annex iii technical specifications 105 c1
TRANSCRIPT
-
7/27/2019 Annex III Technical Specifications 105 C1
1/254
SRI LANKA OPERATIONS CENTRE
AnnexIII Technical Specification
SSppeecciiaallPPrroovviissiioonnssttooSSttaannddaarrddSSppeecciiffiiccaattiioonnss
FFoorr
IICCTTAADDCCoonnssttrruuccttiioonnaannddMMaaiinntteennaanncceeooffRRooaaddss
aa
nn
dd
BB
rr
iidd
gg
ee
ss
-
7/27/2019 Annex III Technical Specifications 105 C1
2/254
SRI LANKA OPERATIONS CENTRE
PREAMBLETOICTAD
STANDARDSPECIFICATIONSFORCONSTRUCTIONANDMAINTENANCEOFROAD
ANDBRIDGES
The works shall be carried out in conformity with the ICTAD standard specifications for
constructionandmaintenanceofRoadsandBridgesICTADPublicationnoSCA/5,1989issued
under the Authority of the General manager, Road Development Authority, Ministry of
highways,SriLanka.
References to the Specification in the Contract Documents mean the Sri LankanICTAD
Construction Specification. The Sri LankanICTAD Construction Specification is hereby
incorporatedintotheContractasaContractDocumentandtheContractorwillbedeemedto
havefullknowledgeofthisSpecification.
Copiesof
the
Sri
Lankan
ICTAD
Construction
Specification
are
available
at
the
above
address
onpaymentoftherelevantfee.IntheeventofanyconflictintheSpecificationthefollowing
precedenceshallbeapply:
1. Part A: General Technical Specifications: ICTADStandard Specifications for
ConstructionandMaintenanceofRoads&Bridges
2. Part B: Particular Technical Specifications: Special Provision to Standard
Specification
-
7/27/2019 Annex III Technical Specifications 105 C1
3/254
SRI LANKA OPERATIONS CENTRE
SERIES100 GENERAL
CONTENTS
101. ABBREVIATIONS..................................................................................................................7
102. DEFINITIONS .......................................................................................................................7
103. ARRANGEMENTSFORTRAFFICDURINGCONSTRUCTION...................................................11
103.1. GENERAL .............................................................................................................................11
103.2. USINGPARTOFTHEROAD ......................................................................................................13
103.3. TEMPORARYDIVERSION..........................................................................................................13
103.4. TRAFFICSAFETYANDCONTROL ................................................................................................13
104. CONTROLOFWORKS ........................................................................................................14
104.1.
AUTHORITYOFTHEENGINEER..................................................................................................14104.2. CONFORMITYWITHPLANSANDSPECIFICATIONS..........................................................................15
104.3. STANDARDS ..........................................................................................................................15
104.4. HEALTHANDSAFETY ..............................................................................................................15
104.5. PROTECTIONOFPUBLICSERVICEFACILITIES ................................................................................16
104.6. SAFETYRELATINGTOTEMPORARYSTRUCTURES...........................................................................16
104.7. SAFETYRELATINGTONAVIGABLEWATERWAYS ...........................................................................16
104.8. ENVIRONMENTAL REQUIREMENT..............................................................................................17
EmissionstandardvaluesforMotorVehicleExhaust....................................................................18 EmissionstandardvaluesforBlackSmokeEmissionfromboat/ship/vessel.................................18
104.9. CONSTRUCTIONPROGRAMMING ..............................................................................................21
104.10. PROGRESSMEETINGS.............................................................................................................22
104.11.
RETURNSANDREPORTS ..........................................................................................................22104.12. TELECOMMUNICATIONS..........................................................................................................23
104.13. COMPACTIONGENERAL .......................................................................................................23
104.14. MIXING&CONTROLOFMOISTURECONTENTBEFORECOMPACTION ..............................................24
104.15. COMPACTIONEQUIPMENT ......................................................................................................24
104.16. WATERANDPOWERSUPPLYARRANGEMENTS ............................................................................24
104.17. DRAINAGEDURINGCONSTRUCTION...........................................................................................25
104.18. PREVENTIONOFDAMAGESTOEMBANKMENTS,SUBGRADELAYERS,PAVEMENTLAYERSANDSHOULDERS
INPOSITION...........................................................................................................................................25
104.19. COMPACTIONTRIALS..............................................................................................................25
104.20. COMPACTIONCONTROL..........................................................................................................25
104.21. DISPERSALOFHAULINGEQUIPMENT .........................................................................................26
104.22.
PROTECTIONTONEWLYCONSTRUCTEDLAYERS ...........................................................................26104.23. BRIDGECONSTRUCTIONSEQUENCE ...........................................................................................26
104.24. MATERIALSTESTINGBYINDEPENDENTLABORATORIES ..................................................................27
104.25. SPECIALANDADDITIONALTESTING ...........................................................................................27
104.26. STAFFFORMATERIALSTESTING................................................................................................27
104.27. CODESANDSTANDARDS .........................................................................................................27
104.28. TESTRESULTSANDRECORDS ...................................................................................................27
104.29. MEASUREMENTANDPAYMENT ................................................................................................27
105. CONTROLOFMATERIALS ..................................................................................................28
105.1. SOURCESOFSUPPLYANDQUALITYREQUIREMENTS......................................................................28
105.2. STORAGEOFMATERIALS.........................................................................................................28
105.3.
HANDLING
OF
MATERIALS.......................................................................................................28
105.4. APPROVALOFSOURCESOFMATERIAL(ADDTHEFOLLOWING) .......................................................29105.5. STOCKPILINGOFMATERIALS(ADDTHEFOLLOWING) .................................................................... 29
-
7/27/2019 Annex III Technical Specifications 105 C1
4/254
SRI LANKA OPERATIONS CENTRE
105.6. TEMPORARYSTOCKPILINGOFMATERIALS(ADDTHEFOLLOWING)...................................................29
105.7. CONTROLTESTSONMATERIALDURINGCONSTRUCTION(ADDTHEFOLLOWING) ...............................29
105.8. MATERIALTESTING(ADDTHEFOLLOWING) ................................................................................31
105.9. APPLICABILITYOFGENERALSPECIFICATIONS(ADDTHEFOLLOWING)................................................31
105.10. PAYMENT(ADDTHEFOLLOWING).............................................................................................31
106.
GENERALRULESFORMEASUREMENTANDPAYMENT .......................................................31
106.1. OVERHAUL ...........................................................................................................................33
106.2 MEASUREMENTOFPAVEMENTFORAREAANDVOLUMEBASEDPAYMENT........................................33
a. AreaBasis..............................................................................................................................33 b. VolumeBasis.........................................................................................................................33
106.3 SCOPEOFRATESFORDIFFERENTITEMSOFWORK .......................................................................33
106.4 FACILITIESFORVERIFICATIONOFMEASUREMENTS .......................................................................33
106.5 SELECTIONOFPAYITEMS ........................................................................................................33
106.6 SUBDIVISIONSWITHINPAYITEMS ...........................................................................................33
106.7 SUBSTANTIALCOMPLETIONOFTHEWORKS(ADDTHEFOLLOWING) ................................................ 33
107. SIEVEDESIGNATIONS ........................................................................................................34
108. CONTRACTORSESTABLISHMENTONSITE .........................................................................34
108.1. OFFICE,EQUIPMENTTESTINGFACILITIESETC. .............................................................................34
108.2. LEGALRELATIONSANDRESPONSIBILITYTOTHEPUBLIC..................................................................34
108.3. MEASUREMENT.....................................................................................................................34
108.4. PAYMENT.............................................................................................................................35
109. INFORMATIONFURNISHEDBYTHEEMPLOYER..................................................................36
110. WORKMANSHIPANDQUALITYCONTROL..........................................................................36
111. SELECTIONOFLABOUR .....................................................................................................37
112. WORKEXECUTEDBYTHEEMPLOYEROROTHERCONTRACTORS........................................37
113. PROTECTIONOFPUBLICSERVICEFACILITIES......................................................................38
113.1. EXISTINGSERVICES.................................................................................................................38
113.2. PAYMENT.............................................................................................................................38
114. MAINTENANCEOFEXISTINGROADS..................................................................................39
114.1. GENERALOBLIGATIONS ..........................................................................................................39
114.2. PAYMENT.............................................................................................................................39
115. PROTECTIONOFTHEWORKSANDREQUIREMENTSTOBEMETBEFORECONSTRUCTIONOF
NEWWORK
ON
TOP
OF
COMPLETED
WORK
IS
COMMENCED ........................................................39
115.1. PAYMENT.............................................................................................................................40
116. REMEDIALWORK..............................................................................................................41
116.1. EARTHWORKS .......................................................................................................................41
116.2. LOCALDEFECTSINPAVEMENTLAYERS .......................................................................................41
116.3. CONCRETE............................................................................................................................42
116.4. PAYMENT.............................................................................................................................42
117. WATERSUPPLYARRANGEMENTS......................................................................................42
117.1. PAYMENT.............................................................................................................................42
118.
