annex 1 - epr smokvica - prdejci_eng_final

Upload: vlatkoodgranit

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    1/163

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    2/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    CONTENT:

    1 GENERAL INFORMATION ....................................................................................................... 9

    2 TYPE OF REPORT .................................................................................................................... 9

    3 COMPETENT BODY FOR APPROVAL OF ENVIRONMENTAL PROTECTION REPORTS .. 9

    4 DESCRIPTION OF THE PROJECT IN WHICH THE ACTIVITY IS PERFORMED ................ 104.1 SHORT NON-TECHNICAL SUMMARY OF THE ACTIVITY.............................................................. 10

    4.2 DESCRIPTION OF THE LOCATION........................................................................................... 11

    4.2.1Macrolocation of the area ................................................................................................ 11

    4.2.2Microlocation of the area ................................................................................................. 13

    4.3 TECHNICAL-TECHNOLOGICAL DESCRIPTION OF THE ACTIVITY.................................................. 17

    4.3.1Technical-technological description of the project........................................................... 17

    4.3.2Project activities ............................................................................................................... 20

    4.3.3Equipment, means of transportation and machinery ....................................................... 30

    4.4 RAW AND AUXILIARY MATERIALS........................................................................................... 31

    5 DESCRIPTION OF THE ENVIRONMENT AROUND THE PROJECT AREA ........................ 34

    5.1 GEOLOGICAL CHARACTERISTICS OF THE TERRAIN.................................................................. 345.2 HYDRO-GEOLOGICAL CHARACTERISTICS OF THE TERRAIN...................................................... 35

    5.2.1Categorization of the ground by engineering-geological features ................................... 37

    5.3 GEOMORPHOLOGICAL CHARACTERISTICS.............................................................................. 37

    5.4 PEDOLOGICAL CHARACTERISTICS......................................................................................... 37

    5.5 CHARACTERISTICS OF THE LANDSCAPE................................................................................. 38

    5.6 EXISTING WATER RESOURCES............................................................................................. 39

    5.7 CLIMATIC CHARACTERISTICS OF THE AREA............................................................................ 43

    5.8 EXISTING ROAD AND COMMUNAL INFRASTRUCTURE............................................................... 45

    5.9 BIODIVERSITY...................................................................................................................... 50

    5.10 CADASTRAL DATA IN THE PROJECT SCOPE............................................................................ 53

    5.11 DESCRIPTION OF THE SOCIAL ENVIRONMENT IN THE PROJECT AREA........................................ 535.11.1 Socio-demographic profile ........................................................................................ 53

    5.11.2 Socio-economic profile .............................................................................................. 55

    5.11.3 Urban profile .............................................................................................................. 57

    5.11.4 Socio-cultural profile .................................................................................................. 58

    6 ENVIROMENTAL IMPACT ASSESMENT .............................................................................. 59

    6.1 EMISSION............................................................................................................................ 60

    6.1.1Air emissions ................................................................................................................... 60

    6.2 EMISSIONS ON WATER AND SEWER....................................................................................... 65

    6.2.1Construction phase .......................................................................................................... 65

    6.3 WASTE GENERATION............................................................................................................ 68

    6.3.1Construction phase .......................................................................................................... 686.3.2Operational phase ........................................................................................................... 70

    6.4 EMISSION ON SOIL............................................................................................................... 71

    6.4.1Construction phase .......................................................................................................... 71

    6.4.2Operational phase ........................................................................................................... 71

    6.5 NOISE,VIBRATION AND NON-IONIZING RADIATION................................................................... 72

    6.5.1Noise ................................................................................................................................ 72

    6.5.2Vibration ........................................................................................................................... 75

    6.5.1Non-ionizing radiation ...................................................................................................... 76

    6.6 BIODIVERSITY (FLORA,FAUNA AND HABITATS) ....................................................................... 76

    6.6.1Construction phase .......................................................................................................... 76

    6.6.2Operational phase ........................................................................................................... 776.7 SOCIO-DEMOGRAPHIC IMPACTS............................................................................................ 77

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    3/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    6.7.1Land Acquisition .............................................................................................................. 77

    6.7.2People and Livestock Health and Safety Impact ............................................................. 77

    6.8 SOCIO-ECONOMIC IMPACTS.................................................................................................. 78

    6.8.1Impact on Business and Agricultural Activities ................................................................ 78

    6.8.2Impact on tourism ............................................................................................................ 79

    6.9 INFRASTRUCTURAL IMPACTS................................................................................................ 806.9.1Impact on local residents ................................................................................................. 80

    6.9.2Impact on local road infrastructure .................................................................................. 80

    6.9.3Impact on water supply, sewerage system, irrigation system and other infrastructureobjects ...................................................................................................................................... 80

    6.10 SOCIO-CULTURAL IMPACTS.................................................................................................. 81

    6.10.1 Labour impacts .......................................................................................................... 81

    7 ENVIRONMENTAL PROTECTION PROGRAM ..................................................................... 81

    7.1 MITIGATION MEASURES FOR IMPACTS ON AIR........................................................................ 82

    7.1.1Construction phase .......................................................................................................... 82

    7.1.2Operational phase ........................................................................................................... 83

    7.2 MITIGATION MEASURES FOR IMPACTS ON WATERS AND SEWER............................................... 83

    7.2.1Construction phase .......................................................................................................... 83

    7.2.2Operational phase ........................................................................................................... 84

    7.3 MITIGATION MEASURES FOR REDUCE THE IMPACT OF WASTE.................................................. 84

    7.3.1Construction phase .......................................................................................................... 84

    7.3.2Operational phase ........................................................................................................... 84

    7.4 MITIGATION MEASURES FOR IMPACTS ON SOIL...................................................................... 84

    7.4.1Construction phase .......................................................................................................... 84

    7.4.2Operational phase ........................................................................................................... 85

    7.5 MITIGATION MEASURES FOR REDUCTION OF THE NOISE,VIBRATION,NON -IONIZING RADIATION85

    7.5.1Construction phase .......................................................................................................... 85

    7.5.2Operational phase ........................................................................................................... 86

    7.6 MITIGATION MEASURES FOR IMPACTS ON BIODIVERSITY......................................................... 87

    7.6.1Construction phase .......................................................................................................... 87

    7.6.2Operational phase ........................................................................................................... 87

    7.7 MEASURES FOR MITIGATION OF SOCIAL IMPACTS................................................................... 87

    7.8 RISK MANAGEMENT (OCCURRENCE OF A DISASTER,ACCIDENT OR EMERGENCY) ..................... 89

    7.8.1Construction Phase ......................................................................................................... 89

    7.8.2Operational phase ........................................................................................................... 92

    8 ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN ........................................ 110

    8.1 ENVIRONMENTALMANAGEMENTPLAN-EMP ........................................................... 111

    8.2 ENVIRONMENTALMONITORINGPLAN ....................................................................... 126

    9 SUMMARY AND CONCLUSION ........................................................................................... 133

    10 ANNEXES .............................................................................................................................. 136

    11 STATEMENT .......................................................................................................................... 162

    12 REFERENCES ....................................................................................................................... 163

