  Committee  in  December,  2011.  

 

6. Stewardship:  Local  Consultative  Group  

a)    LCG  WG-­‐Health  quarterly  meetings  took  place    b)    Task  Groups  formed  (verified  by  notification)  and  functioning  (verified  by  at  least  2  meetings  per  year)  

 Planning  Wing,  MOHFW  

‒ Quarterly  LCG  WG-­‐Health  meetings  are  taking  place  regularly.  The  4th  meeting  was  held  on  24  May  2012.  The  5th  meeting  is  scheduled  to  be  held  on  25  September  2012  during  APR  2012.  

‒ Nine  Task  Groups  (TGs)  were  formed  on  24  May  2012  (vide  notification  no.  MOHFW/Health-­‐7/HPNSDP-­‐task  Group/2012-­‐104).  Since  then,  meetings  of  different  TGs  have  been  held.  Two  rounds  of  meetings  are  scheduled  to  be  held  during  APR  2012.  

Page 61: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 4  

5 4  

A N N E X   5  

T E AM   L E A D E R   T E RM S   O F   R E F E R E N C E  

Terms  of  Reference  INDEPENDENT  TEAM  LEADER  

for  Annual  Program  Review  (APR):  2012  

Health,  Population,  Nutrition  Sector  Development  Program  (HPNSDP),  2011-­‐2016  Ministry  of  Health  and  Family  Welfare  (MOHFW)  

Bangladesh  1.  Background    

Ministry  of  Health  and  Family  Welfare  (MOHFW),  Government  of  Bangladesh  (GOB)  has  been  implementing  the  Health,  Population  and  Nutrition  Sector  Development  Program  (HPNSDP)  for  a  period  of  five  years  from  July  2011  to  June  2016,  with  the  goal  of  ensuring  quality  and  equitable  health  care  for  all  citizens  in  Bangladesh  by  improving  access  to  and  utilization  of  health,  population  and  nutrition  services.  After  Health  and  Population  Sector  Program  (HPSP)  (1998-­‐2003)  and  Health,  Nutrition  and  Population  Sector  Program  (HNPSP)  (2003-­‐2011),  HPNSDP  is  the  third  sector  program  prepared  following  the  sector-­‐wide  approach  (SWAp)  in  the  health  sector  of  Bangladesh,  through  an  extensive  consultative  process  building  on  the  lesson  learned  of  the  previous  sector  programmes  for  overall  improvement  of  health,  population  and  nutrition  sub  –sectors.  The  priority  of  the  programme  is  to  stimulate  demand  and  improve  access  to  and  utilization  of  HPN  services  in  order  to  reduce  morbidity  and  mortality,  particularly  among  infants,  children  and  women;  reduce  population  growth  and  improve  nutritional  status,  especially  of  women,  children  and  vulnerable  population.    

2.  Introduction  and  Objectives  of  the  Annual  Program  Review  (APR)  

APR  is  a  management  instrument  designed  for  both  the  Government  of  Bangladesh  (GOB)  and  Development  Partners  (DPs)  to  monitor  progress  in  the  implementation  of  the  program  and  to  verify  that  management  and  policy  responsibilities  are  met  in  the  health  sector  program  (HPNSDP).  The  2012  APR  is  the  first  for  HPNSDP,  and  will  focus  both  on  institutional  and  service  delivery  issues.  The  overall  intention  of  the  APR  is  to:  

‒ Review  implementation  of  HPNSDP  in  the  light  of  an  up-­‐to-­‐date  results  framework  using  the  latest  data,  indicators  and  targets  as  provided  in  the  APIR3;  

‒ Assess  initial  progress  of  the  program  during  the  first  months  (including  independent  perspectives  on  the  DAAR  indicators4  and  the  GAAP5);  

‒ Review  the  financing  arrangements  and  assess  how  well  the  GOB  and  DP  support  meets  the  priorities  and  requirements  of  the  HPN  sector;    

‒ Undertake  analysis  in  thematic  areas  (see  below),  to  set  the  baseline  /  document  the  building  blocks  related  to  the  key  health  systems  identify  issues/challenges  concerning  effective  delivery  of  services,  and  recommend  ways  to  improve  progress.    

