Angola LNG Project
Progress Photos
May 2009 to May 2010
Angola LNG Project
Progress Photos
May 2009 to May 2010
May 28, 2010
01N – PROPANE
CONDENSER
01A–COMPRESSORS
10A/10N – GTGS
01S/01R – CRYO
RACK
LNG – TANK B
ISBL - APRIL 26, 2009
ISBL - MAY 10, 2010
01N – Propane
Condenser
10A/10N – GTGS 01S/01R – CRYO
RACK
01G – Methane Liquification
Cold Box
01A–COMPRESSORS
LNG – TANK A/B
LNG – PROPANE
& BUTANE TANK
LNG – CONDENSATE
TANK
TANK AREA - 15 Feb 2009
LNG – TANK A & B
LNG – PROPANE
& BUTANE TANK
LNG – CONDENSATE
TANK
TANK AREA - MAY 10, 2010
11A - BUILDINGS
11A – CONTROL
BUILDING
08A-WET & DRY
FLARE
01N-PROPANE
CONDENSER RACK 01A - COMPRESSORSOSBL EAST SIDE - 27 MAY 2009
10H – CONTROL
BUILDING
11A - BUILDINGS
08A-WET & DRY
FLARE
01A - COMPRESSORS
01N-PROPANE
CONDENSER RACK
OSBL EAST SIDE - 16 MAY 2010
LNG – PROPANE
& BUTANE TANK
LNG JETTY
PB JETTY
LPG JETTY
LNG – CONDENSATE
TANK
MARINE FLARE
MARINE & TANK AREA - 12 April 2009
CHEC – MARINE
FLEET
LNG JETTY
MARINE FLARE
LPG JETTY
PB JETTY
LNG – CONDENSATE
TANK
LNG – BUTANE
TANK
MARINE & TANK AREA - 10 April 2010
WTP/STP PLANT
6500 BED CAMP - 26 Apr 2009
5000 MAN DINER
UNDER CONST.
“D” BLOCK UNDER
CONST.
6500 BED CAMP - 21 Feb 2010
WTP/STP PLANT
May 28, 2009
1st Steel Erection for Propane
Condenser Pipe rack (Area 01N)
May 27, 2010
Today – Propane Condenser Pipe rack (Area 01N)
1st erection of Vessel 1V-1421/22/23 &
1V-1411/12/13 Knock out Suction Drum
At Propane Refrigeration (Area 1J)
Aug 03, 2009
Today – Propane Refrigeration (Area 01J)
Suction Drums Behind 01J Steel
May 27, 2010
Erection of Frame 7 South Compressor
Oct. 05, 2009
Today – Compressors (Area 01A)
May 27, 2010
1st Erection of GTG (Area 10A/10N)
Aug. 27, 2009
Today – Gas Turbine Generators (Area 10A/10N)
May 27, 2010
Erection of CO2 Absorber (Area 01C)
(1,125 Tons)
Oct. 28, 2009
Erection of CO2 Absorber (Area 01C)
(1,125 Tons)
Oct. 28, 2009
Erection of CO2 Absorber (Area 01C)
(1,125 Tons)
Oct. 28, 2009
Today – CO2 Absorber (Area 01C)
May 27, 2010
Setting of Ethylene Refrigeration
Cold Box (Area 01H)
January 14, 2009
Today – Ethylene Refrigeration
Cold Box (Area 01H)
May 27, 2010
Erection of Heavies Removal Column
1V-1701 (Area 01F)
(540 Tons)
January 19, 2009
Erection of Heavies Removal Column
1V-1701 (Area 01F)
(540 Tons)
January 19, 2009
Today-De-ethanizer 1V- 1702
& Heavies Removal Column
1V-1701 (Area 01F)
May 27, 2010
Erection of Dry Flare Stack (Area 08A)
May 27, 2010
Today – LNG Tanks A & B
May 27, 2010
LNG TANK BLNG TANK A
Today – LNG Propane & Butane Tanks
May 27, 2010
PROPANE TANK
BUTANE TANK
07D PIPE RACK
Great work….
Great Team…
Bechtel & Sub-contractors
LNG Team