    TABLES

    Table 1List of materials which will be used during the construction activities ..................................... 32

    Table 2 Demographic data of the project area .................................................................................... 53

    Table 3Number of pupils in Municipality of Gevgelija for 2011/12 school year ................................... 55

    Table 4Unemployment in Gevgelija ..................................................................................................... 55

    Table 5Active enterprises in the Municipality of Gevgelija, by sector of activity ................................. 56

    Table 6Agricultural statistics in the Municipality of Gevgelija .............................................................. 57

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    4/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Table 7Measured concentration of CO2in ambient air........................................................................ 62

    Table 8Measured concentration of dust (PM) in ambient air at measurement point at village Prdejci 63

    Table 9 Measured dust (PM) concentration in ambient air at measurement point at village Smokvica

    .............................................................................................................................................................. 64

    Table 10List of wastes ......................................................................................................................... 68

    Table 11Noise levels from construction equipment ............................................................................. 72

    Table 12 Noise levels from the construction site (15 m from the source) ............................................ 72

    Table 13 Distance of theinhabited place from source of noise............................................................ 73

    Table 14Equivalent noise levels and maximum values measured at village Prdejci and near village

    Smokvica ............................................................................................................................................... 74

    FIGURES

    Figure 1 The location of the Municipality of Gevgelija compared to the other municipalities in the

    Republic of Macedonia .......................................................................................................................... 12

    Figure 2 Position of the A1 motorway (E75) compared to the Municipality of Gevgelija ..................... 12

    Figure 3Part of the surrounding of the section "Smokvica-Prdejci ................................................... 13

    Figure 4Satellite images of the immediate surrounding of the section Smokvica-Prdejci .................. 15

    Figure 5 Satellite image of the wider surrounding of the section Smokvic-Prdejci .............................. 15

    Figure 6Location of the section Prdejci-Smokvica on a topographic map with a scale of 1:25 000 ... 16

    Figure 7 Part of the motorway A1 (75), section Smokvica-Prdejci .................................................... 17

    Figure 8Systems of canals for drainage on the motorway .................................................................. 19

    Figure 9Bridge on river Zuica .............................................................................................................. 19

    Figure 10Bridge on river Kovanska ..................................................................................................... 19

    Figure 11 Underpass at the chainage km 1151+523.00 ...................................................................... 20

    Figure 12Cross section of the motorway drainage system ................................................................. 23

    Figure 13Schematic view of the asphalting and the thickness of the layers ....................................... 24

    Figure 14 The method for traffic redirection and signalisation and equipment during construction of

    the left carriageway ............................................................................................................................... 25

    Figure 15 The method for traffic redirection and signalisation and equipment on the locations where

    the newly designed carriageway overlaps the existing one .................................................................. 26

    Figure 16 The necessary signalisation and equipment on the places when the new carriageway

    passes from the left to the right side ..................................................................................................... 28

    Figure 17 The method for traffic redirection and signalisation and equipment during reconstructionand extension of the existing road ........................................................................................................ 29

    Figure 18 Some of the equipment and machinery that will be used for the extension and

    reconstruction of the carriageway ......................................................................................................... 30

    Figure 19Geological map of the wider area ........................................................................................ 35

    Figure 20 Hydro-geological map of the wider area .............................................................................. 36

    Figure 21Characteristics of the landscape .......................................................................................... 38

    Figure 22 Water-economy areas in the Republic of Macedonia .......................................................... 39

    Figure 23 Rivers in the project area ..................................................................................................... 40

    Figure 24 River Kovanska .................................................................................................................... 41

    Figure 25River Zuica ........................................................................................................................... 42

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    5/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 26Existing and planned hydropowerplants ............................................................................. 43

    Figure 27 Climatic map of the Republic of Macedonia ........................................................................ 44

    Figure 28Rose of winds ....................................................................................................................... 44

    Figure 29 Road network of the Republic of Macedonia ....................................................................... 45

    Figure 30 Railway corridors.................................................................................................................. 46Figure 31 Electricity distribution networks and hydro/thermal power plants in the Republic of

    Macedonia ............................................................................................................................................ 46

    Figure 32System for irrigation South Vardar Valley......................................................................... 47

    Figure 33 The route of the oil pipeline Skopje-Thessaloniki ................................................................ 48

    Figure 34The route of the water supply and sewerage network at village Prdejci.............................. 49

    Figure 35Existing vegetation along the section .................................................................................. 50

    Figure 36Cultivated land ..................................................................................................................... 51

    Figure 37 River Kovanska .................................................................................................................... 51

    Figure 38River Zuica ........................................................................................................................... 52

    Figure 39 Measurement points at villages Prdejci and Smokvica........................................................ 62

    Figure 40 Measurement point at village Smokvica ..................................................................................

    Figure 41Measurement point at village Prdejci ................................................................................... 62

    Figure 42 Intensity of the noise reduction according to the distance from the source ......................... 73

    Figure 43 Measurement points of noise levels at Prdejci and Smokvica ............................................. 74

    GRAPHS

    Graph 1Gender constitution of the population in Municipality of Gevgelija ......................................... 54

    Graph 2Measured concentration of dust in ambient air at measurement point at village Prdejci ....... 63

    Graph 3 Measured concentration of dust (PM) in ambient at measurement point at village Smokvica

    .............................................................................................................................................................. 64

    ANNEXES

    ANNEX 1............................................................................................................................................. 136

    ANNEX 2............................................................................................................................................. 142

    ANNEX 4............................................................................................................................................. 147

    ANNEX 4............................................................................................................................................. 158

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    6/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    TECHNICAL NUMBER 01-111/1

    Based on the concluded Contract between the Environmental Management Associates

    DEKONS EMA LTD, Skopje and PE for National Roads-Skopje, no. 03-82 of 17/05/2013,

    Environmental protection report from realization of the Project-Extension with reconstruction

    of the existing carriageway, left carriageway of the Motorway A1 (E75), Smokvica-Gevgelija,

    section Smokvica-Prdejci, in accordance with Article 24 of the Law on environment (Official

    Gazette of RM" no. 53/05, 81/05, 24/07, 159/08, 83/09, 48/10, 124/10, 51/11 and 123/12)

    has been prepared.

    In accordance with the Decree on the activities for which preparation of elaborate is

    mandatory and competent authority is the body of the state administration responsible for

    the affairs of the environment ("Official Gazette of RM" no. 36/12), the extension with

    reconstruction of the A1 (E75) motorway, Smokvica-Gevgelija belongs in Appendix, XI-

    Infrastructural projects; 15.Reconstruction of Motorways and national roads more than 10

    km1.

    The Report was prepared in accordance with the Opinion no.11-3235/2 from 18.04.2013

    issued by the Department of the Environment, in which the Investor (PE for National Roads)is committed to prepare an Environmental Protection Report.

    Within the project activity, in May 2013, site visit was conducted in order to be made

    prospection of the current state of the location, where the activity will be carried out and to

    identify potential sources of pollution in the environment from their operation.

