annexure 1 -...
TRANSCRIPT
+98.50 M
E
X
I
T
T
O
M
A
I
N
R
O
A
D
PROJECT
9
8
.
0
C D
A
B
9
8
.
0
26.96
6.17
29.04
7.07
3
4
.
6
6
4.32
22.92
9
.
4
7
2
1
.
6
5
1.50
1.39
3.67
1
7
.0
8
17.00
2.00
5.40
20.80
2.53
6.80
7
.
2
9
6.82
1.20
+98.80 M
BRIGADE INLET
CONNECTION
CONNECT TO EXISTING
MUNICIPAL SEWER
CHAMBER BY PUMPING
16770 14410 14420 11390
8515
12970 17455 15440 14360 17985
FIRE BOX-01
0.9 X 0.6 1.2M
FIRE BOX-02
0.9 X 0.6 1.2M
FIRE BOX-03
0.9 X 0.6 1.2M
FIRE BOX-04
0.9 X 0.6 1.2M
FIRE BOX-05
0.9 X 0.6 1.2M
FIRE BOX-06
0.9 X 0.6 1.2M
FIRE BOX-07
0.9 X 0.6 1.2M
FIRE BOX-08
0.9 X 0.6 1.2M
FIRE BOX-09
0.9 X 0.6 1.2M
FIRE BOX-10
0.9 X 0.6 1.2M
FIRE BOX-11
0.9 X 0.6 1.2M
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
300MM WIDE
STORM CHANEL
300MM WIDE
STORM CHANEL
TO
RAINWATER
HARWESTING
FIRE-FIGHTING HYDRENT
PIPE OUTLET FROM PUMP
ROOM
WATER LINE CONNECTED TO
EXTERNAL MUNICIPAL STORM
WATER LINE (BY PUMPING)
13220
+101.50 M
61057435
1725
5715
DROP
CHAMBER
17335
LVL
+98.80 M
SEWER TRAP
CHAMBER
E
X
I
T
T
O
M
A
I
N
R
O
A
D
PROJECT
D
A
B
+98.50 M
26.96
6.17
3
4
.
6
6
4.32
22.92
9
.
4
7
2
1
.
6
5
1
.5
0
1.39
3.67
1
7
.0
8
17.00
2.00
1
.5
0
1.39
3.67
1
7
.0
8
17.00
2.00
5.40
20.80
2.53
6.80
7
.
2
9
6.82
1.20
5.40
20.80
2.53
6.80
7
.
2
9
6.82
1.20
12.27
1
3
.
7
5
5.81
16.82
5.55
8
.
1
8
3.64
7.95
+98.80 M
BRIGADE INLET
CONNECTION
CONNECT TO EXISTING
MUNICIPAL SEWER
CHAMBER BY PUMPING
16770 14410 14420 11390
8515
1297017455
15440 14360 17985
FIRE BOX-01
0.9 X 0.6 1.2M
FIRE BOX-02
0.9 X 0.6 1.2M
FIRE BOX-03
0.9 X 0.6 1.2M
FIRE BOX-04
0.9 X 0.6 1.2M
FIRE BOX-05
0.9 X 0.6 1.2M
FIRE BOX-06
0.9 X 0.6 1.2M
FIRE BOX-07
0.9 X 0.6 1.2M
FIRE BOX-08
0.9 X 0.6 1.2M
FIRE BOX-09
0.9 X 0.6 1.2M
FIRE BOX-10
0.9 X 0.6 1.2M
FIRE BOX-11
0.9 X 0.6 1.2M
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
300MM WIDE
STORM CHANEL
300MM WIDE
STORM CHANEL
TO
RAINWATER
HARWESTING
FIRE-FIGHTING HYDRENT
PIPE OUTLET FROM PUMP
ROOM
WATER LINE CONNECTED TO
EXTERNAL MUNICIPAL STORM
WATER LINE (BY PUMPING)
13220
+101.50 M
61057435
1725
5715
DROP
CHAMBER
17335
LVL
+98.80 M
SEWER TRAP
CHAMBER
(2100 x 3080)
SERVICE
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
(2750 x 2050)
DUCT
LIFT
LIFT
(2000 x 2000)
(2100 x 3080)
DU
CT
SERVICE
LIFT
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
DUCT
LIFT
LIFT
(2000 x 2000)
(2000 x 2000)
RAMP DOWN TO BASEMENT
RAMP UP TO UPPER GROUND
PROJECT PROJECT
+98.50 M
61057435
1725
5715
(2000 x 2000)
DU
CT
LIFT
(2750 x 2050)
6.00
7.44
7.39
6.00
6.00
6.00
6.00
6.00
6.00
6.00
6.00
6.98
7.26
6.00
6.00
6.00
6.00
6.00
6.00
6.00
CHILLER PLANT
METER ROOM
(2500 x 2350)
SERVICE
LIFT
(2500 x 2350)
SERVICE
LIFT
FIRE D
RIVEW
AY
F
I
R
E
D
R
I
V
E
W
A
Y
F
I
R
E
D
R
I
V
E
W
A
Y
FIRE DRIVEWAY
WATER BALANCE CHART
SL NO DESCRIPTION AREA IN SQM. POPULATION WATER REQ.(LIT)
PER PERSON
TOTAL WATER
REQ.(LIT)
DOMESTIC CAPACITY
(LIT)
FLUSHING CAPACITY
(LIT)
SEWAGE GENERATION
(LIT)
1 HOTEL ROOMS(121 NOS) --- 242 180 43560 29185.2 14374.8 42101
2 BANQUET 419.83 280 45 12594.9 5598 6997 12315
3 RESTAURANT 871.34 484 70 33885 22703 11182 32750
4 SHOPPING 4567.13 761 45 34253 15224 19030 33492
5 OFFICE 581.41 58 45 2616 1163 1454 2558
7 STAFF & OTHERS 121 45 5445 2420 3025 5324
8 SPORTS 2378.65 463 45 20835 9260 11575 20372
9 SWIMMING POOL MAKE UP 406 16443 16443
TOTAL WATER REQUIREMENT(LIT) 169633 101996 67637 148913
STP CAPACITY (LIT PER DAY) 160000
UGR CAPACITY (LIT)1.5 DAYS STORAGE ( ONLY FOR DOMESTIC) 152994
FIRE CAPACITY (LIT)( AS PER FIRE NOC) 200000
RAW WATER TANK(LIT) 50998
TOTAL UGR ( DOM+FIRE+RAW)(LIT) 403992
ALL ABOVE WATER DEMAND PER CAPITA ARE AS PER CPHEEO CLAUSE (2.2.8.3 RECOMMENDATIONS-b)
PROJECT
6820
+98.80 M
T
O
E
X
I
T
T
O
M
A
I
N
R
O
A
D
BRIGADE INLET
CONNECTION
CONNECT TO EXISTING
MUNICIPAL SEWER
CHAMBER BY PUMPING
16.77 14.41 14.42 11.39
5
.
4
4
9.39
19.39
19.4
18.2
24.5
12.97 17.46 15.44 14.36 18.74
8
.
1
1
1
9
.
3
7
1
3
.
7
1
21.47
19.4
10.67
17.16
FIRE BOX-01
0.9 X 0.6 1.2M
FIRE BOX-02
0.9 X 0.6 1.2M
FIRE BOX-03
0.9 X 0.6 1.2M
FIRE BOX-04
0.9 X 0.6 1.2M
FIRE BOX-05
0.9 X 0.6 1.2M
FIRE BOX-06
0.9 X 0.6 1.2M
FIRE BOX-07
0.9 X 0.6 1.2M
FIRE BOX-08
0.9 X 0.6 1.2M
FIRE BOX-09
0.9 X 0.6 1.2M
FIRE BOX-10
0.9 X 0.6 1.2M
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
300MM WIDE
STORM CHANEL
300MM WIDE
STORM CHANEL
TO
RAINWATER
HARWESTING
7.76
FIRE-FIGHTING HYDRENT
PIPE OUTLET FROM PUMP
ROOM
WATER LINE CONNECTED TO
EXTERNAL MUNICIPAL STORM
WATER LINE (BY PUMPING)
13.22
+101.50 M
6.11
6
7.44
7.34
1.73
4.46
5.72
11.79
DROP
CHAMBER
ME
TE
R R
OO
M
17.34
LVL
+98.80 M
DRAINAGE ACCESS PIPE
DRAINAGE ACCESS PIPE
SEWER TRAP
CHAMBER
4
.
1
4
0
.
9
8
5
.
4
8
2
1
.
8
6
1
2
.
4
7
FIRE BOX-11
0.9 X 0.6 1.2M
6
.
7
5
1
4
.
4
9
4
.
2
5
9
.
