annual introduction to last planner system
TRANSCRIPT
![Page 1: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/1.jpg)
© LEAN CONSTRUCTION INSTITUTE
O V E R C O M I N G O U R I N D U S T R Y C H A L L E N G E S W I T H L E A N S O L U T I O N S
Introduction toLast Planner System®
October 15, 2019
Douglas Lee – Brasfield & GorriePreconstruction Operations Manager – Vice President
Houston Brown – Brasfield & GorrieSenior Lean Manager
O V E R C O M I N G O U R I N D U S T R Y C H A L L E N G E S W I T H L E A N S O L U T I O N S
2 1 S T A N N U A L
© LEAN CONSTRUCTION INSTITUTE
![Page 2: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/2.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Lean Construction Institute Provider Number H561
Introduction to Last Planner System®LCITB.IntrLPS
Presenterdate
2
![Page 3: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/3.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
4 LU Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product._______________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
4
![Page 4: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/4.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
This introductory training will include an overview to Last Planner®
System (LPS) implementation. LPS integrates Lean principles and is based on conversation leading to reliable commitments by team members. Participants will learn the fundamentals of LPS. The training will include a hand on simulation to revel the importance of removing variation in work flow.
5
Course Description
![Page 5: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/5.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
01. 02. 03. 04.At the end of this presentation, participants will have an overview understanding of each of the 5 levels of Last Planner® System (LPS) and how they inter-relate.
At the end of this presentation, participants will understand the need for reliability on projects and how LPS produces it.
At the end of this presentation, participants will understand the need to reduce variation in work flow and how LPS supports this.
At the end of this presentation, participants will know the basic mechanics of the 5 levels of LPS.
6
Learning Objectives
![Page 6: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/6.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
8
Lean Journey to Mastery
Unaware
Awareness
Understanding
Mastery
Competency
Continuous Learning Cycle(s)
8
How will you reach the next level on your journey?
![Page 7: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/7.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
9
Learning Overview
Why Last Planner® System
LPS Overview
Milestone Planning
Phase Pull Planning
Look Ahead Planning
Weekly Work Planning
Learning/Improving
9
1.
2.
3.
4.
5.
6.
7.
![Page 8: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/8.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
12
Discussion Question
What are your dissatisfactions with the way projects are currently planned?
Large Group Discussion 5 min
![Page 9: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/9.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
13
Six Tenets of Lean
2
13
1
2
3
4
5
6
Respect for people
Optimize the Whole
Generate Value
Eliminate Waste
Focus on Flow
Continuous Improvement
![Page 10: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/10.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
54%of commitments
made on construction projects were
completed on time
Brief History
14
![Page 11: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/11.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
15
2004 study by the Construction Industry Institute
The Opportunity…
Productive Time
Waste 12%
Productive Time Waste 57%
Productive Waste
MANUFACTURINGDESIGN/
CONSTRUCTION
15
![Page 12: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/12.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Time —70% were delivered late
70%Delivered Late
20%Delivered On
Time
10%Delivered Early
73%Over Tender
Price
14%On Tender
Price
13%Under Tender
Price
Cost —73% were over budget
Why Use Last Planner System®?
16
Source: Benchmarking the Government Client Stage Two Study December 1999
![Page 13: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/13.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Completed Ahead ofSchedule
Completed UnderBudget
Low Lean Intensity High Lean Intensity
3X
2X
Correlation of Lean intensity to outcomes (% likelihood on best projects)
Correlation of Lean
![Page 14: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/14.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Workflow and Risk
1. Workflow losses are real, lead to adversarial relations, and are difficult to quantify, so…
2. Everyone protects themselves by adding contingency and/or holding back labor to keep utilization high.
3. This further reduces workflow predictability and increases project risk
4. By their/our actions, we increase that risk and shift it along.
18
![Page 15: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/15.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
19
1. Traditional planning systems are unable to producepredictable workflow.
2. Workflow reliability directly affects system speed and cost.
3. All plans are forecasts, all forecasts are wrong, further in advance –more wrong, more detail – more wrong.
Key Concepts
![Page 16: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/16.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
20
1. Improves communication & reliability.
2. Fosters an enjoyable environment, trust, and collaboration.
3. Promotes early stakeholder engagement.
4. Improves visibility of the project plan (transparency).
5. Creates team buy in.
6. Rapid learning through metrics, revealing areas for improvement.
7. Improves planning in both design & construction phases.
Benefits
![Page 17: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/17.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
21
Project is a Promise
A project is a very big promise delivered by
people in an ever changing network of
promises.