    The Environmental protection report gives a review of the current state of the investment

    facility-A1 (E75) Motorway, Smokvica-Gevgelija, section Smokvica-Prdejci, identifies the

    potential adverse impacts from the extension and reconstruction of the Motorway in the

    environmental media and proposed measures for their reduction or mitigation.

    1Both sections which are subject of preparation of the Environmental protection reports are covered by one main project and

    are in length of 6,726 km and 3,427 km, or a total of 10,153 km.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    7/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    In the preparation of the Environmental protection report from realization of the Project-

    Extension with reconstruction of the existing carriageway, left carriageway of the Motorway

    A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci for the needs of PE for national

    roads-Skopje, the following team participated:

    DEKONS-EMA

    Manager

    Menka Spirovska

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    8/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    9/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    1 GENERAL INFORMATION

    Name and surname of the legal entity

    or individual that implements

    activities

    Public Enterprise for National Roads (PE for

    National Roads)

    Legal status PENR was founded in 2013 by the Law on

    public roads, as the legal successor of the

    Agency for State Roads

    Ownership PE for state roads is owned by the

    Government of the Republic of Macedonia

    Business office of the legal entity

    (registered in the central register)

    Str.Dame Gruev No.14

    1000 Skopje

    Address where activities are/will be

    implemented

    Municipality Gevgelija,

    Smokvica-Prdejci

    Unique number of the legal entity 6839673

    Identification of core activity

    according to NCA

    64.99

    Category of activity that is the subject of the

    application under the provisions of Article

    24 paragraph (4) and (5)

    Other financial-service activities, except

    insurance and pension funding, not mentioned

    elsewhere

    Number of employees at the facility where

    the activity is performed or activity for

    which the application is submitted

    /

    Total number of employees in the

    legal entity or individual that carries

    on business or activity

    319

    Projected capacity 6,726 km

    Name and surname of contact person

    responsible for the approval of the study

    and his position

    Joze Jovanovski, Environmental engineer,

    Environmental protection consultant

    Telephone number - contact 02/ 3118-044 lok.135

    Fax: 02/ 3220-535

    2 TYPE OF REPORT

    New activity

    Existing activity

    Expansion of existing activity

    3 COMPETENT BODY FOR APPROVAL OF ENVIRONMENTAL PROTECTION

    REPORTS

    Body name Ministry of Environment and Physical Planning- Department ofEnvironment

    Adress Goce Delcev bvd No. 8, building MRTV 10thfloor,1000 Skopje

    Telephone 02/3251-400

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    10/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    4 DESCRIPTION OF THE PROJECT IN WHICH THE ACTIVITY IS PERFORMED

    4.1 Short non-technical summary of the activity

    The Project activity is implemented by PE for National Roads. In chapter10 (Annexes) of

    this Report, the Certificate from the Central Register is presented, i.e. the current status ofthe company.

    The Project envisages extension with reconstruction of the existing carriageway, left

    carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci.

    Accordingly, one more lane of the already existing five lanes Motorway will be constructed,

    in order to get full motorway with six lanes in both directions (three lanes in direction).

    With the construction of this section, the connectivity between Macedonia and Greece will be

    greatly improved and finally, the completion of the motorway A1 (Pan European Corridor 10)

    in the Republic of Macedonia will be enabled, on level of complete Motorway with 6 lanes,

    parallel with finalizing of the project for construction of the section Demir Kapija-Smokvica.

    All of this will contribute to improving of the economy, the economic development will be

    accelerated, safety and, in general, the quality of life of the people, not only in this part of the

    country, but also wider.

    The land on which the extension of the section is planned is state owned, which means that

    the planned extension will not usurp fertile agricultural land, because the extension will be

    carried out in the green area between the two carriageways, for which there is a projected

    space.

    In accordance with the Decree on the activities for which preparation of elaborate2

    ismandatory and competent authority is the body of the state administration responsible for

    the affairs of the environment ("Official Gazette of RM" no. 36/12), the extension with

    reconstruction of the A1 (E75) motorway, Smokvica-Gevgelia belongs in Appendix, XI-

    Infrastructural projects; 15.Reconstruction of Motorways and national roads more than 10

    km3.

    For performing of these activities a detailed design dating from 1999 was made. The data

    from the project are base on which the preparation of this document is based.

    The section Smokvica-Prdejci starts from the junction at the village Smokvica and continues

    moving by the agriculture land, nearly parallel with the river Vardar on its right side and ends

    south of the village Prdejci. The total length of the section is 6,726 km, starting from

    chainage km 1145+073.20 to chainage km 1151+799.61. In the preparatory phase, before

    starting of the construction works, samples will be taken and an analysis of the existing

    materials from which the Motorway is constructed will be conducted, taking into account the

    thickness of the asphalt layer, the protective layer against sliding on the road, the thickness

    of granulation tampon layer that is applied under the asphalt, reinforced concrete structural

    base of the underpass and bridges on rivers Kovanska and Zuica. This will provide data on

    2Enviromental protection report3Both sections which are subject of preparation of the Environmental protection reports are covered by one main project and

    are in length of 6,726 km and 3,427 km, or a total of 10,153 km.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    11/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    the current state of the section and materials which will be used for construction of a new

    lane, new bridges on rivers Kovanska and Zuica, the new underpass on chainage km 1151

    +523.00, as well as the reconstruction of the existing lanes of the carriageway.

    The Project envisages major construction activities on the underpass, which is in poor

    condition, i.e. it will be demolished and in its place a new underpass will be constructed and

    new fence, type "New Jersey". But despite this, all overpasses, underpasses, culverts, pipes

    for drainage and irrigation passing under and near the Motorway. They will be repaired or

    reconstructed.

    During the analysis of the submitted documentation, several inadequacies were identified,

    i.e. lack of a final design for the section Smokvica-Prdejci, no detailed information available

    for extension and reconstruction of the existing carriageway, left carriageway of the section

    Smokvica-Prdejci, lacking a clear quantification of materials which will be used, precise

    locations of the borrow pits, asphalt and concrete base, landfills, characteristics and type of

    machinery and equipment which will be used in the construction phase, number of workers

    and workdays, accurate quantities of waste, lack of monitoring stations for monitoring of air

    quality in the vicinity of the project section resulting in a more general definition of emissions

    and potential impacts of pollutants on the environment.

    During the site visit, conducted on 30.05.2013 by the expert team, the locations of the

    constituent elements of the Motorway along the section were determined.

    4.2 Description of the location

    4.2.1 Macrolocation of the area

    The reconstruction and extension of the Motorway A1 (E75), south of the intersection near

    the village Smokvica to the south of the intersection near the village Prdejci (left

    carriageway), belongs to the municipality of Gevgelija.

    The Municipality of Gevgelija is one of the largest municipalities in the Republic of

    Macedonia and it is located in the southern part of the country, along the valley of the river

    Vardar and Motorway E-75 (Trans-European Corridor 10). On the north and on the east it is

    bounded by the municipalities of Valandovo and Bogdanci, on the west by the municipalities

    of Demir Kapija and Kavadarci and on the south with Machukovo (Evzoni) in Greece.