1
1
160 KLD STP
1000.003400.00
5000.00
3400.00
4600.00
2164.63
5.6
SIZE-7.5(l)X2.5(w)X3.2(h)
static weight-11000kg
dynamic weight-17500kg
FOR HOTEL-630 KVA-1
Smart Drum Composter- 500 -
SM25
Dry Waste , Wet Waste& E-Waste
Storage Area
ENTRY TO B1 LVL
6.00
6.00
TRANSFORMER
YARD LOCATION
TRANSFORMER-1
630KVA
Size-2055(l)x1670(w)x1975(h)
Wt-1980 Kg
(for shop/ office area)
TRANSFORMER-1
250KVA
Size-1320(l)x1840(w)x1600(h)
Wt-1065 Kg
(for Ent area-2nd floor)
2055
1840
2055
TRANSFORMER-2
630KVA
Size-2055(l)x1970(w)x1975(h)
Wt-2260 Kg
(for Hotel area)
2055
TRANSFORMER-1
630KVA
Size-2055(l)x1970(w)x1975(h)
Wt-2260 Kg
(for Hotel area)
RMU
for ent+hotel
4000
HT PANEL
for ent+hotel
4000
1200
1500
1714
1250
1000
2000
FF
1000
1700
1700
R.S
R.S
R.S
R.S
R.S
R.S
METERING KIOSK
FOR HOTEL & 2ND
FLOOR ENTAREA
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
DESIGN BASIS REPORT
PROJECT : RUNWAL GROUP
REPORT PREPARED BY: (AMOD GHAMANDE)
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
DESIGN BASIS
This Sewage treatment plant has been designed to treat the domestic wastewater generated in
the project of RUNWAL GROUP having following characteristics:
Flow : 160 m3 /d Average
Peak factor : 3 times for Average flow
Operating Hours : 24 Hours.
DESIGN PARAMETERS WITH INLET & OUTLET CHARACTERISTICS:
Sr.
No.
Design Parameters Inlet
Characteristics
Outlet
Characteristics
1. pH
6.0 – 8.5 5.5 – 9.0
2. Oil & Grease (mg/l)
10 – 20 < 10
3. Biological Oxygen Demand
( BOD) (mg/l)
200 – 250 < 10
4. Chemical Oxygen Demand
( COD) (mg/l)
350 – 450 < 60
5. Total Suspended Solid
( TSS) (mg/l)
150 – 200 < 10
6. Total Nitrogen (mg/l) 120 < 50
7. Nitrate (mg/l) 15-16 < 10
8. Dissolve PO4 (mg/l) 13-15 < 5
9. Fecal Coliform
(MPN/100 ml)
106 NIL
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
ASSUMPTIONS
1. The plant is designed to operate at max. +/– 10 % variation in raw wastewater
parameters for short period only.
2. No other parameters other than mentioned above is present in the raw wastewater
which is beyond Pollution Control Norms and hazardous to micro – organisms.
LEVEL OF AUTOMATION
The plant is designed based on Moving Media Bio Reactor (MMBR) which needs no
skilled manpower. The operations involved are ON / OFF of the pumps and air blower,
sludge removal, filter backwash. These operations can be done by the security or gardener.
The pumps are provided with level switch for ON / OFF based on the tank water level and to
avoid dry run and mechanical damage. This is SEMI – AUTOMATIC design.
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
PROCESS DESCRIPTION
The raw sewage generated will be passed through the BAR SCREEN CHAMBER wherein
the free, floating, coarse suspended solids having particle size greater than 10 mm will be
trapped and removed manually. The effluent is then collected in the EQUALIZATION
TANK wherein the wastewater will be collected by gravity and pumped into downstream
units. The tank will be provided with coarse bubble aeration to avoid settling of solids and to
keep the effluent in homogenous condition.
The effluent is then pumped into the AERATION TANK wherein the aerobic microbes will
utilize the organic matter in presence of oxygen. In this tank dissolved Oxygen, Active micro
organism and organic impurities from the raw sewage feed water are allowed to react
together. This is a bio chemical reaction, organic decomposition is completed and new cells
are produced. Thus BOD in the sewage is reduced and also COD reduces to that extent. The
moving media is provided as surface for micro-organisms to attach.
The partially treated wastewater then flows by gravity into the SETTLING TANK. The dead
biomass generated in the bacterial activity allow to settle under gravity. After removal of
settlable solids , the parameter like BOD ,COD and TSS gets reduced. The sludge get
collected in hopper bottom portion & clear water flows from top in FILTER FEED TANK.
The sludge in the hopper bottom needs to be removed in proper intervals . The treated
wastewater will be dosed with ozone for disinfection purpose. The tank is provided with
aeration to improve the dissolved oxygen level in treated wastewater.
The partially treated wastewater will then be pumped through PRESSURE SAND FILTER
to remove fine suspended solid which is difficult to settle by gravity. After Pressure Sand
Filter it is passed through ACTIVATED CARBON FILTER. In Activated Carbon Filter
organic impurities will be removed by adsorption on surface area of Activated Carbon.
After filteration, treated wastewater will be stored in TREATED W/W TANK wherein
aeration is provided to improve Dissolve Oxygen level. This treated waste water will be then
reuse for gardening, toilet flushing, etc. purpose as required by client.
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
PROCESS FLOW DIAGRAM
RAW SEWAGE
EQUALIZATION
TANK
SCREENING
AERATION TANK
FILTER FEED TANK
PRESSURE SAND
FILTER
OZONATION
SYSTEM
TREATED WASTEWATER
FOR SUITABLE REUSE
SETTLING TANK
ACTIVATED CARBON
FILTER
SLUDGE FOR
DISPOSAL AS
MANURE
SLUDGE HANDLING
SYSTEM
TREATED W/W TANK
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
EQUIPMENT DETAILS – CIVIL
1. BAR SCREEN CHAMBER (T – 01)
Units provided : One
Size : 1.2 x 1.0 x 0.2 m SWD
Material of Construction : RCC
2 OIL & GREASE TRAP (T – 02)
Units provided : One
Size : 1.2 x 3.4 x 2.6 m SWD
Material of Construction : RCC
3. EQUALIZATION TANK (T – 03)
Units provided : One
Size : 3.2 x 4.6 x 3.1 m SWD
Material of Construction : R.C.C
4. AERATION TANK (T – 04)
Units provided : One
Size : 2.8 x 3.4 x 3.6 mSWD
Material of Construction : R.C.C
5. SETTLING TANK (T – 05)
Units provided : One
Size : 1.8 x 3.4 x 2.5 m SWD
Material of Construction : R.C.C
6.. FILTER FEED TANK (T – 06)
Units provided : One
Size : 1.6 x 3.4 x 3.3 m SWD
Material of Construction : R.C.C
6. SLUDGE HOLDING TANK (T – 07)
Units provided : One
Size : 1.6 x 4.6 x 4.3 m SWD
Material of Construction : R.C.C
7. TREATED W/W TANK (T – 08)
Units provided : One
Size : 19.47 Sq.m. x 4.2 m SWD
Material of Construction : R.C.C
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
ELECTRICAL DETAILS
Sr. No.
Equipment
Qty.
Connected Power (HP)
Operating Power (HP)
1.
Feed Pump
2
2.0
1.0
2.
Filter Feed Pump
2
4.0
2.0
3.
Sludge Pump
1
1.0
1.0
4.
Air Blower
2
15.0
7.5
5.
Ozonation Pump
2
4.0
2.0
6.
Ozonator
1
2.0
2.0
7.
Filter Press Feed Pump
1
1.0
1.0
Total
29.0
16.5
8.
Extra
1
2.0
2.0
Sludge Details:-
1) Dewatering technique: - Mechanical Dewatering .
2) Dried sludge disposal: - 23.8 kg/d, As Manure.
3) Sludge quantity :- 2.33 m3 /day ( includes 35 – 40% Organics & 60 – 65%
inerts/Minerals)
. A) Area required for STP: - 82.64 Sq.m
Sr No.
Description Size (m) Volume (m3)
Retention Time (Hrs)
1 Bar Screen Chamber 1.2 x 1.0 x 0.2 m SWD 0.24 m3 0.04
2 Oil & Grease Trap 1.2 x 3.4 x 2.6 m SWD 10.60 m3 1.60
3 Equalization Tank 3.2 x 4.6 x 3.1 m SWD 45.63 m3 6.70
4 Aeration Tank 2.8 x 3.4 x 3.6 mSWD 34.27 m3 5.00
5 Settling Tank 1.8 x 3.4 x 2.5 m SWD 15.3 m3 2.30
6 Filter Feed Tank 1.6 x 3.4 x 3.3 m SWD 17.95 m3 2.40
7 Sludge Holding Tank 1.6 x 4.6 x 4.3 m SWD 31.64 m3 4.70
8 Treated W/W Tank 19.47 Sq.m. x 4.2 m SWD 81.77 m3 12.00
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
CAPITAL COST
For Civil Work
Rs. 38,00,000 /-
For Mechanical + Electrical + Instrumentation
Rs. 20,00,000 /-
TOTAL
Rs. 58,00,000/-
OPERATING COST (Per year)
Sr.
