An investigation to determine the impact of lean construction techniques on project performance by comparing Design and Build with traditional construction procurement methods Johan Bezuidenhout Supervisor: Dr H Parker A research report prepared in partial fulfilment of the requirements for the Degree of Masters in Business Administration at the Graduate School of Business, University of Cape Town

Upload: others

Post on 26-Jan-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

An investigation to determine the impact of lean construction techniques on project performance by comparing Design and Build with

traditional construction procurement methods

Johan Bezuidenhout

Supervisor: Dr H Parker

A research report prepared in partial fulfilment of the requirements for the

Degree of Masters in Business Administration at the Graduate School of

Business, University of Cape Town

Page 2: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

i

ABSTRACT

According to Naidoo (2006), the South African construction industry will need

to double its output to meet public and private sector growth targets projected

for 2014. The industry’s ability to meet this demand however is compromised

due to poor performance in this sector globally. Low levels of productivity

results in millions of Rands lost annually.

This report investigates the link between the implementation of lean

techniques in construction and increased levels of productivity. In order to

explore this link, productivity amongst construction projects making use of

lean techniques such as benchmarking, partnering, total quality management

(TQM), just in time (JIT) and value engineering (VE) were compared against

projects less inclined to the implementation of these techniques. According to

Lam (2006), Design and Build (D&B) projects lend itself to the implementation

of these lean techniques, as apposed to traditional procurement (DBB) -

highly fragmented in nature. For the purpose of this report, D&B performance

was compared with traditionally procured projects in order to asses the impact

of lean techniques on productivity. Furthermore, interviews were carried out in

order to determine industry perceptions amongst various members of the

supply chain. Once key themes from the interviews were identified, a survey

was conducted in order to gain deeper insight into the impact of specific

techniques such as partnering and D&B procurement.

Evidence in this report suggests that, ceteris paribus, D&B projects

outperform traditionally procured construction projects. The reason for this is

that these projects lend themselves to the implementation of lean techniques.

As a result, levels of productivity increase, primarily through improved

communication, -coordination, better teamwork and higher levels of

integration and better project planning upfront.

Key Words: Productivity, Lean, Design and Build (D&B), Design Bid and Build (DBB)

Page 3: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

ii

DECLARATION

1. I know that plagiarism is wrong. Plagiarism is to use another’s work

and pretend that it is one’s work own.

2. I have used the Harvard convention for citation and referencing. Each

contribution to, and quotation in, this report from the work(s) of other

people has been attributed, and has been cited and referenced.

3. This report is my own work.

4. I have not allowed, and will not allow, anyone to copy my work with the

intention of passing it off as his or her own work.

Bezuidenhout, J. December 2008

Page 4: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

iii

ACKNOWLEDGEMENTS My sincere thanks to the following people for their contribution:

• Lynn O’Neill

• Peu Bezuidenhout

• Stephen Chambers

• Chris McMinn

• Alan Commerford

• Erik Nieuwenhout

• Billy Northcott

• David Elliot

• Marius vd Berg

• Bernard Minnaar

• Marcel Hoebe

Special thanks to Dr Hamieda Parker for supervising this report. Your

conviction and commitment is highly valued.

Page 5: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

iv

TABLE OF CONTENTS ABSTRACT ............................................................................................................ i

DECLARATION ...................................................................................................... ii

ACKNOWLEDGEMENTS ..................................................................................... iii

TABLE OF CONTENTS ........................................................................................ iv

LIST OF FIGURES ................................................................................................ vi

ACRONYMS ......................................................................................................... vii

1. INTRODUCTION ............................................................................................... 1

1.1 Introduction to research ............................................................................ 1

1.2 Background ................................................................................................ 2

1.3 Research outline ........................................................................................ 3

1.4 Research objectives .................................................................................. 4

1.5 Scope and Limitations ............................................................................... 4

2. HYPOTHESIS & PROBLEM STATEMENT ...................................................... 5

3. LITERATURE REVIEW ..................................................................................... 6

3.1 The construction industry in South Africa .............................................. 6

3.2 Performance in the construction industry .............................................. 6

3.3 Productivity: Historic survey .................................................................... 7

3.4 Lean and construction ............................................................................... 8

3.5 Lean techniques in construction ............................................................ 10

3.5.1 Standardisation and Specialisation ..................................................... 10

3.5.2 Benchmarking ..................................................................................... 10

3.5.3 Supply Chain Integration ..................................................................... 11

3.5.4 Just In Time (JIT) ................................................................................ 11

3.5.5 Total Quality Management (TQM) ....................................................... 12

3.5.6 Value Management (VM) .................................................................... 13

3.5.7 Partnering ............................................................................................ 14

3.6 Obstacles facing the implementation of lean ........................................ 14

3.7 D&B vs. traditional procurement (DBB) ................................................. 17

3.7.1 Definitions ............................................................................................ 17

3.7.2 Risk ...................................................................................................... 18

3.7.3 D&B Trends ......................................................................................... 19

Page 6: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

v

4. HISTORICAL CASE ANALYSIS ..................................................................... 21

4.1 Background .............................................................................................. 21

4.2 Case Structure .......................................................................................... 21

4.3 Metrics ....................................................................................................... 22

4.4 Case Findings ........................................................................................... 23

4.4.1 Industry Group ..................................................................................... 23

4.4.2 Nature .................................................................................................. 24

4.4.3 Cost ..................................................................................................... 24

4.4.4 Performance Comparison ................................................................... 25

4.4.5 Summary ............................................................................................. 28

5. METHODOLOGY ............................................................................................ 29

5.1 Literature Review ..................................................................................... 29

5.2 Interviews .................................................................................................. 31

5.3 Surveys ..................................................................................................... 32

6. FINDINGS ........................................................................................................ 33

6.1 Productivity............................................................................................... 33

6.2 Lean ........................................................................................................... 33

6.3 Design & Build and Design Bid & Build ................................................. 34

6.4 Case Comparison ..................................................................................... 34

6.5 Interviews .................................................................................................. 35

6.6 Survey ....................................................................................................... 43

6.7 Summary of findings ............................................................................... 48

6.7.1 Interview: ............................................................................................. 48

6.7.2 Survey: ................................................................................................ 49

7. CONCLUSIONS AND IMPLICATIONS ........................................................... 51

7.1 Conclusions .............................................................................................. 51

7.2 Implications for managers ...................................................................... 52

7.3 Implications for future research ............................................................. 53

BIBLIOGRAPHY AND REFERENCES ............................................................... 54

APPENDIX ........................................................................................................... 58

1. Literature ..................................................................................................... 58

2. Interviews .................................................................................................... 62

3. Survey .......................................................................................................... 67

4. Case Comparison ....................................................................................... 74

Page 7: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

vi

LIST OF FIGURES

Figure 1: Productivity survey ................................................................................. 8

Figure 2: Lean construction wheel ........................................................................ 9

Figure 3: Costs and benefits of quality management ......................................... 13

Figure 4: Industry culture in construction and manufacturing ............................. 15

Figure 5: A: Single- and fragmented point responibility ...................................... 17

Figure 6: Allocation of risk for each type of procurement contract .................... 18

Figure 7: Risk Profile of different procurement systems ..................................... 18

Figure 8: A: Growth in Design and Build as preferred procurement method ...... 19

Figure 9: A: Perception of growth in Design and Build as procurement Method 20

Figure 10: Case comparison structure. ............................................................... 22

Figure 11: Case comparison structure 2. ............................................................ 23

Figure 12: Case comparison by industry. ........................................................... 23

Figure 13: Case comparison by nature. .............................................................. 24

Figure 14: Case comparison by cost................................................................... 25

Figure 15: Case comparison overall performance by owner submitted projects 26

Figure 16: Case comparison by performance by contractor submitted projects. 27

Figure 17: Overall performance of owner and contractor submitted projects. .... 28

Figure 18: Overall performance of owner and contractor submitted projects ..... 35

Figure 19: Interviewee Profile………………………………...……………………...35

Figure 20: Interviewee key point summary ......................................................... 42

Figure 21: Integration amongst value chain members ........................................ 43

Figure 22: Rated importance in terms of influencing productivity ....................... 44

Figure 23: Perception of D&B apposed to traditional procurement (DBB) ......... 44

Figure 24: Perception of the construction industry .............................................. 45

Figure 25: Perception of partnering’s ability to influence productivity ................. 45

Figure 26: Key point summary - areas that influence productivity ...................... 46

Figure 27: Ranked perception of areas to improve productivity. ........................ 47

Figure 28: Summary of findings based on literature, interviews and survey ...... 50

Page 8: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

vii

ACRONYMS

• AOMS Adirondack Oral & Maxillofacial Surgery

• BRE Building Research Establishment

• CII Construction Industry Institute

• CPMS Construction Productivity Metrics System

• D&B Design and Build

• DBB Design, Bid and Build

• DPW Department of Public Works

• GDP Gross Domestic Product

• IBS Industrialized Building Systems

• ICD Integrated Collaborative Design

• JBCC Joint Building Contracts Committee

• JIT Just In Time

• KPI Key Performance Indicators

• QS Quantity Surveyor

• SA Republic of South Africa

• SAPOA South African Property Owners Association

• TQM Total Quality Management

• WIP Work in Process

Page 9: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

1

1. INTRODUCTION

1.1 Introduction to research The construction industry in South Africa is rapidly growing. According to

Naidoo (2006), the industry will need to double its output to meet public and

private sector growth targets projected for 2014. Low levels of productivity in

construction worldwide however are hampering the sector’s ability to meet this

target.

In 1998, Sir John Egan’s Construction Task Force launched an investigation

to address the low levels of productivity faced by the industry. The study

concluded that production in other industries (such as manufacturing and

retailing) benefited substantially from the implementation of lean production

techniques such as total quality management (TQM), value management

(VM) and just-in-time (JIT). Even though the construction sector differs in

many respects, it was suggested that the same benefits may be obtained if

these techniques were implemented properly.

This report identifies lean techniques applicable to the construction industry

and determines their impact on productivity. However, due to the explicit

nature of the industry, barriers to implementing lean techniques were

identified, as well as countermeasures to accommodate these obstacles in

order to realise the full potential of lean techniques in construction.

For the purpose of this report, productivity amongst D&B projects were

compared with that of traditional projects (DBB). The reason for this is

because D&B projects lend themselves to the implementation of lean as

opposed to traditional procurement. This report also made use of relevant

literature, interviews with professionals in the industry and a survey

administered to various members of the supply chain. Conclusions and

recommendations were drawn from these findings.

Page 10: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

2

1.2 Background The construction industry experienced faster growth in percentage

contribution to South Africa’s GDP than any other sector from 2004 to 2008

and is currently the 8th biggest overall contributor to the GDP. This sector also

contributes approximately 6% of South Africa’s employment (Exhibit 1 & 2 in

Appendix: Literature review). However, according to Naidoo (2006), the

construction industry will need to double its current output (approximately

R100 billion) to meet public and private sector growth targets projected for

2014. Achieving this target will not be easy. This is because the construction

industry is associated with fast track projects, a heterogonous environment

and its dependency on many other trades. These factors more often than not

contribute to bad construction project planning right from the briefing phase,

which results in deadline and cost overruns, as well as inferior workmanship

and ultimately client dissatisfaction.

