February 2, 2018 1

Completed and ongoing tasks:

• Below grade waterproofing ongoing.

• Concrete footings and foundation walls ongoing.

• Erection of elevator core walls ongoing.

• Installation of below grade utilities ongoing.

• Major structural steel in fabrication.

• Temporary electrical power was installed and generator removed from site.

Construction activities next month:

• Continuation of concrete footings, foundation walls, and underground utilities.

• Start concrete slab on grade at basement level.

• Curtainwall material will be released for fabrication.

Process related activities:

• Final Design and Construction Contract Award for full GMP was approved at the School Board meeting

on January 18. See the link below for the presentation:

https://www.boarddocs.com/vsba/arlington/Board.nsf/files/AUXRFU67B4D2/$file/F-

2%20Wilson%20Presentation-%20Final%20Design%20and%20GMP.pdf

• Construction workers parking has been in a nearby commercial garage since December 1, 2017.

Secondary School @Wilson

Community Newsletter (January 2018)

February 2, 2018 2

B2 level soil final grading for slab on grade

B2 level retaining wall

February 2, 2018 3

Foundation rebar

Steel formwork and rebar

February 2, 2018 4

Steel formwork and wall sleeves