                                                                                                                         3  Annual  Program  Implementation  Report  4  Disbursement  for  Accelerated  Achievement  of  Results  5  Governance  and  Accountability  Action  Plan  

Page 62: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 5  

5 5  

As  HPNSDP  (2011–2016)  moves  to  its  first  year  of  implementation,  the  2012  APR  provides  an  opportunity  to  assess  progress  and  focus  on  key  priorities  in  the  following  thematic  areas:  

1 Voice  and  Accountability  2 Monitoring  and  Evaluation  3 Procurement  and  Supply  Chain  Management  4 Financial  management  with  Planning  and  Budgeting    5 MNCH  and  Family  Planning  (including  human  resources)  6 Nutrition  (including  human  resources  7 Disease  Control  (including  human  resources)  8 Urban  Health  (including  population  and  nutrition)  9 IEC  &  Behavior  Change  Communications  (BCC)  

 The  APR  is  expected  to  (i)  be  more  focused  on  key  program  initiatives  in  the  HPNSDP  where  early  results  /  or  the  lack  thereof  are  evident;  (ii)  develop  shared  problem  analysis  and  solutions  using  existing  institutional  structures,  e.g.,  the  joint  GOB–DP  task  groups  and  other  working  committees;  (iii)  focus  on  implementation  level  realities  –  with  focus  on  HPN  outcomes,  specifically  HPN  service  utilization,  nutrition  issues  and  initiation  of  important  reforms.  Specifically,  the  2012  APR  aims  to:  

‒ Review  the  progress  of  start-­‐up  measures  essential  to  meet  the  objectives  defined  in  the  policy  and  planning  documents,  and  whether  adequate  measures  have  been  proposed  for  effective  implementation  of  HPNSDP;  

o Review  the  progress  in  service  delivery  as  laid  out  in  the  Program  Implementation  Plan  (PIP)  of  HPNSDP  based  on  Results  Framework  (RFW);    

o Assess  the  progress  of  the  establishment  of  PMMU,  PLMC,  IUFR,  institutional  arrangement  of  FMAU  etc.  of  HPNSDP;  

o Identify  TA  requirement  for  the  smooth  implementation  of  the  program  focusing  particularly  on  key  system  areas  such  as  Financial  Management,  Human  Resources,  Procurement,  M&E,  Governance  and  stewardship;  

o Review  the  financing  of  the  sector  in  the  previous  year  in  terms  of  commitment  and  contributions  of  GOB  and  DPs  (including  parallel  support),  fund  utilization,  reporting,  and  overall  efficiency  achieved;  

o Review  and  highlight  health  system  issues  and  challenges  in  delivering  on  HPN  outcomes,  and  capacity  building  measures  initiated;    

o Assess  progress  of  implementation  of  DAAR  and  take  stock  and  revise  GAAP;  

o Assess  the  progress  of  procurement  (goods  and  services)  and  provide  recommendation  on  procurement  performance.  

o Review  the  working  arrangement  between  DPs  and  government  and  how  well  DP  support  (including  parallel  financing)  is  presently  supporting  the  HPNSDP  2011-­‐2016.  This  will  also  include  a  stock  take  of  the  funding  commitments  of  HPNSDP.  

The  APR  Steering  Committee  has  primary  responsibility  for  the  oversight  of  the  process,  and  is  chaired  by  Government  (Joint  Chief,  Planning  Wing,  MOHFW)  and  inclusive  of  DP  representatives.  The  Committee  will  lead  the  process  of  ensuring  the  main  deliverables  which  include:  

Page 63: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 6  

5 6  

a. An  Aide  Memoire,  agreed  between  Government  and  DPs    

b. Updated  Results  Framework  and  GAAP  using  the  latest  data  and  information  to  inform  baselines  and  targets  

c. Thematic  Analytical  Reports  that  inform  the  Aide  Memoire  and  form  the  baseline  of  analysis  for  determining  future  progress.  