![Page 18: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/18.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
22
Performance
PERFORMERCUSTOMER
Credit: Dr. Fernando Flores
Preparation
Acceptance
Negotiation
Conditions of
Satisfaction,Time
Request or Offer
Acceptance(2 mutual promises)
Declaration ofSatisfaction
Report of Completion
Basic Action Flow
22
![Page 19: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/19.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
23
Last Planner System® OverviewMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 20: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/20.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
24
Lookahead
Phase Pull
Milestone
Weekly
Learning
Milestoneinforms
Phase Pull
Phase Pullinforms
Lookahead
Lookaheadinforms Weekly
Weeklyinforms
Learning
Learninginforms
Milestone
System for Planning
![Page 21: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/21.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
25
Continuous Improvement
25
Last Planner® System follows the Continuous Improvement Cycle of:
Plan, Do, Check, Act/Adjust
![Page 22: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/22.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Focus on Hand-offs
![Page 23: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/23.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Last Planner System®
27
Courtesy of : PCL
DAILY HUDDLE
PHASE PULL PLANNING LOOKAHEAD PLANNING
WEEKLY WORK PLANNING
MILESTONE PLAN
![Page 24: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/24.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Levels of Granularity
Milestone Planning
Phase Pull Planning
Lookahead Planning
Weekly Work Planning
Boulder
Rock
Pebble
Sand
![Page 25: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/25.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
29
Last Planner System® OverviewMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 26: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/26.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
A Last Planner® (LP™) can make the reliable
commitment to complete the work
Person closest to work, with authority to make
decisions creates schedule
Who is the Last Planner®?
30
![Page 27: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/27.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
31
Milestone PlanningMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 28: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/28.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
32
Define the overall road map and gain alignment
Identify milestones important to client and stakeholders – especially immovable dates
Informs the Phase Pull Planning
MILESTONE PLANNING
32
Phase “Pull” Planning Phase “Pull” Planning
Milestone Planning
![Page 29: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/29.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
33
Milestone Planning Example Tag
Complete Structure11/8/16
CompleteExterior2/10/17
CompleteFinishes2/13/18
Color CodeOrient as Diamond
or other distinguishing
manner
Add dates or durations
Add intermediate milestones to
create small batch phases of 8-12 weeks duration
Add intermediate milestones for date to pull each phase
![Page 30: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/30.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
34
Milestone Planning Example
![Page 31: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/31.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Courtesy of : The ReAlignment Group of California
Milestone Planning Example
![Page 32: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/32.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
37
![Page 33: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/33.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
38
through Floor 35
etc . . .
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor2
Floor 1
Parade of Trades
01.
02.
03.
04.
05.
The building has 35 floors.
There are seven trades.
Each trade has work on every floor.
The work must be done in sequence, with each trade only able to work on those floors that have been given to them by the previous trade.
The trades mobilize to the site one week apart.
38
![Page 34: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/34.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
39
Parade of TradesHow will you develop the
project schedule?
![Page 35: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/35.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
40
40
Build-out 35 Floors
![Page 36: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/36.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
41
Work Sequence
Week 1 Week 2 Week 3 Week 4 Week 5
Build-out 35 Floors
41
![Page 37: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/37.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
42
Distribute score sheets as directed
Chips START in the queue of Layout
Establish queue spaces
Give die to Casework
Move 35 pieces of work through 7 tasks. Work is completed at the end of the week and passed to next trade. Place materials on table as shown.
Layout
35
FramingRough
Plumbing
RoughElectrical
DrywallPaint
Casework
42
Dice
![Page 38: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/38.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
43
Pass the Die to the LEFT, Pass Chips to the RIGHT !