    According to the latest administrative division from 2004, the former Municipality of Miravci is

    annexed to the Municipality of Gevgelija. Municipality of Gevgelija covers an area of 48.5 ha

    or 485 km2, with 17 settlements: Gevgelia, Bogorodica, Gabrovo, Davididovo, Kovanec,

    Konsko, Miletkovo, Miravci, Moin, Mrzenci, Negorci, Novo Konsko, Petrovo, Prdejci,

    Smokvica, Sermenin and Huma. The municipality is geographically important "bridge for

    connection" between Central and Eastern Europe, southern part of Europe and the Middle

    East.

    Section Smokvica-Prdejci starts from the junction at the village Smokvica and continues

    moving by the cultivable areas, nearly parallel with the river Vardar on its right side and ends

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    12/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    south of the village Prdejci. The total length of the section is 6,726 km, starting from

    chainage km 1145+073.20 to chainage km 1151+799.61.

    Viewed in the direction from village Smokvica towards the village Prdecji, from the starting

    point of the five-lane Motorway, the right carriage has 3 lanes and the left one has left lanes.

    It means that the extension will be with one lane on the left carriageway in the green belt in

    towards the right carriage. Then, in the total the length of about 1.5 km south of the village

    Prdejci, the Motorway is complete with 6 lanes and on that part of the Motorway, no

    construction works will be performed.

    The location of the Municipality of Gevgelija compared to the other municipalities of the

    Republic of Macedonia is presented on the following figure.

    Figure 1 The location of the Municipality of Gevgelija compared to the other municipalities in the

    Republic of Macedonia

    The following figure shows the position of the A1 Motorway (E75) compared to the

    Municipality of Gevgelija.

    Figure 2 Position of the A1 motorway (E75) compared to the Municipality of Gevgelija

    Municipality of

    Gevgelija

    Motorway1 (75)

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    13/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    4.2.2 Microlocation of the area

    The envisaged project activities "Extension with reconstruction of the existing carriageway,

    left carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci"

    will be performed at the location of the existing Motorway section "Smokvica-Predejci". The

    Motorway section passes near the settlements Smokvica and Prdejci, at the closest distance

    of about 100-150 m.

    There are not any registered facilities that perform medical, social and educational activities

    in the vicinity of project area.

    Geomorphologicaly, the field of the locations is plain, which is part of Gevgelija field. On the

    north and on the east are the transitions of the plain part and the rocky masses from Triassic

    and Jurassic age. The terrain is characterized by disaggregated morphology.

    The project area is a landscape unit under strong anthropogenic influence. It is flat and fertile

    area where intensive agricultural activities are performed. Characteristic feature of this

    landscape unit is the presence of human settlements and commercial complexes.

    The project area is located in the basin of the lower course of the river Vardar and is situated

    along its course.

    The river Vardar is the most important watercourse in the Republic of Macedonia and covers

    about 83% of the catchment area of the counrty. In the project area, thee river Vardar drains

    the surface and groundwaters. Along the river Vardar, which is located in the distant

    surroundings of the Motorway route, the project area includes rivers Zuica and Kovanska,

    which are its tributaries. Near the village Smokvica there are rich sources of thermomineral

    water.The industrial zone "Biloto" is in the immediate vicinity of the project area, for which Urban

    Plan outside Settlement is already made and whose construction will start soon. Also, there

    are two gas stations operating near the village Smokvic.

    The route of the pipeline Skopje-Thessaloniki is passing south of the village Prdejci. Also,

    near the village Prdejci, part of the irrigation system "South Vardar Valley" is passing, which

    is used for irrigation of the agricultural land in the area of Prdejci-Negorci. The route passes

    near the pipeline for water supply of the village Smokvica.

    Figure 3 Part of the surrounding of the section "Smokvica-Prdejci

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    14/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    The immediate and wider surroundings of the Motorway section "Smokvica-Prdejci is shown

    on the next "Google" images.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    15/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 4 Satellite images of the immediate surrounding of the section Smokvica-Prdejci

    Figure 5 Satellite image of the wider surrounding of the section Smokvic-Prdejci

    The location of the section Prdejci-Smokvica on a topographic map with a scale of 1:25 000

    is presented in the next figure:

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    16/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 6 Location of the section Prdejci-Smokvica on a topographic map with a scale of 1:25 000

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    17/163

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    18/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    conducted, taking into account the thickness of the asphalt layer, the protective layer against

    sliding on the road, the thickness of granulation chorused stone layer that is applied under

    the asphalt, reinforced concrete structural base of the underpass and bridges on rivers

    Kovanska and Zuica. This will provide data on the current state of the section and materials

    which will be used for construction of a new lane, new bridges on rivers Kovanska andZuica, the new underpass on chainage km 1151+523.00, as well as the reconstruction of the

    existing lanes of the carriageway

    The Project envisages major construction activities on the underpass, which is in poor

    condition, i.e. it will be demolished and in its place a new underpass will be constructed and

    new fence, type "New Jersey". But despite this, all overpasses, underpasses, culverts, pipes

    for drainage and irrigation passing under and near the Motorway. They will be repaired or

    reconstructed.

    During the site visit, conducted on 30.05.2013 by the expert team, the locations of the

    constituent elements of the Motorway along the section were determined.

    Structures found along the route of the motorway section Smokvic-Prdejci, on which major

    construction works will be conducted are the bridge on the river Kovanska, located before

    the overpass at the village Prdejci on the chainage km 1150+546.00, as well as the bridge

    on the river Zuica at the chainage km 1148+774.51, consisting of two carriage lanes with an

    average width of 12.9 m for each lane, built as a flat plate with three connections to the

    motorway, with wing walls and upgrades, surrounded by specific fence. They are

    constructed transversely to the river bed without additional regulation of the river beds, but it

    is considered that it is not necessary, because the rivers in most of the year are dried.

    Due to the dilapidation of the bridges and the weak structure, unsuitable for the planned

    extension and reconstruction, they will be demolished and in their place new bridges with

    three lanes in addition of the motorway will be built. The fence of the bridges called "New

    Jersey" will be demolished and re-assembled. The demolition of the the bridges will be

    performed by using heavy machinery, excavators and drillers, without using explosives.

    Then, additional excavation of about 13.000 m3of earth will be performed, in order to make

    the space from the river beds that are required for setting the foundations for the new

    bridges. After that, the concrete and reinforced concrete works with a total volume of 2.000

    m3 of concrete and iron reinformcement weighing 32 t will be conducted. In addition, the

    preparatory works, placement of the crushed stone and asphalting will continue in the same

    manner as at the motorway, with the only difference in the asphalt layer, which at the bridges

    has a thickness of 8 cm. This would include an extension of the drainage system, building of

    the structure and laying the pipes on the motorway, construction of sidewalks and fencing of

    the bridges. At the end, testing of the new bridges in terms of load, weight load of the

    structure and surface friction load on the bridge will be performed.

    The systems for drainage of storm water that are collected on the motorway during rain are

    set in the middle of the central reservation in the form of a network of canals, collection

    sumps, pipes for conveying water and storm water culverts, through which without no

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    19/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    previous treatment water is discharged in the vicinity and in the beds of the rivers Kovanska

    and Zuica. The following figures show the layout of the drainage systems on the motorway.

