an integrated model for production line ...1.3.1 problem description 4 1.3.2 problem statement 6 1.4...

26
AN INTEGRATED MODEL FOR PRODUCTION LINE BALANCING PLANNING ALI ASGHAR JOMAH ADHAM Thesis submitted in fulfillment of the requirements for the award of degree of Doctor of Philosophy of Technology Faculty of Technology UNIVERSITI MALAYSIA PAHANG 12 April 2012

Upload: others

Post on 01-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • i

    AN INTEGRATED MODEL FOR PRODUCTION

    LINE BALANCING PLANNING

    ALI ASGHAR JOMAH ADHAM

    Thesis submitted in fulfillment of the requirements for the award of degree of Doctor of

    Philosophy of Technology

    Faculty of Technology

    UNIVERSITI MALAYSIA PAHANG

    12 April 2012

  • vi

    ABSTRACT

    Automobile manufacturing is one of the most important industries in the world. The

    production line is one of the main supply chain of this industry. The production line

    consists of four shops. The shops include many stations. Each station has several

    variables such as car parts, materials, task's number, cycle time, number of workers, etc.

    The task's numbers depend on the number of car parts and pieces depending on the type

    of car. To complete tasks at the station, the workers need time to weld the pieces to the

    structure of the car. The cycle times of these tasks are not equal in each station and

    shop. The unbalance cycle time stations create queuing and idle time. The Production

    Line Balancing Problem (PLBP) is one of the main focuses of research in automobile

    manufacturing. The problem in PLBP is the queuing and the idle time during task

    achievement that is an obstacle to efficient assembly line. Moreover, the unbalancing

    problems also include the tasks number and the number of workers among the stations.

    In addition, the unbalancing problem includes the unbalance between the quantity of the

    customers demand and the production quantity, which are the Production Line Planning

    (PLP) problems. This study used a new method to solve these problems. The new

    method is the Multi-Objectives Model (MOM) combined with the Genetic Algorithm

    (GA) system (MOM/GA). Furthermore, the Simulation Model (SM) is used to solve the

    PLP problem to achieve the customer order by increasing the quantity of production.

    The new approach is called Hybrid Model of the Production Line (HMPL) which is a

    combination of MOM, GA, and SM. This approach is employed to solve the production

    line problems and to develop the efficiency of the production line. As a result, the

    Mixed Model (MM) that combines the MOM and GA is developed to solve the PLBP

    and efficiency of the Production Line System (PLS) in order to reduce the queuing and

    the idle time to obtain the best balance among the stations. Also the MM is applied to

    PLS to re-regulate the tasks' number and re-distribute the jobs to the workers among the

    stations in order to obtain the optimum solution. On the other hand, the SM is applied to

    solve the planning problem to make new plans then to make several strategies to solve

    the PLP problem and to achieve the customer orders. The aim of this study is to

    combine MM and SM to develop the efficiency of the production line and to solve both

    problems by using the output of MM as an input for SM and vice versa. This is a new

    method to obtain the best or the optimum balance among the stations and also between

    the quantity of customers demand and the production quantity. The method increased

    the ratio of production and reduced the queuing and idle time by minimizing the

    queuing and idle time and maximizing the productions, as well as balancing the tasks’

    number and distributing the jobs to the workers evenly.

  • vii

    ABSTRAK

    Pengilangan keluaran automotif merupakan salah satu industri yang terpenting di

    dunia. Operasi pengilangan automotif ini juga merupakan salah satu daripada rantaian

    bekalan utama bagi industri ini. Operasi di kilang kebiasaannya dibahagikan kepada

    empat pusat utama. Bagi setiap pusat ini pula terdapat bahagian-bahagian lain yang

    dikenali sebagai stesen. Untuk setiap stesen ini terdapat beberapa parameter penting

    seperti komponen kereta, bahan-bahan, nombor tugas, masa kitaran, bilangan pekerja,

    dan lain-lain yang bergantung pula kepada bilangan alat-alat ganti kereta dan model