The implementation of lean production techniques such as TQM, JIT, VM,

partnering and benchmarking to improve productivity has been successfully

applied in many other sectors, such as motor manufacturing (Toyota), retail

(Tesco), aircraft manufacturing (Cessna) and even surgery (AOMS). The

construction industry on the other hand is adept at delivering exceedingly

complex products and services. Construction products are normally

assembled on site, unlike in a controlled factory environment. Furthermore,

according to Root (2007), these projects are characterised by a myriad of

relationships between many organisations as well as thousands of different

processes.

Due to the unique construction environment, it is much more challenging to

successfully implement these lean techniques. Some of these obstacles

include: fragmentation of the industry, limitations to standardisation and

specialisation, limitations imposed by a traditional tender based procurement

system as well as being highly reliant on multiple industries and team

member’s different functions, making communication and coordination very

difficult, hence the loss of productivity throughout the process.

Page 11: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

3

1.3 Research outline This report is divided into the following 7 chapters:

• Chapter 1: Introduction

The introduction focuses mainly on the research hypotheses, as well

as introducing the rest of the report

• Chapter 2: Hypothesis and problem statement

This chapter states the field of interest and the significance of the

research.

• Chapter 3: Literature review

The literature examines relevant literature with regards to productivity

in the South African- and other construction industries globally.

Information was obtained from journals, books, the World Wide Web as

well as publications. Key words include: Lean construction techniques,

productivity, design and build (D&B), design bid and build (DBB)

• Chapter 4: Historical case comparison: D&B vs. DBB

This chapter introduces construction projects in the form of a case

study, to gain a deeper insight into the actual mechanics of a

construction project and the relevance of lean in construction. Its focus

is specifically on D&B projects and traditionally procured projects.

• Chapter 5: Methodology

This chapter describes the qualitative research methods used in this

study. These include data from the Literature Review, Interviews,

Historical Case Comparison as well as a Survey

• Chapter 6: Findings

This chapter analyses data gathered from the literature review,

interviews, case studies and the survey

• Chapter 7: Conclusions and Implications

The final chapter draws conclusions and makes recommendations

based on the findings from the previous chapter

Page 12: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

4

1.4 Research objectives The objective of this research report is to answer the following question: How

can productivity in the construction industry benefit from the implementation of

lean construction principles?

In order to answer the above, the following was taken into account for

analysis.

• Current performance of the construction industry and the future outlook

for South Africa

• Definition, measurement and relevance of productivity in the

construction industry

• Definition and implementation of lean production techniques in the

construction industry as well as other industries in contrast.

• Obstacles and barriers for implementing lean production in the

construction industry

• Possible benefits and detriments of successfully implementing lean

production in the construction industry

1.5 Scope and Limitations Although the literature is not restricted to the South African context,

questionnaires, interviews and case studies are mostly South African based.

Moreover, the bulk of the information comes from a small sample of

construction related professionals in the Western Cape only. The correlation

of the interpreted data and its application must therefore be seen in this

context.

Page 13: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

5

2. HYPOTHESIS & PROBLEM STATEMENT

So far it is clear that the construction industry has a vital role to play in

promoting developments in the economy. However, this industry experiences

major obstacles in delivering projects on time, within budget and to quality due

to low productivity. According to research conducted by SAPOA, “contractors

face many problems when delivering construction projects, as a result of poor

contractor performance, characterised by poor work quality and low

productivity which is common in the industry” (Thwala, 2007:2)

As highlighted in the Egan Report (1998), the South African construction

industry is not the only construction industry facing this challenge.

Construction industries around the world are characterised by high

fragmentation, client dissatisfaction, low levels of investment in research and

development, low levels of training and traditional tender based project

systems.

The purpose of this report is to determine whether productivity on construction

projects can be improved by the implementation of lean construction

techniques, such as partnering, value engineering and benchmarking. In order

to solve the hypothesis, projects making use of lean construction techniques

must be compared with projects not currently making use of lean construction

techniques (not exclusively) in terms of productivity. As a result, two particular

methods of procurement for construction projects have been identified in order

to test the hypotheses – D&B procurement and traditional procurement. The

reason for this is that, according to Lam (2004), innovative procurement

methods, specifically D&B projects, lends itself to the implementation of lean

in construction as apposed to traditional projects, hence the reason for

comparing their performance in order to draw reasonable conclusions and

make recommendations.

Page 14: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

6

3. LITERATURE REVIEW

3.1 The construction industry in South Africa As mentioned earlier, the SA construction industry is a major role player in the

economy. According to Statistics SA, the construction industry experienced

annual employment growth of approximately 390 000 people between 2001

and 2006, bigger than any other sector in this period. Furthermore, according

to the DPW, the industry contributed a total of R122 345 billion to the total

gross capital formation in 2006, which is equal to approximately 38%!

In 2006, the sector saw an increase in growth from 10% to 14% from 2005 to

2006. According to Thwala (2007) this trend will continue, underpinned by

strong public infrastructural expenditure. Furthermore, public sector

infrastructural expenditure has increased by 15.8% per year between 2003

and 2007. Evidence to support Thwala’s prediction is the fact that the SA

government is the largest contributor to domestic construction expenditure,

totalling between 40% and 50%.

3.2 Performance in the construction industry Worldwide, productivity levels in the construction industry have been classified

as relatively poor. Sir John Egan launched an investigation into this

phenomenon (known as the Egan Report: Rethinking Construction) as early

as 1998 to establish the main causes. According to Egan (1998), these

include (but are not limited to) the fragmentation of the industry, customer

dissatisfaction, untrained workforce, low profit margins and a tender based

procurement system. Another major stumbling block in the construction

environment is the difficulty of measuring productivity, due to its highly

customised and complex nature. This has fuelled research for standardising

methods for measuring productivity, such as CPMS, with the emphasis on

benchmarking.

Page 15: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

7

Egan saw the manufacturing and service industries making major productivity

gains from implementing lean production systems that focus on the following:

• Supply chain integration: Partnering with the supply chain by

establishing and working towards mutual goals and objectives benefits

the process by shared progress measurement,

• Standardisation: By pre-assembling units or components the

construction time is dramatically reduced and quality can be increased

by manufacturing in controlled factory conditions as apposed to

exposed construction sites.

• Performance measurement: Systems such as benchmarking, VM,

TQM and JIT are used in various other industries for eliminating waste

and improving quality and efficiency (explained elsewhere)

3.3 Productivity: Historic survey As mentioned previously, the construction sector in South Africa and in most

other counties is a significant contributor to the country’s GDP, as well as total

employment, hence the importance of the performance of this industry. On

these grounds, a survey was conducted by the Michigan Tri-Partite

Committee in 2002 to investigate low levels of productivity in the construction

sector in North America, and methods to improve it. Respondents totalled 182

construction professionals, of whom 90% had more than 10 years experience

in the industry. The main objective of this qualitative survey was to determine

what professionals consider to be the greatest barriers to productivity, as well

as areas for improving productivity. The top 5 results for ‘greatest barriers to

productivity’ and ‘greatest areas for improving productivity’ were respectively

as follows:

Page 16: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

8

Greatest Barriers to Productivity:1 Design: Specifications, drawings, documents have to be improved2 Field support for timely responses: Engineer/Architect on site3 Coordination of design4 Timely information (Based on RFI Schedules)5 Construction/ Project Mangement competancy

Greatest Areas for Improving Productivity:1 Constructibility of design documents (Realism)2 Coordination among major contractors and designers3 Pre-Project planning4 Communication and teamwork between various parties involved5 Improvement of the construction management process

Figure 1: Productivity survey. Source: Michigan Tri-Partite Committee (2002)

It is clear from the survey findings that factors such as communication,

coordination, integration and planning play a vital role in influencing levels of

productivity on projects. The next section investigates the link between lean

construction techniques and factors such as communication, coordination and

integration.

3.4 Lean and construction The principle of lean was originally developed by Toyota motor manufacturing

and later refined and expanded in other industries. In Sir John Egan’s report,

‘Rethinking Construction’ (1998), he highlights the benefits of implementing

lean procedures in various industries, such as offshore engineering, grocery

retailing, steel making and of course motor manufacturing.

The Egan report continues by suggesting that the implementation of lean

principles (discussed in more detail elsewhere) in the construction industry will

be just as beneficial as experienced by other industries. The benefits of ‘first

mover’ construction related firms that have implemented some of these lean

principles are evident. Examples of such organisations are Raynesway

Construction Southern (Hampshire), The Neenan Company (Colorado),

Pacific Contracting (San Francisco), and NMC (South Africa) who were all

able to reduce costs & time as well as increase productivity & output per

Page 17: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

9

employee by implementing techniques such as TQM, VM and JIT. Diekmann

(2003) identified the following as the five main enablers for lean construction:

• Standardisation

• People/Culture

• Continues Improvement/Built in Quality

• Elimination of Waste

• Customer Focus

Figure 2: Lean construction wheel. Source: Diekmann (2003)

Diekmann’s reflection of lean production in the construction sector is quite

encapsulating, for the purpose of this report, the emphasis will only be placed

on a selected group of principles, best explained in the next section.

Page 18: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

10

3.5 Lean techniques in construction 3.5.1 Standardisation and Specialisation

This technique contains visual management, workplace organisation as

well as defined work processes. Because every construction project is

unique, the implementation of standardisation is of course limited.

However, recently construction projects are making use of systems

such as IBS (Industrialised Building Systems), modularisation, pre-

assembly and pre-fabrication which dramatically reduces construction

time (since components can be mass produced in controlled

environments off-site), reduces cost (economies of scale due to

decreased set-up costs, rental costs as well as time spent) and

increase quality (controlled environment as well as mass produce).

3.5.2 Benchmarking

Egan (1998:10) describes benchmarking as “a management tool which

can help construction firms to understand how their performance

measures up to their competitors’ and drive improvement up to ‘world

class’ standards”. The successful implementation of benchmarking in

the manufacturing industry since the early 90’s has sparked the interest

for applying it elsewhere. According to Mohamed (1996), the

construction industry is slow to adopt this technique due to:

misunderstanding the concept, not knowing how to properly apply it in

context, the availability of data (the structure of the construction

process does not allow field-based data to be collected readily), as well

as the fact that benchmarking requires drastic changes in the way

information and communication is handled and documented.

Despite the apparent complexity and restructuring of traditional

methods associated with benchmarking, construction organisations

globally have seen the benefits of implementing this technique. For

example, Taywood Engineering Ltd uses benchmarking on projects to

identify strategies for achieving ‘zero defects’ in construction, based on

principles of a ‘zero defect culture’. Mohamed (1996) suggests that for

benchmarking to be successfully applied in the construction sector,

Page 19: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

11

three distinct types of benchmarking must be addressed – Internal

benchmarking, project benchmarking and external benchmarking

(discussed in more detail in the report).