ELECTRCITY
SUPPLY...........................................................................................................42
118.1. PAYMENT.............................................................................................................................42
-
7/27/2019 Annex III Technical Specifications 105 C1
5/254
SRI LANKA OPERATIONS CENTRE
119. PAYMENTS&TOLERENCES................................................................................................42
119.1. PAYMENT.............................................................................................................................43
120. PHOTOGRAPHICRECORDS ................................................................................................43
120.1. PAYMENT.............................................................................................................................43
121. ACCESSTOSITE .................................................................................................................43
121.1. PAYMENT.............................................................................................................................44
122. COOPERATIONATSITE.....................................................................................................44
122.1. PAYMENT.............................................................................................................................44
123. ROADSANDSITETOBEKEPTCLEAN..................................................................................44
123.1. PAYMENT.............................................................................................................................44
124. SECURITYOFTHEWORKS..................................................................................................44
124.1. PAYMENT.............................................................................................................................45
125. SUPPRESSIONOFNOICE....................................................................................................45
125.1. PAYMENT.............................................................................................................................45
126. SAFETY..............................................................................................................................45
126.1. PAYMENT.............................................................................................................................46
127. METHODOFWORKING .....................................................................................................46
127.1. PAYMENT.............................................................................................................................46
128. TEMPORARYWORKS.........................................................................................................46
128.1. PAYMENT.............................................................................................................................46
129.
SETTINGOUTANDCROSSSECTIONSURVEYANDDRAWINGS ............................................47
129.1. GENERAL .............................................................................................................................47
129.2. SETTINGOUTANDCROSSSECTIONS..........................................................................................47
129.3. MEASUREMENT&PAYMENT ...................................................................................................48
129.4. PAYMENT.............................................................................................................................48
130. FACILITIESFORTHEENGINEERANDHISSTAFF...................................................................48
130.1 DESCRIPTION ........................................................................................................................48
130.2 LANDFORFACILITIES ..............................................................................................................49
130.3 SOLEUSEOFFACILITIES ..........................................................................................................50
130.4 SERVICES..............................................................................................................................50
130.5
RENTEDPREMISES .................................................................................................................50130.6 OFFICESANDFURNISHINGS .....................................................................................................50
130.7 ACCOMMODATION FORTHEENGINEER ......................................................................................52
130.8 ENGINEERSLABORATORYANDEQUIPMENT................................................................................54
A) MATERIALSTESTINGBYINDEPENDENTLABORATORIES ..................................................................54
B) SPECIALANDADDITIONALTESTING ...........................................................................................54
C) STAFFFORMATERIALSTESTING................................................................................................54
130(15) SPECIALANDADDITIONALTESTING PROVISIONALSUM .................................................................55
130(16) STAFFFORMATERIALSTESTING PERSONMONTH.......................................................................55
130.9 STATIONERYFORTHEENGINEER ...............................................................................................55
130.10 PROVISIONOFHOTELACCOMMODATIONFORTHEENGINEERANDHISSTAFF ....................................56
130.11 SURVEYEQUIPMENT ..............................................................................................................57
130.12
MAINTENANCEOFENGINEERSFACILITIES ..................................................................................58130.13 CLERICALANDTECHNICALSTAFF...............................................................................................59
-
7/27/2019 Annex III Technical Specifications 105 C1
6/254
SRI LANKA OPERATIONS CENTRE
130.14 VEHICLESFORTHEENGINEER, ..................................................................................................60
131. PROJECTSIGNBOARDS .....................................................................................................61
131.1 DESCRIPTION ........................................................................................................................61
131.2 MEASUREMENT.....................................................................................................................61
131.3
PAYMENT.............................................................................................................................62
132. PROVISIONOFINSURANCES,BONDSANDSECURITIES.......................................................62
132.1 DESCRIPTION ........................................................................................................................62
132.2 MEASUREMENTANDPAYMENT ................................................................................................62
133. MARBLESTONEFORFOUNDATIONLAYING.......................................................................62
133.1 DESCRIPTION ........................................................................................................................62
133.2 MEASUREMENT.....................................................................................................................62
133.3 PAYMENT.............................................................................................................................63
133 MARBLESTONEFORFOUNDATIONLAYING.......................................................................59
133.1
DESCRIPTION ........................................................................................................................59133.2 PAYMENT..........................................................................................................................59
-
7/27/2019 Annex III Technical Specifications 105 C1
7/254
SRI LANKA OPERATIONS CENTRE
SERIES100 GENERAL
101. ABBREVIATIONS
Addthefollowing:
m metre
km kilometre
Sq.m squaremetre
Cu.m cubicmetre
cm centimetre
mm millimetre
gm. gram
kg kilogram
N Newton
kN kilonewton
HFL HighFloodLevel
LWL LowWaterLevel
WMM WetMixMacadam
102. DEFINITIONS
Addthefollowing:
AggregateHardmineralelementsofconstructionmaterialmixtures,forexample:
sand,gravel(crushedoruncrushed)orcrushedrock
AsphaltConcreteAmixturetopredeterminedproportionsofaggregate,fillerand
bituminous binder material plant mix and usually placed by means of a paving
machine.
AsphaltSurfacing Thelayerorlayersofasphaltconcreteconstructedontopofthe
roadbase.
BackFill Excavatedmaterial,whichisplacedandcompactedintrenchesandaround
foundations.
BatterBoard
A
board
of
wood
fixed
to
posts
at
the
top
of
cuttings
or
the
bottom
of
embankmentswhichindicatestheslopeatwhichthecuttingorembankmentistobe
constructed.
Bitumen Aclassofblackordarkcoloured(solid,semisolid,orviscous)cementitious
substances,naturalormanufactured,composedprincipallyofhighmolecularweight
hydrocarbons,ofwhichasphalts,tars,pitches,andasphaltitesaretypical.
Borrow Area/Borrow Pit An area, within designated boundaries, outside the
PermanentWorks,approvedforthepurposeofobtainingfillorpavementmaterials.
Aborrowpitistheexcavatedpitinaborrowarea.
-
7/27/2019 Annex III Technical Specifications 105 C1
8/254
SRI LANKA OPERATIONS CENTRE
Borrow Material Borrow material is a general term used to describe material
obtainedfromaborrowpit.
Boulder A rock fragment, usually rounded by weathering or abrasion, with an
averagedimensionof300mmormore.
Capping Layer A layer of selected fill material placed on the top of the topmost
embankmentlayerorthebottomofexcavation.
Chippings Chippingsaresinglesizedparticlesofcrushedrock,crushedbouldersor
crushedgravelusedforsurfacedressing.
CoarseAggregate Courseaggregateismaterialretainedonthe4.75mmsieve.
ComplianceTesting Testingofthecompletedworkstoascertaincomplianceofthe
requirementsoftheSpecification.
Cut Cutshallmeanallexcavatedmaterialfromtheroadprismincludingsidedrains.
Cutting Thatportionof the roadprism fromwherematerial isexcavated tosub
gradeorroadbedlevel.
Earthworks The excavation of material from cuttings and/or the construction of
embankments.
Embankment Thatportionof the roadprismcomposedofapproved fillmaterial,
whichliesabovetheoriginalgroundandisboundedbythesideslopes,describedin
the
Contract,extending
downwards
and
outwards
from
the
outer
shoulder
break
pointsandonwhichthepavementisconstructed.
FalseworkTemporarystaging&workingplatforms.
Fill Materialwhichisusedfortheconstructionofembankments.
FineAggregate Fineaggregateismaterialpassingthe4.75mmsieve.
Footway An area normally adjacent to the carriageway provided for the use by
pedestrians.
Formwork Temporary boarding or sheeting erected to contain concrete during
placing,compactingandinitialhardeningincludingsupports.
Gabions Gabionsconsistofwovensteelmeshboxesormattressesfilledwithstone.
Gravel Gravel is naturally occurring, rounded, granular material with an average
dimension of more than 5mm and less than 300mm, (it does not apply to Gravel
WearingCourses).
PrimeCoat Abituminoustreatmentappliedtothesurfaceofanewlyconstructed
unbound
road
base
prior
to
the
construction
of
a
bituminous
layer
or
surface
treatment.
-
7/27/2019 Annex III Technical Specifications 105 C1
9/254
SRI LANKA OPERATIONS CENTRE
Quality Control Procedures, and/or testing, carried out prior to, or during, the
construction of the Works for the purpose of ensuring compliance with the
requirementsoftheSpecification.
Quarry Anareawithindesignatedboundaries,approvedforthepurposeof
obtainingrock.
RoadBase Alayerofmaterialofdefinedthicknessandwidthconstructedontopof
the subbase, or in the absence thereof, the subgrade. A road base may extend
beyondthecarriageway.
Roadway Theroadwaycomprisesthecarriageway,shouldersandmedian.
Rock Amassofhardmineralmaterialwhich,whenexcavated,requirestheuseof
explosives,sawingorsplittingbymechanicalmeans.
Riprap Unboundedstoneprovidedtoprotectthesurfacesofslopesandthebeds
ofwatercoursesfromerosionandscour.
Scarify Loosenandbreakupsoilorexistingpavementlayersbymeansofamachine
fittedwithtines.
ShoulderBreakpoint Thepointonacrosssectionatwhichtheextendedflatplanes
of the surface of the shoulder and the outside slope of the fill and pavement
intersect.
SideDrain
A
longitudinal
drain
offset
from,
and
parallel
to,
the
carriageway.
Stabilisation The treatment of pavement materials by the addition of lime or
Portlandcement.
Subsurface Drain A covered drain constructed to intercept and remove subsoil
water.Itincludesallpipesandfiltermaterialinthedrain.
