DISTRICT IMPLEMENTATION PLANNING
An Update
Dr B Muzah
CONTENTS
• DIP journey
• National HIV tracer indicator performance
• District zoom in: Thabo Mofutsanyana
• District zoom in: Greater Sekhukhune
• Next steps
DIP Journey
Phase 1
-Districts selected 3 Tracer Indicators
-Developed remedial plans
-Implementation: Jul 15-Mar 16
• Y14/15
Phase 2
Province selected 12 tracer indicators
Developed DIPs
Implementation: Apr 16-Mar 17
• Y16/17
Phase 3
-All tracer indicators
-Commences: Jul 16
• Y17/18
Thabo Mofutsanyana: Clients Tested for HIV 15yrs & older
38647
93866
143827
189631
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
200000
Y15 Q 1 Y15 Q 2 Y15 Q 3 Y16 Q 4
Clients tested for HIV 15 yrs & older
Phase 1
Implementation
Target Line
Source: District
Phase 1: HCT Action Dashboard
Limpopo: Adult Viral Load Completion @ 6 Months
Source: DHIS
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Jan 2013 Apr 2013 Jul 2013 Oct 2013 Jan 2014 Apr 2014 Jul 2014 Oct 2014 Jan 2015 Apr 2015
Adult with Viral load completion rate at 6 months
Sekhukhune Limpopo
Limpopo: Adult Viral Load Completion @ 12 Months
Source: DHIS
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Jan 2013 Apr 2013 Jul 2013 Oct 2013 Jan 2014 Apr 2014 Jul 2014 Oct 2014
Adult with Viral load completion rate at 12 months
Sekhukhune Limpopo
Limpopo: Remedial Actions
Approach branded “road shows”
8
Step 1• Each facility presented on
performance on VL completion rate
Step 2• In-house training on cohort data
analysis and file audits
Step 3• Best practice sharing among
facilities
Next Steps: Link Between District reports
and NDoH
Branch Technical
Team
Branch DIP Meeting
Chair: Dr Pillay
National DIP-TWG
Feedback to Provinces
and Districts
District
Dashboards
DIP Phase 3
• All Tracer indicators
• Cascade bottleneck analysis process
• Aligned to Conditional Grant Business planning cycle
• Aligned to Conditional Grant Business plan template
MUCH IMPROVED…………………………………………..
10
Closing Remarks
• DIP is working
• Intensive monitoring of Phase 2 implementation will be conducted
• Much improved 2017/18 DIP process will starting in August