3.5.3 Supply Chain Integration

According to Root (2007:8) “Construction projects involve relationships

between many organisations and thousands of processes. The industry

has evolved highly developed methods of accommodating this

complexity, with the evolution of many specialised roles and embedded

relationships. These are mediated through well-established contractual

arrangements, while the delivery and assembly of components to

dispersed locations is being continually refined with improving working

methods and assembly technologies.” As mentioned, the construction

sector relies on the collaboration of many different role players. The

need to improve the delivery process as a whole, especially in the

design phase has been recognised worldwide. Supply Chain

Management and Integration techniques (such as partnering) aims at

improving the relationship throughout the supply chain (from briefing to

handover), and as a result, remove unnecessary costs typically stored

up in the supply chain of the construction sector. Lastly, project

collaboration allows for the real-time sharing of information, drawings,

programmes as well as budgets. From the client’s perspective, benefits

of project collaboration and supply chain integration are improved

communication, increased speed as well as quality. The “D&B” concept

focuses primarily on the integration of the supply chain and the benefits

from doing so. The D&B concept will be discussed in more detail under

the case study section of the report.

3.5.4 Just In Time (JIT)

Just In Time methods was first introduced in the manufacturing industry

(Toyota) in order to reduce WIP inventory (hence working capital), but

ultimately according to Ballard (1995) the main benefit of implementing

JIT is in the reduction of the variability of work flow, therefore

contributing to continuous improvement. However, Ballard continues by

Page 20: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

12

stating that the construction industry is much more complex and

uncertain than the manufacturing industry, due to the number of parts

and processes involved, limited standardisation and multiple

participants. When combined with the economic pressures of

minimising time and cost as well as optimising quality, the effective

implementation of JIT is much more challenging. Despite this, Das

(1997) states that firms following JIT practices derive benefits of more

frequent deliveries, smaller lot sizes as well as lower on-hand

inventory, levels (which arguably forms a critical part of all construction

projects) driven by increased quality, information sharing and ultimately

trust.

3.5.5 Total Quality Management (TQM)

Implementing TQM is a continuous process of incremental

improvements. It is a process orientated (as apposed to a result

orientated) approach, meaning that the results will follow as a

consequence of implementing the process correctly.

According to Peng (1996:40), “Total quality management (TQM)

consciously focuses all parties to the common goal of systematically

identifying and meeting the customer’s requirements as the super

ordinate goal. It should, however, be noted that the tools associated

with TQM can be as readily applied in a stable environment as in the

manufacturing sector. In construction, where customers’ requirements

are increasingly complex, and expectations uncertain, the application

of such tools can become difficult.” Despite the obstacles posed by the

construction sector, Peng continues to say that 15% savings on total

cost of a construction project can be achieved through the

implementation of TQM by eliminating re-work, reducing waste and

increasing attention or concern for prevention of rejects or wastes on

remedial works. See Figure 3 below:

Page 21: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

13

Figure 3: Costs and benefits of quality management. Source: BRE (1982)

3.5.6 Value Management (VM)

Value management (VM) or value engineering (VE) is basically the

implementation of a service that maximises the functional value of a

construction project by managing its development from start to finish. In

other words, VM is an organised approach of identifying and

eliminating unnecessary cost throughout the lifecycle of a project.

According to De Leeuw (2001), value management covers the

following phases:

• Information Phase (Develop understanding of the project)

• Objective Phase (Focus on common objectives project must fulfil)

• Functional Analysis Phase (Develop functionality of the project)

• Creativity Phase (Brainstorming)

• Evaluation Phase (Identify possible alternatives)

• Development Phase (Technical development of ideas)

• Reporting Phase (Agree on outcome and consensus on actions

needed to keep project on track)

Lastly, De Leeuw states that although value management is currently

not readily adopted throughout the industry (for reasons mentioned in

previous sections), it is bound to be become more popular due to its

benefits, which amongst other include the fact that value management

aids in the identification of constraints which might not have been

Page 22: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

14

obvious, as well as providing “optimum value for money projects with

improved functionality” (De Leeuw, 2001:11)

3.5.7 Partnering

According to Ronco (1996:2), “Partnering is a formal program to

improve communications among the people and organisations working

on a design and construction project.” Key members of the project

team collaborate during the design phase, pre-construction and

regularly during construction phase of a project. According to Li

(2000), Partnering has been a primary management strategy for

improving organisational relations and project performance. Li

Continues to argue that, to increase productivity and efficiency in the

construction industry, a strong focus has been set on better integration

of the different parties (including the client, architects, engineers,

general contractors, subcontractors, suppliers, etc.) in one integrated

project organisation. These parties referred to by Li, are normally

independent organisations, with separate aims and operations. Typical

problems that occur, according to Laedre (2001), are lack of

communications and co-ordination leading to changes and alterations

during the process. This causes disputes, higher costs, lower

performance and lower overall quality, hence the significance of

collaboration and partnering.

3.6 Obstacles facing the implementation of lean As mentioned earlier, the difficulty for implementing lean techniques in

construction is mainly due to the distinct nature of this sector. Most ‘lean’

techniques (such as value engineering, partnering and benchmarking) have

been developed and refined in the manufacturing industry. Since these

industries differ in many respects, it will be worth wile doing a comparison:

Brokmann’s (2005) research concluded the following comparative table with

regards to the differences between these two industries (also see exhibit 4-5

in appendix: literature review):

Page 23: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

15

Figure 4: Industry culture in construction and manufacturing. Source:

Brockmann (2005)

According to Barrie (1992), production in construction can be described as

project based unit production, contract production and on-site production.

Manufacturing on the other hand is inversely characterised by mass-

production, replication, stock- and factory production, which lends itself to

generating economies of scale (as apposed to construction). Peng (1996)

adds to this by stating that the reliance on migrant labour and the short-term

nature of construction projects add to the difficulty of implementing these lean

techniques. Peng continues to argue that new methods of procurement are

the key to overcoming inhibitive tendencies posed by the complex nature of

Page 24: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

16

the construction industry. This is in line with Egan (1998:14) which states “the

industry rightfully complains about the difficulty of providing quality when

clients select designers and constructors on the basis of the lowest cost

(traditional procurement) and not the overall value for money.” Egan further

contributes by saying that, currently the fragmentation, low skill levels,

limitation of standardisation and pre-assembly (due to the highly customised

nature of construction) as well as limited or poor communication between the

large amount of key players on a project all act as barriers to the successful

implementation of lean principles in the construction industry.

In summary, the barriers can be categorised as follows:

• Traditional methods of procurement lead to poor contractor

performance and workmanship as a result of low tender prices. This is

mainly due to the fact that client’s wrongly associate ‘low cost’ with

‘value for money’

• The large amount of key role players on a project makes effective

communication and proper coordination difficult. This in turn has the

effect of wasting valuable time on a project, as well as constructing a

product that is not in line with the client’s expectations.

• Low levels of integration between the whole team (i.e. contractors and

the design team), which have a significant knock-on effect on time, cost

and quality of the project.

• The customised nature of a construction project makes it very difficult

to implement standardised, modular or pre-assembled products on a

project, which in turn makes it almost impossible to generate the cost,

time and quality benefits of economies of scale

• The highly fragmented nature of the industry leads to the extensive use

of sub-contracting, which in turn prevents the continuity of teams that is

essential to efficient working.

Page 25: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

17

3.7 D&B vs. traditional procurement (DBB) 3.7.1 Definitions

Design and Build projects differ from traditional procurement in the sense

that the D&B contractor is responsible for both the design and construction

of the facility to deliver a building to the satisfaction of the client. According

to Masterman (1992), “Design and Build has almost been unanimously

interpreted and defined as being an arrangement where one contracting

organisation takes sole responsibility, normally on a lump sum fixed price

basis, for the bespoke design and construction of a client’s project.” This

can be divided in the following three categories: 1.the responsibility of the

design and construction of a project, 2.reimbursement occurs through a

fixed sum / upfront agreement, 3.the project is designed and built to

exactly match the client’s needs. Furthermore, according to Chappell

(1997), Design and Build contracts place responsibility for both design and

construction in the hands of the contractor one point of responsibility for

everything, as apposed to traditional procurement, where the design and

construct responsibility is kept separate. See figure 5 below:

Figure 5: A: Single point responsibility (D&B), and B: Fragmented responsibility (Traditional). Source: Seng (2006)

Page 26: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

18

3.7.2 Risk

As mentioned, D&B projects significantly increase the risk for the one party

assuming the point of responsibility (for both building and designing).

According to Solomon (2005:5), one of the biggest fears professionals

have about leading a design-build project is the increased risk associated

with construction. “While the tasks traditionally associated with architecture

and design is insurable, work occurring on a construction site is not.”

However, according to Solomon, this creates a huge opportunity for

professionals who take the risk – risk is not managed by insurance, but by

significantly higher profits. The graph below describes the difference in risk

structure between D&B projects as apposed to traditional procurement:

Figure 6: Allocation of risk for each type of procurement contract. Source:

Seng (2006)

Figure 7: Risk Profile of different procurement systems. Source: Perry, 1985

Page 27: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

19

3.7.3 D&B Trends

According to Seng (2006), Design and Build tends to be quicker than

traditional procurement, both in terms of site construction and total project

time. Most importantly, Seng continues to argue that time savings with

D&B are maximised at the pre-contract stage, with upfront integration of

parties. According to studies carried out by Fitchie (1996), procurement

time for traditional projects can be up to two times that of D&B. Seng

continues by saying that the benefits of D&B are accrued simply because

of its ability to integrate the project team members, produce open

communication and encourage effective cooperation. As a result of these

and other proven benefits in terms of project performance of D&B, the

trend is definitely indicating rapid growth for this type of procurement.

Figure 6 below illustrates the growth in usage of D&B as a procurement

method as opposed to traditional procurement. Figure 7 is a summary of

the survey conducted by Zweig-White Information services in conjunction

with the Design-Build Institute of America in 2005, which shows the

perception of projected growth for D&B amongst construction

professionals:

Figure 8: A: Growth in Design and Build as preferred procurement method. Source: Design and Build Institute of America (2005)

Page 28: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

20

Figure 9: A: Perception of growth in Design and Build as procurement Method.

Source: Design and Build Institute of America (2005)

Page 29: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

21

4. HISTORICAL CASE ANALYSIS 4.1 Background The following case comparison was adapted from the 2002 Construction

Industry Institute (CII) study on the impact of different construction

procurement systems. The purpose of the CII report was to produce data that

records the economic impacts of the type of procurement system used for

construction projects, specifically on productivity. For the purpose of this

research report, Design and Build and traditional procurement (Design, Bid

and Build) will be compared exclusively.

The following distinction is vital for reference throughout the case: In D&B

contracts, a single entity (normally the main contractor) is responsible for both

the design and construction of the project. Contractually, this provides the

owner with a single point of reference. Traditional procurement (DBB) on the

other hand separates the design and construction aspects of a project. The

owner contracts with a design organisation for the complete design

specifications. Thereupon fixed price bids (tenders) are solicited from

construction contractors (main contractors) to carry out the erection of the

building. The successful selected contractor will then enter into an agreement

with the owner to build the facility according to submitted plans and

specifications.