WEEKCOLUMN 1CAPACITY
NUMBER ON DICE
COLUMN 2CAPACITY
PIECES PASSED
COLUMN 3REMAINING INCOMING
INVENTORY (BACKLOG)AVAILABLE - PASSED
1 3 3 32
2
3
Week 1
43
![Page 39: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/39.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
44
Layout
32
RoughElectrical
3
44
![Page 40: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/40.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
45
WEEKCOLUMN 1CAPACITY
NUMBER ON DICE
COLUMN 2CAPACITY
PIECES PASSED
COLUMN 3REMAINING INCOMING
INVENTORY (BACKLOG)AVAILABLE - PASSED
2
3
NO INVENTORY THIS WEEK. DO NOT ROLL – JUST PASS DICE.
Framing
Pass the Die to the LEFT.
45
Week 2
![Page 41: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/41.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
46
WEEKCOLUMN 1CAPACITY
NUMBER ON DICE
COLUMN 2CAPACITY
PIECES PASSED
COLUMN 3REMAINING INCOMING
INVENTORY (BACKLOG)AVAILABLE - PASSED
1 3 3 32
2 1 1 31
3
Layout
46
Week 3
![Page 42: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/42.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
47
Layout
30
FramingRoughPlumbing
RoughElectrical
Drywall
Paint
Casework
1
31+0
47
![Page 43: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/43.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
Casework
It’s your job to keep everyone at the table on the same week
. Announce the week as you get the dice (and to start the game)
Layout
35
FramingRough
Plumbing
RoughElectrical
DrywallPaint
Casework
1
3
Layout
You will finish first.
Please tally the results on the Tally Sheet and send it to your right.
48
![Page 44: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/44.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
49
We’ll ask you to report when everyone’s done
Note the highest amount of Inventory in any week for each trade.
Sum and record the total Remaining Inventory for all Trades except Layout.
Record the week each Trade finishes. Sum and record the Available Capacity for all Trades.
When Work is Complete
49
Craft Week Complete
Total Capacity
(Sum of Column 1)
Total Unused Crew Potential
(Sum of Column 3)
Highest Unused Crew Potential in any week for this
trade (Highest Value in
Column 3)
Total Inventory (Sum of
Column 4)
Highest Inventory i any week for this
trade (Highest Value in
Column 4)
Concrete
Framing
Rough Plumbing
Rough Mechanical
Rough Electrical
Drywall
Paint
Sum of Column
![Page 45: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/45.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
TABLEWEEK
LAYOUT COMPLETE
WEEK PROJECT
COMPLETE
TOTAL USED
CAPACITY
TOTAL REMAINING INVENTORY
MAX INVENTORY
IN ANY WEEK
Blue
Black
Green
Red
Summary
50
![Page 46: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/46.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
1.2.2.5.5.6 1.2.3.4.5.6 2.2.3.4.5.5 2.3.3.4.4.5 3.3.3.4.4.41.1.1.6.6.6
AverageWorst
Best
40
35
30
25
20
10
10
5
0
Results
51
![Page 47: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/47.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
52
What would be the specific advantages of improved work flow
reliability on your projects?
Group discussion 10 min
Discussion Question
![Page 48: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/48.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
53
Phase Pull PlanningMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 49: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/49.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
54
Phase of the work (~8-12 weeks)
After – add dates and transfer to the Look Ahead Plan
Work out the structure and durations
Informed by the Milestone Plan
Phase Pull Planning
Courtesy of : PCL
![Page 50: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/50.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
55
Push vs. Pull
55
Pull: • A method of advancing work when the next in line customer is
ready to use it. A “Request” from the customer signals that the work is needed and is “pulled” from the performer.
• Pull releases work when the system is ready to use it.
Push:• An “order” from a central authority based on a schedule; advancing
work based on central schedule. • Releasing materials, information, or directives possibly according
to a plan, but irrespective of whether or not the downstream process is ready to process them.