    kereta. Untuk menyelesaikan tugasan di stesen ini, para pekerja memerlukan masa

    tertentu untuk mengimpal kepingan alatan pada struktur kereta. Masa menyiapkan

    tugasan ini tidak sama bagi setiap stesen-setesen ini. Disebabkan masa melakukan

    sesuatu tugasan yang berbeza ini menyebabkan wujudnya keadaan menunggu giliran

    dan masa tidak produktif. Masalah ketidakseimbang ini (PLBP) merupakan salah satu

    fokus utama penyelidikan dalam industri pengilangan automotif. Masalah giliran dan

    masa yang tidak produktif menyebabkan pencapaian tugasan menjadi penghalang

    kecekapan pemasangan kenderaan. Selain itu, masalah ketidak seimbangan ini juga

    berlaku dalam pengagihan bilangan tugasan dan pekerja di stesen-stesen berkenaan. Ia

    juga menyebabkan ketidak seimbangan diantara kuantiti permintaan oleh pelanggan dan

    kuantiti pengeluaran oleh kilang. Kajian penuelidikan ini dijalankan dengan

    menggunakan metod baru bagi menyelesaikan masalah-masalah yang dinyatakan di

    atas. Kaedah-kaedah baru ini dikenali sebagai Model Multi-Objektif (MOM) yang

    digabungkan dengan Algoritma Genetik (GA) dikenali MOM/GA. Disamping itu juga,

    Model Simulasi (SM) digunakan untuk menyelesaikan masalah PLP bagi memenuhi

    permintaan pelanggan dengan meningkatkan kuantiti pengeluaran. Pendekatan baru ini

    dikenali sebagai pemodelan Hibrid Pengeluaran (HMPL) yang merupakan gabungan

    MOM, GA, dan SM. Pendekatan ini digunakan untuk menyelesaikan masalah-masalah

    pengeluaran dan meningkatkan kecekapan pengeluaran kenderaan. Juga Model

    gabungan ( MM) digunakan untuk mengawal selia bilangan tugasan dan mengagihkan

    semula tugasan kepada pekerja-pekerja di stesen-stesen berkenaan bagi mendapatkan

    penyelesaian optimum. SM juga digunakan untuk menyelesaikan masalah perancangan

    bagi menilai beberapa strategi untuk menyelesaikan masalah PLP dan untuk menmenuhi

    permintaan pelanggan. Tujuan kajian ini juga adalah untuk menggabungkan MM dan

    SM bagi meningkatkan kecekapan pengeluaran dan untuk menyelesaikan masalah

    kedua-duanya dengan menggunakan output MM sebagai input untuk SM dan

    sebaliknya. Ini adalah satu kaedah baru untuk mendapatkan yang terbaik atau

    keseimbangan yang optimum di kalangan stesen-stesen dan juga antara kuantiti

    permintaan pelanggan-pelanggan dan kuantiti pengeluaran. Kaedah ini berjaya

    meningkatkan nisbah pengeluaran dan mengurangkan masa menunggu dan masa tidak

    produktif dengan meminimumkan masa menunggu dan masa tidak produktif. Ia juga

    berupaya memaksimumkan pengeluaran kilang dan mengimbangi bilangan tugasan

    dengan mengagihkan tugasan secara sama rata.