    Figure 8 Systems of canals for drainage on the motorway

    In the middle of the central reservation, cement canals with a width of 50 cm are built, which

    collect water and brings it to a collective manhole on every hundred meters. Drainage

    systems are currently in poor condition due to the dilapidation and irregular maintenance,

    part of the manholes and pipes are clogged by debris from vegetation (leaves, grass and

    soil) that flow in the canals, therefore there is flooding of the motorway during the heavy

    rains.

    Figure 9 Bridge on river Zuica

    Figure 10 Bridge on river Kovanska

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    20/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 11 Underpass at the chainage km 1151+523.00

    4.3.2 Project activities

    The planned activities are extension with reconstruction of the existing carriageway of the

    Motorway A1 (E75) Smokvica-Gevgelija, i.e. extension of the left carriageway of the section

    Smokvica-Prdejci and right carriageway of the section Negorci-Gevgelija, with special

    reference to the above mentioned existing structures on and around the motorway. The

    reconstruction includes set of preparatory works that will ensure uninterrupted operations

    and that in terms of protecting the environment and the occupational health and safety of the

    workers and the traffic participants are of great importance.

    4.3.2.1 Preparatory works

    Marking and securing of the alignment-before the commencement of the civil works

    envisaged in the main design, the first thing that needs to be done is marking and securing

    of the alignments of the envisaged roads with all signs for traffic safety, adjustment of the

    speed of to the road conditions and traffic diversion.

    Clearing of the alignment of from roots, trees and shrubs-because the road extension will

    take place in the central reservation through the middle of the motorway, clearing along the

    green central reservation in length of 6.726 km will be made. Then, the protective fencing

    and plants along the construction site will be removed. Because it is vegetation consisting of

    plants, grass, stubs and oleanders along the central reservation, there is no need for using

    heavy machinery for clearing the ground, except hand saws, trimmers and scythes, rakes

    and other hand tools.

    Demolition of existing structures along the section-this work includes excavation and

    dismounting of traffic signs, gutters, concrete channels (in length of 318 m), man holes,

    demolition of bricks, stone or concrete walls (in amount of 80 m3), demolition of the existing

    carriageway constructions, removal of kerbs, demolition of fences, buildings, existing flat

    culverts, pipe culverts and their entry and exit heads and/or any other obstacles that could in

    any way impede the construction.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    21/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    4.3.2.2 Substructure

    Scraping of the existing asphalt-to provide comprehensive reconstruction and merging the

    new with the existing carriageway lanes and correction of the damage that occured with the

    continuous attrition and weathering, the surface layer of the asphalt along the project section

    will be removed, with a thickness of 0-3 cm, 3-6 cm, >6 cm, determined by the construction

    experts, with a total area of 15.428 m2.

    Excavation of humus-this work encompasses the surface excavation of the humus

    performed during the wide excavation of the alignment for the extension with the third lane in

    total amount of 33.416 m3. Next, excavation of earth in a wide ditch in amount of 98.641 m3

    will be made and compression of the formed broad plateau. After that, the surface and the

    substructure with an area of about 155.398 m2 will be performed, with construction of

    enhanced base from earth of about 68.642,5 m3. Once all of the construction works will be

    completed, the central reservation will be restored and the excavated humus and soil will be

    reused for filling the holes and damages in the project area and disposal of the waste

    generated during earth works.

    Subgrade-is a natural layer of soil on which the foundations of the embankments will be

    placed. Works for construction of the subrage include compaction, possible excavation for

    drying or suppression of the natural soil layer for gaining a thickness determined by the

    design of about 30 cm. If the composition of the soil-subgrade is such that it prevents the

    fulfillment of the criteria established with standards (saturated soil, mud, soil with organic

    materials etc.) it will be necessary to prepare the subgrade which would be consistent with

    the design criteria.

    Embankment construction-for the embankment construction non-organic material with the

    prescribed quality will be used. The embankments can contain organic rubble, roots, bushes,

    or material that over time due to biochemical action, will change its mechanical and physical

    characteristics. The material for the construction of an embankment can be obtained from

    the cuts of the alignment or supply locations. The regulations controlling the quality of the

    material used for embankment construction is given in the standards (MKS U.B1.010/79,

    MKS U.B1.012/79, MKS U.B1.014/88 etc.). When examining the suitability of materials for

    embankment construction, examinations will be made of every cut and supply location, as

    well as when changing the material. The experiments should be done on a minimum of 2

    samples for each type of material.

    Nails near the structures-are constructed to eliminate deformations of the carriageway on

    the joints between the embankment and the structure. The nail construction will be made in

    one of the following manners: a) if the structure is finished before the embankment, then the

    nail should be constructed in parallel b) If the structure is not finished and the embankment

    is being constructed, then the nail should be constructed as near as possible to the structure

    so that the subgrade could consolidate faster.

    Level of the substructure-this works includes levelling of the substructure in the cuts,

    embankments with rough and fine levelling and compacting. The works have to beperformed to the elevation envisaged in the design along the whole width of the level and in

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    22/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    accordance with the standards. The same applies to the materials for the construction of the

    final layer of the embankment.

    Planning and distribution of the rest of the humus-this position will utilize the humus

    material that had been previously taken to a temporary landfill. The construction of the

    grassing and vegetative protection will be made immediately after the completion of the

    embankment or the cut. The humus should be placed, leveled and compacted on a

    previously arranged surface with a specific thickness determined by the design.

    Excavation-the excavation of the canals will be performed before the commencement of

    embankment works. The excavation will be made precisely according to the design details.

    All excavation surfaces at the bottom or at the slopes will be constructed smoothly with the

    proper slopes as to avoid the retention of water or the erosion of earth. The entire excavated

    material will be used for embankments or other individual works, or it will be transported in

    landfills determined by the Municipality.

    Draining of the body of the road-Reconstruction of drainage system for storm water will be

    carried out in accordance with the details of the Detailed design. In order to follow the

    existing drainage system for storm water, reconstruction and rehabilitation of the drainage

    system in the central reservation will be made in the new situation along the section. The

    system of drainage canals with a total length of 972 m will be restored, because the old

    canals are closed and clogged from different types of waste and the surrounding vegetation

    and allocation to the interior of the central reservation the moving of the carriageway will be

    performed. The pipes for drainage of storm water will be reconditioned and new concrete

    manholes will be constructed for conveying the water to the culverts along the motorway.

    The drainage system will be constructed of materials with the same quality and features as

    the already renovated drainage system where construction has been completed. The system

    will be consisted of collecting canals that will go in the middle of the central reservation in

    width of 50 cm. Around them, the earth will make natural filtration and the water will be able

    to dive to the layer of crushed stone, which is with larger granulation of the grains, and will

    serve as a filter material so the water can easily f low to the pickup polyethylene pipe, with an

    average diameter of 250 mm, perforated on the upper side. In this way, the storm water will

    be successfully collected and drained. The tube will be placed in the appropriate base canal

    with a width of about 100-130 cm, which at the bottom will be placed in sand with thickness

    of 5 cm. Imperforated half of the pipe will then be incorporated into the concrete MB-20 to

    provide a solid structure to further protect the system from external influences such as

    vibrations, various pests etc. The following figure shows the cross section of the motorway

    drainage system.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    23/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 12 Cross section of the motorway drainage system

    4.3.2.3 Superstructure

    Construction of sub-base layer of buffer-after completion of the construction works and

    preparation of surface, the layer of crushed stone-feldspad with thickness of 35 cm will be

    placed, with different grain size, which will serve as a basis for compaction in total amount of

    40.000 m3which will prevent collapsing of the motorway.