Surface Dressing The sealing or resealing of the surface of the carriageway or
shouldersbymeansofoneormoresuccessiveapplicationsofbituminousbinderand
chippings.
TackCoat Abituminoustreatmentappliedtothesurfaceofanexistingbituminous
layerpriortotheconstructionofanewbituminouslayer.
Topsoil A surface layer of soil which contains organic matter and is capable of
supportingthegrowthofvegetation.
Traffic Vehicles,pedestriansandanimalstravellingalongaroute.
Traffic Lane Part of a carriageway intended for a single stream of traffic in one
direction,whichhasnormallybeendemarcatedassuchbyroadmarkings.
-
7/27/2019 Annex III Technical Specifications 105 C1
10/254
SRI LANKA OPERATIONS CENTRE
California Bearing Ratio (CBR)Test method toevaluate thebearingcapacityof the
soil.
MaximumDryDensity(MDD) Maximumdrydensityasdeterminedinthelaboratory
usingStandardCompaction.
OptimumMoistureContent(OMC) Optimummoisturecontentasdeterminedfrom
moisturedensityrelationshiptestsforStandardCompaction.
DynamicConePenetrometer(DCP) DeviceforfieldcheckingofinsituCBR,
AllkindsofSoil Thesoiltypeincludeclay,sand,gravel,boulders,hardrocksetc.
In this Specification the following terms, words or expressions shall have the
meanings hereby assigned to them. For ease of understanding certain cross
sectionalandpavementstructureelementsareillustratedinandFigure2&Figure2.
Figure1TermsandDefinitionsforRoadCrossSectionElements
ShoulderTraffic Lane
Shoulder Break
Point
Shoulder
Right of Way
Roadway
Carriageway
Traffic Lane
Side Drain
Sub-grade (Bottom
of Excavation)
Capping Layer
(if Required)
Roadbed (Existing
Ground under
Embankment)
Sub-grade (Top of
Fill Material)
Pavement Layers
Fill
Embankment
Limit of Roadbed
-
7/27/2019 Annex III Technical Specifications 105 C1
11/254
SRI LANKA OPERATIONS CENTRE
Figure2TermsandDefinitionsforPavementStructure
Capping Layer
( i f required)
Sub-base
R o a d B a s e
Sub-grade
Surfac ing Layers
Base Co urse ( i f any )
W e a r i n g C o u rs e
RoadPavementLayers
Wherethe
definition
in
the
General
Conditions
of
Contract
differ
from
those
in
the
StandardSpecificationsandSpecialprovisionstoStandardSpecifications,theformer
shallapply.
103. ARRANGEMENTSFORTRAFFICDURINGCONSTRUCTION
103.1. General
Deletethissubsectionandsubstitutethefollowing:
FromthedateofCommencementoftheWorkstothedateof issueofTakingover
Certificate for the whole of Works as provided for in the contract the Contractor
shall
be
responsible
for
maintaining
the
uninterrupted
passage
of
vehicles
and
pedestriansalong theproject road/rightofway. The road isextensivelyusedand
dueattentionshallbepaidbytheContractortothemaintenanceandridingcomfort
ofallroads/detours/diversions.
Thetypesofmaintenancesituationsdescribedbelowinclude:
(i) Construction and maintenance of temporary detours (away from existing
roadembankment)requiredtobebuiltbecausethefullwidthoftheexisting
road is under construction or where works on cross drainage structures
requires theprovisionofatemporarydetour includingmaintenanceofthe
existingBridge.
(ii) Construction and maintenance of temporary diversions along an existing
embankmentwhen roadconstruction isprogressinghalfwidthbeyond the
proposedcenterline.
(iii) Maintenanceoftheexistingroadpriortocommencementofconstruction.
(iv) Maintenance of completed half width of road and shoulder opened to
traffic.
(v) Maintenance
of
traffic
on
exposed
granular
layers
in
a
carriageway
under
construction.
-
7/27/2019 Annex III Technical Specifications 105 C1
12/254
SRI LANKA OPERATIONS CENTRE
TheContractorsresponsibilitiesshallincludetherectificationofanydeteriorationor
damage to the road, intersections or driveways, and drainage structures; due to
passageoftraffic,orrainsorflood.Thespecificlocationsofanydetourordiversions
shalldependupontheContractorsmethodofworkingandtheContractorshallbe
deemedtohavecoveredthesameinquotinghisrates.
Upon completion of a days work, or if the Works are to be left unattended, the
ContractorshallleavetheWorksinsuchaconditionsoastoallowthesafepassage
of traffic. The Contractor shall be responsible for complying with all regulations
relatingtothetemporaryclosureofroadsinSriLanka.
The Contractor shall provide and maintain for the period of construction, traffic
control and safety devices including Traffic Signs, Barricade Boards, Traffic Cones,
LightingDevicesetc.,atall locationswherework is inprogress inaccordancewith
Part II of the Manual of Traffic Control Devices, Road Development Authority,
Ministryof
Transport
and
Highways.
The Contractor shall so conduct his operations as to offer the least possible
obstruction and inconvenience to the public. He shall have under construction no
greaterlengthoramountofworksthanhecanproperlymanageatatimewithdue
regardtotherightsofthepublicinmaintainingafreeflowoftraffic.Unlessprovided
otherwise in this specification all traffic shall be permitted to pass through the
sections of the works, which have been completed and opened to traffic in
accordancewiththecontract.
Areaofexistingpublicroadway,trafficdiversionsordetoursshallnotbeobstructed
orused
in
any
way
by
the
Contractor
for
the
dumping
or
stockpiling
of
materials,
or
parkingofContractorsequipment
At least 15 days before commencing work on any section of the works the
ContractorshallsubmittotheEngineerhisproposalsforthemaintenanceoftraffic
including Working Drawings of traffic control arrangements, road signs, and any
temporary road works including detailed typical cross sections of proposed
detours/diversions indicating clearly the type of diversion, proposed material and
thickness of pavement structure and surfacing not inferior to specifications stated
hereinafter,andaprogramshowingthetimeoverwhichthediversionisrequiredto
carrythetraffic.
TheEngineermayrequirechangestotheContractorsproposalspriortoapproving
the proposal of temporary works and program. The standard of road surfacing
required may depend on the duration that the detour/diversion is required to be
operational. Approval to the Contractors proposal shall not take away the
Contractors obligation to provide for the uninterrupted passage of vehicles and
pedestrians at all times. Where necessary the Contractor shall strengthen by the
addition of pavement layers or by additional compaction or other means, any
detoursordiversionsthatmaybefound inadequatefortrafficnoextracosttothe
contract.
Materialand
equipment
temporarily
stored
on,
or
adjacent
to,
the
existing
roadway
shall be so placed, and the work at all times, shall be so conducted as to cause
-
7/27/2019 Annex III Technical Specifications 105 C1
13/254
SRI LANKA OPERATIONS CENTRE
minimum disruption to the travelling public. Warning signs and barrels will be
requiredtoseparatetheContractorsmaterialandequipmentfromthepublic.
TheContractorwillnotbepermittedtohaveexcavationsopenonbothsidesofthe
roadataparticularchainagesuchthatthereisastepadjacenttopublictrafficwhich
may create a danger to traffic i.e. the excavation and backfilling with subbase or
base shall be flush with the existing road level on one side before excavation can
proceedontheothersideoftheroad.
Themaximum lengthofonewayworkingcontrolledbystop/goboardsorflagmen
shall be 500 metres. This length may be further reduced if visibility is reduced at
bendsonincreasedwhereappropriateattheEngineersdiscretion.
DuringconstructionforoperationswhichrequireonewaytraffictheContractorshall
beresponsiblefortheremovalofbrokendownvehiclesincludingvehiclesdamaged
inaccidentsandshallmaintainonewayuninterruptedtrafficflowatalltimes
As
an
alternative
or
in
addition
to
oneway
working,
traffic
diversions
may
be
arrangedwherethisisfeasible. SuchdiversionsshallbeapprovedbytheEngineerin
conjunction with the Traffic Police. The Contractor shall be responsible for the
provisionandmaintenanceofadequatesigningforthedurationofanydiversion.
The Contractor shall arrange for the Traffic Police to be in attendance for traffic
managementwheneverrequired.
Noseparatepaymentforthemaintenanceoranyothercostsincurredwhilstutilising
the diversion shall be made. All costs shall be deemed to be included in the
Contractorsrates.
Allearthandgravelbypassesandexistinggravel roadsusedasbypassesshallbe
maintainedinasafetrafficableconditionbytheContractor. Whereverrequiredby
the Engineer, the roads and bypasses shall be graded by motor grader or by
approved means to provide a smooth riding surface free of corrugation. All pot
holesshallbepromptlyrepairedbythecontractor. Drainageshallbekept ingood
orderandtheContractorshallwaterthebypassesasoftenasisnecessarytokeep
dustdown.
103.2. UsingPartoftheRoad
Nochange.
103.3. TemporaryDiversion
Nochange
103.4. TrafficSafetyandControl
Deletethissubsectionandsubstitutethefollowing:
The Contractor shall, after consultation with the Engineer, all the concerned Local
AuthoritiesandPoliceprepareaschemeoftrafficmanagementforcarryingoutthe
Works. SuchproposalsshallbesubmittedtotheEngineerforhisapproval,together
withwrittenapproval/noobjectioncertificatesfromtheconcernedauthorities,not
lessthan30daysbeforetheplannedimplementationofeachproposal.