  • viii

    TABLE OF CONTENTS

    Page

    SUPERVISOR’S DECLARATION ii

    STUDENT’S DECLARATION iii

    DEDICATION iv

    ACKNOWLEDGEMENTS v

    ABSTRACT vi

    ABSTRAK vii

    TABLE OF CONTENTS viii

    LIST OF TABLES xiv

    LIST OF FIGURES xviii

    LIST OF NOMENCLATURES xxii

    LIST OF ABBREVIATIONS xxiv

    CHAPTER 1 INTRODUCTION

    1.1 Background 1

    1.2 System Description 3

    1.3 Problem Background 4

    1.3.1 Problem Description 4

    1.3.2 Problem Statement 6

    1.4 Research Objectives 7

    1.5 Method of Analysis 7

    1.5.1 Multi Objectives Model and Genetic Algorithm System 7

    1.5.2 Simulation Model 8

    1.5.3 Hybrid Model 8

    1.5.4 Decision Support System 9

    1.6 Scope of Study 9

    1.7 Significant of Study 9

    1.8 Thesis Organization 10

  • ix

    CHAPTER 2 LITERATURE REVIEW

    2.1 Introduction 12

    2.2 Overview on Study of the Production Line 13

    2.2.1 History of the Production Line 13

    2.2.2 Design of the Production Line 15

    2.2.3 Operation Research Models of Manufacturing System 17

    2.3 Structure of the Production Line System 18

    2.4 Background of Production Line Problems 20

    2.4.1 Unbalanced Processing Time of Production Line 21

    2.4.2 Production Line Plan Problem 22

    2.5 Modeling Approaches to Production Line Problems 23

    2.5.1 Multi-Objectives Model 23

    2.5.2 Genetic Algorithm 26

    2.5.3 Simulation Model 28

    2.5.4 Hybrid Model 30

    2.5.5 Decision Support System of the Manufacturing System 31

    2.6 Different Approaches to Production Line Study 33

    2.6.1 Researches that Applying Multi-Objectives Model 33

    2.6.2 Researches that Applying MOM and GA system 35

    2.6.3 Applying Simulation Model to Production Line Plan 37

    2.6.4 Applying Hybrid Model of Production Line 39

    2.6.5 Other Models Applied to the Production Line 40

    2.7 Summary 43

    CHAPTER 3 PRODUCTION LINE LAYOUT AND DATA COLLECTION

    3.1 Introduction 44

    3.2 Plant Layout of Production Line 45

    3.3 Problems at Production Line 47

    3.3.1 Balancing Problems in PLS 47

    3.3.2 Problem Related to PLP 49

    3.4 Methods of Data Collection 50

  • x

    3.4.1 Technical Data (Reports) 50

    3.4.2 Interview 51

    3.4.3 System Observation 51

    3.4.4 Other Resources 51

    3.5 Production Line and Data Analysis 51

    3.5.1 Body Shop (Welding Shop) 52

    3.5.2 Assembly Shop 56

    3.6 Production Line Plan 67

    3.6.1 Production Line Plan for Case Under Study 68

    3.7 Summary 70

    CHAPTER 4 FORMULATION OF THE MIXED-MODEL OF MULTI-

    OBJECTIVES MODEL AND GENETIC ALGORITHM

    4.1 Introduction 71

    4.2 Mixed Model of a Production Line 71

    4.3 Formulating the Multi-Objectives Model 73

    4.3.1 Objectives 73

    4.3.2 Constraints 74

    4.4 Genetic Algorithm Formulation 75

    4.4.1 Objectives 76

    4.4.2 Procedure of Genetic Algorithm 78

    4.5 Mixed Model Optimum Solution 78

    4.5.1 Algorithm of Mixed Model 80

    4.5.2 Flowchart of Mixed Model 81

    4.6 MATLAB`S Algorithm 84

    4.7 Output of the Mixed Model 86

    4.7.1 Output of Multi Objectives Model 86

    4.7.2 Output of Genetic Algorithm 93

    4.8 Summary

    104

  • xi

    CHAPTER 5 CONSTRUCTION OF SIMULATION MODEL OF

    PRODUCTION PLAN

    5.1 Introduction 105

    5.2 Simulation Approach to the Production Planning Problem 105

    5.3 Strategies of the Production Planning 107

    5.4 Development of Production Line Plan Using Simulation 109

    5.5 Formulation of Simulation Model 110

    5.6 Simulation Modeling using MATLAB 112

    5.6.1 Algorithm of the Software 112

    5.6.2 Computer Programs 113

    5.7 Simulation Model and Production Planning Analysis 115

    5.8 Algorithm of the Planning Problem 117

    5.9 The Flowchart of the Simulation Model 117

    5.10 Output of Simulation Model 119

    5.10.1 Daily plan 119

    5.10.2 Weekly Plan 122

    5.10.3 Monthly Plan 125

    5.10.4 Six Monthly Plan 128