    Construction of a bitumen bearing layer-then, over the tampon layer a layer of bituminous

    mixture, BNS 32 YA with thickness of 13 cm on an area of about 106.000 m2

    will be applied.The modern top supportive bases made of bitumen granulated stone material, produced in

    an asphalt base using Czech procedure, are defined with the standard MKS U.E9.021/86.

    The production and implementation if the asphalt mixes BNS is done during favourable

    climactic conditions, without rainfalls and when the surface temperature and the air

    temperature (without wind) is above +5C. Standard stone aggregates, send, connective

    substance-bitumen and filler are used as basic materials for the production of asphalt mixes

    for BNS.

    Construction of final layer of asphalt concrete-over the bituminous layer, after fine

    compaction, asphalt layer in thickness of 6 cm will be layed, which will be further physicaly

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    24/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    processed against wethering during usage. The asphalt concrete4will be applied as final

    wear courses on the carriageway constructions. The construction of asphalt concretes

    includes: supply of standard stone pebbles, connective substance (bitumen), production,

    transport and implementation of the asphalt concrete mix in the final layer of the carriageway

    construction.

    The following figure shows the schematic procedure of application of all layers of the

    superstructure and bringing it to the final stage of the motorway.

    Figure 13 Schematic view of the asphalting and the thickness of the layers

    After completing the procedures for coating the road, the road will be marked, carriageway

    lanes will be drawn and the protective metal or concrete embankments and fences will be

    placed, on the places where it is required by the project, which would secure the road from

    illegal crossing of the surrounding people or animals and protection from possible slidings

    from the road vehicles moving at inappropriate speeds and/or during worsened road

    conditions.

    4.3.2.4 Temporary diversion including traffic management

    The reconstruction and extension of the motorway A1 (E75) will be done in phases:

    1. During the construction of the left carriageway of the motorway, the traffic will flowcontinuously but with a reduced speed due to the presence of machinery. Themethod for traffic redirection and signalisation and equipment is given on thefollowing figure.

    4The production and implementation are defined with MKS U.E4.014/90.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    25/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    Figure 14 The method for traffic redirection and signalisation and equipment during construction of

    the left carriageway

    2. On the locations where the newly designed carriageway overlaps the existing one, the

    existing road will be extended from the left and right side. If the existing road is

    extended at the same time when the new carriageway is being built, the construction

    site will encompass a part of the carriageway (about 1.2 m) and so the free driving

    surface will be 6.5 m wide. The traffic here will be two way with a speed limit of 60

    km/h. The maximal length of the site will be 0.5 km. The method for traffic redirection

    and signalisation and equipment is given on the following figure.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    26/163

    Environmental Protection Report from realization of the Project-Extension with reconstruction of the existing carriageway, left carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, sectionSmokvica-Prdejci

    26

    Figure 15 The method for traffic redirection and signalisation and equipmenton the locations where the newly designed carriageway overlapsthe existing one

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    27/163

    Environmental Protection Report from realization of the Project-Extension with reconstruction of the existing carriageway,left carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    3. When the new carriageway passes from the left to the right side, the construction

    site encompasess half of the existing carriageway. On the free driving surface with

    a width of 3.5 m the traffic will be one way and the other way will flow when the

    one way is being stopped. The regulation will be manual. The allowed speed is 40

    km/h. The length of the construction site is 200 m. The necessary signalisationand equipment is given on the next figure.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    28/163

    Environmental Protection Report from realization of the Project-Extension with reconstruction of the existing carriageway, left carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, sectionSmokvica-Prdejci

    28

    Figure 16 The necessary signalisation and equipment on the places when the new carriageway passes from the left to the right side

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    29/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    29

    4. After the construction of the new carriageway the existing road will be rehabilitated and

    extended. The traffic, before the start of of the construction site, will be redirected along

    the new carriageway. The new carriageway is with a width of 11.0 m or two driving lanes

    and a stopping lane and a speed limit of 120 km/h. The traffic will flow in two directions

    with a speed limit if 60 km/h. The method for traffic redirection and signalisation and

    equipment is given on the next figure.

    Figure 17 The method for traffic redirection and signalisation and equipment during reconstruction and

    extension of the existing road

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    30/163

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    31/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    31

    4.4 Raw and auxiliary materials

    For the construction of all envisaged activities, new materials will be needed.

    In the Main project, which is the basis for the preparation of the Environmental Protection Report,

    the type and quantity of the materials which will be used in the construction phase, the source for

    supply and the location (as borrow pits, concrete base, facilities for crushing the aggregate, fuel

    stations, water supply, asphalt, etc.), temporary storage and management of the project area etc.

    are not precisely defined5.

    Also, there is no data in the Main project related to the use of labor, accommodation of the

    workers and working conditions, in particular the number of employees, location of camps for

    workers, working days/shifts, hours, water for sanitation, waste water management, waste

    management, etc. The need for labor will be determined based on the preliminary data for

    construction/rehabilitation, assessment of the intensity of the work and the available labor in the

    companies engaged.

    The transport of the excavated material will be performed by road, using the existing roads. For

    reconstruction of the existing carriageway, the same way of transport for the construction

    materials will be used.

    In the main project, also, the place for disposing of the waste material is not defined6.

    All the above missing data in the Main project will be provided by the Contractor engaged to

    carry out the construction works on the basis of a tender.

    Some data available in the basic project related to the types of building materials, anticipated

    amounts and supply are presented in the following table.

    5

    All the above data missing in Main project will be provided in the Detailed design, prepared by a contractor, engaged to carry outconstruction work on the basis of activities defined in the tender documentation.

    The final Design will define the type of materials, quantity, location of the borrow pits for materials, concrete and asphalt base, a way

    of delivery and transportation etc. If there is a need for setting a concrete and asphalt base and also it is form borrow pits for materials

    only for the project within the project area, in that case the Contractor will prepare appropriate documentation to protect the

    environment upon which he will obtain pemit for working.

    6The

    locations for disposal of the waste generated in the construction phase will be defined in the Final design.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    32/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    32

    Table 1 List of materials which will be used during the construction activities

    Type of construction and

    additional materials

    Source Quantity Unit Storage area Remarks

    Asphalt Asphalt base Not defined in this

    phase

    m3 Not defined in this

    phase

    The data will be

    provided by the

    Contractor7

    Sand and gravel Provider -//- m3 -//- -//-

    Cement Provider -//- m3 -//- -//-

    Concrete Concrete

    base

    -//- m3 -//- -//-

    Metal Provider -//- m3 -//- -//-

    Plastic Provider-//-

    m3 -//- -//-

    Insulating materials Provider-//-

    m -//- -//-

    Welding materials Provider-//-

    m -//- -//-

    Electronic devices Provider-//-

    m -//- -//-

    Paints and coatings Provider-//-

    m3 -//- -//-

    Oil Provider-//-

    m3 -//- -//-

    Water Provider-//-

    m3 -//- -//-

    Water supply will be made with bottled water and by using tanks to carry water to meet the

    sanitary needs of workers.

