Status of Torino-Dubna Production

amedeo.staiano@to.infn.it

Aluminum Plates production:

• Torino: steady production ongoing, 2715 plates cut, 194 chambers=48MB1 +54MB2+50MB3+41MB4).

• Dubna: steady production ongoing. Plates for 34 MB1, 40 MB2, 39 MB3, 3 MB4 produced insofar (116 total). Time estimated to complete full production + spares march 2005 (as specified in the contract).

Status of Torino-Dubna Production

amedeo.staiano@to.infn.it

Position Quality of strip production:stable since change of strip deposition head in august 2002.

Strip Whole Average Position

-5

-4

-3

-2

-1

0

1

2

3

4

5

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49

Strip Number

Pix

els

Series1

Plate MB1 n. 300220

1 pixel = 0.106mm

Status of Torino-Dubna Production

amedeo.staiano@to.infn.it

HV test performance of strip production:Plates which pass 1st HV test 84%

Last plate of the day left under HV test during the night, 10 hours. No extra bad plates found so far.

HV test on 411 plates

Good

Trip

Overcurrent

Others

Status of MB4 Production Preparation

amedeo.staiano@to.infn.it

• Production of FE and HV SL frames ongoing in Torino. 20 MB4 HV side + 9 FE side frames produced.

Status of MB4 Production Preparation

amedeo.staiano@to.infn.it

Plotter Y axis supports 99% ready for table installation. Completion expected by delivery of last part (rails protective tape fixations).

Status of MB4 Production Preparation

amedeo.staiano@to.infn.it

Inflatable tube (2.5m,=7.5mm) Elastic rubber

Commercial profile

I beam tool drawings(P.Mereu)

12.7 mm ALCOA support OPEN

CLOSED

Status of MB4 Production Preparation

amedeo.staiano@to.infn.it

Final prototype executive drawings ready

Torsion springs

RailsMovable locating block

Status of MB4 Production Preparation

amedeo.staiano@to.infn.it

Main Structure:RohacellSandwich

Thickness 500mm

Load 5000N