    5.11 Summary 130

    CHAPTER 6 DEVELOPMENT OF HYBRID MODEL OF THE

    PRODUCTION LINE AND DSSPL

    6.1 Introduction 131

    6.2 Hybrid Model of the Production Line 131

    6.3 Problem Background at Production Line 133

    6.4 Structure of Hybrid Model 134

    6.5 Hybrid Model Options 135

    6.5.1 Option I 135

    6.5.2 Option II 138

    6.6 Development of the Hybrid Model 141

    6.7 Optimum Solution of HMPL 142

  • xii

    6.8 Significance of Hybrid Model 143

    6.9 Results of the Hybrid Model 143

    6.9.1 Results of Option I 143

    6.9.2 Results of Option II 151

    6.10 Decision Support System 155

    6.11 Summary 157

    CHAPTER 7 MODELS OUTPUT ANALYSIS

    7.1 Introduction 158

    7.2 Output Analysis of the Mixed Model 158

    7.2.1 The Mixed Model with Queuing and Idle time 159

    7.3 Analysis the Output of the Simulation Model 182

    7.3.1 Quantity of Demand

    7.3.2 Opportunity Loss

    7.3.3 Capacity of the Production Line

    183

    184

    184

    7.4 Strategies of the Multi Plans 184

    7.4.1 Strategy I 185

    7.4.2 Strategy II 186

    7.4.3 Strategy III 186

    7.5 Analysis the Output of the HMPL 187

    7.5.1 Analysis the Output of Option I 187

    7.5.2 Analysis the Output of Option II 189

    7.6 Optimum Solution 190

    7.7 Summary 192

    CHAPTER 8 CONCLUSION AND RECOMMENDATIONS FOR FUTURE

    STUDY

    8.1 Introduction 193

    8.2 Overview of the Research Problem 193

    8.3 Development of the Models 194

    8.4 Discussion on the Approaches Methods 195

  • xiii

    8.4.1 Using MOM/GA for Solving PLS Problems 195

    8.4.2 Using SM for Planning and Strategies 196

    8.4.3 Using Hybrid Model at Production Line 197

    8.4.4 Using Decision Support System to Aid the Managers for

    Making Decision

    198

    8.5 Contributions of the Study 198

    8.6 Recommendations for Future Study 199

    REFERENCES

    200

    APPENDICES

    A1 Photos of the Body Shop 208

    A2 Photos of the Assembly Shop 209

    B1 Data Analysis of the Body Shop from Station 1 to Station 9 210

    B1 Data Analysis of the Body Shop from Station 10 to Station 17 212

    B2 Data Analysis of the Trim Section 214

    B3 Data Analysis of the Chassis Section 218

    B4 Data Analysis of the Finally Section 221

    C1 The MM Outcome of the Body Shop from Station 1 to Station 8 224

    C1 The MM Outcome of the Body Shop from Station 9 to Station 17 226

    C2 Applied the MOM Objectives and Constrains to the Body Shop 228

    C3 The MM Outcome of the Trim Section 232

    C4 The MM Outcome of the Chassis Section 236

    C5 The MM Outcome of the Finally Section 239

    C6 Tasks Movement Matrixes of Trim Section 242

    D1 MATLAB Software for MM 244

    D2 MATLAB Software for SM “Daily Plan” 252

    D3 Menus of the MATLAB System 256

    E List of Publication

    257

  • xiv

    LIST OF TABLES

    Table No. Title Page

    3.1 Variables of the Body Shop 53

    3.2 Process tasks time of the Body Shop 55

    3.3 Variables of the Trim Section 58

    3.4 Process tasks time of the Trim Section 60

    3.5 Variables of the Chassis Section 61

    3.6 Process tasks time of the Chassis Section 63

    3.7 Variables of the Finally Section 64

    3.8 Process tasks time of the Finally Section 66

    3.9 The relationship between the produces and demand 68

    4.1 Cycle time balancing of the BS 87

    4.2 Queuing and idle time at the Body Shop 88

    4.3 Cycle time balancing of the TS 89

    4.4 Queuing and idle time at the TS 90

    4.5 Cycle time balancing of the CS 90

    4.6 Queuing and idle time at the CS 91

    4.7 Cycle time balancing of the FS 92

    4.8 Queuing and idle time at the FS 93

    4.9 Tasks movement of the BS 94

    4.10 Tasks movement of the TS 96

    4.11 Tasks movement of the CS 97

    4.12 Tasks movement of the FS 98

    4.13 Re-balancing at BS 100

  • xv

    4.14 Re-balancing at TS 101

    4.15 Re-balance at CS 102