3.  Description  of  the  APR  Process  

The  APR  process  includes  several  steps  (technical  review,  task  group  meeting,  field  visits,  stakeholder  consultation,  policy  dialogue,  preparation  of  action  plan  and  wrap-­‐up  meeting)  as  detailed  below.      

a. The  Technical  Review  will  be  carried  out  by  an  Independent  Review  Team  (IRT)  comprised  of  international  and  national  consultants  that  will  analyze  data  generated  from  routine  data  sources  of  MOHFW  as  well  as  available  surveys,  analytical  studies,  qualitative  data,  and  conduct  fact-­‐finding  activities  to  review  the  progress  of  HPNSDP.  The  Annual  Program  Implementation  Report  (APIR)  will  be  prepared  by  the  MOHFW  and  made  available  to  IRT  prior  to  the  Technical  Review.  The  IRT  will:  

‒ Review  available  information  and  assist  the  Task  Groups  in  analyzing  data  and  recommending  next  steps  (TORs  pertaining  to  specific  thematic  areas  has  been  developed  separately).  The  IRT  will  prepare  a  technical  report  (IRT  Report)  drawing  on  various  inputs,  including  the  reports  mentioned  in  (b),  (c),  (d)  below  and  the  other  sources  of  information  described  in  section  4,  to  be  discussed  in  the  Task  Groups.  Based  on  these  discussions,  an  action  plan  will  be  developed  to  be  followed  up  in  the  next  year;    

‒ Review  implementation  of  the  HPNSDP  and  provide  a  detailed  analysis  of  a  selected  thematic  areas  of  the  program,  focusing  on  Health  Services  Utilization  and  Nutrition  to  highlight  the  challenges  and  possibility  of  achieving  the  objectives  and  targets  of  HPNSDP  (including  those  relating  to  reducing  inequities);    

‒ Review  the  risk  assessment  of  HNPSP  and  set  the  baseline  for  HPNSDP.  

b. Nine  (9)  task  groups  (viz.  Equity,  Gender  and  Voice;  Monitoring  and  Evaluation;  Procurement;  Financial  Management;  Human  Resources;  Nutrition;  Health  Financing  Resources  Group;  MNCH-­‐FP  and  Sector  Management)  and  ‘task  groups’  have  been  formed  under  the  HPNSDP,  which  comprise  members  from  GOB  and  DPs.  The  issues  identified  in  the  technical  review,  stakeholder  consultation  and  field  visits  will  form  the  agenda  for  discussion  in  the  Task  Groups.  Each  Task  Group  will  identify  a  set  of  actions,  with  time  lines  and  responsibilities.  These  actions  will  be  consolidated  for  further  discussion  and  endorsement  at  the  higher  level  of  MOHFW.  

c. APR  will  include  field  level  discussions  to  understand  implementation  realities  at  the  field  level.  7-­‐member  teams  comprised  of  3  MOHFW,  3  DPs  and  1  IRT  representatives  will  visit  field  with  a  focus  on  identifying  solutions  to  service  delivery  bottlenecks  to  improve  utilization  of  services.  During  the  field  visits,  emphasis  will  also  be  given  to  strategies  to  improving  utilization  of  HPN  services  and  including  nutritional  status  of  poor  women  and  children  on  the  basis  of  discussions  at  the  field  levels.  The  process  is  to  be  managed  by  the  PW  of  MoHFW  and  a  brief  report  on  issues  identified  during  the  field  visit  will  be  included  in  the  IRT  Report.  A  separate  TOR  for  field  visit  will  be  developed  in  consultation  with  DPs  and  IRT  team  leader.  

Page 64: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 7  

5 7  

d. Stakeholder  Consultation  will  be  carried  out  under  the  APR  to  elicit  views  on  service  delivery  and  utilization  from  various  stakeholder  groups  including  academicians  and  civil  society  organizations.  In  order  to  carry  out  the  consultation  and  prepare  the  consultation  report,  an  independent  agency  will  be  contracted.  Stakeholder  consultations  will  be  conducted  in  seven  divisions  feeding  into  a  discussion  at  the  division  HQ  level.  This  year,  the  Stakeholder  review,  while  focusing  on  health  service  utilization,  will  have  an  additional  schedule  to  probe  issues  related  to  nutrition  and  will  elicit  views  of  stakeholders  including  poor  pregnant  women,  HPN  service  users,  and  HNP  service  providers  from  NGO,  public,  and  private  sectors.  Based  on  these  consultations  and  focused  group  discussions  (FGDs),  the  agency  will  prepare  a  Stakeholder  Consultation  Report  that  will  feed  into  the  APR  process.    

e. On  the  basis  of  the  IRT  report,  a  Policy  Dialogue  will  take  place  between  the  senior  representatives  of  MOHFW  and  the  DPs.  The  Key  Objectives  of  the  policy  dialogue  will  be  defined  by  the  APR  SC  with  the  aim  to:  