![Page 51: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/51.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
56
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Work
Information
Pull Creating Flow
56
![Page 52: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/52.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
57
Phase Pull Planning Example Tag
57
Name
MY PROMISE / ACTIVITY
• What I will Deliver
• Be specific
• Small batchWork Zone / Area
MY REQUEST / TRIGGER
• What Releases my Work
• Be specific
# Days1 week max
# People
Constraint
Name of person making the commitment
Description of the activity
Work zone or area
Description of the predecessor activity or work that releases the start of your activity
Known constraint such as RFI
# of People for the work
Duration of the work in daysSmall batch work into 5 days maximum
• Format tag to best fit your team needs
• Add more information as valued
• Color code by trade or discipline
![Page 53: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/53.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
58
Phase Pull Example
Mike G 5 days4 Crew
Underground Piping Zone 1
Vaults Backfilled
Dave S 3 days3 Crew
Backfill Vaults Zone 1
Vaults Set
Mike G 3 days4 Crew
Vaults Set Zone 1
Vaults on Site
Dave S 3 days3 Crew
Backfill UG PipingZone 1
UG Piping
Promise Promise Promise
Request Request58
![Page 54: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/54.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
59
Start at End
59
Phase Pull PlanStart at End
Courtesy of : Turner Construction
![Page 55: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/55.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
60
Pull the Work
60
Phase Pull PlanPull the Work
Courtesy of : Turner Construction
![Page 56: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/56.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
61
Arrive at the Start
61
Phase Pull Plan Arrive at the Start
Courtesy of : Turner Construction
![Page 57: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/57.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
62
Innovative Pull Planning
![Page 58: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/58.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
63
Lookahead PlanningMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 59: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/59.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
64
• Transferred from the Phase Pull Plan to a plan with dates/weeks
• Boards, P6 or other software documentation• Rolling (6-10 weeks) Lookahead to
“make work ready”• Supports Team Meeting Discussion/Action for:• Identify Risk – Risk Log
– High/Medium/Low– Plan to Mitigate
• Identify Constraints – Constraint Log– Plan to Mitigate
• Informs the Weekly Work Plan64
Lookahead Planning
![Page 60: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/60.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
65
Lookahead Planning Example
Track PPC & Variance
2 WeeklyWork Plan
Boards
Constraint Log
Lookahead
5-6 LookaheadPlan Boards
65
Courtesy of: Turner Construction
![Page 61: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/61.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
66
• P6• Microsoft
Project• TouchPlan
• LeanKit• vPlanner• Others
Electronic Examples
Lookahead Planning Options
![Page 62: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/62.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
67
Date Promised
DateResolved
Constraint Log Example
ConstraintDescription
ResponsiblePerson & CO
DateIdentified
DateNeeded
Date Promised
Date Resolved
67
![Page 63: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/63.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
68
Discussion Question
How will looking ahead to remove constraints help your projects?
Discuss amongst selves in small groups
Table discussion 10 min with 5 min report out
![Page 64: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/64.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
69
Weekly Work PlanningMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 65: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/65.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
70
• Informed by the Look Ahead Plan
• Detail work by trade at the Daily Level
• Detail of the current week
• Detail of the next week
• Informs the Daily Huddle
• Take to the field70
Weekly Work Planning
![Page 66: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/66.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
71
Weekly Work Plan Informs the Daily Huddle
Weekly Work Planning
71
Courtesy of : PCL Courtesy of : Turner/DPR JV
![Page 67: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/67.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
72
“What, Who & When”
Commitment Description
What & Where?
Who?
When will it be done?
Crew Size?