    4.16 Re-balance at FS 103

    5.1 Daily plan for Case I 119

    5.2 Daily plan for Case II 120

    5.3 Daily plan for Case III 122

    5.4 Weekly plan for Case I 123

    5.5 Weekly plan for Case II 123

    5.6 Weekly plan for Case III 124

    5.7 Weekly plan for Case IV 124

    5.8 Weekly plan for Case V 125

    5.9 Monthly plan for Case I 126

    5.10 Monthly plan for Case II 126

    5.11 Monthly plan for Case III 127

    5.12 Monthly plan for Case IV 127

    5.13 Case I for Six Months plan 129

    5.14 Case II for Six Months plan 129

    5.15 Case III for Six Months plan 130

    6.1 The best solution of first stage for Option I 145

    6.2 The optimum of second stage for Option I 146

    6.3 The output of the scenario I 148

    6.4 The output of the scenario II 148

    6.5 The output of the scenario III 150

    6.6 First scenario of the Option II 152

  • xvi

    6.7 Second scenario of the Option II 153

    6.8 Third scenario of the Option II 154

    7.1 Difference time after apply the MM to the BS 159

    7.2 Queuing and idle time before and after applying the MM

    to the BS

    161

    7.3 Re-distribute the jobs to the workers at BS 163

    7.4 Tasks number of each station before and after apply the

    MM to the BS

    166

    7.5 Difference time after apply the MM to the TS 167

    7.6 Queuing and idle time before and after applied the MM

    to the TS

    168

    7.7 Re-distribute the jobs to the workers at TS 169

    7.8 Tasks number of each station before and after apply the

    MM to the TS

    171

    7.9 Difference time after apply the MM to the CS 172

    7.10 Queuing and idle time before and after applied the MM

    to the CS

    173

    7.11 Re-distribute the jobs to the workers at CS 174

    7.12 Tasks number of each station before and after apply the

    MM

    176

    7.13 Difference time after apply the MM to the FS 177

    7.14 Queuing and idle time before and after applied the MM

    to the FS

    178

    7.15 Re-distribute the jobs to the workers at FS 179

    7.16 Tasks number of each station before and after apply the

    MM to the FS

    181

    7.17 Increasing the rate of production by applying the MM 181

    7.18 Summary results of the queuing and idle time of the BS

    and the AS

    182

  • xvii

    7.19 New plan by apply the SM 185

    7.20 First strategy 185

    7.21 Second strategy 186

    7.22 Third strategy 186

    7.23 HMPL of option I 188

    7.24 HMPL of option II 190

    7.25 The best and optimum solution of production line 191

    7.26 Total time increase by using HMPL 192

  • xviii

    LIST OF FIGURES

    Figure No. Title Page

    1.1 Production line of automobile manufacturing system 3

    1.2 Production line of assembly and sub-assembly line 4

    1.3 Unbalance problem of the PLS 5

    1.4 Relation between demand and produces 6

    1.5 Structure of the HMPL 8

    1.6 Thesis organization 10

    2.1 The framework of Chapter 2 13

    2.2 Production line development 14

    2.3 Production line in 1955 15

    2.4 U-shape assembly line 16

    2.5 Two-sided design system 16

    2.6 The PLS in automobile manufacturing 18

    2.7 Production line with stations 19

    2.8 PLS in automobile manufacturing 20

    2.9 Unbalance problems in production line 21

    2.10 Relations between the demand and the produces 22

    2.11 Relation between the objectives and constraints 26

    3.1 Framework of Chapter 3 44

    3.2 Production line in automobile manufacturing system 45

    3.3 Production line (Stations, Assembly, and Sub-assembly) 46

    3.4 Variables of production line 47

    3.5 Unbalancing problem in PLS 48

  • xix

    3.6 Queuing and idle time of the production line 49

    3.7 Relations between the produces and demand 50

    3.8 Framework of the Body Shop 52

    3.9 Relationship among variables of the BS 54

    3.10 Cycle time stations at the BS 56

    3.11 Framework of the Assembly Shop 57