No.
Parameter
I. POWER (kwh / d x Rs. 7.5 per unit)
For Sewage Treatment Plant (234.7 kw hrs/d x 365 days)
6,43,000 /-
II. LUBRICANTS Oil – 15 L/ Annum x 300 Rs./ L
Grease – 3.0 kg / Annum x 300 Rs./ kg
4500.0/-
900.0/-
III. MANPOWER
Operator – 1 operator per shift x 3 shift x 12 month x 12000 Rs./
Month
4,32,000/-
IV.
Annual Maintenance Charges
80,000 /-
TOTAL (Rs. per year )
11,60,400/-
DECCAN ENVIRONMENTAL CONSULTANTS PVT. LTD.
Note On Ozonation : Sizing of Ozonation : Disinfection by Ozonation is considered with a dosage of 7 ppm. After considering 70 % of mixing efficiency, actual dose will be 5 ppm of ozone. For 160 KLD, ozonation system provided is for 50 gm/hr. Electrodes : Electrode in ozone generator is of stailess steel 316. And dielectric used is quartz which can withstand very high temperature.Our ozone generator has multiple ozone cells operated together to produce desired quantity of ozone. ORP Oxidation – Reduction potential of over 600 mV ensures complete disinfection. Using an online ORP controller the ozone generator is turned on & Off to maintain ORP between 650 – 750 mV. ORP make : HACH Make of Ozonator manufacturer: Universal Ozone Generator / Eltech Engineers / Eq.
DECCAN ENVIRONMENTAL
CONSULTANTS PVT.LTD., PUNE
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCTP
RO
DU
CE
D B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
HYDROGEOLOGICAL REPORT
FOR:
RUNWAL DEVELOPERS
SOIL INVESTIGATION PROJECT AT HADAPSAR, PUNE
SEPTEMBER 2015
PREPARED BY:
PLOT NO. 119, SUB PLOT 39, LANE NO -7
RAMTEKDI INDUSTRIAL AREA, NEAR SANGAM PRESS
RAMTEKDI, HADAPSAR, PUNE 411013
ISO 9001-2008
(Certificate No. 01.11.3027.7860.D)
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 2
INTRODUCTION
M/s Runwal Developers, Pune entrusted the work of Hydro Geolocical studies at
Hadapsar, Pune for the feasibility of ground water prospecting for the project
“RESIDENCY” to Soiltech (India) Pvt. Ltd.
In this regard, a site visit was made to the area, which was followed by field
investigations using electrical resistivity on the same day. During this, visit the
following studies were carried out in the field:
Observations were made in the entire area to infer the role of local geological,
geomorphological and climatological factors leading to weathering of the rock.
Electrical Resistivity Surveys were conducted to infer subsurface geological
conditions in general and thickness / depth of different layers, in particular
besides Geotechnical strata classification for estimating the extent and
thickness of the different layers.
M/S Soiltech India Pvt. Ltd. Pune conducted Hydrogeological investigations by
adopting Electrical Resistivity Method. The main objectives of these investigations
were to:
a. Establishing ground water potential & finding out the feasibility of Rain
Water Harvesting.
b. Attempt Geo-technical strata classification by using resistivity method
c. To delineate the areas suitable for groundwater exploitation
d. Locating the site for bore hole
e. Delineate the groundwater table
The results of the electrical resistivity surveys along with the strata
classification and aquifer conditions are included in this report.
In order to understand the hydrogeological conditions of the area, investigations
were carried out at the site. The total area of the site is ~ 4.4 acres. The investigations
were conducted in two parts, viz. Hydrogeological and Geophysical (Electrical
Resistivity). The outcome of the investigations is discussed in the present report.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 3
CLIMATE AND RAINFALL
The climate of the district is on the whole is pleasant. The winter season is from
December to about the middle of February followed by summer season which last up
to May. June to September is the south-west monsoon season, whereas October and
November constitute the post-monsoon season. The mean minimum temperature is
about 12°C and means maximum temperature is about 39°C.
The normal annual rainfall over the district varies from about 500 mm to 4500
mm. It is minimum in the eastern part of the district around Daund (468mm),
Baramati (486 mm) and Jujuri (494 mm). This increases towards west and reaches a
maximum around Khandala (4659 mm) in the western ghat. The chances of receiving
normal rainfall are maximum (50 to 55%) in the eastern part around Indapur and
Daund, in the central part around Pune city and small area around Junnar in
northern part of the district. The rainfall analysis also indicates drought area in the
eastern, southern, south easter n, central and north western parts around Indapur,
Baramati, Jujuri, Daund, Talegaon, Dhamdhare, Alandi, Shirur and Bhor covering
around 50% area of the district.
GEOMORPHOLOGY & SOIL TYPES
The Pune district forms part of Western Ghat and Deccan Plateau.
Physiographically the district can be divided in to three distinct belts i.e., (1) The
western belt stretching from 16 to 31 km. East of Sahayadri – an extremely rugged
country cut by deep valleys, divided and crossed by hill ranges. (2) The central belt
extending for about 30 km. East of the western belt across the tract whose eastern
boundary is roughly marked by a line drawn from Pabal in the north, southwards
through Pune to Purandhar. In this belt a series of small hills stretch into valleys and
large spurs from Plateauxnd (3) The eastern belt with a rolling topography and the low
hills sinking slowly into the plains with relatively broader valleys. Therefore, the
physiography of the district has given rise to four major characteristic land forms
namely; (1) The hills and ghats (2) the foothills (3) the plateau and (4) the plains. The
district has three major drainage system namely (I) The Bhima – Gold River system in
the northern, north eastern and eastern part, of which Bhima River has a total length
of about 355 km. and Ghod River has a drainage of about 196 km. in the district – (ii)
Mula – Mutha River system covering the central part and have a total length of 242
km. in the district.(iii) Nira River system covering the south, south east and eastern
part and has a total length of about 231 km. in the district .The other Important rivers
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 4
that are flowing through the district are Bhima, Andhra, Karna, Shivganga, Pauna
and Indrayani. All the rivers have most semi-dendritic drainage pattern and the
drainage density is quite high. Based on geomorphological setting and drainage
pattern the district is divided into 71 watersheds.
HYDROGEOLOGICAL
The entire area of the district is underlain by the basaltic lava flows of upper
Cretaceous to lower Eocene age. The shallow alluvial formation of recent age also
occurs as narrow stretch along the major rivers flowing in the area. A map depicting
the hydrogeological features is shown as
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 5
HARD ROCK AREAS
a. Deccan trap (Basalt): The Basaltic lava flows occupies more than 95% of the
area of the district. These flows are normally horizontally disposed over wide
stretch and give rise to table land type of topography also known a plateau.
These flows occur in layered sequences ranging in thickness from 7 to 45m and
represented by massive unit at the bottom and vesicular unit at the top of the
flow. These flows are separated from each other by marker bed known as ‘bole
bed’. The water bearing properties of these flows depend upon the intensity of
weathering, fracturing and jointing which provides availability of open space
within the rock for storage and movement of ground water. The thickness of
weathering in the district various widely up to 20 m bgl. However, the
weathered and fractured trap occurring in topographic lows forms the potential
aquifer in the district. In Deccan Trap Basalt, the yield of the dugwells in
different formations ranges from 30 to 150 lpm/day depending upon the local
hydrogeological conditions. The yields of borewells also show wide variations
and it ranges from traces to 30.62 lps (Lavle) a seen from CGWB exploration
data.
