angola lng project progresse photos | may 2009 to may 2010

37
Angola LNG Project Progress Photos May 2009 to May 2010

Upload: toke-head

Post on 20-Mar-2016

219 views

Category:

Documents


5 download

DESCRIPTION

Angola LNG Project Progresse Photos | May 2009 to May 2010

TRANSCRIPT

Angola LNG Project

Progress Photos

May 2009 to May 2010

Angola LNG Project

Progress Photos

May 2009 to May 2010

May 28, 2010

01N – PROPANE

CONDENSER

01A–COMPRESSORS

10A/10N – GTGS

01S/01R – CRYO

RACK

LNG – TANK B

ISBL - APRIL 26, 2009

ISBL - MAY 10, 2010

01N – Propane

Condenser

10A/10N – GTGS 01S/01R – CRYO

RACK

01G – Methane Liquification

Cold Box

01A–COMPRESSORS

LNG – TANK A/B

LNG – PROPANE

& BUTANE TANK

LNG – CONDENSATE

TANK

TANK AREA - 15 Feb 2009

LNG – TANK A & B

LNG – PROPANE

& BUTANE TANK

LNG – CONDENSATE

TANK

TANK AREA - MAY 10, 2010

11A - BUILDINGS

11A – CONTROL

BUILDING

08A-WET & DRY

FLARE

01N-PROPANE

CONDENSER RACK 01A - COMPRESSORSOSBL EAST SIDE - 27 MAY 2009

10H – CONTROL

BUILDING

11A - BUILDINGS

08A-WET & DRY

FLARE

01A - COMPRESSORS

01N-PROPANE

CONDENSER RACK

OSBL EAST SIDE - 16 MAY 2010

LNG – PROPANE

& BUTANE TANK

LNG JETTY

PB JETTY

LPG JETTY

LNG – CONDENSATE

TANK

MARINE FLARE

MARINE & TANK AREA - 12 April 2009

CHEC – MARINE

FLEET

LNG JETTY

MARINE FLARE

LPG JETTY

PB JETTY

LNG – CONDENSATE

TANK

LNG – BUTANE

TANK

MARINE & TANK AREA - 10 April 2010

WTP/STP PLANT

6500 BED CAMP - 26 Apr 2009

5000 MAN DINER

UNDER CONST.

“D” BLOCK UNDER

CONST.

6500 BED CAMP - 21 Feb 2010

WTP/STP PLANT

May 28, 2009

1st Steel Erection for Propane

Condenser Pipe rack (Area 01N)

May 27, 2010

Today – Propane Condenser Pipe rack (Area 01N)

1st erection of Vessel 1V-1421/22/23 &

1V-1411/12/13 Knock out Suction Drum

At Propane Refrigeration (Area 1J)

Aug 03, 2009

Today – Propane Refrigeration (Area 01J)

Suction Drums Behind 01J Steel

May 27, 2010

Erection of Frame 7 South Compressor

Oct. 05, 2009

Today – Compressors (Area 01A)

May 27, 2010

1st Erection of GTG (Area 10A/10N)

Aug. 27, 2009

Today – Gas Turbine Generators (Area 10A/10N)

May 27, 2010

Erection of CO2 Absorber (Area 01C)

(1,125 Tons)

Oct. 28, 2009

Erection of CO2 Absorber (Area 01C)

(1,125 Tons)

Oct. 28, 2009

Erection of CO2 Absorber (Area 01C)

(1,125 Tons)

Oct. 28, 2009

Today – CO2 Absorber (Area 01C)

May 27, 2010

Setting of Ethylene Refrigeration

Cold Box (Area 01H)

January 14, 2009

Today – Ethylene Refrigeration

Cold Box (Area 01H)

May 27, 2010

Erection of Heavies Removal Column

1V-1701 (Area 01F)

(540 Tons)

January 19, 2009

Erection of Heavies Removal Column

1V-1701 (Area 01F)

(540 Tons)

January 19, 2009

Today-De-ethanizer 1V- 1702

& Heavies Removal Column

1V-1701 (Area 01F)

May 27, 2010

Erection of Dry Flare Stack (Area 08A)

May 27, 2010

Today – LNG Tanks A & B

May 27, 2010

LNG TANK BLNG TANK A

Today – LNG Propane & Butane Tanks

May 27, 2010

PROPANE TANK

BUTANE TANK

07D PIPE RACK

Great work….

Great Team…

Bechtel & Sub-contractors

LNG Team