4.2 Case Structure As mentioned, for the purpose of this report, D&B and traditionally procured

contracts were compared exclusively. For a project to be classified as a D&B

project in this study, one particular organisation had to perform 50% or more

of both the design and construction of a project. If this was not the case, the

project was classified as a DBB (traditional). The total number of project

participants equated 617 from various countries in the world. The project

participants fell into two categories: Owner submitted projects, and contractor

submitter projects. Of the 617 participants, 326 (split: 82 DB, 244 DBB) were

owner projects, and 291(split: 128DB, 163DBB) were contractor projects. The

participant structure is represented by the figure below:

Page 30: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

22

Figure 10: Case comparison structure. Source: Construction Industry Institute (2002)

4.3 Metrics This case compared D&B with traditional procurement with regards to the

following metrics:

• Performance: Cost, Schedule, Safety, Changes, Rework and

Productivity

• Practice: Pre-Planning, Team Building, Zero Accident

Techniques, Project Change Management,

Information Technology, Materials Management,

Start-up Planning, Total Quality Management (TQM)

Based on the metrics described above, the study was divided up into sub-

sections for comparisons. Each project (D&B and traditional) was compared

by: 1. The type of industry it operates, (industrial or building), 2. The nature of

the project (modernisation, add-ons and Greenfield – meaning a brand new

project) and 3. Cost categories (total project value). This structure is

represented by the figure below:

Page 31: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

23

Figure 11: Case comparison structure 2. Source: Construction Industry Institute (2002)

4.4 Case Findings 4.4.1 Industry Group

As indicated by figure 12 below, the study indicated that the majority of

submitted projects were traditionally procured as opposed to D&B, especially

owner submitted projects where DBB was used 9 times more often than D&B

in the building industry, and about 2 times more often in the industrial industry.

Although contractor submitted projects indicated a much closer split, DBB was

still more common than D&B. The word “traditional’ might explain the reason

for this, as this is still the preferred method for procuring construction projects

as a result of experience, but this trend is definitely changing (see figure 8 in

literature review).

Figure 12: Case comparison by industry. Source: Construction Industry Institute (2002)

Page 32: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

24

4.4.2 Nature

The literature indicates that D&B projects are more commonly used in higher

cost projects as apposed to traditional procurement, which tends to be used in

smaller projects. Greenfield projects have by far the higher cost component

compared to add-ons and modernisations. Owner submitted projects (see

figure below) still however indicated that traditional procurement is preferred

to D&B, even in higher cost projects such as green-field projects. Contractor

submitted projects on the other hand clearly illustrated that D&B is preferred

to traditional for higher cost projects. See figure 13 below:

Figure 13: Case comparison by nature. Source: Construction Industry Institute

(2002) 4.4.3 Cost

Although owner submitted projects clearly indicated that traditional

procurement was preferred to D&B, as project size (in terms of cost)

increased the ratio difference between DBB and D&B decreased. As indicated

below, for projects worth R500 Mil ($50 Mil) or more, the ratio is almost 1:1 as

opposed to projects worth less than R150 Mil ($15 Mil) where the ratio is

almost 1:5. Contractor submitted projects on the other hand clearly indicated

that D&B projects were preferred for higher cost projects (as per the

literature). On average, it was found that D&B projects had mean cost of R805

Mil as apposed to traditionally procured projects, with a mean cost of R227

Mil. Please see figure 14 below for a graphical representation.

Page 33: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

25

Figure 14: Case comparison by cost. Source: Construction Industry Institute (2002)

4.4.4 Performance Comparison

In terms of overall performance, owner submitted projects indicated that D&B

outperformed DBB (traditionally procured) projects in the cost, schedule,

changes, rework and practice use components (5 out of the 6 metrics). Safety

was the only metric where DBB procurement outperformed D&B. The

‘schedule’ metric, which looks at project timelines, indicate that DBB

outperformed D&B under ‘construction phase duration’ – this could be

explained by the fact that D&B projects (as mentioned under cost) tend to be

higher cost, and as a result take longer to complete. The table below is a

direct comparison between owner submitted D&B projects and DBB projects.

Shaded blocks indicate better performance:

Page 34: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

26

Figure 15: Case comparison overall performance by owner submitted

projects. Source: Construction Industry Institute (2002) Construction submitted projects painted a slightly different picture. Although

on average, D&B projects outperformed traditionally procured projects, the

split was slightly more balanced. Traditional projects outperformed D&B

projects in cost as well as schedule related metrics. However, differences

were not significant. The cost component could be explained by the fact that

D&B contractors have to quote (tender) on a project before any design work is

done. This could also be as a result of how changes were handled in D&B

projects (considering that they had an average duration far longer than DBB

projects.

Page 35: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

27

The schedule component could be explained by the fact that D&B contractors

are responsible for the majority of the design and construct (above 50% as

defined previously). This could result in D&B contractors not being able to

estimate or predict durations accurately, as D&B projects tend to last much

longer than DBB, and have more uncertainty upfront as apposed to DBB

where the contractor only commences work after the design is complete, and

project requirements have been ‘ironed out’. The table below is a graphical

representation of contractor submitted projects with respect to D&B and DBB.

Again, shaded blocks indicate better performance.

Figure 16: Case comparison overall performance by contractor submitted projects. Source: Construction Industry Institute (2002)

Page 36: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

28

4.4.5 Summary

The study found that D&B projects were significantly larger on average in cost

than traditionally procured projects, for both owner and contractor submitted

projects. Also, project performance should not be seen in isolation, since

factors influencing productivity and performance, such as the size, industry,

nature and cost, should be accounted for. Ceteris paribus, the study revealed

a clear performance advantage for owners when D&B procurement was used.

However, for contractors, the performance of D&B over traditionally procured

projects was not that clear. This may be as a result of the increased risk,

uncertainty, increased scope of works and longer timeframe that contractors

operate in when procuring a D&B project. Despite this, overall for contractor

submitted projects, D&B still outperformed traditionally procured projects. The

results of the overall comparison between the D&B projects and traditionally

procured projects (DBB) for both owner-submitted and contractor submitted

projects are summarised below. The white block in the ‘Overall’ section

indicates which procurement methods outperformed the other.

Figure 17: Case comparison of overall performance of owner and contractor submitted projects. Source: Construction Industry Institute (2002)

OWNER CONTRACTOR OWNER CONTRACTOR OWNER CONTRACTOROVERALL DB *** DB Traditional *** ***

OWNER CONTRACTOR OWNER CONTRACTOR OWNER CONTRACTOROVERALL DB DB DB DB DB DB

*** No DifferenceBold Significant Difference

CHANGES REWORK PRACTICE USE

COST SCHEDULE SAFETY

Page 37: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

29

5. METHODOLOGY

Choosing the correct methodology is vital if this report is to add value. For the

purpose of this report, qualitative, quantitative, action research and historical

case studies were all considered. Brymann (1992) outlines that the most

important difference between the qualitative and quantitative approach is as

follows: a qualitative approach focuses mainly on the perspectives of those

being interviewed and in contrast, a quantitative approach focuses

predominantly on the concerns of the researcher. Furthermore, according to

Saunders (2003), action research is the management of a change initiative. In

other words: being able to implement a change agent in an existing process to

determine its impact. Alternatively, historical case studies, as the name

suggests, makes use of a past event or process, which allows the researcher

to analyse the outcome as well as its implications.

After careful consideration, it was decided that for the purpose of this report,

the researcher should focus predominantly on the following qualitative

methods:

• Literature review including historical case study comparing Design and

Build (D&B) projects with Design Bid and Build Projects (DBB)

• Semi-structured interviews

5.1 Literature Review The literature review in this proposal makes it clear that the hypothesis can

not be solved by exact science. According to Naoum (2001), each

construction organisation operates in a different environment and with a

different culture, hence the need to focus on the perspectives by those

interviewed. For this, a qualitative approach needs to be adopted. Reviewing

and analysing current as well as dated literature related to the research

question to gain a broad understanding of the present situation as well as a

possible future outlook. Literature was gathered in the form of accredited

journals, books and by interacting with researchers in this area.

Page 38: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

30

The following were identified as key topics for addressing the research

hypothesis:

1. Productivity in the South African construction Industry

2. Lean methods applied in the industry

3. Design and Build Procurement and traditional procurement

Even though action research would have been a good method for measuring

the effectiveness of the implementation of the hypothesised procedures, time

constraints made this process simply impossible, especially due to the long

term nature of construction projects. However, historical case studies allowed

the researcher to compare different construction projects to determine the

impact of specific implemented procedures, methods or systems over time.

One limit to this type of research is of course the availability of project history

and the accuracy of recorded data.

For the purpose of this report, two types of projects and procurement methods

were examined specifically:

1. Design and Build procured construction projects

2. Traditionally procured construction projects

The reason for comparing these two types of projects is simply because D&B

projects and traditionally procured projects operate on different sides of the

scale, in terms of legal setup, risk, responsibility, party interface as well as

value chain integration as described in the literature review. Lam (2004)

argues that, because of the way design and build projects are structured, it

lends itself to the implementation of lean techniques such as partnering,

benchmarking, value engineering, etc. If this is the case, then it can be

determined what the impact of lean techniques are on productivity by

comparing design and built projects with traditionally procured projects (see

research hypothesis).

Page 39: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

31

As discussed in the literature review, design and build projects make the

integration of information easier, streamlines communication as well as

resulting in time efficiency and cost savings. This claim is endorsed by results

from the interviews and survey. Furthermore, it also became evident by

comparing design and build projects with traditionally procured projects from

historical cases.

5.2 Interviews Interviews with 7 different members of the construction value chain were

conducted. Individuals interviewed all reside in the Western Cape. A semi

structured interview approach with guideline questions was adopted. All

questions related to relevant issues raised in the literature review, with

regards to improving productivity in construction by implementing lean

methods. The semi structured interviews were divided into the following

categories:

1. Design and Build procurement vs. traditional procurement

2. Productivity

3. Lean methods in construction

4. General

For a detailed list of questions and references, please see appendix. After

typing up the interviews, recurring themes were identified and compared with

the literature review. (See the ‘Findings’ section and appendix). Lastly,

representative quotes from the interviews were identified and grouped with the

recurring themes. The findings from the collected data were used as the

foundation for the conclusion and recommendations for this report.

Page 40: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

32

5.3 Surveys As explained by Saunders (2003), surveys are a methodology whereby a

sample of subjects is drawn from a population and studied to make inferences

about the population. Compiling a survey involves the use of questionnaires to

gather data from the sample.

An on-line survey for the purpose of this report was conducted in order to gain

deeper industry insight with regards to productivity in construction, and

especially the implementation of lean methods. 47 individuals responded to

the survey. Responses were limited to individuals operating in the Western

Cape. Respondents include members from the following professions in the

construction industry:

1. Developers (3 total)

2. Project managers (5 total)

3. Architects (4 total)

4. Engineers (5 total)

5. Consultants (8 total)

6. Main Contractors (14 total)

7. Co-Contractors (7 total)

8. Suppliers (1 total)

The questions for the survey were compiled after analysing the interviews. As

a result, the main focus of the survey was to determine the response with

regards to specific factors. Amongst these were partnering, procurement

preference and implications as well as ranking items related to productivity

such as communication, integration and transparency. Data from the survey

was analysed by comparing individual responses, filtering results (where

relevant) as well as identifying recurring themes (where relevant) in order to

make reasonable assumptions. Findings from the survey were also used as

the cornerstone for the conclusion and recommendations. Please see the

appendix for the complete survey analysis.