WATER LEVEL SCENARIO
Central Ground Water Board periodically monitors 49 National Hydrograph
Network Station (NHNS) stations in the district four times a year i.e. during January,
May (Pre-monsoon), August and November (Post-monsoon).
a. Premonsoon Depth to Water Level: The water levels in the range of 5 to 10 m
bgl have observed in central, eastern and north eastern parts of the district. The
deeper water levels of more than 10 m bgl have been observed around Otur
village in northern part of the district where as at village Sirur in east and
village Nimbgaon in south eastern part of the district.
b. Depth to Water Level – Postmonsoon : The water levels between 2 and 5 m
bgl have been observed in major parts of the district in the south, south eastern,
central and north western parts occupying almost entire Purandar, Bhor,
Mulshi, Maval and Khed talukas and parts of Daund, Baramati, Velhe and
Shirur. The water levels in 5 to 10 m bgl range are mainly seen in three isolated
pockets i.e., in northern, central and south eastern parts of the district in parts
of Junnar, Ambegaon, Haveli, Daun d and Indapur talukas. Very shallow water
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 6
levels of less than 2 m bgl are observed in isolated patch in central part of the
district.
c. Seasonal Water Level Fluctuation: The pre and post-monsoon water level
fluctuation varies from 0.10 (Mulsh) to 8.00 m (Zendewadi) is observed in the
district.
d. Water Level Trend: Trend of water levels for premonsoon and postmonsoon
periods has been computed for 42 NHNS. Analysis of long term trend water level
data indicates that rise in water levels in premonsoon period has been recorded
at 18 NHNS and it ranges from negligible to 0.97 m/year (Otur) and fall in water
levels has been observed in 24 NHNS and it ranges between negligible to 0.48
m/year (Zendewadi). During postmonsoon period rise in water levels has been
recorded at 12 NHNS ranging from negligible to 0.41 m/year (Ale) while at 30
NHNS fall in water level have been recorded and it ranges between negligible to
0.44 m/year (Otur). Thus in m ajor parts of the district, both during
premonsoon and postmonsoon seasons declining water level trend has been
recorded. It shows that the fall in water level trend of up to 20 cm/year is
observed in major parts of the district, occupying north, central, western and
southern parts of the district in entire Purandhar,Bhor, Haveli, Mulshi,
Maval,Ambegaon and parts of Junnar, Khed, hirur, Daund, Baramati and
Indapur talukas. Thus the situation is quite critical in almost entire district and
the future ground water conservation and recharge structures needs to be
prioritized in these areas. He rises up to 20 cm/year has been observed in 2 to 3
isolated patches in south eastern, southern and northern parts occupying parts
of Indapur, Baramati and Daund talukas entire Velhe and parts of Junnar
taluka.
GEOPHYSICAL
In order to study the overall sub-surface geological conditions of the area,
Geophysical investigations (Electrical Resistivity Surveys) were carried out. This was
to understand the overall spread of sub-surface geological formations in the entire
area. From the Electrical Resistivity Surveys, Electrical Resistivity Method (IS: 1892-
1979 Appendix B clause 3.3 B-2):
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 7
METHODOLOGY
Electrical Resistivity Method (IS: 1892-1979 Appendix B clause 3.3 B-2):
By applying this method the resistance to the flow of an electric current through
the subsurface materials is measured at intervals on the ground surface. The
resistivity is usually defined as the resistance between opposite phases of a unit cube
of the material. Each material has its own resistivity depending upon the water
content, compaction and composition. The test is conducted by driving four metal
spikes to serve as electrodes into the ground along a straight line at equal distances. A
direct voltage is imposed between the two outer potentiometer electrodes and the
potential drop is measured between the inner electrodes. To interpret the resistivity
data for knowing the nature and distribution of the subsurface formations, it is
necessary to make preliminary trial on known formations. The potential ‘V’ thus
obtained divided by the current ‘I’ applied gives the resistance ‘R’ of the ground. The
product of the resistance and the spacing factor, which is depending upon the
disposition of the electrodes, is the resistivity of the ground.
This method is routinely used for:
a. Establishing ground water potential & finding out the feasibility of Rain
Water Harvesting.
b. Determining the sub-surface strata classification
c. Determination of hard rock foundation
d. Estimation of overburden thickness and hard rock quantities and
e. Determination of the suitability of the area for quarrying and excavation
A great variety of electrode arrangements have been used to measure the earth
resistivity but essentially they may be grouped into three classes.
Arrangements in which the potential differences between two widely spaced
measuring electrodes are recorded.
Arrangements in which a potential gradient or electric field intensity is
measured using closely spaced pair of measuring electrodes.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 8
Arrangements in which the curvature of the potential function is measured
using a closely spaced current electrode pair as well as a closely spaced measuring
electrode pair.
Any one of these arrays may be used to study variations in resistivity with depth
or in lateral condition. In studying the variation of resistivity with depth, as in the
case of a layered medium the spacing between the various electrodes is gradually
increased. With larger spacing, the effect of material at depth on the measurements
becomes more pronounced.
In studying the lateral as well as vertical variations, various electrode
configurations are adopted and the array is moved as a whole along a traverse line.
The first type of measurement is called as ‘Vertical Electrical Sounding’ (VES) and the
second one is ‘Horizontal Profiling’ (HP). In the present work both VES and HP were
conducted at different locations. The L sections generated on the basis of values of
electrical resistivity for the site have been used to depict 2-D subsurface images of the
strata as given below.
Profiles –
1-2-3-4
The geoelectrical cross-sections passing through various points have been
presented in the above figures. It is to be noted that these are apparent resistivity L
sections, which broadly match the true resistivity of formations. The values of true
resistivity have been computed and thickness, depth and true resistivity have been
Hard Rock
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 9
presented in appendix. Using IPI2 software, the values of true resistivity of strata (ρ),
its thickness (h) and depth (d) have been obtained after modeling of data and are
depicted in table form besides each curve.
Based on the resistivity modeled values it can be seen that the area shows
presence of shallow aquifer restricted to 15-20 meters depth at VES 2 & 3 locations.
The rainwater harvesting structures can be sited at all VES locations.
Note: - hydrogeological survey was carried out during monsoon season.
Rainwater harvesting feasibility analysis and Water Budgeting:
It would be necessary for anyone to know first the nature, movement and
occurrence of ground water in hard rock before the formulation and implementation of
artificial recharge works in the hard rock region. Some salient characteristics of
occurrence of ground water in hard rock are listed below:
Features of Occurrence of Ground Water in Hard Rocks are:
Ground water reservoir (aquifer) in hard rock’s is dominantly shallow
The bulk of the ground water is stored in the zone of weathering (Vadose zone)
Fractures and joints in hard rock occur as conduits for rapid transport of water
as they do not provide large space for storage of ground water
The width of fractures & lineaments and weak planes narrows as depth
increases
Fairly limited aquifer water yield by wells and borewells in comparison to
alluvial and sedimentary rock aquifer wells
Unpredictable ground water occurrence over short distances
The principle ground water reservoir in hard rocks therefore consists of two
parts viz
“Vadose zone” or unsaturated zone that lie between ground surface and water
table; and
The phreatic or unconfined zone that lie below the water table
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 10
The deeper ground water below water table in zone of fractures lack substantial
storage unless it is connected with thick vadose zone above or else is connected to a
surface water source. Exclusively from the issue of ground water storage, the “vadose
zone” in hard rocks is extremely important, because the pore spaces in this domain
undergo resaturation during infiltration and recharge and undergo desaturation
under conditions of evaporation and drainage. The volume of saturation involved in
the process of change in saturation in vadose zone (zone of weathering) is far large
than the changes in volume of water involved in the elastic storage of water below the
water table. It therefore may be noted, that the dynamic resource in ground water
reservoir in the hard rock areas is governed by the “vadose zone” through which water
levels fluctuate. It is, therefore, imperative for any rechargeable scheme to have first
hand information obtained/required about the water saturation and permeability of
the vadose zone/weathering zone before undertaking execution of ground water
recharging works. This information is very much rare in its availability. It may also be
mentioned that available storage in weathered zone in hard rock is very much linked
to base flow fluctuations in local streams.
The aquifers in hard rocks are characterized by low permeability and low
specific yield. In hard rock the framework of fracture system in which groundwater
occurs is highly variable and aquifers are of heterogeneous nature.
The feature of the low permeability of Basalts, their multilayered occurrence,
fractured and jointed natures, vesicular character besides topographic and other
geological features are to be normally considered in the formulation and construction
of recharging schemes in Plateau forming basaltic rock terrain. Broad hydraulic
features for consideration with regard to water harvesting and ground water
recharging in Basaltic rock regions are given in table. The success of a recharge
scheme will depend on a combination of various topographic and hydrologic situations.
The following factors should receive consideration in the formulation of a water
harvesting & recharge scheme.
Table: Topographic - Hydrogeological framework
Hydrologic Considerations The weathered, fractured and vesicular
basalts constitute most favorable hydraulic
zones which need to be delineated on large
scale maps.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 11
Topography of Watershed area The piedmont slopes constitute the best
topographic geologic environment followed by
valley floors. Highly dissected slopes and
plateau tops are less favorable.
Hydraulic conductivity of
basaltic layers
The weathered, jointed and vesicular portions
of basaltic rocks have high permeability and
shall constitute favorable places in
comparison to massive basalts that are less
suitable for recharge and percolation.
Ground Water table and
fluctuation in levels
The position of water table & its value of
annual fluctuation
Thickness of Soil cover and
infiltration rates.
Granular soil cover will have high infiltration
rate in comparison to clay / black cotton soil
that would impede infiltration and deep
percolation.
Rate of Recharge In favorable zones, fractured and vesicular
basalts are expected to attain a recharge of
10 – 15% whereas in non-favorable zones,
underlain by massive basalts the rates may
be 2 to 3%.
Considering an annual average rainfall of 700 mm for the Pune region the total water
available for rainwater harvesting is calculated.