    3.12 Relationship among variables of the Trim section 59

    3.13 Cycle time stations at the Trim section 61

    3.14 Relationship among variables of the Chassis section 62

    3.15 Cycle time stations at the Chassis section 64

    3.16 Relationhip among stations at the Finally section 65

    3.17 Cycle time stations at the Finally section 67

    3.18 Quantity of demand and productions 69

    3.19 Unbalance between the produces and demand 70

    4.1 Mixed model (MOM / GA) 72

    4.2 Tasks movement using GA 76

    4.3 Movement type of the tasks 77

    4.4 Optimazition method 79

    4.5 Flowchart of MM 83

    4.6 Programming using MATLAB 85

    4.7 Tasks movement at Body Shop 95

    4.8 Tasks movement at Trim section 96

    4.9 Tasks movement at Chassis section 97

    4.10 Tasks movement at Finally section 99

  • xx

    4.11 Best balance at Body Shop 100

    4.12 Best balance at Trim Section 102

    4.13 Best balancing at Chassis Section 103

    4.14 Best balancing at Finally Section 104

    5.1 Unbalancing problem between the demand and production 107

    5.2 Strategy planning between demand and products 108

    5.3 Formulation of the SM 112

    5.4 The algorithm of PLP using MATLAB 113

    5.5 MATLAB software programming 114

    5.6 Result of the MATLAB programming 115

    5.7 Goals of the simulation model 116

    5.8 Flowchart of the new plan 119

    5.9 Daily plan for Case I 121

    5.10 Daily plan for Case II 120

    5.11 Daily plan for Case III 122

    5.12 weekly plan for Case V 125

    5.13 Monthly plan for Case IV 128

    5.14 Case III for six months plan 131

    6.1 Framework of hybrid models 132

    6.2 Problems at the production line 133

    6.3 Hybrid model in the Option I 135

    6.4 Hybrid model flowchart of the Option I 137

    6.5 Hybrid model in the Option II 138

    6.6 Hybrid models flowchart of the Option II 140

  • xxi

    6.7 Framework of hybrid model of production line 141

    6.8 Optimum solution of the hybrid model for production line 142

    6.9 Main menu for MATLAB software 155

    6.10 Second menu of the MATLAB software 156

    6.11 Third menu of the MATLAB software 157

    7.1 Cycle time stations before and after applying the MM to the BS

    160

    7.2 Queuing and idle time among the stations before re-distribute the

    jobs to the workers at BS

    163

    7.3 The queuing and idle time after re-distribution the jobs to the

    workers at BS

    163

    7.4 Cycle time stations before and after applying the MM to the TS

    167

    7.5 Queuing and idle time among the stations before apply the MM

    to the TS

    169

    7.6 The queuing and idle time after distribution of the jobs to

    workers at the TS

    170

    7.7 Cycle time stations before and after applying the MM to the CS

    172

    7.8 Queuing and idle time among the stations before re-distribute the

    jobs to the workers at the CS

    174

    7.9 The queuing and idle time after distribution the jobs to the

    workers at the CS

    175

    7.10 Cycle time stations before and after applying the MM to the FS

    177

    7.11 Queuing and idle time among the stations before re-distribute the

    jobs to the workers at the FS

    179

    7.12 Queuing and idle time after distribution the jobs to the workers

    at the FS

    180

    7.13 Bottleneck of production line 183

    7.14 The relations among the capacity, demand, and production 191

  • xxii

    LIST OF NOMENCLATURES

    Q Total Queuing Time in production Line

    P Number of Shop

    S Total Number of Stations

    CTs Cycle Time at stations

    X Variable for Each Task

    DT Idle Time

    W Number of Worker

    Nw Limitation Number of Workers for each station

    Tw Total Number of Workers

    Nws Number of Workers in Each Station

    tn Tasks number

    PTT Processing Tasks Time

    Wn Number of Workers append

    No.T Number of Tasks

    RJS Ratio of the Jobs of each station.