Weekly Work Planning Example
![Page 68: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/68.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
73
Learning & ImprovingMILESTONE
Planning
PHASE PULL Planning
LOOKAHEADPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Make Work Ready
Make Promises
PPC/Variance
5 Connected Conversations
![Page 69: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/69.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
74
1. What did I complete?
2. What will I complete?
3. What needs to bere-planned?
4. How can we prevent this from happening again?
Daily HuddleCourtesy of KHS&S
![Page 70: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/70.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
75
Percent Plan Complete
![Page 71: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/71.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
76
Reasons for Variance
![Page 72: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/72.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
77
Standard Work Available @ LeanConstruction.org
![Page 73: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/73.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
LPS® Construction:
• Pull Plans identify work structure and duration
• Milestones must be clearly defined by expected outcome which will be observable
• Is linear and the flow is “tangible materials”
LPS® For DesignLPS® Design:
• Pull Plans identify work needed and date needed
• Milestones are often “decision points”
• Milestones must be clearly defined by expected outcome which will describe what we need to know
• Is emerging based on new information and the flow is “information”
![Page 74: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/74.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
79
Last Planner System® in DesignMILESTONE
Planning
PHASE PULL Planning
DESIGN CYCLEPlanning
WEEKLY WORKPlanning
LEARNING/IMPROVING
Set Milestones
Specify Handoffs
Advance the Plan
Make Promises
PPC/Variance
5 Connected Conversations
Key Difference
![Page 75: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/75.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
LPS® In DesignPhase Pull
Plan/DesignCycle Planning
Continuously Advance 2-3 Week
Cycles(Should)
Weekly Work Planning
Work Register& Constraint Log
(Can)
Check – in Sessions
Percent PlanComplete PPC
(Did)
![Page 76: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/76.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
81
Pull-Creating Flow
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Promise/Request
Work
Information
![Page 77: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/77.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
82
Massport Logan Airport Team Turner Alamodome Renovations Team
Phase Pull PlanningPhase Pull Planning “schematic phase”
![Page 78: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/78.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
83
What new actions or ideas that you learned today can you take
back to your project?
Write down on Take Away Sheet (5 minutes)Share with your neighbor (5 minutes)
Discussion Question
![Page 79: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/79.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
84
Lean Journey to Mastery
Unaware
Awareness
Understanding
Mastery
Competency
84
How will you reach the next level on your journey?
Introduction to Lean Project Delivery: Classroom, eLearning & WebinarIntroduction to Last Planner® System: Classroom & eLearningLean in the Design Phase: Classroom & eLearningIntroduction to Lean in Design-Build: ClassroomThe Business Case for Learn: Classroom
Target Value Delivery: Classroom & eLearning (release 2019)Lean in the Design Phase: Classroom & eLearningMindset of an Effective Big Room: Classroom & eLearning (release May 2019)Last Planner® System in Design: Classroom & eLearning (release 2019)Conducting Gemba Walks: Classroom
![Page 80: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/80.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
85
More on LearningEvents:• Local Community of Practice• Congress (October)• Design Forum (May)
Start learning now:www.LeanConstruction.org
Books:
![Page 81: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/81.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
eLearning
86
• Learn on your own time without taking time off project work
• Increase knowledge retention by up to 60% with interactive, small-batch learning
• Access field resources to use with teams
• Earn 1.5 CEUs (self report to AGC CM-Lean and/or AIA)
• Incentivize with LCI badging credentials for email signatures and a certificate of completion
• Save money by eliminating instructor and travel expenses
• Enterprise-level model: unlimited access to all our eLearning courses directly from your own internal Learning Center or Learning Management System.
![Page 82: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/82.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
eLearning Courses
87
Available now:• Introduction to the Last Planner System®
• Introduction to Lean Project Delivery
• Lean in the Design Phase• Effective Big Room
Coming soon:• Target Value Delivery (Fall 2019)
![Page 83: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/83.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
88
Conduct Plus/Delta
88
Conduct a Plus/DeltaCapture on a flip pad or white board:Plus: What produced value during the session?
Delta: What could we change to improve the process or outcome?
![Page 84: ANNUAL Introduction to Last Planner System](https://reader034.vdocuments.site/reader034/viewer/2022051406/627d21fd3bca1502412fc58c/html5/thumbnails/84.jpg)
© LEAN CONSTRUCTION INSTITUTE
I N T R O D U C T I O N T O L A S T P L A N N E R S Y S T E M ®
This concludes The American Institute of Architects Continuing Education Systems Course
Lean Construction Institute [email protected]
89