Page 41: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

33

6. FINDINGS 6.1 Productivity According to the Egan Report (1998), the construction industry globally is

underperforming. Shakantu (2007) endorses this by stating that the South

African construction industry is underperforming in terms of return on

investment. Egan claims this is due to customer dissatisfaction, untrained

workforce, low profit margins, and a tender based procurement system. The

2002 study conducted by the Michigan Tri-Partite Committee concluded that

the greatest barriers to productivity are coordination of design, information

flow and constructability, and the greatest areas for improving productivity on

construction projects are communication between members, pre-project

planning and coordination amongst members again. Despite the fact that

construction has experienced faster growth than any other sector, low levels

of productivity continue to cost South Africa millions of Rands every year.

6.2 Lean Lean production methods have been applied with great success in the

manufacturing industry. According to Diekmann (2003), 1.customer focus,

2.eliminiation of waste, 3.continuous improvement, 4.people (culture) and

5.standardisation are the 5 enablers for implementing lean in construction.

However, the construction industry differs significantly from the manufacturing

industry. This is in line with Barrie’s (1992) claim that the construction industry

is unique-project based production as mass replication and factory production.

As a result, lean techniques are often difficult to successfully implement in

construction. Some of the barriers for lean implementation are (but not limited

to): the duration and complexity of construction projects, the fragmented

nature of the industry, the high amount of role players and low levels of

integration and communication amongst them. Peng (1996) argues that new

methods of procurement are the key to overcoming inhibitive tendencies

posed by the complex nature of the construction industry.

Page 42: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

34

6.3 Design & Build and Design Bid & Build Egan (1998) states that the construction industry rightly complains about the

difficulty of providing quality output when clients select designers and

contractors on a lowest cost basis. This is exactly the problem that the

traditional procurement system enforces – based on a fragmented design and

build division, and a ‘lowest-cost’ appointed contractor.

Design and Build (D&B) on the other hand makes use of one organisation to

provide the client with both the design and construction element. According to

Seng (2006), Design and Build tends to be quicker than traditional

procurement, both in terms of site construction and total project time. Seng

continues by saying that the benefits of D&B are accrued simply because of

its ability to integrate the project team members, produce open

communication and encourage effective cooperation. Furthermore, Cornick

(1991) states that because the design and build method of procurement offers

a single point of responsibility for both the design and production, it supports

the successful application of quality management to a building.

Research by the Design and Build Institute of America (2005) indicates that

the use of D&B as procurement is increasing rapidly, and according to

predictions, should surpass the traditional form of procurement in

construction.

6.4 Case Comparison This case compared D&B projects with traditionally procured projects (Design

Bid & Build). A total of 617 projects were submitted comprising of contractor

submitted projects as well as owner submitted projects. In terms of

performance and practice - these two procurement methods were compared

against each other with regards to total cost-, schedule/programme related

items as well as safety, change (or rework items) and practice use (i.e.

constructability etc). Furthermore, projects (both D&B and DBB) were

categorised per industry, nature and cost structure.

Page 43: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

35

METRIC Owner ContractorCost DB ***Schedule DB TraditionalSafety *** ***Changes DB DBRework DB DBPractice use DB DB(*** -- No Significant Difference)(BOLD -- Significant Difference)

The study found that the use of traditionally procured projects still far

outweighs D&B projects, although less significantly in the industrial sector.

Furthermore, it was found that D&B have a mean project value of R805 Million

as opposed to DBB with a mean of R229 Million in comparison. This may

explain why ‘green-field’ projects made more use of D&B as opposed to ‘add-

ons’ and ‘modernisations’, since both the latter are smaller in size and cost.

Lastly, the study concluded, ceteris paribus, that the use of D&B projects

showed a significant advantage over traditionally procured projects for

owners. For contractor submitted projects, the results were not as convincing,

however, overall D&B still outperformed traditionally procured projects.

Results are summarised below:

Figure 18: Case comparison of overall performance of owner and contractor

submitted projects. Source: Construction Industry Institute (2002) 6.5 Interviews Interviews were carried out, compiled and analyzed over a period of 3 weeks.

All the interviewees had more than 10 years experience in the construction

and property development, with the exception of 1. See figure 19 below:

Figure 19: Interviewee profile

Interviewee Position Division No. of years in No. of years inname* current organization the industry

Mark Construction director All construction** 5 25Brian D&B coordinator D&B 1 21Peter Contracts Manager All construction** 14 21Thomas General Manager Construction Business School 11 14Paul PQS Quantity Surveying 4 4Barry Project Manager Project Management 18 28John Developer New Developments 15 19

* Interviewee names have been changed for confidentiality purposes** Industrial, Residential, Commercial and Residential

Page 44: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

36

As mentioned in the methodology section, the purpose of the interviews were

to determine what the perception of influencing factors were with regards to

lean, productivity and the difference between D&B procurement as apposed

to the traditional method of procurement. The following themes emerged

throughout these interviews under the mentioned categories (respectively):

• Lean: Partnering, construction environment, synergy, standardisation

total quality management (TQM) and value engineering (VE)

• Productivity: Communication, integration, performance measurement,

teamwork and management issues

• D&B: Efficiency, design and construction overlap, risk and

responsibility

• Traditional: Flexibility, design and construction overlap, risk and `

responsibility

Below is a summary of the four categories (D&B procurement, Traditional

procurement, Productivity and Lean) and overarching themes from the

interviews. Each theme is described by representative quotes derived from

the interview transcripts. A complete questionnaire set for the semi-structured

interviews can be viewed in the appendix: interviews.

Page 45: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

37

Categories and Themes Design and Build

A. Efficiency

B. D & B Overlap

C. Risk

Representative Quotes “The main benefit of this method is that the contractor can influence the design process right from the start and make use of valuable information from the rest of the team” “In my experience the design and build is generally quicker” ”It allows the client to streamline and integrate this whole process of design and build, and as mentioned, ends up saving him significantly over the lifecycle of the building.” “The overlap between design and build is much higher, because the contractor is in control of all the information, with less ‘foreign’ communication hurdles to overcome.” “The design and construction phase overlap tends to be a lot bigger compared to those of traditional projects. Mainly because the contractor takes responsibly for the facilitation of the whole process” “The contractor becomes responsible for overseeing the contract and therefore coordinating the different functions of the design team” “The contractor takes control of the project, in other words, he becomes responsible for the successful outcome of the project. In doing that, he takes on the risk for the design as well as the construction process”

Page 46: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

38

Traditional A. Flexibility

B. D&B Overlap

C. Risk

“You’ll see that design and build is described as giving the client minimum flexibility, but the clients risk is also the lowest compared to the other methods like traditional, which is more flexible for changes at a later stage in the contract” “This is why I think traditional construction projects may be a bit more flexible to suit the clients ALWAYS changing needs” “With traditional – a lot of times the project can be novel for the whole team. This places tremendous stress on both the design and build part of the project.” “In my opinion, traditional construction projects’ design phase and building phase can overlap more. Why should the design for the roof trusses (example) be finished when the foundations are not cast yet? This design function can be performed while the construction is underway” The contractor assumes less risk. The client however, takes final responsibility of making sure the project ties up in the end. “Design and build project will be worth undertaking, is when the client knows exactly what he wants, and makes use of a contractor who is familiar with what the client wants, otherwise it make more sense using the traditional procurement system that allows the client some flexibility in terms of changes”

Page 47: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

39

Productivity A. Communication

B. Integration

C. Performance

measurement

D. Teamwork

E. Management

“Clear lines of communication, collaboration and detailed and clear specifications from the client increases productivity” “As mentioned earlier, improved productivity is definitely a consequence of better communication.” “EVERYTHING MUST BE INTEGRATED if you want to become world class.” “…but once we put the measurements in place, integrate everyone in the organisation and analyse the data that we have gathered afterwards, I believe that it will have a significant impact on productivity” “What we as a professional team did in (which is standard by the way) to measure performance, is the construction programme” “The main tool for measuring productivity is probably the information required schedule (IRS), the contractors report, and the contractors programme “ “At the end of the day, by understanding how the other works, we are able to gel together a lot better. This then translates in delivering a better service, as a team, on the project at the end of the day, which means that the client will want to work with us all again!” “The wrong tool for the job is constantly an issue that stops sites from achieving high productivity – a result of bad management.”

Page 48: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

40

Lean Construction A. Partnering

B. Environment

C. Synergizing

D. Standardization

E. TQM and VE

“The main benefit of partnering with members of the supply chain, including members from the professional team, is of course that we all understand the way the other works, we all have mutual goals, and we are all open to each other – transparent. “ “Partnering is about delivering a better product” “All projects are unique, positions are different, and environment is different etc. whereas in the manufacturing environment, everything is standardised and mechanised” “Construction projects, no matter how close to a previous building, are ALWAYS different. Ground conditions, municipal regulations, weather conditions, you name it. Manufacturing happens in a factory, pumping out one after the other of a standard product.” “Synergy is what pushes production and a superior product at the end of the day” “The supply chain for both of these procurement systems is the same, the way in which the chain differs, is how they integrate and work together” “The implementation of standardised tools in the construction industry is very limited, mainly because it is different from other for example manufacturing” “D&B lends itself for making use of lean techniques such as partnering, TQM and value engineering” “TQM essentially looks at ways that companies such as us or our partners, can ‘unlock’ their potential”

Page 49: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

41

The table below is a key point summary by interviewee with regards to the four categories covered. The key points under each

category by interviewee describe the essence of the interview findings. Please note: names have been changed for confidentiality

purposes.

Design and Build Traditional Productivity Lean Construction Mark Contractor increased responsibility Less design and construct overlap Don’t use productivity measurements Projects are unique and not standardized

Contractor coordinating entire team because control lies with many parties Implementing in 2009 on the following: Standardization opportunity is limitedBigger design and construct overlap Clients are moving away from traditional Turnover, profitability, money received on Better communication reduce time wastagefor D&B projects towards D&B time, wastage, construction guarantee Partnering creates a mutual driveDependant on relationships and trust Barriers between parties causing loss Partnering increases communication efficiency

of productivity.Better communication = higher productivityCollaboration and early involvement of all the key players

Brian More risk for the contractor Less risk for the contractor Better and more effective commutation Partnering, value engineering etc are all Less risk for the client More risk for the client between all the members in the project based on a principle of capturing value from Less flexibility for the client Flexible in terms of changes later increase total productivity all the members involved, hence the import-Benefit - everyone's input from the start Valuable input from members lower in ance of good communicationMore efficient (cost and time) the supply chain are lostBetter commutation

Peter Market is moving towards this form Currently this form of procurement is Can not stand in isolation, must be seen Partnering - understanding how others workof procurement, especially overseas becoming less attractive, as clients see Depends on involvement, communication Transparency and mutual goals improve clients the gains made overseas from D&B teamwork etc communication dramaticallyRisk transferred to the contractor Must be measured in order to improve Synergizing in order to create supers productTo work - the contractor has to be To increase productivity, make everythingfamiliar with the type of project visible, and focus on people's happinessLends itself to lean techniques (TQM) Leverage by proper planning

Thomas Ultimately lower cost, higher quality Much more flexible for client if he is Make use of a construction programme Partnering - collaboration in order to More risk for contractor not 100% sure what he wants, but for the project to measure productivity for create a better product for the clientMinimum flexibility for client wants to start building the whole team (output over time) TQM - to unlock potential amongst variousContractor operates in set framework Less cost effective membersbased on the lump sum provided Value Engineering - make use of a wide ray Client can leverage lifecycle cost by of input to be more efficientproper design work