-
7/27/2019 Annex III Technical Specifications 105 C1
14/254
SRI LANKA OPERATIONS CENTRE
TheContractorshallnotcommenceanyworksaffectinganypublichighwayuntilall
approvedtrafficsafetymeasuresconformingtotheEngineerspriorapprovalhave
beenfullyimplementedtothesatisfactionoftheEngineer.
The Contractor shall take necessary measures for the safety of traffic and third
parties by providing, erecting and maintaining all signs, lamps, barriers, traffic
control signals, road markings, etc. in a clean and legible condition, and shall
position, reposition, cover or remove them as required by the progress of the
Works.Thebarriersshallbestrong.Redlanternsorwarninglightsshallbemounted
on the barriers at nights and shall be kept lit till sunrise. If the Contractor fails to
complywiththeserequirements,theEngineershallorderathirdpartytorectifythe
shortcomingsandshallrecoverthecostofsuchworksfromtheContractor.
a. Measurement
Arrangements for traffic during construction shall be measured per month for the
period
during
which
the
Contractor
maintains
the
arrangement
to
achieve
full
compliancewiththerequirementofSection103.
b. Payment
ThequantitiesmeasuredinmonthandtenthsofamonthwillbepaidattheContract
ratepermonth.
PaymentwillcommencefromthedaythattheContractorcommencesasectionof
road work on bridge work which require one way traffic working or when be
constructsadiversioninaccordancewithSection103.
Paymentwill
continue
while
such
one
way
working
or
traffic
diversions
are
in
proper
operationinaccordancewiththeContractorsprogrammeandtothesatisfactionof
theEngineer. Paymentwillceasewhennoonewayworkingortrafficdiversionsare
inplace. Thepay itemshallbedeemedtoincludeforcompliancewithSection103
forasmanylocationsthattheContractorisoperatingonewayworkingordiversions
fortrafficatanyonetimewhetherthisbeoneorseveral.
Noadditionalpaymentwillbemadeforcompliancewiththisclause.
Payitemsshallbe:
ItemNo. Description Payunit
103(1) Provision and Maintenance of
Arrangements for traffic during
construction. month.
104. CONTROLOFWORKS
104.1. AuthorityoftheEngineer
Nochange.
-
7/27/2019 Annex III Technical Specifications 105 C1
15/254
-
7/27/2019 Annex III Technical Specifications 105 C1
16/254
SRI LANKA OPERATIONS CENTRE
ThecontractorshallreporttotheEngineerpromptlyandinwritingparticularsofany
accident or unusual or unforeseen the occurrences on the site, whether likely to
affectprogressoftheworkornot.
No payment would be made for services under this clause as the same shall be
deemedtohavebeenincludedinthegeneralobligationoftheContractor.
104.5. ProtectionofPublicServiceFacilities
Immediatelyonreceiptofthenoticetocommencetheworks,theContractorshall
make a survey to identify all surface and under ground Electric/Telephone poles,
service lines viz gas/fuel pipe, water line, survey Bench Marks (BM) and other
facilities etc. likely to impede/obstruct his works and shall submit a survey and
chainagewiselistoftheseobstructionstotheEngineer.
AnyservicesaffectedbytheWorksshallbetemporarilysupportedbytheContractor
who shall also take all measures reasonably required by the various bodies to
protecttheirservicesandpropertyduringtheprogressoftheworks.
Noseparatepaymentshallbemadeforthesurvey,identificationandanytemporary
support or protection of services, as it will be deemed to be under the general
obligationoftheContractor.
As directed by the Engineer, the Contractor will arrange for the relocation and/or
removalofpublicservicesbytheappropriateauthority.
Payment for any charges made by these authorities shall be made as shown in
Section203.
104.6. SafetyRelatingtoTemporaryStructures
Thecontractormustsubmitcompletedesigncalculationsplansandtechnicaldetails
ofallproposed temporary structures for the engineers priorapprovalbefore their
constructioncommences.TheEngineersapprovalwillnotrelieve thecontractorof
anycontractualliabilities.
The contractor must also ensure that all necessary safety regulations and
precautions
must
be
complied
with
during
the
erection,
use
and
dismantling
of
temporary structures no separate payment will be made for temporary structures
which are not scheduled in the Bill of Quantities. They will have been deemed to
havebeenincludedintherateitemslistedintheBillofQuantities.
104.7. SafetyRelatingtoNavigableWaterways
TheContractorshall inadditiontocomplyingwiththespecificrequirementsofthe
GeneralConditionsandwiththenationalstandardsoftheGovernmentofSriLanka
inrespectofnavigablewaterways,shallcomplywithallordersanddirectionsgiven
by the Engineer in respect of the safety of navigation and with requirements for
markingwatchingandlightinganystructure,craftorequipmentwhichmaybeusedintheconstructionoftheworks.
-
7/27/2019 Annex III Technical Specifications 105 C1
17/254
SRI LANKA OPERATIONS CENTRE
The contractor shall not lay down or provide permanent moorings for his floating
plant.TheContractorstemporarymooringsshallbepositionedandinstalledtothe
approval of the Engineer. Prior notification of their installation shall be officially
giventoallusersofthewaterway.
Spoil excavated or dredged by the Contractor shall not be deposited in such
locationsaswillinfillorcausesiltingupofexistinglowwaterchannels.
The Contractor shall without delay raise and remove or recover any material,
construction plant (floating or otherwise) or vessel belonging to or hired by him
whichmaybesunkstrandedorgoneadriftinthecourseofconstructioncompletion
ormaintenanceoftheworks,orotherwisedealwiththesameastheEngineermay
direct.
The Contractor shall take all necessary precautions and measures to avoid
interruption
of
service
of
the
existing
ferry
or
navigation
as
a
consequence
of
his
temporaryworksorconstructionofthepermanentworks.
No payment would be made for services under this clause as the same shall be
deemedtohavebeenincludedinthegeneralobligationoftheContractor.
104.8. EnvironmentalRequirement
The Contractor shall comply, with the Environmental Monitoring guideline in
accordance with the requirement of Statutes/Law of the Government of Sri Lanka
and International standards. In respect of controlling damage to the environment
andcontrolling
pollution
the
Contractor
shall
be
bound
to
follow
the
regulation/law
oftheGovernmentofSriLankaandanystatutorybodiesortherequirementofsuch
lawsofhisownhomecountrywhicheverismorestringent
(1) SpecificEnvironmentalConcerns
Thespecificenvironmentalconcernsare:
Emissionstoair(dust,smokeetc.)
Emissionstoland(solidandliquiddomestic&industrialwasteetc.)
Emissiontowater(dredgespoil,surface&foulwaterdrainageetc.)
Noiseandvisualpollution
These are now discussed one by one while it will be indicated to which particular
contracttheyareapplicable.
(2) Emissionstoair
Generationofdust
The spread of wind blown soil particles derived from unpaved haulageandaccess
roads,reclaimedareasandstockpilesofsoil,anddustfromrockhandlingmaycause
-
7/27/2019 Annex III Technical Specifications 105 C1
18/254
SRI LANKA OPERATIONS CENTRE
aproblemduringthedryseasonifstrongwindsprevail.Suchdustmaycausehealth
risksforthelabourersandforthepopulationlivingnearby.
As part of hisobligation to minimisedisturbance to otherusers.TheContractor is
required towaterunpaved roadsunderdryweatherconditionsand imposespeed
limitsonaccessandhaulageroads.
Thenatureofamajorearthworksoperation inevitablygivesrisetoadustnuisance
theeffectsofwhicharetobeminimizedasfaraspracticablebywateringandroute
and speed control of vehicles. The dust nuisance from the Contractors crushing
plantistobecontrolledbytheuseofwatersprays.
Airpollution
Exhaustemissionscausedbytheuseofvehicles,machineryandotherenginedriven
equipment used by the contractors should not exceed the exhaust emission
standardsassetforwardinthetablesbelow.
EmissionstandardvaluesforMotorVehicleExhaust
Parameters
determinates
Unit Standard
Value
Blacksmoke(1)
CO(2)
hydrocarbon(2)
NOx(2)
HattridgeSmokeUnit(HSU)
g/m3
percentvolume
g/m3
ppm
g/m3
ppm
65(3)
24
4(4)
2
180
2
600
(1) measuredattwothirdsofmaximumrotatingspeed
(2) whicheverisloweroutoftwovaluesexpressedintwodifferentunits
(3) Forvehiclesmorethan5yearsold,orthathavecompleted80,000kmthestandard
valueis75HSU
(4) Twoandtreewheelervehicleswithenginedisplacementlessthancm3thestandard
valueis5volumepercentage.
EmissionstandardvaluesforBlackSmokeEmissionfromboat/ship/vessel
Parametersdeterminats Unit Standard
Value
Blacksmoke(1) HattridgeSmokeUnit(HSU) 65(3)
(1) measuredattwothirdsofmaximumrotatingspeed
Theambientairqualityinandaroundtheworksiteshouldmeetthestandardvalues
for ambient air quality described in the following table. Regular maintenance of
engines and equipment is considered to be important for reducing emission and
emissions.