    The required amount of water depends on the workload and the weather conditions, and thatswhy it cannot be accurately determines the consumption of drinking water and water for

    sanitation needs. Also, water will be required for spraying the access roads and washing the

    machines. The required amounts of technical water cannot be determined at this stage.

    The working activities on the local road will be carried out only during the day so as not to use

    electricity for lighting of the section.

    The construction machinery will use diesel as fuel, in amounts that will depend on the dynamics

    of the construction activities

    As auxiliary materials for the extension and reconstruction of the section will be used:

    Fuel;

    Motor oil for the mechanization;

    Lubricating oils for the mechanization etc.

    7Contractors will be obligated to prepare Project for executing of the works, which will define the quality, sources of supply of raw

    materials, management etc.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    33/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    33

    The total amount of these auxiliary materials cannot be determined and will depend on the pace

    and workload.

    Other auxiliary materials that will be used during the extension and reconstruction are: pipes,

    tires, spare parts for the machinery etc. Their volume cannot be accurately determined at this

    stage.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    34/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    34

    5 DESCRIPTION OF THE ENVIRONMENT AROUND THE PROJECT AREA

    The planned project activities "Extension with reconstruction of the existing carriageway, left

    carriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci" will be

    performed at the location of the existing motorway section "Smokvica-Predejci". The motorway

    section passes near the settlements Smokvica and Prdejci, and the closest housing facilitiesand commercial buildings are located at about 100-150 m from the project area (motorway) in

    the village Prdejci and at least 400 m in the village Smokvica.

    Along the motorway alignment industrial buildings are registered, a quarry near the village

    Prdejci, agricultural plantations, greenhouses and fallow land.

    Near the project area there are no registered facilities that perform medical, social and

    educational activities.

    5.1 Geological characteristics of the terrain

    The geology of the wider area generally is represented by:

    Unbounded rocky masses

    The part of the quarterly-alluvial sediments belongs to this group: sands and gravels, diverse

    granulate with singles.

    Half-bounded rocky masses

    Clayey and dusty materials from the quarterly-alluvial sediments belong to this group. They are

    characterized by lower representation in the narrower and the wider area.

    Tied petrified rocky masses

    The parent rocky masses that are from Triassic and Jurassic age belong to this group. These

    are quarterly-alluvial sediments and have good physical and mechanical properties with good

    bearing characteristics.

    In most of the motorway route and beyond, parent rock mass are the diabases, which build up

    the largest component of Paleorelief and alluvial sediments along the river Vardar. The

    diabases are characterized by good physical and mechanical properties, and good bearing

    characteristics.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    35/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    35

    Figure 19Geological map of the wider area

    5.2 Hydro-geological characteristics of the terrain

    Represented lithological units, according to their hydrogeological function can be divided into:

    hydrogeological collectors, hydrogeological conductors and hydrogeological insulators.

    According to the hydrodynamic characteristics and the conditions that are dominant in this type

    of aquifers area, a compact formations with free level of groundwater was developed.

    Aquifer is formed in the terraces of river Vardar and it nourishes from the rainfall, and also has

    direct transmissibility of river Vardar. As for the groundwater level, it ranges from 4.0 m to 10.0

    m and has small fluctuations. According to yield, the ground belongs to the group of fields with

    good yield.

    Because of the unbounded lithological units registered with depths over 10 m and their

    collection characteristics, hydrogeological parameters of the groundwater are with high values.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    36/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    36

    Hydro-geological collectors

    Sands and gravels belong to this group , which have a coefficient of filtration from n x 10 -2m/s to

    n x 10-5m/s.

    They developed well with free groundwater level and it is compact type.

    Hydro-geological conductors

    Clayey and dusty materials belong to this group, with a coefficient of filtration from n x 10-5m/s

    to n x 10-7 m/s.

    Hydro-geological insulators

    Dusts and clays belong to this group, which are featured with good density and plasticity and

    firmly bound petrified rock masses-diabases and they are with waterproof barrier and have

    insulating capabilities. The coefficient ranges from n x 10-7m/s to n x 10-9m/s.

    With the construction activities, the hydraulic characteristics of the environment will not bechanged.

    Figure 20Hydro-geological map of the wider area

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    37/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    37

    5.2.1 Categorization of the ground by engineering-geological features

    Based on the characteristics presented in the field of geological engineering-geological and

    hydro-geological characteristics of the terrain, it belongs to the following categories, according

    to construction standards, G.N.200:

    Part of the sandy-gravel materials with clay binder of Alluvial and Proluvial sediments,

    they belong to category III, mining can be done manually or with easy machinery.

    Part of tightly bound petrified rocky masses-diabases that are base of the ground,

    belong to category VI and VII. Partitioning is performed by machines but only in surface

    areas with explosives into the deeper parts.

    5.3 Geomorphological characteristics

    The field, geo-morphologically is a plane, which is part of Gevgelija field. On the north and on

    the east is the plain of transitions and rocky masses from Triassic and Jurassic age. The terrain

    is characterized by disaggregated morphology.

    Most of the alluvial layers is located on the western peripheral parts on the valley of the rivers

    Sermeninska, Kovanska, Zuica and Stara, which are characteristic for the tributaries of the right

    bank of the river Vardar. On both sides of the river Vardar, in the lowest parts of the valley has a

    large area covered with tiered storage material.

    Tectonic units of the field is mostly associated with Alpine and Hercins orogenesis. The field

    belongs to the Vardar geotectonic unit, where there are no registered tectonic appearances and

    processes.

    5.4 Pedological characteristics

    The presence and distribution of the soil types in the area of the motorway corridor is given

    according to "Soils of the Republic of Macedonia" (Filipovich 1997-2004). Along the river Vardar

    alluvial soils are distributed in the middle part of the valley which extends to 100 m above the

    sea level. The layers of this soil are well aligned. They are water permeable and have good

    capacity for water permeability. Alluvial soils containing low concentration of humus (below 1%).

    There are many types of alluvial soil depending on certain special features. Such variations are

    alluvial fine sorted carbonates, shallow alluvial soil of gravel material, alluvial soil etc. The most

    common are sorted fine alluvial soils, alluvial covered soil.

    Anthropogenic soils are distributed in the agricultural area of the motorway, because their

    genesis is exclusively associated with anthropogenic activities.

    The rigosolites are soil that is formed by human intervention in vineyards and orchards.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    38/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    38

    5.5 Characteristics of the landscape

    The project area is a landscape unit under strong anthropogenic influence. It is flat and fertile

    area where are performed intensive agricultural activities. Characteristic feature of this

    landscape unit is the presence of human settlements and commercial complexes.