QUANTIFICATION:
(A) Total availability of water at the site
= Geographical area x Rainfall x Runoff Coefficient
= 8362 Sq.Mt. x 0.70 Mt. (700 mm) x 0.6
= 3,512.00 M3
We have considered runoff coefficient for calculating flow for rainwater design based
on Central Pollution Control Board Ministry of Environment & Forests data. They are
as under.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 12
Surface Type Runoff coefficient (Range)
Roof (Metal, gravel, asphalt, shingle,
fiber-glass, asbestos, concrete) 0.95 – 0.90
Pavement (Concrete, asphalt, Gravel,
Brick) 1.00 – 0.90
Ground Surface (Hard flat ground
without Vegetation) 0.75 – 0.25
Ground Surface (Hard flat ground
with Vegetation) 0.60 – 0.15
Lawns (Flat, Sandy soil)
(Flat , Heavy soil)
0.10 – 0.05
0.20 – 0.15
(B) Water that can be accommodated in the Aquifer.
Area of aquifer (Sq.Mt.) x Thickness of aquifer x specific yield of aquifer.
= 8362 Sq.Mt. x 25 Mt. x 0.03
= 6,271.5 M3
(C) Rainwater that can be harvested
= No. of Boreholes * depth of recharge bore hole * Area of recharge influence
= 2 x 15 x 150
= 4500 m3.
Considering an area of influence of 150 meters and depth of 10 meters for 2 boreholes
a total quantity of 4500 m3 water can be recharged in the ground, the quantity is
much less than the rain water available for harvesting. Hence the excess water either
can be accommodated in a farm pond or else should be discharged as runoff.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 13
Rainwater Harvesting structures:
Recharge Injection well:
Based on the resistivity surveys test performed two recharge injection wells are
suggested drilled through the center of the recharge pits (Fig.1). The surface run off is
not directly led into the injection well, to avoid chances of contamination of
groundwater. Instead rainwater is collected in a recharge pit which are generally 1 to
2 meters wide and two to three meters deep. After the excavation the pits are filled
with pebbles, boulders as well as coarse sand which act as filter.
The size of the filter material is generally taken as:
Coarse sand – 1.5 to 2 mm
Gravels – 5 to 10 mm
Boulders- 5 to 20 cm
The filter material should be filled in graded manner. Boulders at the bottom, gravels
in the middle and coarse sand at the top. The diameter of the well suggested is 500
mm while the depth of the tube well is fixed at 20 meters. Inside this tube well a
perforated casing of 200 mm should be inserted up to the depth where the upper loose
strata give way to the hard strata. The annular space between the tube well and the
slotted casing should be filled with gravel.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 14
Fig 1: The design of the recharge injection well Note : - Size of recharge pit will be minimum 1m x 1m x1m and maximum 3m x 3m x 1.5m depending upon the site condition.
CONCLUSION:
Based on the resistivity modeled values it can be seen that the area shows the
presence of shallow aquifer restricted to 15-20 meters depth at 2 & 3 VES locations.
The all VES shows continuous increase in the resistivity values beyond ~ 10 meters
indicating presence of massive hard rock. The site is suitable for rainwater harvesting.
It is to be noted that from the groundwater potential point of view the overall area can
be categorized as with very low potential.
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 15
APPENDIX I: MODELED ELECTRICAL RESISTIVITY DATA
VES- 1
VES -2
VES -3
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 16
VES – 4
HYDROGEOLOGICAL INVESTIGATION REPORT FOR
RUNWAL DEVELOPERS , PUNE
HydroGeological Report 8th September 2015 Page| 17
LOCATION PLAN
REV. DATE DESCRIPTION
DRG.NO.
CHD.BY
DRN.BY
DATE
SCALE
JOB NO. ARCHITECT:
INFRA. ELECT. HVAC PLMB. FIRE IBMS
SIGN
SUBHASH.K
24.03.17
NTS
RAJAT
CLIENT:
PROJECT:
TITLE:
R-0160
R-0160/PHE/04/000
RAJATR0 24.03.17FOR APPROVAL
PROCESS FLOW DIAGRAM RWP
RUNWAL GROUP.
RUNWAL MALL
ARCHITECTURAL ENERGY SOLUTION (P) LTD101 B-C, 1st Floor, PARK PLAZA, Near State Bank Colony,Karve Nagar, Karve Road, Pune 411 052.TEL: 020 -6500 5577 / 020-25478181.FAX: 020 -6500 5577. Email : [email protected] us at: www.aesindia.co
Ar. KULIN DHRUV AND ASSOCIATES
RAIN WATER HARVESTING TANK CALCULATIONS
SN DESCREPTION AREA
IN SQ.M
RAIN INTENSITY
CM/HR
RUNOFF COEFFICIENT
STORM WATER RUNOFF
(cubicM/sec)
STORM WATER RUNOFF (lit/sec)
STORM WATER RUNOFF (lit/min)
1 AREA
CONSIDERED FOR DESIGN
7858 7.5 0.9 0.1473375 147.3375 8840.25
RAIN WATER HARVESTING TANK FOR 16.40 MINUES HOLDING CAPACITY 144980.1
SAY 1,45,000 LIT
PROJECT
+98.80 M
T
O
E
X
I
T
T
O
M
A
I
N
R
O
A
D
STORM WATER
LINE
STORM WATER
LINE
STORM WATER
LINE
STORM WATER
LINE
STORM WATER
LINE
STORM WATER
LINE
STORM WATER
LINE
300MM WIDE
STORM CHANEL
300MM WIDE
STORM CHANEL
TO
RAINWATER
HARWESTING
WATER LINE CONNECTED TO
EXTERNAL MUNICIPAL STORM
WATER LINE (BY PUMPING)
+101.50 M
DROP
CHAMBER
ME
TE
R R
OO
M
LVL
+98.80 M
ENTRY TO B1 LVL
WATER LINE UP TO THE
GROUND LEVEL
ENTRY TO B1 LVL
CONNECT TO EXISTING
MUNICIPAL SEWER
CHAMBER BY PUMPING
16.4714.41 14.42
11.39
5
.
4
4
9.39
19.39
19.4
18.2
24.5
17.33
DRAINAGE ACCESS PIPE
DRAINAGE ACCESS PIPE
SEWER TRAP
CHAMBER
6
.
7
5
1
4
.
4
9
4
.
2
5
9
.
1
1
160 KLD STP
1000.003400.00
5000.00
3400.00
4600.00
2164.63
5.6
6.66
6.08
6.66
6.08
8.79
9.34
10.46
5
.
1
9
5.36
5.96
6.45
6.89
6.89
6.45
6.89
6.89
0.82
0.81
10.11
6.34
17.16
7.76
10.67
19.4
21.97
12.95
17.43 15.42 14.3418.67
8
.
1
2
1
9
.
3
6
1
9
.
5
6
1
3
.
7
1
4
.
1
4
0
.
9
8
5
.
4
8
2
1
.
8
6
1
2
.
4
7
10.81
11.04
7
.
6
9
8
.
3
1
1
0
.
7
9
1
0
.3
3
Calculation on sizing of solar water heating systems
Sr.No Description No Of
Rooms Person / Room Ltr / Person
Delta T
121 2 40 35
1 Number of person 242
2 Water requirement per Ltr 9680
3 Water requirement Ltr/Hr 1613
4 Energy requirement in Kcal 56467
5 Energy requirement in Kw/Hr 66
No of Solar Panel Required For Hot Water
Total Water Requirement 9680 Ltr/Day
Solar Hot water for rooms
20% solar hot water system has been proposed for the project which complies with ECBC. 0.25
Total Water Requirment after diversity 2420 Ltr/Day
Total no of solar panel required 19 Nos
Cost for 1 no soalr panel
12,000.00
TOTAL PROJECT COST FOR SOLAR PANEL
232,320.00 Nos
Solar lighting for common areas and landscaping
Sr.No FLOOR Common Load details
Parking + Passage + Lobby + Staircase
area
1 Lower Basement 10 KW
2 Upper Basement 10 KW
3 Ground 6 KW
4 First 6 KW
5 Second 3 KW
6 Service-I 2 KW
7 Third 2 KW
8 Fourth 2 KW
9 Fifth 2 KW
10 Sixth 2 KW
11 Seventh 2 KW
12 Eighth 2 KW
13 Nineth 2 KW
14 Terrace 2 KW
TOTAL 53
Sr.No
Description
1 Street Lights/Landscaping/Parking/Passage/Lobby/Staircase
73 KW
10 % ON SOLAR 7 KW
TOTAL 10% COMMON AREA LIGHTING LOAD ON PV PANEL(SOLAR) 7 KW
PV Panel Generation for 12 Hrs (KWH) 88
Required KW Generation 18 KW
Considering 0.85 efficiency 21 KW
1 no PV Panel generate 400 w electricity in 5 Hrs (Size- 2 m x 1 m) 52
Required no of PV Panels 52 Nos
Cost for 1 KW
85,000.00
TOTAL PROJECT COST FOR PV PANEL
1,752,000.00
SITE SPECIFIC INTEGRATED WASTE MANAGEMENT PLAN
FOR
M/S RUNWAL REGALIA, HADAPSAR, PUNE.