-
7/27/2019 Annex III Technical Specifications 105 C1
19/254
-
7/27/2019 Annex III Technical Specifications 105 C1
20/254
SRI LANKA OPERATIONS CENTRE
Unlessapprovedotherwise,dredgedmaterialshallbedepositedonland.
Landdisposal
Testhaverevealedthepresenceofanytoxicorpollutingsubstanceintheriverbed
material.
the bunds or embankments for the hydraulic fill are to be of such quality that no
spillsorbreachesoccur,damagingneighboringland;
to prevent water logging of agricultural areas in the flood plains surrounding
hydraulicfillareas,drainsshallbeconstructedaroundtheembankmentstoevacuate
waterbygravitytotheriver;
Aquatedisposal
Theconcentrationofsuspendedsedimentintheeffluentfromtheexcavationworks,
dischargedintonaturalorexistingwatercoursesshallneverexceed4,000ppm.
Disposal ofdredgedmaterialshallonlytakeplaceonchar land ifnotoccupied foragriculturalpurposesorinthemajorriverchannelminimizingtheimpactonriverine
transportandonaquatic(organismslivinginorattheriverbottom);
(4) Noiseandvisualpollution
Visualpollution
Thecontractorshallensurealltemporaryworksarekeptneatandtidyandthesite
cleanedregularly.
Noisepollution
TheContractor,inplanninghisworksmustrecognizethedistinctionbetweennoise
pollutionasexperiencedbythevillagers livingaroundtheworksandnoisehazards
tothelabourworkingontheconstructionsites
Inthecaseofvillagersthemainformsofnoisepollutionwillbe:
- piledriving
- crushingplant
- generators
- haulage
and
compaction
equipment
- earthandrockmovingequipmentisofconsideration.
Theseactivitiesshouldbeconfinedtodaytimeoperationandnotafter10pm.
In the case of Contractors labour the impact of noise pollution on operators and
adjacentpersonnelcouldbemuchmoreofaproblem:
Ear protectors shall be used in any environment where the noise may exceed the
levelof80dB(A).
Noticeboardsmustbeplacedinareaswherethenoiseexceedsthislevelandwhere
earprotectors
must
be
worn.
Noise
levels
should
be
measured
if
any
doubt
exists.
-
7/27/2019 Annex III Technical Specifications 105 C1
21/254
-
7/27/2019 Annex III Technical Specifications 105 C1
22/254
SRI LANKA OPERATIONS CENTRE
originalprogrammenecessarytoensurecompletionoftheworksoranypartthereof
withinthetimeforcompletionasdefinedinClause13oftheConditionsofContract
oranyextendedtimegrantedpursuanttoClause43oftheConditionsofContract.
Anyproposal to increasethetempoof theworkmustbeaccompaniedbypositive
stepstoincreaseproductionbyprovidingmorelabourandplantonSite,orbyusing
theavailablelabourandplantinamoreefficientmanner.
FailureonthepartoftheContractortoworkaccordingtotheprogrammeorrevised
programme,shallbesufficientreasonfortheEmployertotakestepsasprovidedfor
intheConditionsofContractandshallbeconstruedasnotexecutingtheWorks in
accordancewiththeContract.
TheapprovalbytheEngineerofanyprogrammeshallhavenocontractualsignificance
otherthanthattheEngineerwouldbesatisfiediftheworkiscarriedoutaccordingto
such programme and that the Contractor undertakes to carry out the work in
accordancewiththeprogramme,norshallitlimittherightoftheEngineertoinstruct
theContractor
to
vary
the
programme
should
circumstances
make
this
necessary.
The
aboveshallnotbetakento limittherightoftheContractortoclaimfordamagesor
extension of time to which he may be fairly entitled to in terms of the General
ConditionsofContractfordelayordisruptionofhisactivities.
ShouldtheEmployerrequestandtheContractorundertaketofinishthewholeorpart
of the Works ahead of the time originally required by the Contract, payment for
accelerating the work shall only be made if agreed to beforehand in writing and
accordingtothetermsofsuchagreement
No payment would be made for services under this clause as the same shall be
deemedto
have
been
included
in
the
general
obligation
of
the
Contractor.
104.10. ProgressMeetings
Meeting will be held at intervals not exceeding one month between the Engineer
andthecontractortodiscusstheprogressoftheworksandanyproblemsthatmay
havearisen.ThecontractorshallgivetotheEngineeratthesemeetingsdetailsofhis
progresstodateinrelationtotheprogramme.
No payment would be made for services under this clause as the same shall be
deemedtohavebeenincludedinthegeneralobligationoftheContractor.
104.11. ReturnsandReports
At monthly intervals the contractor shall, inaccordance with his obligations under
Clause35oftheGeneralConditionsofContract,supplytotheEngineer,returnsof
labourandconstructionalPlantand,inaddition,ascheduleofthemainworkitems
in each section of the works showing progress during the previous week and
proposedprogressforthecomingweekandtotalprogresstodate.
At monthly intervals, and not later than the first week in every month, the
contractor shall submit to the Engineer a progress report for the previous month
thatshall
include,
but
not
be
limited
to
the
following:
-
7/27/2019 Annex III Technical Specifications 105 C1
23/254
SRI LANKA OPERATIONS CENTRE
a) a programme marked up with any agreed amendments and showing the
actualpercentagecompletionofeachofthemain itemsofwork, insucha
way that comparison can be made with the scheduled percentage
completionofeachitem.
b) Weatherandotherconditions, includingdailytemperaturerange,humidity
rainfall,windspeedanddirection,riverlevelsetc.
c) Summaryofstaffandlabouremployedonthesite.
d) Schedule of Constructional Equipment on site with dates of arrival and
departureasappropriateincludingequipmentoperationalcondition..
e) Scheduleofprincipalmaterialitemswithdatesofplacingordersprogressof
manufacture,datesofdeliverytositeetc.
f)
Recordof
site
safety
All reports, statements, returns, diagrams ordrawings etc. which thecontractor is
required to submit to the Engineer during the progress of the works shall be
furnishedinquadruplicateunlessotherwisedirected.
No payment would be made for services under this clause as the same shall be
deemedtohavebeenincludedinthegeneralobligationoftheContractor.
104.12.Telecommunications
The Contractor shall provide and maintain telephone, fax and email and mobile
telephone
with
necessary
connections
and
facilities
in
the
site
office
during
the
periodoftheconstructionandmaintenance.TheContractorshallalsomaintainthe
telephonefacilitiesandpayallbillsforthewholeperiodasstatedabove.
104.13.CompactionGeneral
Compaction of materials shall be carried out in layers of uniform thickness using
approvedcompactionequipment includingcombinationsthereof ifrequiredbythe
Engineertoachievethespecifiedcompaction.
Compaction with rollers shall commence at the edges and progress towards the
centre
except
in
super
elevated
and
other
stretches
of
unidirectional
crossfall,
wheretherollingshallcommenceattheloweredgeandprogresstowardstheupper
edge. When commencing rolling from an edge, rollers shall run forward and
backwardalong theedgeseveral times till theedgestripbecomes firm toprovide
lateralsupport. Therollershallthenmoveinwardsparalleltothecentrelineofthe
road in successive passes with the tracks made by successive passes overlapping.
Rollingshallcontinuetillthespecifieddegreeofcompactionisachievedthroughout.
Whenrollingisterminatedatanedge,theproceduresimilartothatforcommencing
rollingatanedgeshallbeadopted. Duringrolling,thetopofthelayerbeingrolled
shall be checked for levels and crossfall and any irregularities in these regards,
correctedbyscarifyingthematerialintheaffectedareaandbyremovingoradding
materialsand
continuing
with
the
rolling
until
the
entire
area
being
rolled
has
been
broughttoastateofuniformanddesiredcompaction.
-
7/27/2019 Annex III Technical Specifications 105 C1
24/254
SRI LANKA OPERATIONS CENTRE
104.14.Mixing&ControlofMoistureContentBeforeCompaction
Beforecompaction iscommenced (otherthan forbituminousmixes),each layerof
uncompactedmaterialshallbebrought to astateofuniformcomposition, texture
and
moisture
content
by
thorough
mixing
and
addition
of
water
or
drying
asrequired. TheContractorshallbedeemedtohavetakenaccountofthefactthatthe
materials encountered may vary widely with respect to their insitu moisture
contentsandthemoisturecontentsatwhichthematerialsaretobecompactedas
tobespecifiedseparatelyforeachtypeofmaterial. Accordingly,thematerialsmay
have to be wetted by adding water or dried to the required degree, along with
intimatemixingoftheentiremassofthematerials.
104.15.CompactionEquipment
Mechanical equipment shall be used for compacting materials by rolling, tamping
andwatering
the
materials
(if
needed)
before
compaction.
For
other
operation
such
as spreading, mixing and shaping, manually operated tools and equipment is
preferred on mechanical equipment alone or a combination of two shall be used.
The choice of equipment and the procedure of their use shall be subject to the
approvalof theEngineer,uponhisbeingsatisfiedabouttheireffectivenessonthe
basisoftrialcompactions.
ItshallbeunderstoodbytheContractorthatdifferenttypeofmaterialsarelikelyto
require different kind of compaction equipment, including successive applications
thereof,forachievingthespecifieddegreesofcompactionandtheContractorshall
keep available a fleet of compaction equipment of the requisite kinds, sizes and
number.