    AVCT Average Cycle Time

    D Difference in time among stations (Queuing and Idle Time)

    Pro Quantity of the production

    NWADD Number of Workers Add to production line

    TTS Total Time Saving

    NWT Total Time Can the Company Work Per Day

    CPL Capacity of the Production Line

    QD Quantity of Demand

  • xxiii

    ATPOC The Average Time to Produce One Car

    TJTEW Total Jobs Time for Each Worker in each station

    NWES Number of Workers of Each Station

  • xxiv

    LIST OF ABBREVIATIONS

    ALB Assembly Line Balance

    AS Assembly Shop

    BDP Bounded Dynamic Programming

    BS Body Shop

    CPL Capacity of the Production Line

    CS Chassis Section

    CT Cycle Time

    CTs Cycle Time Station

    DSS Decision Support System

    DSSPL Decision Support System for Production Line

    EC Evolutionary Computation

    FS Finally Section

    GA Genetic Algorithm

    GP Goal Programming

    HM Hybrid Model

    HMPL Hybrid Model of the Production Line

    INT Inventory Theory

    JIT Just In Time

    LP Linear Programming

    MM Mixed Model

    MMOS Mixed Model Optimization Solution

    MOM Multi Objectives Model

    NLP Nonlinear Programming

  • xxv

    NN Neural Network

    OR Operation Research

    PL Production Line

    PLBB Production Line Balancing Problem

    PLP Production Line Plan

    PLS Production Line System

    PS Paint Shop

    PSO Particle Swarm Optimum

    PTT Processing Tasks Time

    QA Queuing Analysis

    SA Simulation Annealing

    SCM Scheduling Model

    SD System Dynamic

    SM Simulation Model

    TES Test Shop

    TS Trim Section

  • 26

    CHAPTER ONE

    INTRODUCTION

    1.1 BACKGROUND

    The automobile manufacturing is one of the most important industries to date

    established in Germany in 1886. The industry has been relying on intensive labor since

    its inception. Due to the durability of product life cycles and fierce competition, the

    automobile industry has moved towards cost-effective products i.e., they produce a

    variety of product types. Moreover, these automobile companies face tough challenges

    in automobile production such as reducing time of the production line and developing

    production plan that meets customers demand (Toshio et al., 1996; Gnoni and

    Lavagilio, 2003; Mehrdad, 2004).

    In the automobile manufacturing system, one of the areas under consideration is

    Production Line Balancing Problem (PLBP) which distributes the total workload among

    manufacturing stages (Toshio et al., 1996). There are many researchers who studied on

    the problems regarding PLBP and Production Line System (PLS) in order to obtain the

    best solution (Minh and Soemon, 2008). These important problems present the first

    major problem of the production line.

    Production Line Plan (PLP) is an important requirement of the automotive

    manufacturing system to ensure the optimum balances between the quantity of

    customers demand and the productions quantity, by producing a new management plan.

    Sometime the managers of the production line cannot satisfy the customers due to gap

    between the quantity of productions and the demand (Gnoni and Lavagilio, 2003). This

    problem presents the second major problem of the production line.

  • 27

    There are several mathematical models that have been developed in the

    automobile manufacturing industry such as linear programming (LP), queuing,

    probability, simulation models, scheduling, neural network, system dynamic, and

    statistics (Dalvi and Guay, 2009; Resano and Luis, 2009; Birkan and Cathal, 2012.).

    Many of these models were developed based on decision support system that is used for

    assisting the management to make decision (Poon et al., 2011). Nowadays, there is a

    trend to develop a hybrid model which can be more efficient in solving complex

    problems (Amir and Farhad, 2006; Burcin et al., 2011). In this study, two distinct

    models are developed to solve PLBP and PLP problems. The two models are Multi

    Objectives Model (MOM) and Simulation Model (SM). Further, a combination of these

    two models will form a Hybrid Model of Production Line (HMPL). It is a desire that

    HMPL will be a more powerful model that could solve a wider scope of problems for

    producing an optimum plan for the production line. The study will also present a

    Genetic Algorithm (GM) system that is embedded with MOM for obtaining an optimum

    solution. This approach is still at an infancy stage among researchers.