17-MARCH-17
SMART ENVIRO SYSTEMS (MANUFACTURER OF COMPOSTING MACHINES)
1
Table of Contents 1. Preliminaries .......................................................................... 2
1.1 Purpose of this document ................................................... 2
1.2 Objectives of Waste Management Plan ................................ 2
2. Operational overview of the Project ......................................... 3
2.1 Overview of Project ............................................................. 3
2.2 Solid waste…………………………………………………………….5
3. Solid Waste Management Plan ............................................. …7
3.1 Solid Waste Management Plan- .......................................... 8
5. Waste Minimisation Strategies .............................................. 10
2
1. Preliminaries
1.1 Purpose of this document
As a part of responsibility towards environment and commitment to provide
better livelihood for residents, the Commercial Project is obligated to develop a waste
management strategy and implement appropriate solutions for the cradle to grave
management of the waste streams that are generated during the construction and
operational phases of the project. The State Level Expert Appraisal Committee has
further recommended identification the opportunities to reduce the creation and
disposal of the waste generated hereby.
This waste management plan (WMP) is prepared to provide a working tool for the
environmental managers during construction and operation phase. This WMP is
therefore a key management tool that will contribute towards achieving sustainable
waste management throughout the operation of the project.
1.2 Objectives of Waste Management Plan
The objective of this WMP is:-
To formalize waste handling, transfer and disposal activities associated with
various types of wastes from the project;
To prevent inappropriate disposal of waste streams and associated risk of
pollution of the surrounding area;
To facilitate waste minimization through waste avoidance, reduction, reuse,
recycling or treatment before disposal;
To streamline waste segregation, storage, and disposal and promote resource
recovery from waste;
To define responsibility for waste management at the various levels of operation
associated with the project;
3
2. Operational overview of the Project
2.1 Overview of Project
2.1.1 Introduction:-
The proposed Ruwal Regalia is Commercial project of Runwal Erectors Pvt Ltd. This
site is located on the East site of the Pune city at S.no.153A/1 to 4/1/1, Hadapsar,
Taluka-Haveli, Dist.- Pune, Maharashtra and has co-ordinates Latitude 18°30'13.86"N
and longitude 73°55'30.20"E.The site can be categorized as a Commercial used, as per
land use pattern in the area.
General Location map of Ruwal Regalia is Commercial project of Runwal Erectors Pvt
Ltd Surrounding area
4
2.1.2 Project Statement:-
Below is the Floor wise development plan of whole project with Tenement Statement &
Population details.
OWC Users Area Total
population
1
Hotel rooms 119 363
Banquet 420 280
Restaurant 871 484
Shopping 4567 761
Office 581 58
Sports 2379 463
Grand Total 8,937 2,409
2.1.3 Floor wise Waste generation:-
Below is a Phase wise waste generation detail with Bio-degradable & Non Bio-
degradable of waste qty.
OWC Users Area Total
population Total waste
Total
wet waste
Total
dry waste
1
Hotel rooms 119 363 91 36 54
Banquet 420 280 70 42 28
Restaurant 871 484 121 73 48
Shopping 4567 761 190 76 114
Office 581 58 15 6 9
Sports 2379 463 116 46 69
Grand Total 8,937 2,409 602 279 323
5
2.2 Solid waste
In Commercial project, waste such as biodegradable, Non-biodegradable, Hazardous waste
and E-waste are generated. Following is the description for theses waste.
2.2.1 Bio-degradable waste
Bio-degradable waste will be generated from the Project from kitchen, houses,
landscape/garden and minor quantities from Common Area.
Kitchen waste (include food wastes, fruit and vegetable peelings, leftovers (including meat
and fish), egg and nutshells, coffee grounds, tea bag, etc.) is expected to be a major
component of the Project’s bio-degradable waste stream. Landscaping waste will include
predominately vegetation wastes (straw, leaves grass cuttings, flowers or trimmings from
bushes and hedges) These wastes are grouped into one waste stream, on the basis that
they can be subject to composting and may be managed collectively. This waste stream
specifically excludes kitchen cooking oil, grease and fat which is not suitable for
composting and needs to be handled in oil & grease trap before the waste water from
kitchen enters sewage treatment plant.
2.2.2 Non bio-degradable waste
Non bio-degradable waste refers to waste classified as non-hazardous and can be defined
as waste that does not pose an immediate threat to public health or the environment if
properly managed. The general waste stream generated at the household is expected to
consist of solid waste generated from daily operation activities wood, paper, cardboard
metal and plastic packaging, glass etc. It is an inert waste stream that can be sent for
recycling or needs to be sent for energy recovery or land filling. Various common activities
in the society such as conferences, functions, festivals, Minor celebrations (Birthday etc.)
may result in generation of non bio-degradable wastes.
2.2.1.3 Hazardous waste
Hazardous Waste is defined as waste that has the potential, even in low concentrations, to
have significant adverse effects on public health and the environment because of its
inherent toxicological, chemical and physical characteristics. Common potential
hazardous wastes that are expected to be generated at the project include:
Unwanted, expired or contaminated chemicals including cleaning agents and
detergents, disinfectants, oils, greases, solvents and solvent based paints, pool,
landscaping and pest control substances.
Office products including expired printer cartridges and photocopying fluids, and
waste electronic equipment;
Used cooking oils, fats and greases from the kitchen
2.2.1.4 E-waste
As per the E-waste (Management) Rules 2016, E-waste means electrical and electronic
equipment, whole or in part discarded as waste by the consumer or bulk consumer
as well as rejects from manufacturing, refurbishment and repair processes. Discarded
electronic or electrical equipment from the project along with batteries, lamps and tube
lights will contribute to the E-waste stream and need separate attention.
6
3. Solid Waste Management Plan Integrated Solid waste management plan includes Scheduled of collection, transportation,
segregation, storage and disposal of all type of waste. Following process flow will be
followed by housekeeping supervisor/ any equivalent person.
Stage 1. Collection
Stage 2. Transportation
Stage 3. Secondary Segregation
Stage 4. Disposal
Secondary sorting of waste
OWC Location
Collection of Primary Segregated
Waste at source
Transportation of Primary
segregated waste to OWC
location
Secondary segregated waste will
be transfer to respective disposal
Process
Dry waste,
Hazardous waste,
and E-waste will be
stored in storage
area room
Handover of stored
waste to
Authorized vendor
of respective waste.
Bio-degradable
waste
Processing Unit
(Smart OWC)
Generated Compost will be
utilized for gardening and
excessive compost can be given
to farmers for applying on Fields.
Collection Timing 8.00AM to 10.00AM
Transportation
Timing 10.00AM to 11.00AM
Segregation Timing
11.00AM to 12.00AM
Disposal Process
Timing 1.00PM to 5.00PM
OWC Processing Timing 1.00PM to 3.00PM
Storage Timing
3.00PM to 5.00PM
7
3.1 Solid Waste Management Plan
3.1.1 Collection & Transportation
During operation phase, at source, we will provide two separate bins for wet waste and dry
waste. Housekeeping people will collect primary segregated waste and send that waste to
primary collection area. After collection Housekeeping people will Transfer the primary
segregated waste from primary collection area to OWC location by using convenient
transportation medium. OWC location is not too far from primary collection area of each
apartment.
3.1.2 Secondary Segregation
For further processing of waste, there is need of secondary segregation of primary
segregated waste. Secondary segregation will take place in the OWC location. After the
secondary segregation we will get following categories of segregated waste
1. Biodegradable waste
2. Non-Biodegradable waste
3. Hazardous waste
4. E-waste
3.1.3 Disposal
After secondary segregation process, we will obtain categorized waste such as
Biodegradable waste, Non-Biodegradable waste, hazardous waste and E-waste. As per the
type of waste, different disposal method will be followed as follows:
3.1.3.1 Biodegradable waste
Bio-degradable waste will be treated in Organic Waste Converter. The Housekeeping
supervisor will have the ultimate responsibility to ensure collection, segregation and
efficient running of OWC. Details of Organic waste converter are attached herewith
(Annexure-1)
3.1.3.2 Non-Biodegradable waste
After Secondary Segregation Non-Biodegradable waste once collected from the source, will
picked-up by the authorized vendor for further disposal and recyclable material will be
sold to recyclers. Also Permission and agreement copy/NOC from the authorized vendor
along with their authorization is attached herewith (Annexure-2)
3.1.3.3 Hazardous waste
Hazardous waste is to be handled, stored and disposed of / recovered in a manner that
does not result in environmental pollution or health and safety hazards to personnel. Only
authorized service providers will be used for the management of hazardous waste. This
entails ensuring that all transportation and disposal held by the service provider.