‒ Discuss  key  findings  and  recommendations  proposed  by  the  IRT  report;  ‒ Discuss  MOHFW’s  and  DP  comments  on  IRT’s  report;    ‒ Prioritize  HPNSDP  issues  and  recommendations  to  prepare  the  action  plan;  and  ‒ Agree  on  proposed  actions  required  for  moving  the  HPNSDP  forward  and  to  achieve  

the  program  objectives  and  targets.      

f. The  Aide  Memoire  for  the  2012  APR  will  be  jointly  written  by  the  GOB  and  DPs.  A  drafting  committee  will  deliver  the  first  draft  for  discussions  to  the  MoHFW.  The  final  Aide  Memoire  will  be  discussed  and  agreed  upon  in  the  Wrap  up  meeting.  The  LCG  -­‐Health  group  will  be  appraised  of  the  overall  situation.    

g. Following  the  policy  dialogue  and  an  agreed  Aide  Memoire  with  an  Action  Plan  will  be  developed  and  agreed  upon.  Action  Plan  implementation  might  require  revision  of  Operational  Plan,  budget  and  procurement  plan  for  the  following  year.  LCG  -­‐  Health  group  will  review  progress  of  implementation  of  agreed  upon  Action  Plan  following  the  APR.    

4.  Tasks  of  the  Independent  Team  Leader  for  the  APR  

The  Team  Leader  for  the  21012  APR  will  report  directly  and  ultimately  to  the  Senior  Secretary  of  Health  in  the  MoHFW,  and  to  the  Local  Consultative  Group  for  Health.  S/he  will  take  lead  responsibility  for  the  overall  APR  process  and  the  production  and  quality  of  the  main  reports,  most  specifically  the  Technical  Review  Report  and  the  coordination,  consensus,  and  final  production  of  the  aide  memoire  (as  detailed  above).    

The  Team  Leader  will  assist  in  the  selection  of  the  independent  reviewers  for  the  thematic  studies  mentioned  above.  In  addition  s/he  will  provide  overall  supervision,  guidance,  and  production  of  the  main  outputs  of  the  APR  process  (outlined  below  under  deliverables).  The  Team  Leader  will  be  provided  with  administrative  assistance  from  the  World  Bank  Health  Team  to  ensure  logistics  are  available  to  complete  the  work  in  a  consultative  manner  and  on  time.  Towards  this  the  Team  Leader  will  produce  a  schedule  of  activities  and  meetings  early  in  the  process  (by  18  September)  which  includes  a  consolidated  plan  for  field  visits  by  those  working  on  thematic  areas,  as  well  as  consultations  on  other  elements  outlined  above.  

Particular  emphasis  should  be  on  actions  which  provide  strategic  direction  and  lesson  learning  to  the  sector  programme,  and  most  especially  in  relation  to  adjustments  to  

Page 65: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 8  

5 8  

operational  plans  which  could  enhance  results  and  performance.  Reports  should  provide  recommendations  based  on  findings  and  the  AIR,  a  risk  assessment,  reflections  on  the  results  framework  and  DLIs,  and  a  commentary  on  actions  taken  in  relation  to  the  GAAP.  The  final  report  should  also  make  recommendations  in  relation  to  processes  for  future  APRs.  

The  Team  Leader  will  be  expected  to  use  methodologies  which  are  inclusive  of  a  wide  range  of  stakeholders,  and  to  hold  regular,  well-­‐planned  discussions  with  senior  Government  officials,  Development  Partners,  and  non-­‐state  actors.  S/he  will  be  expected  to  familiarize  him/herself  with  the  range  of  background  documents,  and  to  participate  in  Task  groups,  LCG  meetings,  and/or  other  meetings  as  appropriate.  All  stakeholders  will  avail  information  to  the  Team  Leader  openly.  

5.  Deliverables  

‒ The  Team  Leader  of  IRT  will  submit  a  written  report  to  the  APR  SC.  The  final  version  of  the  report  will  include:  

‒ A  report  containing  concise  information  on  the  key  issues  to  be  discussed  during  the  policy  dialogue;  the  main  report  should  be  a  maximum  of  20  pages.  This  will  include:  (a)  progress  against  objectives  and  main  findings  of  thematic  reviews;  (b)  updated  results  framework  (c)  institutional  constraints  in  implementation  including  any  updates  required  on  the  Risk  Assessment;  (d)  priority  actions  for  follow-­‐up  for  the  remainder  of  HPNSDP;  (e)  financial  framework  for  the  sector  including  DP  funding;  (f)  progress  on  key  areas  of  GAAP.  

o The  background  reports  of  all  Thematic  Reviews  and  key  findings  from  the  stakeholder  consultation  meeting  will  be  attached  in  an  annex  to  the  main  report.  These  should  form  an  important  analytical  baseline  for  this  sector  programme.  