For compacting along narrow strips e.g. along widening of pavements and in
restricted areas e.g. behind bridge abutments, appropriate sized purpose made
compacting equipment will be required and the same shall be provided by the
Contractor.
Allequipmentshallbeofmodernconstructionbyestablishedmanufacturersandof
proven efficiency and shall be operated and maintained at all times by skilled
personnelinamanneracceptabletotheEngineer.
104.16.WaterandPowerSupplyArrangements
TheContractorshall
a. provideathisownriskandcostallwater, lightingandelectric powerrequiredfor
useintheworksatsuchfrequent locationsasarenecessaryandshallpayallcosts,
feesandcharges inconnectiontherewithandallowallsubcontractors freeuseof
thesame.TheContractorshallmakehisownarrangementforhisrequirementsof
potablewater,by
-
7/27/2019 Annex III Technical Specifications 105 C1
25/254
SRI LANKA OPERATIONS CENTRE
b. provideandmaintaintemporarywaterstoragetogetherwithanydistributionpiping
whichmaybenecessaryandsubsequentlyremoveallinstallationstotheapprovalof
theEngineers.
c. Provide,wirefor,andconnectlightingandpowerfortheworks.
d. Provide mechanically driven and operated water bowsers with effective spray
equipmentatalltimestoensurethatcompactioncanproceedwithoutanyholdup
onaccountofwatering.
104.17.DrainageduringConstruction
Allembankment,subgrade,shoulderandpavementlayersunderconstructionshall
beprotectedfromanyaccumulationofwaterduetorainsorothercausesandfrom
erosionduetoflowofwater.Allsuchlayersunderconstructionshallbeprovided
withcrossfalltofacilitatesurfacerunoffand,ifnecessary,thecrossfallshallbe
supplementedwithtemporarydrainstopreventaccumulationofwater.
104.18.PreventionofDamagestoEmbankments,SubgradeLayers,PavementLayersand
ShouldersinPosition.
Excavations for new constructions and placement of materials and their in situ
processingandcompactionfornewconstructionshallbedoneinsuchamannerand
with such precautions as not to cause any damage to embankments, subgrade
layers, shoulders and pavement layers in position including those preexisting and
intendedtoformpartoftheimprovedroad.
104.19.CompactionTrials
For demonstrating the efficacy of mixing and compaction equipment and the
working methods proposed to be used by the Contractor for different kinds of
materials, the Contractor shall carry out compaction trials before fullscale
construction on the road and during construction throughout the course of the
contractasrequiredbyandinclosecooperationwiththeEngineer. Basedonresults
of compaction trials and construction observation, the Engineer shall reserve the
righttodirecttheuseofparticularmixingandcompactionequipmentandmethods
and disallow the use of others for compacting different kinds of materials in
accordancewiththesespecifications.
104.20.CompactionControl
Afterthecompactionofeach layerofmaterial,fielddensitytestsshallbedoneon
the compacted material. For locating test points, successive compaction panels
coveringtheentireareaofworkshallbedesignatedinadvanceofcompaction.The
frequencyofthetests(intermsofsquaremetresofcompactedareaofeach layer
forwhichminimumonetestistobedone)shallbeseparatelyspecifiedfordifferent
kinds
of
material.
The
test
locations
shall
be
chosen
through
random
sampling
techniques.
-
7/27/2019 Annex III Technical Specifications 105 C1
26/254
SRI LANKA OPERATIONS CENTRE
AcceptanceofcompactionbytheEngineershallbebasedonthemeanvalueof5to
10determinationsoffielddrydensity.Themeandrydensityofasetoftestsshallbe
equal to or exceeding the specified value and the standard deviation shall not
exceed4percentofthemeandrydensity.Ifthisisnotsatisfiedtheentireworkto,
whichthesetofdensitytestsrelatesshallbetreatedasnonacceptable.
For material other than bituminous mixes, the compaction panels in which the
compaction work is found as nonacceptable shall be given recompaction
accompanied with scarifying and wetting/drying for the entire thickness of the
compacted layer to achieve the specified degree of compaction. In case of
bituminousmixes,thecompactionpanelsinwhichthecompactionworkisfoundas
nonacceptable shall be strippedoff and relaidwith freshbituminousmixand re
compacted.
104.21.DispersalofHaulingEquipment
Hauling equipment bringing materials to the site of work shall be dispersed
uniformly over the surface of the previously constructed layers in order to avoid
ruttingandunevencompaction. Thematerialsfromhaulingequipmentshallnotbe
dumpedinconcentratedheapsbutdepositedasevenlydistributedlayers.
104.22.ProtectiontoNewlyConstructedLayers
No traffic other than construction traffic shall be allowed on any earthwork or
pavementlayeruntilasurfacinghasbeenappliedeitherassinglesurfacetreatment
oranasphaltconcretelayer. TheapprovaloftheEngineershallberequiredbefore
trafficisallowedtopassovernewlyconstructedroad. Anydefectscausedbytraffic
passing over the construction layers shall be remedied in accordance with these
Specifications.
104.23.BridgeConstructionSequence
The Contractor shall programme the construction sequences for all bridges and
submit a written statement thereof for the approval of the Engineer. The bridge
construction sequence shall consider, as a minimum, each phase of bridge
constructionwithrespecttotrafficcontroltheeffectsontheexistingbridgesandthe
completedbridges. WheretheContractorproposestopartiallydemolishanexisting
bridge to allow for phased construction, he shall demonstrate to the Engineers
approvalthat thepartiallydemolishedbridge issafe forusebyhisequipmentand
otherroadusers.
Thecontroloftrafficduringtheconstructionofthebridgewillbeinaccordancewith
theSpecification,103. Wherethebridgeconstructionsequencehasbeenspecified
ontheDrawings,theContractorshallfollowthesequencespecified. TheContractor
mayproposeanalternativeconstructionsequenceprovidedhecandemonstrate,in
awrittenstatement,thatthesequenceisnotdetrimentaltotheWorksorroadusers
inanyway.
-
7/27/2019 Annex III Technical Specifications 105 C1
27/254
SRI LANKA OPERATIONS CENTRE
Noworkshallcommenceonabridgeuntilthewrittenconsenttotheconstruction
sequence has been given by the Engineer in compliance with clause 13 of the
GeneralConditionsofContract.
104.24.MaterialsTestingbyIndependentLaboratories
InadditiontotheSitetesting facilitiesdescribedSubSection130.8,theContractor
shallberesponsibleforarrangingforthefieldandoffSitelaboratorytestsindicated
as the responsibility of the Contractor in the Specifications, to be performed by
testing laboratoriesapprovedby theEngineer. TheContractor shallbe responsible
for all attendance on staff from these approved testing laboratories, including if
necessarytheprovisionoftransportforpersonnel,equipmentandtestspecimens.
104.25.SpecialandAdditionalTesting
Inadditiontothetestingdescribedabove,theEngineermayrequirefurthertesting
to be carried out. Such special and additional testing shall be arranged by the
ContractorunderthedirectionoftheEngineer.
104.26.StaffforMaterialsTesting
TheContractor shallprovidequalified laboratoryengineers,technicians,assistants,
labourers, etc. to carry out sampling and testing of materials in accordance with
theseSpecifications.LaboratorystaffshallbesubjecttotheapprovaloftheEngineer
andbeavailabletoassisttheEngineerwithmaterialstesting,asandwhenrequired.
104.27.CodesandStandards
Allthecodesofpractice,standardsandspecificationsapplicableshallbethe latest
editionwithallcorrectionsandincorporationsason30(thirty)daysbeforethefinal
dateforsubmissionofthetender.TheContractorwillsupplytwo(2)copiesofthe
codesofpractices,standards,onetotheEngineerandothertotheContractorsuse.
104.28.TestResultsandRecords
The Contractor shall maintain complete records of test results which may be
inspectedby
the
Engineer
at
any
time.
All
test
results
shall
be
recorded
on
standard
forms approved by the Engineer and shall be countersigned by the Engineer.
Completed forms shall clearly show the locations of samples, sampling dates and
testing dates. Samples shall be numbered serially at the time of sampling. The
Engineer may witness any sampling or testing carried out in the laboratory. The
Contractorshallhavetherighttowitnessanysamplingortestingcarriedoutbythe
Engineer.OncompletionoftheContracttheoriginalcopiesofalltestresultsshallbe
handedovertotheEmployer,viatheEngineer.
104.29.MeasurementandPayment
No
separate
payment
shall
be
made
for
compliance
items
under
this
section.Paymentshallbedeemedtobeincludedinthecontractorsrates.
-
7/27/2019 Annex III Technical Specifications 105 C1
28/254
SRI LANKA OPERATIONS CENTRE
105. CONTROLOFMATERIALS
105.1. SourcesofSupplyandQualityRequirements
Deletethetextofsubclause105.1andsubstitutethefollowing:
The Contractor shall be responsible for the provision of all materials required to
constructtheWorks. Allmaterialsalvagedand/orremovedfromtheworksremains
thepropertyoftheGovernment. TheContractorshallberesponsibleforthecostof
replacementintheeventofunauthoriseduseorremoval.
TheContractorshallberesponsibleforopeningupallquarriesandborrowareasand
shallorganisehismethodofoperationssothatonlymaterialsofatypeandquality
approvedbytheEngineershallbeselectedforuseintheWorks.