    In this study, MOM/GA is used to solve the queuing problem of the production

    line which include several stations that consists many operations. The developed model

    will be used to reduce the queuing among these stations, hence, resulting in minimized

    cycle time, and maximized workload (Amir and Farhad, 2006). On the other hand, SM

    approach was used to solve the planning problem by improving PLP and ensuring

    optimum balance between the quantity of the customer’s demand and production

    quantity (Ruey-Shun, C. and Kun-Yung, 2002).

    The developed Decision Support System for Production Line (DSSPL) for this

    study is an ultimate integration of MOM, GA, SM, and HMPL. The Decision Support

    System (DSS) is an advanced method that applies these models to develop a plan and

    system of the automobile manufacturing.

  • 28

    Body Shop Paint Shop

    Assembly Shop Test Shop

    Check

    Park/ Storage

    Destroy body car

    Yes

    No

    1.2 SYSTEM DESCRIPTION

    The production line in the automobile manufacturing system of plant under

    study consists of four different shops that are Body Shop (BS), Painting Shop (PS),

    Assembly Shop (AS) and Test Shop (TES). Each shop composes of many stations

    which performs different tasks. The semi-finished manufactured products have to move

    in pre-planned sequence among these shops. Figure 1.1 shows the production line of the

    automobile manufacturing system. It starts initially with the body shop, then paint shop,

    later assembly shop, and finally the test shop (Hicom, 2010). The more detail of

    production line of automobile manufacturing will be described in Chapter 3.

    Figure 1.1: Production line of automobile manufacturing system

    Each shop in the production line has an assembly and sub-assembly line. The

    parts are pre-prepared in the sub-assembly before they were sent to the assembly line for

    processing. For the assembly line to perform at an optimum level, the operation at the

    station must be balanced with respect to its cycle time. Figure 1.2 shows the assembly

    line and the sub-assembly of all shops of the production line system (Christian et al.,

    2009; Junfeng et al., 2011).

  • 29

    Figure 1.2: Production line of assembly and sub-assembly line

    1.3 PROBLEM BACKGROUND

    The case under study focuses on two main problems of the production line of the

    automobile manufacturing system. Both of the problems are production line balancing

    and production line planning that will be explained in more detail in the next section.

    1.3.1 Problem Description

    The production line under study focuses on two main problems namely,

    production line balancing and production planning, balancing problem occur when not

    all stations are able to complete all tasks at the same time (Christian and Armin, 2009).

    As a result, it causes a congestion problem at the production line and the resources are

    under utilized. The problem is illustrated in more details as shown in Figure 1.3 which

    contains three scopes with the L1 represents processing tasks time, L2 represents

    number of tasks, and L3 for number of workers.

    Sn

    S4

    S3

    S2

    S1

    S1 S2 S3 S4 S5 Sn

    Sn S5 S4 S3 S2 S1

    S1 S2

    S3

    S4

    S5

    Sn

    BS

    AS

    PS

    TS

    Assembly

    Sub-Assembly

    Sub-Assembly

    Sub-Assembly Station

  • 30

    Figure 1.3: Unbalance problem of the PLS

    Production line plan and scheduling strategy are important to the production

    managers because both are used as a basis to make decision on production quantity. The

    plant has a few standard plans for different quantities of production capacity. The plant

    however will face a problem when the quantities of demands are different from the

    company`s allocated standard (Gnoni and Lavagilio, 2003). The current practice in the

    company is not flexible enough to accommodate production the changes of quantity of

    demand. Figure 1.4 illustrates this problem, where L1 represents the quantity of

    demands and the L2 represents the quantity of products. The figure shows that the

    quantity of demand is more than the quantity of production. The gap demonstrets that

    the plant is unable to fulfill the demand of customers.

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Stations

    UnitL1= Processing tasks time

    L2= Number of tasks

    L3= Number of workers