3.1.3.4 E-waste
Similar to hazardous waste quantity of e-waste expected to be generated from the project
is negligible. However agreement is made with an authorized E-waste collection agency for
periodic collection of e-waste from the project. Renewal of agreement, inspection of
disposal of e-waste is a responsibility of Housekeeping supervisor.
8
5. Waste Minimization Strategies
In accordance with international trends, the management of all waste streams that
will be generated at the project should demonstrate support for the Hierarchy of Waste
Management (HWM), which is the basic principle of this WMP. The HWM aims to
promote the re-use and recycling of wastes, giving effect to the concept of ‘cradle-to-
cradle’ waste management.
The HWM can be viewed as a straightforward set of management plans for waste. The
hierarchy sets forth several waste management strategies or options according to
importance and preference in a descending order. The aim is to extract the maximum
practical benefits from the products and manage waste in the best possible manner,
so that the minimum amount of waste is generated. Options of the hierarchy are listed
as follows:
Figure 1: Waste Management Hierarchy
Prevention is the best and most preferred strategy or option, and therefore ranks
first. It is the most cost effective, as no waste means no cost is involved in its
management.
Minimisation the generation of waste is the first option that should be considered,
refers to the prevention of wastes from arising and optimising material usage. This
approach promotes the efficient use of resources and minimises the volume of waste
material that must be handled by employees and hauled away from the project’s
property. Responsibility for the minimisation of waste generation generally lies with
management, who decides what is brought into the property and, thereby, determines
what eventually leaves the property as waste.
9
Reuse refers to the process of using existing material instead of disposing this
material to landfill. Whenever possible, the Safari project should reuse items in their
original form for the same or a different purpose rather than discarding them. If an
item cannot be reused on site, the project operator should investigate the possibility of
selling it or donating it to employees, charitable organizations, schools, businesses or
other interested parties.
Recycling is considered when reuse can no longer be carried out. Recycling refers to
the collection of the recyclable waste streams that can be reused on site. The
important step to ensure effective recycling practices is onsite waste segregation. This
is the least favorable of the three waste management options and should be
considered only if the reduce and reuse options are not applicable to specific waste
streams. Encourages the separation at source of recyclable material from the general
waste stream (waste separation at source is proposed, as the quality of recyclable
materials is higher when separated there and not when mixed with other waste). It is
also the waste management option that is most difficult to implement.
Energy Recovery can be a viable option after reduction; reuse and recycling have
been fully explored and generally is the final step in the exploitation of maximum
benefits from waste. It can for example involve the incineration of waste (under strictly
controlled conditions and licensing) and the recovery of the latent heat energy of the
materials. The heat energy can then be converted into power to be used commercially
or domestically.
Disposal is the last and least preferred options in the hierarchy. There is always some
residual material left over as waste. This is the case even after undergoing the
preferred options in the solid waste management hierarchy. The left over waste
occasionally requires treatment prior to disposal to safe guard against environmental
risks, pest problems, social, health, and safety issues.
10
Annexure-1
Smart Organic Waste Composters
Details
11
Annexure-2
Dry Waste Noc of
Authorized Vendor
12
smart enviro systems
Corporate Office: 10, Kothrud Indus. Estate, Kothrud, Pune- 411 038 (M.S.) Tel : 91-020-2543 3054, 2543 4328 Fax : 2546 9440 URL: www.smartenvirosystems.com Email: [email protected]
SMARTENVIROSYSTEMSWasteCalculationSheet
Residential&CommercialProjectRunwalErectorsPvt.Ltd."RunwalRegalia"HadapsarPune
OWC Users TOTAL
POPULATION TOTAL WASTE
TOTAL WET WASTE
TOTAL DRY WASTE
OWC AREA Models
CAPITAL COST
O & M COST
Elc Load
1
Hostel Room 363 91 36 54
51 sq. M SM-25 + CD-500 14,75,000 2,93,531 7 HP
Banquet 280 70 42 28
Restaurant 484 121 73 48
Shopping 761 190 76 114
Office 58 15 6 9
Sports 463 116 46 69
Grand Total 2409 602 279 323 14,75,000 2,93,531 7 HP
Sm
art D
rum
Co
mp
oster
- 50
0 -
SM25
Segregation Area
Dry
Waste , W
et Waste
& E
-Waste
Sto
rage A
rea
2.00
1.0
0
1.00
17.1
7
6.0
4
11.0
8
4.00
1.0
01
.50
7.0
01
.40
4.5
01
.60
2.00
17
.00
2.61
SM
AR
T E
NV
IRO
SY
ST
EM
S10
, KO
TH
RU
D IN
DU
ST
RIA
L E
ST
AT
E,P
UN
E3
8.
AL
L D
IME
NS
TIO
NS
AR
E IN
mU
NL
ES
S O
TH
ER
WIS
E S
TA
TE
DD
O N
OT
SC
AL
E T
HE
DR
AW
ING
IF IN
DO
UB
T A
SK
.
TIT
LE
:-
SM
- 25
& C
D - 5
00
DE
SIG
NE
D
BY
:-
CH
EC
KE
D
BY
:-
AP
PR
OV
BY
:-
SC
AL
E:-1
:1Q
TY
:- 1P
AR
T N
O:-
MA
TE
RIA
L:-
MO
DE
L:-
SU
B T
ITL
E:-
SIG
N &
DA
TE
NA
ME
S S
YT
RE
AT
ME
NT
:-
SH
EE
T 1
OF
1D
V K
09
-02
-17
S S
Y
09
-02
-17
09
-02
-17
Ru
nw
al Erecto
rs Pv
t. Ltd
. " Ru
nw
al Go
ld" P
roject A
t Had
apsar, p
un
e
OW
C A
rea Lay
ou
t ( Op
tion
- 1 ) W
ith D
imen
sion
s
smart enviro systems
Corporate Office: 10, Kothrud Indus. Estate, Kothrud, Pune- 411 038 (M.S.)
Tel : 91-020-2543 3054, 2543 4328 Fax : 2546 9440 URL: www.smartenvirosystems.com Email: [email protected]
SMART ENVIRO SYSTEMS
Operation & Maintenance Cost
Organic waste kgs/day - 279
Composter with Curing drum
Sr.No. Description Value
1 SMART Machine - 1 no SMART-25
2 Curing drum - 1 no CD-500
3 Capacity in kgs/hr organic waste 100
4 Total Waste generation kgs/day 279
5 Hrs of operations/day 3
6 Curing drum hrs./day 2
1 Fixed Costs
1.1 No of persons per day 2
1.2 Labour cost @ Rs. 6000/- month 12000
1.3 Maintenance cost @0.5% 7375
Total Fixed Cost 19375
2 Variable Costs
2.1 Energy requirement in KWH/D 12
2.2 Energy Bill @ Rs. 6.0/ kwh 2075
2.3 Culture 500
2.4 Saw dust 2511
2.5 Total Variable cost 5086
Total Operating cost per month 24461
3 Operating Costs per Year
3.1 Total Fixed Cost 232500
3.2 Total Variable cost 61031
Total Cost 293531
ECBC Compliance Report
For
Runwal Developers
Prepared By
SPROUT Date
20.03.2017
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 2 of 11
PROJECT DETAILS
‘Runwal Regalia’ is a commercial project, developed by Runwal Developers and is located at Hadapsar,
Pune.
The project has a connected load more than 500 Kw that meets the ECBC code. The projects meets the
ECBC requiremments through prescriptive method.
Brief Description about the Project:
Name of the Project Runwal Regalia
Category ECBC 2007
Site Area 7854.13
Built-up Area 36925.20
No of Buildings 1
No of Floors G + 10
No of Parking Levels 2
Occupancy 2409
The project falls under warm and humid climate and the building complies the requirements as per the
climatic zone.
BUILDING TYPOLOGY – MIXED USED COMMERCIAL
Showrooms – 8 nos.
Shops – 37 nos.
Offices – 10 nos.
Hotel – 121 nos.
Sports club
COMPLIANCE DOCUMENTS
Plans and specifications shall show all pertinent data and features of the building, equipment and systems
in sufficient details to permit the Authority Having Jurisdiction to verify that the building complies with the
requirements of this code.
1. Building Envelope:
2. HVAC:
3. Service hot water and pumping:
4. Lighting:
5. Electrical power:
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 3 of 11
MASTER PLAN:
VIEW
SPORTS CLUB
SHOPS/ SHOWROMS
RESTAURANT
HOTEL ROOMS
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 4 of 11
COMPLIANCE REPORT
1. BUILDING ENVELOPE
*DETAILS ATTACHED IN APPENDIX ‘A’
Parameter Proposed Case ECBC Prescriptive Compliance
External
Walls
Exterior Wall Construction- AAC Bricks
(150mm Thick), Internal
Plaster(20mm),External Plaster(25mm),
25mm external insulation
U-Value (w/m2-k) - 0.39
R- Value (m2K/W) – 2.56
U-Value (W/m2-k) - 0.44 max. (as per ISO-15099)
Roof
Roof Section-The roof section is 150mm thick
RCC slab with minimum 100mm brick bat
coba + 12.5mm thick chemical waterproofing
with slope in screed to drain and finished
with reflective paint + 40mm insulation
U-Value (W/m2-k) – 0.23
R-Value (m2-k/w) – 4.37
U-Value (W/m2-k) - 0.261 max.