TheContractorisatlibertytoselectandusematerialfromhisownsourcesproviding
therequirementsofthissectionarefullymet.
105.2. StorageofMaterials
Deletethetextofsubclause105.2andsubstitutethefollowing:
Materialsshallbestored insuchamannerastoensurepreservationoftheirspecific
qualityandsuitabilityforuseintheWorks.Storedmaterialsshallbelocatedsothat
theyarereadilyavailableforuseandcanbeeasilyinspectedbytheEngineer.Private
propertyshallnotbeused forstoragepurposeswithout thewrittenpermissionof
the
owner
or
lessee.
Storage sites shall be free of vegetation and debris, free draining and if necessary
shall be elevated. Material placed directly on the ground shall not be used in the
Works unless the site has been prepared and surfaced with a 10 (ten) centimeter
layerofsandorgraveltothesatisfactionoftheEngineer.
Stockpiledmaterialshallbestored insuchamannerastopreventsegregationand
excessive moisture content. The maximum height of stockpiles shall be limited to
fivemetres.
Stockpiling of the various aggregates to be used for asphalt concrete, bituminous
surface treatment, penetration macadam or concrete will be permitted only in
separatestockpilesforeachnominalsizeofaggregate.Theseshallbeseparatedto
preventmixingofmaterials.
Aggregatestockpiles forbase courseandsubbase shallbe protected from rain to
preventsaturationoftheaggregateswhichwouldresultinareductioninthequality
oftheplacedmaterialoradverselyaffecttheplacementofthematerial.
105.3. HandlingofMaterials
Nochange.
-
7/27/2019 Annex III Technical Specifications 105 C1
29/254
SRI LANKA OPERATIONS CENTRE
105.4. ApprovalofSourcesofMaterial(Addthefollowing)
The sources of the materialsshallbe selected by theContractor, butapprovedby
the Engineer before the materials are haulage to be used on the site. For this
purpose, the Contractor shall furnish all relevant test data for representative
samples
from
each
source
area
as
desired
by
the
Engineer
and
also
affordopportunitiesfortheEngineertovisitthesourcesareas.
Notwithstandingapprovalofsourcesofmaterials,materialsasbroughttothework
siteforuseintheWorksshallbesubjecttoacceptanceorrejectionbytheEngineer
basedonqualitycontrolteststobeperformedbeforeuseinconstruction.
105.5. StockpilingofMaterials(Addthefollowing)
AllmaterialsbroughttotheSiteshallbestockpiledandstoredcarefullyatapproved
locations and in a systematic manner so as to prevent deterioration or mixing of
differentmaterials
or
contamination.
Materials
which
have
suffered
contamination
or deterioration due to improper storage shall not be used in Works and shall be
removedfromthestockpilingarea.
Thematerialsshallbefreefromforeign,organicoranyotherdeleterioussubstances
such as vegetation and perishable matters, or any other substance which in the
opinionoftheEngineermayaffectplacingmixingandcompactionofthematerialor
adversely affect the future performance of the Works. Material may be tested in
stockpilesbytheEngineertochecksuitabilityforuseintheWorks.
105.6. TemporaryStockpilingofMaterials(Addthefollowing)
Wheretheworkprogrammeissuchthatmaterialscannotbeplaceddirectlyintheir
required position or mixing of two or more materials is required to meet the
requirements of the Specification for a material the Engineer may authorise their
removal into temporary stockpiles. Stockpile sites shall be to the Engineers
approvalandshallbepreparedbyclearingandgradingfollowedbycompaction.
Thematerialshallbestockpiled insuccessive layersofapprovedthicknessoverthe
fullstockpileareatotheapproximatedimensionsrequiredbytheEngineerandshall
subsequentlybereloadedandplaced.
105.7. ControlTestsonMaterialDuringConstruction(Addthefollowing)
The Contractor shall use only such materials in construction as conform to the
requirements regarding composition, grading, physical properties and engineering
characteristics, as specified for different kinds of materials. For this purpose pre
constructioncontroltestsshallbecarriedoutonrepresentativesamplescollectedat
random of materials brought to construction site or at stockpileson the following
scale. The Engineer shall have the authority to have these tests at more frequent
intervalswherequalityofamaterialisindoubt.
Table1057A
-
7/27/2019 Annex III Technical Specifications 105 C1
30/254
SRI LANKA OPERATIONS CENTRE
TypeofMaterial TypeofTest
Qty.ofmaterialfor
whichminimumone
testoronesetof
testistobedone
Ordinaryfillfor
embankment
Particlesizeanalysis
Atterberglimits
4000cu.m.
4000cu.m.
Moisture density
relationship
CBR Test (set of 3
specimens)
4000cu.m.
4000cu.m
Selectedfillfor
granularcapping
layer
Particlesizeanalysis
Atterberglimits
2000cu.m.
2000cu.m
Moisture density
relationship
2000cu.m.
CBR test (set of 3
specimens)
2000cu.m.
Aggregatesfor
granularsubbase
Particlesizeanalysis
PlasticityIndex
500cu.m.
2000cu.m.
Moisture density
relationship
2000cu.m.
CBR Test (set of 3
specimens)
2000cu.m.
Los Angeles abrasion
test
2000cu.m.
WaterAbsorption 2000cu.m.
Aggregatesforbit
roadbaseand
wearingcourse
Particlesizeanalysis
PlasticityIndex
250cu.m.
1000cu.m.
Waterabsorption 1000cu.m.
Los Angeles abrasion
test
1000cu.m.
Bulkspecificgravity 1000cu.m.
Flakinessindex 1000cu.m.
Moisturecontenttestbeforecompactionofmaterialsshallbecarriedoutonalayer
by
layer
basis
for
each
compaction
panel
on
the
following
scale:
Table1057B
TypeofMaterials
Areaoflayerundercompactionfor
whichminimumonemoisture
contenttestistobedone
Ordinaryfillforembankment 1000m2
Granularcappinglayer 750m2
Aggregatesforgranularsubbase 500m2
Moisture
content
test
shall
be
repeated
whenever
the
moisture
content
of
the
material changes due to drying or wetting or if there be uncertainty (e.g. due to
-
7/27/2019 Annex III Technical Specifications 105 C1
31/254
SRI LANKA OPERATIONS CENTRE
variability)intheresultsofearliertests.
105.8. MaterialTesting(Addthefollowing)
The
physical
properties
and
engineering
characteristics
of
the
materials
mentioned
in these specifications shall be established through appropriate tests on
representative samples collected in such manners and at such frequency as
describedinTable1057AorasdirectedbytheEngineer.Thetestsshallbecarried
out in accordance with test methods as mentioned in these specifications or as
requiredbytheEngineer.
Moisture density relationship tests on fill materials, sands, soilsand mixes and
aggregatesofdifferentkindshallbecarriedout(asperAASHTO:T180).
105.9. ApplicabilityofGeneralSpecifications(Addthefollowing)
These General Specifications shall apply in combinations with specifications in
particular forembankments,pavement layersandshoulders,etc,givenseparately.
In case of any conflict between the General Specifications and the separate
specificationsgiveninparticular,theprovisionsofthelatershallgovern.
105.10.Payment(Addthefollowing)
Noseparatepaymentshallbemadeforitemsunderthissection. Paymentshallbe
deemed
to
be
included
in
the
Contractors
rates.
106. GENERALRULESFORMEASUREMENTANDPAYMENT
Addthefollowing:
Unless stated to the contrary, any thickness, area or volume in any items of the
Worksshallbemeasuredonlyonfinishedworkaftercompaction.
Thepayments forthevarious itemsshown intheBillofQuantitiesshallconstitute
fullcompensationforperformingalloftherequirementsoftheContractfortheitem
of
work
as
specified
including
furnishing
all
necessary
materials,
labour,
tools,
equipment,supplies,testing,andincidentals.
TheContractorshallbedeemed tohavecompliedwiththerequirementsofBillof
Quantities, Contract Rates, Pay Items, Material at site, Provisional Sums, as listed
below.Contractorshouldalso fulfilwith the requirementofGeneralConditions of
Contractclause12SufficiencyofTender.
BillofQuantities
ThequantitiessetoutintheBillofQuantitiesareestimatedquantitiesandareused
for the comparison of Tenders and awarding the Contract. It must be clearly
understoodthatonlytheactualquantitiesofworkdoneormaterialssuppliedwillbe
-
7/27/2019 Annex III Technical Specifications 105 C1
32/254
-
7/27/2019 Annex III Technical Specifications 105 C1
33/254
SRI LANKA OPERATIONS CENTRE
TheContractorshallfurnishtotheEngineersuchreceiptsorothervouchersasmaybe
necessarytoprovetheamountspaidand,beforeorderingmaterials,shallsubmitto
theEngineerquotationsforthesameforhisapproval.Inrespectofsuchoftheworks
executedona day worksbasis, theContractorshall,during thecontinuanceofsuch
work,delivereachdaytotheEngineeranexactlistofthenames,occupationandtime
ofallworkmenemployedonsuchworkandastatementshowingthedescriptionand
quantity ofallmaterialsandequipmentusedother than the Contractors equipment
which is included in the percentage addition in accordance with such day work
schedule. Each list and statement will, if correct, or when agreed, be signed by the
EngineerandacopyreturnedtotheContractor.