Page 50: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

42

Figure 20: Interviewee key point summary

Design and Build Traditional Productivity Lean Construction Barry Client pays premium for reduced risk Possibly cheaper quote upfront Contractors construction programme Difficult, because construction is unique,

Client has a fixed price, knows what More overlap between design and Above = prompts the whole team to per- more components, longer in duration andhe/she is going to pay for the project construct phase, because there is no form make use of a lot more parties involvedWorks when the client knows exactly fixed sum agreement before the project Integration of the supply chain is important (reliant on many members in the chain)what he/she wants starts - hence the design and construct Clear communication is beneficial to Mechanization will improve leanLess overlap between design and can overlap more productivityconstruct phase

Paul Requires a lot of up-fron cordination The main contractor is just another Productivity is determined by workers Taking away the 'fat', i.e. remove the un-from the main contractor link in the chain and how they are managed neccesary bitsOne party manages the complete Involvement is limited Low levels of productivity is often a result Learn from each others business, and project from finish to start Contribution and value is lost of bad management compliment each otherThe final responsibility is with the Differs from design and build Control and cordination between program By gelling better together, delivers a bettermain contracor contractually Set and enforce targets and goals end product

Work with instead of against

John Works on projects that the contractor More involvement required from Make use of information required UK is becoming more standardized, but SAis familiar with the client over the duration of schedule, contractors report and has cheap labout - wont happen soonRelies on trust design and construction contractors programmesAfter negotiation, the clients input is Generally takes longer The team members are not at all as minimum integrated as they should beD&B takes quicker Teamwork and competence of the team

is vital to achieving optimum productivityClear lines of communication, collaborationDetailed and clear specifications

Page 51: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

43

6.6 Survey The survey comprised of a set of 10 in depth questions with regards to lean

techniques in construction, productivity and D&B procurement vs. traditional

procurement (see appendix). A total of 47 professionals responded, ranging

from the client to the suppliers. Main contractors were by far the majority

(30%), followed by consultants and co-contractors (17% and 15%

respectively). Results indicated that value chain members were fairly

integrated, but the level of integration tapered out further down the chain.

Most of the team communicated with consultants on a daily basis (96%), as

opposed to 36% of the team communicating with suppliers daily. See figure

21 below:

Figure 21: Integration amongst value chain members

Communication was rated as one of the most influencing factors with regards

to productivity, with a mean rating of 4.6 out of a possible 5. This is in line with

Koutsikouri’s (2008:216) claim: “...communication is seen as intrinsically

worthwhile within the team in order to create mutual trust between the

different team members”. Accurate documentation and transparency of

information was regarded as less important with respect to influencing

productivity. See figure 22 below:

Integration amongst value chain members

0%

50%

100%Client

Project Manager

Principal Agent

Architect

EngineerConsultant

Main Contractor

Co-Contractor

Supplier

Page 52: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

44

Figure 22: Rated importance in terms of influencing productivity

81% of respondents agreed that the contractor assumes more risk in D&B

projects, but only 66% agreed that the client carries less risk as a result

thereof. 85% thought D&B projects saves time and 64% thought it saves cost.

Also, 77% claimed that D&B projects makes communication and integration

easier and 74% said that this procurement method ‘lends’ itself for the

implementation of partnering. See figure 23 below:

Figure 23: Perception of D&B as opposed to traditional procurement (DBB)

Rated importance in terms of influence on productivity

00.5

11.5

22.5

33.5

44.5

5

Communication Integration Transparancy Motivation Documentation

Ratin

g

Perception of D&B opposed to traditional procurement

05

1015202530354045

Contractor hasmore risk

D&B is lessflexible

D&B saves time D&B saves cost D&B makes foreasier integration

andcommunication

D&B makes lendsitself to partnering

Res

pond

ents

AgreeNeutralDisagree

Page 53: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

45

91% of respondents agreed that the SA construction industry is currently

underperforming in terms of productivity. Interestingly enough, when the

question was asked whether the unique construction environment makes it

more difficult to implement lean techniques, specifically standardization and

pre-assembly, the result was a 50/50 split. Tam (2007:68) specifically argues

that: “The use of prefabrication has been considered as one of the most

effective waste minimisation methods in the construction context - however,

the construction industry has found extreme difficulties to implement it.” See

figure 24 below for findings:

Figure 24: Perception of the construction industry

30 out of the 47 respondents claimed to be a formal ‘partner’ in the industry.

Interestingly, 80% of the formal partners felt that partnering improved project

performance dramatically, as opposed to non-partners with only 17% claiming

dramatic performance improvement. See figure 25 below:

Figure 25: Perception of partnering ability to influence productivity

Perception of the construction industry

0

1020

3040

50

The SAconstructionindustry is

underperforming

The constructionenvironment

makes it difficultto implement lean

There is limitedscope for

standardization inconstuction

Resp

onda

nts

AgreeDisagree

Page 54: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

46

The table below is a key point summary of responses to the open ended question: ‘Name at least one area where productivity can

be improved on construction projects.’ Responses were sorted into 4 overarching categories – 1.communication and integration

2.management and waste 3.training and 4.other.

Figure 26: Key point summary based on perception of areas to influence productivity

Communication and Integration Management and Waste Training OtherCommunication between stakeholders Resource management: Men Time and Materials Re-introducing apprenticeships Wet trades Communication between client, contractor and professional team The workforce understanding what they are building Overcome destructive nature of labour Brickwork Coordination of scaffolding use Critical path contractors Labour Empower through hardware & technology Better planning Do it right the first time Skills Development Formwork Information management Material waste Training Better methods for measuring productivity Team work Material handling/scheduling Improved Knowlede and Skill Quality Information between stakeholders Eliminate waste Improve skills of labour Painting Communication Tools Better training of teams More mechanisation Information management Better Tools Correct training Delivery (Time) Information flow Less waste on site Employ qualified staff Co-Contractor trades Information flow Reduced Wastage Skills Development Improved standards for measuring productivity Communication Reduce Absenteeism Reliable sub-contractors Labour taking ownership Communication of information Reduce time delays Better skills Formwork Making information flow well Materials waste by bad management Skilled labour Better measures of productivity Upfront Integration Labour control Procurement MethodsPre-contract planning Supervision Programming of contracts Less changes after project initiation Communication Specialized Tools Get sub/co-contractors involved sooner Target incentives Accurate and in time information Correct management Time management Better supervisors Communication Clear Instructions Information Absenteeism PARTNERING Sick DaysTrade coordination nvolving team members in innovative problem solving Information flow and distribution Get it right the first time Value Engineering Improved planning of project with client to reduce changes

Page 55: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

47

Based on the above results, the graph below was compiled to illustrate the 5

most observed areas for improving productivity, based frequency in the

survey: “Communication and integration’ was mentioned more than any other

area, closely followed by ‘management and waste’. Lastly, ‘better training’,

‘trade related issues’ (such as improving formwork, painting and brickwork)

and finally ‘method related issues’ (such as improving overall quality,

technology and methods for measuring productivity). See figure 27 below:

Figure 27: Ranked perception of areas to improve productivity.

Perception of areas to improve productivity

0

5

10

15

20

25

30

35

Communicationand integration

Managementand waste

Training Trade relatedissues

Method relatedrelated issues

Res

pons

es

Page 56: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

48

6.7 Summary of findings 6.7.1 Interview:

Results from the interviewees were in line with the literature review, despite

some minor deviations. One of these was the fact that some interviewees

regarded Design and Build projects to increase total contractual risk - not only

for the contractor (responsible party), but for the client as well, due to a

perception of the client putting all his ‘eggs in one basket’. If the contractor

defaults on delivery, then the client starts from scratch – hence the

importance of trust and using a good D&B contractor based on past

experience and performance. Furthermore, all interviewees agreed that

measuring productivity or performance is to first step and key to improving it.

However, there was little evidence to support that this was what was currently

happening in practice.

Interviewees also claimed that partnering dramatically improves coordination,

integration and communication on construction projects, which creates a

culture and spirit of mutual goal setting, understanding and teamwork -

ultimately improving overall productivity and project performance. Some

interviewees mentioned the importance of “taking everything into

consideration”. In other words – issues such as communication, integration,

coordination and culture cannot stand in isolation, but should be considered

as a whole in an attempt to improve productivity.

Lastly, all interviewees mentioned the fact that D&B projects are superior

compared with DBB, in terms of overall cost - no exceptions mentioned.

Although the literature suggested that indeed this is the case overall,

contractor submitted projects indicated inferior ‘cost’ performance by D&B

projects apposed to DBB. The reason for this, according to the case (Thomas,

2002) was as a result of the contractor taking full responsibility of the design

and construction element before any design work has been done – hence

increased uncertainty. Considering that most of the interviewees were

contractors, this result was unexpected.

Page 57: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

49

6.7.2 Survey:

It was evident that integration amongst value chain members takes place on a

much bigger scale than expected, however, integration seemed to taper off

further down the supply chain – the lowest levels of integration existing

between suppliers / co-contractors, and the rest of the value chain.

The majority of respondents viewed D&B projects superior in terms of time

saving, cost savings, integration of members and implementation of

partnering, as opposed to traditional procurement (DBB). The majority of

respondents further claimed that partnering improves productivity on

construction projects dramatically. Interestingly, actual partners in the industry

as opposed to non-partners in the industry had a significantly different opinion

with regards to partnering’s ability to influence productivity. 80% of partners

claimed that partnering improves productivity dramatically, as opposed to only

17% of non-partners claiming dramatic improvement.

Lastly, survey results suggested that productivity in the South African

construction industry is below par, compared with other industries. However,

there was a 50/50 split between respondents agreeing and disagreeing with

the statement that it is significantly more challenging implementing lean

techniques in the construction industry as apposed to other (such as the

manufacturing-) industries, despite the explicit different nature between these

sectors. This was unexpected since Peng (1996) clearly states that the unique

construction environment makes it difficult for implementing lean techniques.

This is endorsed by Barrie (1992) who argues that manufacturing industries

are characterised by mass production and replication, as apposed to

construction where every product is unique and the only one of its kind.