Floor
Same as Base case
R-Value (m2-k/w) - 0.504
U-Value (W/m2-k) - 1.98
Glazing
The propject is proposed to use double
glazed unit.
Saint Gobain Double glazed Nano Icy Menthol
U-Value - 1.8 W/m2-K
SHGC - 0.31
Glass U-Value - 3.3 W/m²-K
SHGC - 0.25
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 5 of 11
2. Heating, Ventilation and Air Conditioning
Parameter Proposed Case ECBC Standard Case
Natural
Ventilation The entire building is mechanically ventilated
The entire building is mechanically
ventilated
Chillers
The project proposes a water cooled screw
chiller with VFD and having capacity of (>150
and < 300 tons)
COP – 5.50
IPLV – 0.65
Test Standard - ARI 550/590- 1998
Centrifugal Water cooled chiller (>150 and
< 300 tons)
COP – 5.80
IPLV – 5.05
Test Standard - ARI 550/590- 1998
Controls Cooling systems shall be controlled by a set
point temperature.
Cooling and heating systems shall be
controlled by a timeclock
Piping and
Ductwork
The project shall comply with the ECBC
insulation value R-0.35 (R-2).
Piping for cooling systems with a design
operating temperature less than 15°C
Refrigerant suction piping on split systems -
R-0.35 (R-2) insulation
Air System
Balancing
The fans above 1 HP will be with the VF
drives and shall comply as per ECBC code Fan system power greater than 0.75 kw
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 6 of 11
3. SERVICE HOT WATER AND PUMPING
Parameter Proposed Case ECBC Standard Case
Solar Water
Heating
20% solar hot water system has been
proposed for the project which complies with
ECBC code.
Centralized system shall have solar water
heating for at least 1/5 of the design
capacity.
Performance/ minimum efficiency level
mentioned in IS 13129 Part (1&2)
Electric
Water
Heater
The project shall comply as per ECBC code Performance/ minimum efficiency level
mentioned in IS 2082
Swimming
Pools
Since heated pools are not provided, this is
not applicable
Since heated pools are not provided, this is
not applicable
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 7 of 11
4. LIGHTING
Parameter Proposed Case ECBC Standard Case
Automatic
Lighting
Shutoff
Shall comply as per ECBC standards
Automatic control device for buildings
larger than 500 m² (5000 sqft)
Occupancy sensors for offices, meeting
rooms with areas less than 30 m² (300 sqft)
Program schedule shall be provided for
areas of no more than 2,500 m² (25,000
sqft)
Space
Control Shall comply as per ECBC standards
Control a maximum of 250 m² (2,500 ft²) for
a space less than or equal to 1,000 m²
(10,000 ft²)
Maximum of 1,000 m² (10,000 ft²) for a
space greater than 1,000 m² (10,000 ft²).
Control in
daylighted
areas
Shall comply as per ECBC standards
Luminaires in daylighted areas greater than
25 m² (250 ft²) - equipped with either a
manual or automatic control device
Exterior
Lighting
Control
Shall comply as per ECBC standards
Display/Accent Lighting greater than 300 m²
- separate control device
Case Lighting greater than 300 m² -
separate control device
Interior
Lighting
Power
LED Lights used
LPD calculations for each space by Building
Space Method
Building Space Method
(Ref ASHRAE 90.1.2007)
Office Area: 10.8 W/m²
Meeting room: 14 W/m²
Dining: 17.2 W/m²
Hotel: 10.8 W/m²
Bar: 14 W/m²
Gymnasium: 11.8 W/m²
Exterior
Lighting
Power
Shall comply as per ECBC standards
Building entrance (with canopy) - 13 W/m²
of canopied area
Building exit - 60 W/lin m of door width
Building facades - 2 W/m² of vertical facade
area
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 8 of 11
5. EXTERIOR LIGHTING
Parameter Proposed Case ECBC Standard Case
Transformers
*1 no 250 KVA Transformer for
entertainment area (2nd floor) - Maximum
allowable losses for oil filled distribution
transformers with highest voltage for
equipment 25 kV, at 50% with 1 KW and
100% with 3.3 KW of the load as per IS2026.
*1 no 630 KVA Transformer for Shop/Office
area (ground + 1st floor) - Maximum
allowable losses for oil filled distribution
transformers with highest voltage for
equipment 25 kV, at 50% with 2 KW and
100% with 6.6 KW of the load as per IS2026.
*2 no 630 KVA Transformer for Hotel area
(from 3rd to 9th floor) - Maximum allowable
losses for oil filled distribution transformers
with highest voltage for equipment 25 kV, at
50% with 2 KW and 100% with 6.6 KW of the
load.
Maximum allowable losses for Dry type
distribution transformers with highest
voltage for equipment 24kV, at 50% and
100% of the load.
Maximum allowable losses for oil filled
distribution transformers with highest
voltage for equipment 36 kV, at 50% and
100% of the load
Energy
Efficient
Motors
*All motors will comply with the EFF-1
standards. All motors efficiency should be
above 80%.
As per electrical load, total motor load =556
HP=415 KW=Diversity 0.67=278 KW
(Operating KW).As per calculation, we have
not crossed the operating load above the
200%.
All permanently wired polyphase motors :
• 0.375 kW or more serving the
building - operate more than 1,500
hours per year
• 50kW or more serving the building
– operate more than 500 hours per
year
Motor horsepower ratings shall not exceed
200% of the calculated maximum load
Power factor
correction
We will provide APFC panel with detuned
Harmonic filter to maintain PF between 0.95
lag to unity.
Electricity supplies exceeding 100 a, 3
phase shall maintain their power factor
between 0.95 lag and unity at the point of
connection
Power
distribution
systems
Our main distribution panel + meter panel
near to main load center (transformer) to
reduce distance of distribution cables and
using XLPE types of cables to reduce losses.
The power cabling shall be adequately sized
as to maintain the distribution losses not to
exceed 1% of the total power usage
Project Logo Runwal Regalia, Pune
APPENDIX ‘A’:
1 Wall section - AAC block wall both side plaster
1.1 Thermal Resistance
1.1.a External air film
1.1.b Intenal air film
1.2 Thermal conductivities (R -
R-value=thickness of the material in meters / thermal conductivity (k) W/mK
1.2.a 20 mm thick external cement plaster
1.2.b 150 mm thick AAC blocks
1.2.c 12mm thick Internal gypsum plaster
1.2.d 25mm insulation
1.3 Total Thermal
Conductivities
Total R value of the section
1.4 U-value of the wall
section
Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
AAC block wall both side plaster
Rso 0.044
Rsi 0.12
value)
value=thickness of the material in meters / thermal conductivity (k) W/mK
20 mm thick external cement plaster 0.02
0.9
0.02
0.15
0.16
0.94
12mm thick Internal gypsum plaster 0.012
0.5
0.024
0.024
1.41
2.56
(1/R value)
0.39
ECBC 2007
COMPLIANCE REPORT
Page 9 of 11
m2K/W
m2K/W
m
W/mK
m2K/W
m
W/mK
m2K/W
m
W/mK
m2K/W
m
W/mK
m2K/W
m2K/W
W/m2K
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 10 of 11
2 Roof section
2.1 Thermal Resistance
2.1.a External air film Rso 0.44 m2K/W
2.1.b Intenal air film Rsi 0.16 m2K/W
2.2 For Roof without Artificial Turf
Thermal conductivities (R - value)
R-value = thickness of the material in meters / thermal conductivity (k) W/mK
2.2.a 100 mm thick Brick Bat Coba & Screeding 0.1 m
0.72 W/mK
0.14 m2K/W
2.2.b 12.5 mm thick Chemical Waterproofing layer 0.0125 m
0.72 W/mK
0.02 m
2K/W
2.2.c 150 mm thick Slab 0.15 m
0.1 W/mK
1.50 m2K/W
2.2.d 40 mm insulation 0.04 m
W/mK
2.11 m2K/W
2.2.e Total Thermal Conductivities
Total R value of the section 4.37 m2K/W
2.2.f U-value of the roof section
(without Artificial Turf)
(1/R value)
0.23 W/m2K
Project Logo Runwal Regalia, Pune ECBC 2007
COMPLIANCE REPORT
Page 11 of 11
3 WWR
Floor WWR
Upper Ground floor 48.62
First floor 46.50
Second floor 34.03
Third floor 17.86
Fourth floor 30.60
Fifth-Seventh floor 30.64
Eighth floor 30.63
Ninth floor 19.27
Average = 32.27