TW@ESI31st January 2016Hope that you and all your families had a good weekend. The following is a forecast of the next week
By now we have most of our employees on this discussion group except ... Ludovic, Clinton, Lino, Victor, Daniele, Pawlu,... Please... All of you.. Join!!
Projects and deadlines• We are presently executing a number of fast track projects
and I would like to summarise the major ones them as follows:– 14_081 - Siggiewi Primary School BMS- We have completed
nearly all snags here... Its now a matter of training, handover, witness commissioning and documentation
– 13_076 - MDH Block D Ext MAU- We have done 70% of our functional tests and will now start importing onto the Master station
– 12_043_Life_Sciences- This is a hot project and we need to complete yesterday- we need to focus on a close out program here... We have done good progress but lots is pending
Projects and deadlines– 14_089_MGA_DAC_PA_Va and 14_027_SCM_FTIS- DAC – This is
now nearly all wrapped up- excluding snags by others– 15_008 - Aurobindo PH02 BMS- The project has been delayed
by the contractor – so my message is to press on doing software until the contractor starts meeting the deadlines- we soon will have to continue on this project soon
– 15_033_Westin_7-AHU- The plan is to commission within Feb 2016 (this delay is due to the fact that we have a delay in carrying out the installation due to Hotel operations). Next installation phases are now cable pulling
– 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project.
DesignLast week• Westin 7AHUs Honeywell Field Devices Tagging• Intercontinental – Continued & Completed MCC-1 Panel
Design & Submitted, Released Panel Material order• MDH MAU D00-CC1 As Built update (P&ID and Panel
Drawing)Next Week• OTM –site visit• Size Hilton Panels, OVt Panel• SCM Lagoon Pump Room Field Termination details on Matrix• Hilton Restaurant & Kitchen AHUs – Start on Points lists,
P&IDs, Panel drawings
Installation
– Continue works at ESI new premises and offices– Testing at Carlos Calamatta residence– Commissioning at Life sciences– Finish cable tray at Westin– Start pulling cables at Westin– Install MCCB on existing MCC at Westin– Sterling PPM
Mater Dei
• We have some extremely good news here- we have signed off a new 7 year contract with MDH. This is an extremely important contract for ESI and we have won it with everyones hard work.
• Things are coming back to normal with the MDH operation and maintenance tasks- I expect all of you to pull the rope and get things normal and in line- it would be good to start getting feedback of what was done during the week and what is planned for the next from MDH
Development and Commissioning• We have done large important steps on finishing off the Parliament we
need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION CERTIFICATION- LVA is to come up with a plan- this plan is now very much needed and we should have this plan by 5th Fen 2016
• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION
• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• The Bosch HSDK interface is well advanced and we awaiting the client• The PLC/SCADA team have been working on the FUN Tests of MAU• We have also been addressing a number of issues for TSP Two Man rule
Development and Commissioning• Commissioning of Life Sciences 12_043- we have done a lot but still have a
bit to do- we need to complete by mid Feb 2016• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are still snags to
be addressed- (wifi router, Intruder alarm door contact and false alarms)• Oncology 14_066- We have done most of the work here and we can close
off shortly• The Siggiewi Primary school project – we need to close off – the quicker
the better!!• Aurobindo is another important and, now, fast track project We are
awaiting the main contractor for us to start commissioning the Priority A items
• Hilton small projects –calorifier monitoring
Sales and Business Development
• We have been working on Home automation offerings, an offer for James Catering, an offer for Portomaso casino controls, quotes for OTM (some of which are quite large) and quotes for variations for existing projects.
• We are also on the verge of concluding on another big HSDK project.
• We also had a good work shop with SEWCU last Friday were we brain stormed on how ESI may be involved in other
• Many thanks to the people who have contributed already... I will shortly put out a summary of what was collected
Team ESI• I urge you all to follow this blog and keep up to date with what is
happening at ESI • I await all your feedback on all the ESI discussions – without this
feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group
• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
• Send me pictures of all your work and what you are up to , so that I may create some videos on this blog- Julian, Claudio, Clifton, Silvio, David and Clinton.... Well done!!