Page 58: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

50

The table below compares key findings across the literature, interviews and the survey:

Figure 28: Summary of findings based on literature, interviews and survey

No Topic Literature Interviews Survey1 Productivity in construction According to Egan (1998), the construction All 7 interviewees agreed that the SA 91% of respondents agreed that the SA

industry is underperforming globally, and Thwala construction industry is currently construction industry in underperforming(2007), low productivity is common in this industry underperforming

2 Productivity: Areas for According to the Michigan Tri-Partite Committee The majority of interviewees claimed that Survey respondents by far agreed that improving (2002), constructability, coordination, communication, factors such as better communication, improved communication has the biggest

planning and improved management ranked as the teamwork, integration and measuring of potential for improving productivity, followedtop 5 areas for improving productivity in construction performance and goal setting leads to by integration, motivation and teamwork

improved productivity

3 Lean: Benchmarking, value According to Peng (1996), TQM is continuous improve- Interviewees agreed that measuring Partnering and teamwork emerged as engineering, TQM, JIT and ment, and identifying common goals to reach client productivity is important for improving an important lean tool applied in partnering satisfaction. According to Mohamed (1996), benchmark- performance, however, it seemed that this practice. It was obvious from the results that

in is measuring performance in order to improve in the future rarely takes place in practice formal partners in the industry find the pro-cess much more beneficial than non-partners

4 Standardization: Application Barrie (1992) states that, because if the differences in environ- Opinion with regards to the implementation The split between those agreeing that standard-in construction ments (construction and manufacturing), it is often difficult of standardization varied. No significant ization could just as easily be applied to the

to transfer the benefits from standardization and pre-assembly conclusion could be drawn construction sector as any other, was exactlyto construction. 50/50. No significant conclusion could be drawn

5 Design and Build (D&B) and Thomas (2002) concluded in his comparative study between D&B 6 out of the 7 interviewees agreed that 85% and 65% felt that D&B outperforms DBBDesign-Bid-Build (DBB) and DBB projects, that D&B projects outperform the latter D&B projects outperform DBB based in terms of time and cost, respectively. Also,

significantly in general (overall performance metrics) on ultimate time, quality and cost of the 77% agreed that D&B makes communication project and integration easier as apposed to DBB

Page 59: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

51

7. CONCLUSIONS AND IMPLICATIONS 7.1 Conclusions The construction industry in South Africa is currently underperforming. This

fact was confirmed by the literature in this study. Furthermore, all interviewees

concurred with this, as well as 91% of survey respondents – hence the need

for improvement in productivity in this sector. Lean production techniques

(such as benchmarking, total quality management, value engineering and

partnering) have been applied extremely successfully in the manufacturing

industry, but because of the distinct nature of construction, the same

techniques are often more difficult to implement with the same effect. Despite

this fact, the literature as well as interview and survey findings shows

evidence of lean techniques applied with great success on construction

projects, especially on projects making use of innovative procurement

techniques such as Design and Build (D&B).

The purpose of this report was to investigate the link between the

implementation of lean techniques on construction projects and higher levels

of productivity. In order to better understand this correlation, it was necessary

to compare productivity levels of projects making use of lean techniques, with

those not making use of lean techniques. In order to achieve this, D&B

projects (making use of lean) was compared with traditional procurement (not

making use of lean).

According to Lam (2004), D&B lends itself to the implementation of lean

techniques, such as partnering and total quality management, with the

specific focus on improving communication, coordination, collaboration,

integration, teamwork and ultimately client satisfaction on projects. Seng

(2006) states that the benefits of D&B procurement are accrued simply

because of its ability to integrate the project team members produce open

communication and encourage effective cooperation, as apposed to

traditional procurement (DBB), mainly due to its fragmented nature.

Page 60: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

52

The historical case study in this report compared 617 different projects, split

between D&B and traditionally procured projects. Ceteris paribus, the study

concluded that D&B projects overall outperformed traditionally procured (DBB)

projects with regards to total cost, changes, rework and practice use. This study

provides sufficient evidence that D&B projects outperform traditionally procured

(DBB) projects by comparison, taking circumstances into account.

Evidence in this report suggests that the implementation of lean techniques in

construction results in higher levels of productivity. This happens primarily

indirectly through improved communication, -coordination, -teamwork, higher

levels of integration, and better project planning (especially upfront).

7.2 Implications for managers As mentioned, to test the true effect of lean on productivity for construction

projects in the future, action research would be ideal as a result of introducing a

change agent. However, due to the long term and complex nature of construction

projects, useful research options are limited since dedicated research over long

periods are required. Despite this, the study has indicated that improved

communication, -integration, -coordination and pre-project planning, significantly

increase productivity on construction projects, hence the importance of managers

to focus on these areas. However, the study also revealed that these issues

should not be seen in isolation, but rather as an ‘interactive whole’ – improving

one area should not lead to a decline in the quality of another

Furthermore, the study also suggested that by establishing formal and consistent

metrics for measuring productivity, managers will be able to record and

benchmark productivity in order to improve performance over time. However, this

rarely realises in practice, mainly as a result of increased onerous administration

and uncertainty with regards to the implementation thereof.

Page 61: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

53

7.3 Implications for future research Based on the research in this study, it would add value to carry out an in-depth

case study on a specific organisation, with regards to the impact of lean

techniques on construction projects. The reason for this is to cancel out

irregularities, inconsistencies and distortion of data that occur as a result of

comparing projects across different organisations, making use of different

standards, metrics and data collection - in other words, comparing apples with

apples instead of comparing apples with oranges. Also, future research in this

field may benefit by focusing on only a couple of metrics for measuring

productivity and performance (e.g. waste, absenteeism and information flow),

and determine what the impact of lean is in these specific areas, respectively by

making use of recorded data on company specific projects.

Page 62: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

54

BIBLIOGRAPHY AND REFERENCES

• Ballard, G et al 1995. “Toward Construction JIT”, Construction

Engineering and Management Programme, Department of Civil

Engineering, University of California

• Barrie, D et al 1992. “Professional Construction Management”, New York:

McGraw-Hill

• Brymann, A 1992. “Research Methods and Organisational Studies”,

London: Routledge

• Cornick, T et al 1991. “Quality Management and Design and Build: The

Opportunities for this Method of Procurement”, International Journal of

Quality and Reliability Management, vol. 8, issue 3, pp. unknown

• Chen, Q et al 2007. “Interface Management – A Facilitator of Lean

Construction and Agile Project Management”, Department of Building

Construction, State University of Backsburg, pp. 57-66

• Das, A et al 1997. “Just in Time and Logistics in Global Sourcing: An

Empirical Case Study”, International Journal of Physical Distribution and

Logistics, vol. 27, no. 3 / 4, pp. 244-258

• De Leeuw, C 2001. “Value Management: An Optimum Solution”,

International Conference on Spatial Information for Sustainable

Development, Nairobi, Kenya, pp. 1-12

• Diekmann, J et al 2003. “Measuring Lean Conformance”, Department of

Civil, Environmental and Architectural Engineering, University of Colorado

• Egan, J 1998. Rethinking Construction, The Report of the Construction

Task Force, Department of Trade and Industry, London

Page 63: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

55

• Frodell, M et al 2008. “Swedish Construction Client’s Views on Project

Success and Measuring Performance”, Journal of Engineering, Design

and Technology, vol. 6, pp. 21-32

• Gregory, A et al 2001. “Reforming Project Management: The Role of Lean

Construction”, Lean Construction Institute, Ketchum, pp. 1-9

• Hyun-Gyung, I 2005. “Temporal Coordination Through Communication:

using Genres in Avirtual Start-up Organization”, Information Technology &

People, vol. 18, pp. 89-119

• Koutsikouri, D 2008. “Critical Success Factors in Collaborative Multi-

Disciplinary Design Projects”, Journal of Engineering, Design and

Technology, vol. 6, pp. 198-226

• Laedre, O 2000. “Use of Project Partnering in Construction”, Examining

the Effect of Project Integration and Target Pricing in Three Pilot Projects,

Trondheim, Norway, pp. 1-8

• Lam, E 2004. “Benchmarking D&B Procurement Systems in Construction”,

Benchmarking: An International Journal, vol.11, no.3, pp. 287-302

• Li, H 2000, “Partnering research in construction”, Engineering,

Construction and Architectural Management, vol. 7, pp.76-92.

• Mastermann, J 1992. “An Introduction to Building Procurement Systems”

E&FN Spin, London

• Mohamed, S 1996. “Benchmarking and Improving Construction

Productivity”, Benchmarking for Quality Management and Technology,

MCB University Press, vol. 3, no. 3, pp. 50-58

• Naidoo, S 2006. “South Africa: Construction Industry to Lead Growth”

Africa News Update, Retrieved in May 2008 at:

Page 64: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

56

http://www.afrika.no/noop/search.php?c=1378&l=en&query=South+Africa

+Construction+Growth&subscope

• Naoum, S 2001. People and Organizational Management in Construction,

Thomas Telford Publishing, London

• Peng, L et al 1996. “A Framework for Implementing TQM in Construction.

The TQM Magazine, vol.8, no.25, pp.39-46

• Ronco, W 1996. Partnering Manual fro Design and Construct, McGraw

Hill, New York

• Root, D et al 2007. “Integrated Collaborative Design”, Journal of

Engineering, Design and Technology, vol. 5, no. 1, pp. 7-22

• Saunders, M et al 2003. Research Methods for Business Students,

Pearson Education Limited, Harlow, England

• Seng, N 2006. “The Success Factors of Design and Build Procurement

Method: A Literature Visit”, Proceedings of the 6th Asia-Pacific Structural

Engineering and Construction Conference, Kuala Lumpur, Malaysia, pp.

1-10

• Shakantu, W et al 2007. “Beyond Egan's supply chain management:

advancing the role of logistics in the South African construction industry”,

Sabinet alectronic Journal, vol. 14, pp. 93-115

• Solomon, N 2005. “The Hopes and Fears of Design-Build”, Architectural

Technology, McGraw Hill Construction. Retrieved in October 2008 at:

http://ce.construction.com/article.php?L=5&C=347

• Sommerville, J et al 2000. “A Scorecard Approach to Benchmarking for

Total Quality Construction”, International Journal of Quality and Reliability

Management, vol. 17, pp. 453-466

Page 65: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

57

• Tam, V 2007. “On Pre-fabrication Implementation for Different Project

Types and Procurement Methods in Hong Kong”, Journal of Engineering

and Design Technology, vol.5, pp. 68-80

• Thwala, W et al 2007.“Motivation as a tool to improve productivity on the

construction site”, Department of Construction Management and Quantity

Surveying, University of Johannesburg, pp. 1-6

• Thomas, S et al 2002. “Measuring the Impact of the Delivery System on

Project Performance – Design-Build and Design-Bid-Build”, Construction

Industry Institute (CII), November 2002

Page 66: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

58

APPENDIX 1. Literature

Exhibit 1: Contribution of the percentage change in real value added by industry

to the total real annual economic growth rate (Source: Stats SA)

Exhibit 2: Estimates of number of employees per industry with 95% confidence

limits (Source: Stats SA)

Page 67: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

59

Exhibit 3: The Relationship of the ICD principles (Source: Integrated Collaborative Design, Root (2007))

Exhibit 4: Dimensions of Industry Cultures (Source: Hofstede, 2003)

Page 68: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

60

Exhibit 5: Technology and Organization (Source: Riley, 2001)

Page 69: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

61

Exhibit 6: Report Programme as at 27th August 20

Page 70: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

62

2. Interviews Interviewees: Background (Please note: Names have been changed for confidentiality purposes)

Name: Mark

Position: Construction Director

Number of years in company: 5

Number of Years in Construction: 25

Company: NMC

Date Established: 1978 (Known as Neil Muller Construction)

2004 (Re-branded as NMC (Pty) Ltd.)

Number of full time employees:

Nature of Business: Construction (Main Contractor)

Recent Projects: Parow Centre Cape Town

De La Rey, Northgate, Cape Town

Wispeco, Tygerberg, Business Park

Pick and Pay Distribution Centre, Airport

Name: Paul

Position: Professional Quantity Surveyor

Number of years in company: 4

Number of Years in Construction: 4

Company: Omkhai Consulting

Date Established: 2002

Number of full time employees: 8

Nature of Business: Quantity Surveying Consultation

Recent Projects: SFP Offices, Montague Gardens

Northharbour, Royal Ascot

Ruby Estates Residential, Milnerton

House Cambouris, Mooley Point

Page 71: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

63

Name: Brian

Position: Design and Build Coordinator / Head of Marketing

Number of years in company: 1

Number of Years in Construction: 21 (design and build in the UK)

Company: NMC (Pty) Ltd

Date Established: 1978 (Known as Neil Muller Construction)

2004 (Re-branded as NMC (Pty) Ltd.)