TheContractorshallnotbeentitledtoanypaymentunlesssuch listsandstatements
havebeen fullyandpunctually provided.Where theEngineerconsiders that forany
reasontheprovisionofsuchlistswasimpracticableheshallneverthelessbeentitledto
authorisepaymentforsuchworkprovidedthat,suchworkorvaluethereofshall,inhis
opinion,be
fair
and
reasonable
106.1. Overhaul
Nooverhaulonmaterialsshallbemeasuredorpaid. Thecostofhaulageisdeemed
to be included in tendered rates for supply of materials in accordance with
ConditionsofContractClauseNo.12
106.2 MeasurementofPavementforAreaandVolumeBasedPayment
a. AreaBasis
Add
the
following
paragraph:
Dimensionsusedtodetermineareashallbemeasuredhorizontally.
b. VolumeBasis
Nochange.
106.3 ScopeofRatesforDifferentItemsofWork
Nochange.
106.4 FacilitiesforVerificationofMeasurements
Nochange.
106.5 SelectionofPayItems
Nochange.
106.6 SubDivisionsWithinPayItems
Nochange.
106.7 SubstantialCompletionoftheWorks(Addthefollowing)
The Contractor shall note that the Engineer reserves the right not to certify the
Worksto
be
"substantially
completed"
as
required
by
the
General
Conditions
of
the
-
7/27/2019 Annex III Technical Specifications 105 C1
34/254
SRI LANKA OPERATIONS CENTRE
Contract,unlessthefollowingportionsoftheWorksarecompletedaccordingtothe
Specifications:
(a) all bituminous seal works or, where a seal is not included, the uppermost
gravellayer.
(b) all drains and drainage structures, for the construction of which timeous
instructionsweregivenbytheEngineer.
(c) finishingofallsupportorretainingstructures.
Opening of individual sections or lots shall not entitle the Contractor to receive a
CompletionCertificateunlessthesectionsareseparately identified inthecontractor
qualifiesotherwiseintermsofClause46oftheConditionsofContract.
107. SIEVEDESIGNATIONS
NochangestoStandardSpecifications.
108. CONTRACTORSESTABLISHMENTONSITE
108.1. Office,EquipmentTestingFacilitiesetc.
It is the Contractors responsibility to acquire land for the siting of all his offices,
accommodation,stores,testingfacilities,equipmentyardsandworkshopsandforall
temporary
works
and
for
the
reinstatement
of
such
land
on
completion
of
the
Contracttothesatisfactionoftheowners. TheContractorshallobtaintheapproval
of the Engineer to the siting of offices, accommodation, stores, testing facilities
equipmentyardsandworkshopsbeforesuchlandisacquiredandheshallindemnify
the Employer against all claims and charges in respect of the occupation, use and
reinstatementoftheland.
The Contractor is solely responsible for the satisfactory accommodation of all his
employeesandforcomplyingwithallregulationsandrequirementsinthisrespect.
108.2. LegalrelationsandResponsibilitytothePublic
The Contractor shall take the steps necessary to comply with the terms of the
Conditions of Contract, particularly in respect of the insurances and indemnities
required,andheshallcomplywithallregulationsofstatutoryauthorities.
108.3. Measurement
TheContractorsSiteEstablishmentshallbemeasuredunderthreeitems:
(a)asa lumpsum forEstablishingofall the facilitiesonoradjacenttothe
SitethattheContractordeemsnecessaryforfulfilmentofallhisobligations
under
the
Contract.
These
facilities
shall
include
but
not
be
limited
to:
Transportof plant,buildings, temporary facilities tothesite,Provisionand
-
7/27/2019 Annex III Technical Specifications 105 C1
35/254
SRI LANKA OPERATIONS CENTRE
erection of temporary buildings, office facilities on the site, Provision of
access roads, hard standings etc. within construction camps, Airfares,
temporary accommodation during the mobilisation phase, permits, bonds
etc. necessary to establish expatriate supervisory personnel upon the site,
Establishmentoftestingandprocesscontrolfacilitiesonthesite,Erectionof
contract signboards, Provision of transportation facilities for supervisory,
administrativeandtechnicalpersonnel,Provisionofhousingforsupervisory,
administrativeandtechnicalpersonnel.
The Contractors price for the lump sum shall be a true reflection of the
Contractors costs taking into account the Advanced Payment and the
Contractorshallprovideabreakdownofthe lumpsumwithproofofactual
coststojustifythelumpsumpricetotheEngineer.Paymentformobilisation
shallbemadewhentheContractorhasestablishedhimselfuponthesiteto
thesatisfactionoftheEngineer.
(b)by
month
or
weeks
for
maintaining
the
Contractors
Site
Establishment
foras longasnecessarytoexecuteandcompletetheWorks. Themonthly
rateformaintainingthefacilitiesshallbedeemedto includeforbutnotbe
limitedto:Salaries,leavefares,gratuitiesandmiscellaneousentitlementsof
supervisory personnel, technical personnel, surveyors, administrative
personnel, security personnel, store men etc, Maintenance of offices,
buildings, laboratories and transportation facilities for administrative,
supervisory and technical personnel, Communications, Maintenance of
housingforadministrative,supervisoryandtechnicalpersonnel,Overheads
off site, Financing charges, Compliance with the provisions of the contract
whetherspecifiedorimplied.
This item shall not include for maintenance or depreciation of plant, the
costofwhichshallbedeemedtobeincludedintherelevantworkitem.
(c)Paymentfordemobilisationshallbecompensationinfullforthecostsof
removingplant,equipment, facilitiesandpersonnel fromthesiteandshall
include (but not necessarily be limited to):Transport of plant, buildings,
temporary facilities from the site and export if required, Dismantling and
removal of all temporary facilities on the site, Airfares for repatriation of
expatriate personnel, Removal of contract sign boards, Restoration of all
constructioncamp
areas
to
asatisfactory
condition.
108.4. Payment
Item Unit
108(1) Mobilisation LumpSum
108(2) MaintenanceoftheContractor's
Establishment Month
108(3) Demobilisation LumpSum
-
7/27/2019 Annex III Technical Specifications 105 C1
36/254
SRI LANKA OPERATIONS CENTRE
109. INFORMATIONFURNISHEDBYTHEEMPLOYER
Certain informationcontained intheseContractdocumentsorprovidedseparately
prior to Tender by the Employer is being offered in good faith but the type of
informationsupplied,
no
guarantee
can
be
given
that
any
or
all
of
the
information
is
correctorrepresentativeoftheactualconditions.
TheEmployeracceptsnoliabilityforthecorrectnessorotherwiseoftheinformation
supplied or for the resulting damages, whether direct or consequential, should it
proveduringthecourseoftheContractthatthe informationsupplied iseithernot
correct or not representative. Any reliance which the Contractor places on this
information shall be at his own risk and the Contractor shall be deemed to have
checkedthecorrectnessoftheinformationpriortosubmissionofhisTender.
110. WORKMANSHIPANDQUALITYCONTROL
The Contractor in responsible for producing work which conforms in quality and
accuracyofdetailtotherequirementsoftheContractseesuchclause6ofGeneral
Conditions of Contract and the Contractor shall, at his own expense, institute a
quality control system and provide experienced engineers, foremen, surveyors,
materials technicians,other techniciansand other technicalstaff, togetherwithall
transport, instrumentsandequipment,toensureadequatesupervisionandquality
controloftheWorksatalltimes.
Thecostofallsupervisionandqualitycontrol, includingtesting,carriedoutbythe
Contractor shall be deemed to be included in the rates tendered for the related
items
of
work,
except
where
as
specifically
provided
for
in
the
Contract.
TheContractorsattention isdrawntotheprovisionsofthevarioussectionsofthe
Specificationsregardingtheminimumfrequencyoftestingthatwillberequiredfor
qualitycontrol. TheContractor shall,athis own initiative, increase this frequency
wherenecessarytoensureadequatecontrol.
On completion of every part of the Works and submission to the Engineer for
examination,theContractorshallsubmittotheEngineertheresultsofallrelevant
tests and survey checks that he has carried out indicating compliance with the
Specifications.
For cement, bitumen, mild steel deformed bars, high tensile steel, prestressing
materials, bearings, and similar other materials the Contractor shall furnish the
manufactures test certificates to the Engineer. When required by theEngineer to
carryoutsomeessentialtestsat themanufacturesplantsorat laboratoriesother
thanthesitelaboratory,thecostofsamples,sampling,testingandfurnishingoftest
certificatesshallbebornebytheContractor.
Themethodofsamplingandtestingofmaterialsshallbeasrequiredunderrelevant
clausesstipulatedintheseSpecificationsorasapprovedbytheEngineer.
TheContractorshallberequiredtodemonstratetheadequacyoftheequipmentfor
each
operation
to
establish
its
their
capability
to
achieve
the
requirements
to
the
SpecificationtothesatisfactionoftheEngineerbeforecommencementofthework.
-
7/27/2019 Annex III Technical Specifications 105 C1
37/254
SRI LANKA OPERATIONS CENTRE
All equipment provided shall be of proven efficiency and purpose made for the
requiredoperationandshallbeoperatedbyskilledoperatorsandmaintainedatall
timestoperformitsproperfunctioninamanneracceptabletotheEngineer.
No