    Figure 21Characteristics of the landscape

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    39/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    39

    5.6 Existing Water Resources

    The project area (motorway section Smokvica-Predejci) is located in the watershed of the lower

    course of the river Vardar and it is situated along the river. The river Vardar is the most

    important watercourse that drains surface and groundwater.

    Figure 22Water-economy areas in the Republic of Macedonia

    Along the river Vardar, which is located in the distant surroundings of the motorway section

    (least distance of 400 m), the project area includes rivers Zuica and Kovanska, which are

    flowing into the river Vardar.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    40/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, left carriageway of the Motorway A1 (E75), Smokvica-

    Gevgelija, section Smokvica-Prdejci

    40

    Figure 23Rivers in the project area

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    41/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    41

    River flow of the river Vardar varies throughout the year. The average existing water quality in

    water measuring station (Gevgelia) is 170 m3/s, maximum is 2400 m3/s and the minimum is 14.4

    m3/s. Yet this amount of water is the largest in the country.

    The river Vardar, in the section from Udovo to Gevgelia has the characteristics of a typical

    planar river. The average inclination of the riverbed in Smokvica is 1.19 , and in GevgelijaValley - 0.72 .

    In terms of water quality, defined in accordance with the Regulation on the categorization of

    streams, lakes, accumulations and groundwater ("Official Gazette of RM" no. 18/99), the river

    Vardar from the estuary of river Crna to the border with Greece belongs in category II and III.

    River Kovanska is a right tributary of the river Vardar, which spring is in the place called Flora

    on Kozuf at an altitude of 1.700 m. From the start it is flowing on the northeast, then near Visoki

    Kamen turns and runs to the southeast and is flowing into river Vardar near the village Prdejci

    on an elevation of 53 m. It is 24 km long, with a catchment area of 62 km2and a relative decline

    of 69 .

    Figure 24River Kovanska

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    42/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    42

    Catchment area of the river Zuica is 27.53 km2, while the length of the basin is 10.71 km. The

    source of the river is located at an altitude of 450 m, while downstream is flowing at an altitude

    of 705 m, and the height of the bridge, which will be reconstructed is 63 m asl. The slope of the

    flow is 30.52 , and the slope of the basin 59.94 .

    The river Zuica receives a number of smaller rivers, which means that the catchment area of theriver has developed hydrological network.

    Figure 25River Zuica

    Water quality of the rivers Kovanska and Zuica is not defined in the Regulation on

    categorization of streams, lakes, accumulations and groundwater ("Official Gazette of RM" no.

    18/99).

    Near the village Smokvica there are rich sources of thermo-mineral water.

    The City of Gevgelia is supplied with water from groundwater wells, with capturing of two sites,

    from the well within the factory Zora and the wells near the motorway or river Vardar.

    The wells for water supply of Gevgelia are not located near the project area.

    In accordance with the Spatial Plan of the Republic of Macedonia, 2004 and the National Water

    Strategy 2012-2040, adopted in 2012 in the wider environment of the project area construction

    of hydropower plants Gjavato and Gevgelia is planned.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    43/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    43

    Figure 26 Existing and planned hydropowerplants8

    5.7 Climatic characteristics of the area

    The wide openness of the Vardar Valley, and with it the Municipality of Gevgelia, towards the

    Thessaloniki basin through the valley of Vardar, conditions strong influence of the

    Mediterranean climate in this region. This influence is especially expressed in the valley up to

    300 m asl and it is less changed in the hilly area to 600 m asl.

    The average annual temperature in Gevgelija is 14.3C. The coldest month of the year is

    January with an average temperature of 3.2C and the warmest is July with an average

    temperature of 25.7C.

    The average annual amount of rainfall is 745.2 mm3. The average humidity is 71-72 %, in winter

    is 81-82 % and in summer it descends up to 56 %.

    Fogs in the area of the municipality are rare occurrence. Fogs arise in the fall and winter

    months, and are most expressed in December with 3.3 days.

    Most expressed winds are Vardarec and Jug. Vardarec occurs from the north and Jug by

    southeast direction.

    8Source: National Water Strategy

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    44/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    44

    Figure 27Climatic map of the Republic of Macedonia

    Figure 28Rose of winds

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    45/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    45

    5.8 Existing road and communal infrastructure

    The planned project activities will be carried out on the motorway E-75 or Corridor X that

    represents the most frequent road in the Republic of Macedonia and it is an important factor for

    the local economic development, especially on transit tourism, in which a central place occupies

    Gevgelija and border crossing Bogorodica.

    Figure 29Road network of the Republic of Macedonia

    Parallel with the projected section passes the international railway corridor Belgrade-Skopje-

    Athens (Corridor X).

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    46/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    46

    Figure 30Railway corridors

    Supply of electricity in Gevgelija is made with the electro energetic power system of Republic of

    Macedonia and all the settlements are supplied with a stable voltage power grid.

    In the widely environment of the project area there are above ground power lines Dubrovo-

    Thessaloniki (400 kV) and Valandovo-Gevgelia (110 kV).

    Figure 31 Electricity distribution networks and hydro/thermal power plants in the Republic of Macedonia9

    9Source: Spatial Plan of the Republic of Macedonia.

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    47/163

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    48/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    48

    Figure 33The route of the oil pipeline Skopje-Thessaloniki

    The route of the oil pipeline

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    49/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, left carriageway of the Motorway A1 (E75), Smokvica-

    Gevgelija, section Smokvica-Prdejci

    49

    Figure 34 The route of the water supply and sewerage network at village Prdejci

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    50/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    50

    5.9 Biodiversity

    The project area, i.e. the motorway section Smokvica-Prdejci is located near the railway line. A

    special feature of this biotope located between the road corridors is the frequent presence of a

    specific type of natural vegetation dictated by anthropogenic influence. Some neophytes are

    present with local plants, and some of ruderal plant communities are adapted exclusively for

    development along the road.

    These kind areas of the road corridor are: Geranio-Silybetum mariani Oberd. (1954

    characteristic for the margins of roads and railways), Lolio-Plantaginetum commutatae H-ic

    (1934) 1963 and Sclerochloetum durae Br-Bl 1931 (typical for rigid soils along the roads and

    streets). Because it is not specific for the area, they dont have high relevance to the overall

    biodiversity of the region.

    Along the section thermophilic mixed evergreen and deciduous forests and shrublands

    belonging to the sub-Mediterranean-European sub-region-Macedonian-Thracian area are

    present. This is the dominant type of vegetation that determines the characteristics of the sub-

    Mediterranean hilly forest landscape.

    Figure 35Existing vegetation along the section

    The characteristic plant community is Coccifero-Carpinetum orientalis which implies dominance

    of Carpinus orientalis. However, in the degraded zones Kermes oak is the dominant species

  • 8/10/2019 Annex 1 - EPR Smokvica - Prdejci_ENG_FINAL

    51/163

    Environmental protection report from realization of the Project-Extension with reconstruction of the existing carriageway, leftcarriageway of the Motorway A1 (E75), Smokvica-Gevgelija, section Smokvica-Prdejci

    51

    and it is characterized by pseudomaquis. The current dominance of Kermes oak over the

    Carpinus orientalis is a secondary characteristic, created because