6.  Availability:  

The  Team  Leader  should  be  available  for  a  ten-­‐day  visit  to  Bangladesh  in  mid-­‐July  and  full  time  in  Bangladesh  from  15  September  though  12  October  2012.    

7.    Information  available  for  the  APR  2012  

The  following  resource  documents  and  reports/sources  of  information  will  be  available  to  be  used  in  the  APR6:  

‒ Strategic  Plan  for  HPNSDP  ‒ Program  Implementation  Plan  (PIP)  of  the  HPNSDP    ‒ Operational  Plans  relevant  to  the  selected  9  thematic  areas  ‒ Governance  and  Accountability  Action  Plan  ‒ Stakeholder  Consultation  Report  2012  ‒ Project  Appraisal  Document  (PAD)  of  Health  Sector  Development  Program  (HSDP)  ‒ Annual  Program  Implementation  Report  2012  ‒ Bangladesh  Demographic  and  Health  Survey  2007  and  2011  ‒ Bangladesh  Maternal  Mortality  Survey  2010  ‒ Utilization  of  Essential  Delivery  Services  Survey  2008  and  2010                                                                                                                            6   Following the first visit of the Team Leader additional areas of analytical work will be initiated in consultation with the APR SC and respective Task Group as an input into the APR process – this October involve follow up on specific aspects of HPNSDP e.g. review of Technical Assistance, Health Care Waste Management and Tribal plans.

Page 66: Annual+Programme+Review+2012+ Bangladesh+Health ......Acknowledgements:+ This!Consolidated!Technical!Report!of!the!findings,!conclusions!and!recommendations! relative!to!the!firstAnnual!Programme!Review!ofthe!Health

 

  5 9  

5 9  

‒ Bangladesh  Health  Sector  Profile  2010  ‒ National  Health  Accounts  2007–08  ‒ Health  Facility  Survey  2009  and  2011  ‒ Public  Expenditure  Review  2008-­‐9  ‒ Joint  Assessment  of  the  Implementation  of  HIV/AIDS  Targeted  Interventions  in  

Bangladesh  2008  ‒ Environment  Management  Plan  of  MoHFW  ‒ Bangladesh  Health  Watch  Report  2007,  2009  and  2011  ‒ Review  Missions/Evaluation  reports  of  GFATM/GAVI/DP  Support  program    (where  

available)  ‒ Rapid  Assessment  of  Demand  Side  Financing  Scheme  2008  ‒ Economic  Evaluation  of  Demand-­‐Side  Financing  for  Maternal  Health  in  Bangladesh  

2010  ‒ Costing  of  Maternal  Health  Services  in  Bangladesh  2010  ‒ Public  Expenditure  and  Financial  Assessment  (PEFA)  of  the  Health  Sector  as  well  as  the  

overall  Sector  2010  (check)    ‒ World  Bank’s  Procurement  Assessment  2010  (check)  ‒ Aid  Modality  Assessment  (check).  

8.  Independent  Review  Team  (IRT)    

‒ Team  Leader  ‒ Gender,  Equity,  and  Voice  Specialist  ‒ M&E  Specialist  ‒ Financial  Management  Specialist  ‒ Procurement  Specialist  ‒ MNCH&FP  Specialist  ‒ Nutrition  Specialist  ‒ Disease  control  Specialist  ‒ Urban  Health  Specialist  ‒ IEC  &  BCC  Specialist  

9.  Reporting  

The  Team  Leader  (TL)  of  the  Independent  Review  Team  (IRT)  will  work  under  the  guidance  of  the  Chair  of  the  APR  Steering  Committee  (APR  SC).  The  TL  will  report  for  all  purposes  to  the  APR  SC.  

10.  APR  Secretariat  

MOHFW  Planning  Wing/  PMMU  will  act  as  the  secretariat  for  the  APR  2012.  

11.  Support  Team:    

The  support  team  will  facilitate  the  APR  process.  

‒ Two  officials  from  the  MOHFW  Planning  Wing  ‒ World  Bank  Bangladesh  HPN  team