Number of full time employees in association: 30

Nature of Business: D&B Construction Exclusively (Main Contractor)

Recent Projects: Masterheads Building, Maitland, Cape Town

Bowler Metcalfe PET Extension, Philippi, Cape Town

Bell Equipment Offices, Airport City, Cape Town

Name: Peter

Position: Contracts Manager

Number of years in company: 14

Number of Years in Construction: 21

Company: NMC (Pty) Ltd

Date Established: 1978 (Known as Neil Muller Construction)

2004 (Re-branded as NMC (Pty) Ltd.)

Number of full time employees in association: 65 - Salary

250 - Wages

Nature of Business: Construction (Main Contractor) Partnering coordinator

Recent Projects: Orley Foods, Montague Gardens, Cape Town

Robertson and Cain Yacht Building Extension,

Woodstock, Cape Town

Page 72: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

64

Name: Thomas

Position: General Manager NMC Business School

Number of years in company: 1 (Business School)

10 (NMC)

Number of Years in Construction: 14

Company: NMC Business School

Date Established: 1978

2007 (NMC Business School)

Number of full time employees: 16

Recent Projects: Thomas has completed more than 12 modules for the

business school – lecturing other value chain members (from suppliers, to

architects), including but not limited to TQM, Value engineering, Corporate

Culture and Partnering

Name: John

Position: Development Manager

Number of years in company: 15

Number of Years in Construction: 19

Company: Old Mutual Investment Group Property Investment)

Date Established: 1845

2007 (Old Mutual Investment Group formed)

Number of full time employees: 4 development managers in Cape Town, 3

in Johannesburg, 2 in Durban (support staff not included)

Nature of Business: Development of properties for sale, lease or own use

in commercial, industrial, office and retail.

Recent Projects: Old Mutual Day Care Centre, Pinelands

Mutual Park Refurbishment, Pinelands

Cavendish Shopping Centre, Claremont

Page 73: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

65

Interviews Theme Summary: Part 1

Design and Build Traditional Productivity Lean Construction Mark Contractor increased responsibility Less design and construct overlap Don’t use productivity measurements Projects are unique and not standardized

Contractor coordinating entire team because control lies with many parties Implementing in 2009 on the following: Standardization opportunity is limitedBigger design and construct overlap Clients are moving away from traditional Turnover, profitability, money received on Better communication reduce time wastagefor D&B projects towards D&B time, wastage, construction guarantee Partnering creates a mutual driveDependant on relationships and trust Barriers between parties causing loss Partnering increases communication efficiency

of productivity.Better communication = higher productivityCollaboration and early involvement of all the key players

Brian More risk for the contractor Less risk for the contractor Better and more effective commutation Partnering, value engineering etc are all Less risk for the client More risk for the client between all the members in the project based on a principle of capturing value from Less flexibility for the client Flexible in terms of changes later increase total productivity all the members involved, hence the import-Benefit - everyone's input from the start Valuable input from members lower in ance of good communicationMore efficient (cost and time) the supply chain are lostBetter commutation

Peter Market is moving towards this form Currently this form of procurement is Can not stand in isolation, must be seen Partnering - understanding how others workof procurement, especially overseas becoming less attractive, as clients see Depends on involvement, communication Transparency and mutual goals improve clients the gains made overseas from D&B teamwork etc communication dramaticallyRisk transferred to the contractor Must be measured in order to improve Synergizing in order to create supers productTo work - the contractor has to be To increase productivity, make everythingfamiliar with the type of project visible, and focus on people's happinessLends itself to lean techniques (TQM) Leverage by proper planning

Thomas Ultimately lower cost, higher quality Much more flexible for client if he is Make use of a construction programme Partnering - collaboration in order to More risk for contractor not 100% sure what he wants, but for the project to measure productivity for create a better product for the clientMinimum flexibility for client wants to start building the whole team (output over time) TQM - to unlock potential amongst variousContractor operates in set framework Less cost effective membersbased on the lump sum provided Value Engineering - make use of a wide ray Client can leverage lifecycle cost by of input to be more efficientproper design work

Page 74: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

66

Part 2

Design and Build Traditional Productivity Lean Construction Barry Client pays premium for reduced risk Possibly cheaper quote upfront Contractors construction programme Difficult, because construction is unique,

Client has a fixed price, knows what More overlap between design and Above = prompts the whole team to per- more components, longer in duration andhe/she is going to pay for the project construct phase, because there is no form make use of a lot more parties involvedWorks when the client knows exactly fixed sum agreement before the project Integration of the supply chain is important (reliant on many members in the chain)what he/she wants starts - hence the design and construct Clear communication is beneficial to Mechanization will improve leanLess overlap between design and can overlap more productivityconstruct phase

Paul Requires a lot of up-fron cordination The main contractor is just another Productivity is determined by workers Taking away the 'fat', i.e. remove the un-from the main contractor link in the chain and how they are managed neccesary bitsOne party manages the complete Involvement is limited Low levels of productivity is often a result Learn from each others business, and project from finish to start Contribution and value is lost of bad management compliment each otherThe final responsibility is with the Differs from design and build Control and cordination between program By gelling better together, delivers a bettermain contracor contractually Set and enforce targets and goals end product

Work with instead of against

John Works on projects that the contractor More involvement required from Make use of information required UK is becoming more standardized, but SAis familiar with the client over the duration of schedule, contractors report and has cheap labout - wont happen soonRelies on trust design and construction contractors programmesAfter negotiation, the clients input is Generally takes longer The team members are not at all as minimum integrated as they should beD&B takes quicker Teamwork and competence of the team

is vital to achieving optimum productivityClear lines of communication, collaborationDetailed and clear specifications

Page 75: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

67

3. Survey Survey Questionnaire:

1. Where do you fit in the value chain? Please select the appropriate box:

• Developer

• Project Manager

• Architect

• Engineer

• Consultant

• Main Contractor

• Co-Contractor

• Supplier

2. What is your position in the organisation?

3. Which other value chain members do you deal with on a daily basis?

Please select:

• Client

• Project Manager

• Architect

• Engineer

• Consultant

• Main Contractor

• Co-Contractor

• Supplier

4. Please rate the following in terms of importance to influencing

productivity (1 lease important, 5 most important)

• Communication between members involved in the project

• Integration of all members of the project

• Transparency of information related to the project

• Motivation of people involved in the process

• Accurate documentation for reference purposes

5. Design and Build projects differ from traditional procurement in the

following ways: (Please choose ‘agree’, ‘neutral’, or ‘disagree’)

Page 76: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

68

• The contractor assumes more risk

• The employer assumes more risk

• Less flexible in terms of changes at a later stage

• D&B projects saves time

• D&B projects saves cost

• D&B projects makes integration and communication easier

• D&B projects lends itself to the implementation of partnering

6. Partnering: Are you currently a partner with any other member in the

value chain?

7. How would you describe partnering’s ability to improve or hinder

project performance. Please choose:

• Dramatic Improvement

• Slight Improvement

• No Effect

• Hindrance

8. What in your opinion is the main goal/benefit of partnering/collaboration

• Deliver a superior product to the client

• For the value chain to become more flexible

• Integration of information (value engineering)

• Increased transparency (performing better as one, as apposed

to working in silos)

9. Please choose ‘agree’ or ‘disagree’ to the following statements:

• The construction industry in SA is currently underperforming in

terms of productivity

• The unique construction environment (as apposed to

manufacturing) makes it difficult to measure and implement

methods for measuring and improving productivity?

• There is very limited scope for implementing standardisation in

the construction industry (e.g. industrialised building systems,

modular buildings, pre-cast elements etc)

10. Please name at least one area where you think productivity on

construction projects can be improved:

Page 77: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

69

Survey Results: Summary

Page 78: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

70

Page 79: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

71

Page 80: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

72

What is your position in the company? 1. Quantity Surveyor

2. General Manager / Partner

3. Project Manager/Commissioner

4. Sole Owner

5. Shareholder

6. Project Director

7. Director

8. Contracts Manager

9. QS

10. Alternate Director

11. Managing Director

12. Project manager / D&B

manager

13. Installation manager

14. Contract surveying manager

15. Operations manager

16. Quantity surveyor

17. Project Manager

18. Contracts manager

19. MD

20. Engineer

21. Development manager

22. Development Manager

23. Architect

24. PQS

25. Partner/Director

26. CEO

27. Engineer

28. Supervisory engineer

29. Divisional Manager

30. Projects Director

31. Architect

32. Business unit manager

33. Project Manager

34. QS

35. Structural Engineer

36. Project Coordinator

37. Projects Facilitator

38. Electrical Engineer

39. Project Developer

40. Architect

41. CEO

42. Managing director

43. Advisor

44. Project Manager

45. CEO

46. Project Manager

47. Alliance Procurement Manager

Page 81: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

73

Recurring themes in survey with regards to improving productivity

Communication and Integration Management and Waste Training OtherCommunication between stakeholders Resource management: Men Time and Materials Re-introducing apprenticeships Wet trades Communication between client, contractor and professional team The workforce understanding what they are building Overcome destructive nature of labour Brickwork Coordination of scaffolding use Critical path contractors Labour Empower through hardware & technology Better planning Do it right the first time Skills Development Formwork Information management Material waste Training Better methods for measuring productivity Team work Material handling/scheduling Improved Knowlede and Skill Quality Information between stakeholders Eliminate waste Improve skills of labour Painting Communication Tools Better training of teams More mechanisation Information management Better Tools Correct training Delivery (Time) Information flow Less waste on site Employ qualified staff Co-Contractor trades Information flow Reduced Wastage Skills Development Improved standards for measuring productivity Communication Reduce Absenteeism Reliable sub-contractors Labour taking ownership Communication of information Reduce time delays Better skills Formwork Making information flow well Materials waste by bad management Skilled labour Better measures of productivity Upfront Integration Labour control Procurement MethodsPre-contract planning Supervision Programming of contracts Less changes after project initiation Communication Specialized Tools Get sub/co-contractors involved sooner Target incentives Accurate and in time information Correct management Time management Better supervisors Communication Clear Instructions Information Absenteeism PARTNERING Sick DaysTrade coordination nvolving team members in innovative problem solving Information flow and distribution Get it right the first time Value Engineering Improved planning of project with client to reduce changes

Page 82: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

74

4. Case Comparison

Exhibit 1: Benchmarking and Metrics Questionnaire, Source: Construction Industry Institute, 2002

Page 83: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

75

Exhibit 2: Data Analysis and Tabulation Tasks, Source: Construction Industry

Institute, 2002

Exhibit 3: Performance Summary for Cost, Schedule and Safety, Source:

Construction Industry Institute, 2002

Page 84: An investigation to determine the impact of lean ...gsblibrary.uct.ac.za/ResearchReports/2008/Bezuidenhout.pdf• IBS Industrialized Building Systems ... concluded that production

76

Exhibit 4: Performance Summary for Changes, Rework and Practice Use, Source: Construction Industry Institute, 2002