salem river crossing: oversight team and task force meeting

Post on 05-Apr-2018

218 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 1/49

Oversight Team

and Task Force

Meeting

 April 26, 2012

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 2/49

What do we want to accomplish tonight?

Statements from the public 

Review decision making structure 

Draft EIS key findings  Statements from the publi 

Next steps

2

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 3/49

Statements from the Public

3

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 4/49

Statements from the public

We will not be accepting comments on the

Draft EIS tonight. Comments on the document can be submitted in

writing or at the public hearing dates (May 8 and

17).  e w accep commen s a ou e process or 

questions for the OT/TF team to consider 

.

4

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 5/49

Review decision makin rocess

5

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 6/49

Ground rules for tonight

Be respectful

Focus questions and comments on the subject

Listen with the intent of hearing

  Wait or n v ua s to n s e ore you respon

When discussing the past, link the past to this discussion

Share the air! Give others the opportunity to speak once before youspeak twice

Put cell phones on silent mode and go outside the room to use them

Be responsible for the group’s success

Brevity is good

6

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 7/49

Decision Making Structure

7

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 8/49

Completed Milestones

8

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 9/49

Upcoming Milestones

The Task Force and Oversight Team will use the information

n e ra , as we as ee ac rece ve ur ng epublic comment period, to make a recommendation on a

9

.

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 10/49

Questions?

10

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 11/49

Review the Draft EIS rocess

11

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 12/49

What is an EIS?

 A full disclosure document detailing a project’seve opmen process

Includes consideration of a range of reasonable

 Analyzes potential impacts resulting from alternatives

 environmental laws and executive orders

Ob ective is to rovide sufficient information for decision-makers to comparatively select a LocallyPreferred Alternative

12

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 13/49

Why do we need to do an EIS?

The National Environmental Policy Act (NEPA)

requires Environmental Impact Statements for major actions that utilize federal funds andsignificantly affect the quality of the human

or natural environment.

13

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 14/49

Purpose of Project

Improve mobility and safety for people and freight

for local, regional, and through-travel across theWillamette River in the Salem-Keizer metropolitana ev a ng conges on

Street and Marion Street Bridges and on the.

14

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 15/49

Next steps for the project

see Decision-Making rocess grap 

 

15

(for the SKATS MPO)

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 16/49

Decision-Making Process:

Next steps for the TF/OT

16

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 17/49

Questions?

17

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 18/49

Draft EIS Findin s

18

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 19/49

Review of DEIS Alternatives

  o u erna ve

3 bridge crossing locations; 8 Build Alternatives

Crossing locations:

1 Existin Brid es Crossin Location 2A & 2B 

2) Hope to Tryon Crossing Location (3)

19

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 20/49

DEIS Alternatives: Crossing Locations

20

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 21/49

No Build Alternative

Alternative 1 No Build : Examines how

the transportation system will operate inthe future without buildin another brid e.

Used as a baseline to compare and measure

the other alternatives

Includes projects already programmed for construction

21

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 22/49

Alternative 2A (widen existing bridges) Adds two new lanes to the Marion Street Bridge (plus a connection to the future Marine Drive

NW) and one new lane to the Center Street Bridge; includes street system modifications

4*

22

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 23/49

Alternative 2A (West Salem in foreground)

23

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 24/49

Alternative 2B (north of existing bridges)New bridge between the Marion and Union Street Bike/Pedestrian bridges;

includes street system modifications

24

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 25/49

Alternative 2B (West Salem in foreground)

25

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 26/49

Alternative 3 (Hope to Tryon)New bridge from Wallace Road NW and Hope Avenue NW to Tryon Avenue NE and the

a em ar way , nc u ng connec ons o e er y ommerc a ree coup e ;includes street system modifications

26

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 27/49

Alternative 3 (northern West Salem in foreground)

27

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 28/49

DEIS Alternative 3 (North Salem in foreground looking west)

28

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 29/49

Alternative 3 (North Salem in foreground looking south)

29

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 30/49

Alternative 4A: (Hope to Liberty via Pine/Hickory)

 NE and the Liberty/Commercial Street NE couplet; includes street system modifications

30

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 31/49

 erna ve

(4A + 2A)ew r ge p us

widen existing bridges(2A); includes street

31

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 32/49

Alternative 4B (North Salem in foreground looking west)

32

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 33/49

Alternative 4B (West Salem in foreground)

33

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 34/49

Alternative 4C(4A + DirectConnection toSalem Pkwy &

OR 22)New bridge (4A), but Pine/HickoryStreet NE extends to Broadway

Street NE and has a direct

elevated & direct connection to OR22 and Marine Drive NW; includesstreet system modifications

34

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 35/49

Alternative 4D(like 4C but with

Pine/Hickory

Same as Alternative 4C

but the bridge connectionto Pine/ Hickory StreetNE would touch down atLiberty Street NE (not

includes street systemmodifications

35

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 36/49

Alternative 4E(like 4C but

to Wallace Marine

New bridge (4C) but with

22 to minimize impacts toWallace Marine Park;includes street s stem

modifications

36

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 37/49

Alternatives 4C & 4D (northern West Salem in foreground)

37

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 38/49

Alternatives 4C & 4D (West Salem in foreground)

38

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 39/49

Alternatives 4C, 4D & 4E (OR 22 in foreground)

39

Alternatives

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 40/49

SelectedDifferentiators¹ Impact Scale 2A 2B 3 4A 4B 4C 4D 4E

 

Alternatives

Regional MobilitySystem vehicle hours of delay (AM/PM). 2031 No-Build: 674/371

461/303

131/198

144/134

141/125

111/124

87/124

104/136

87/124

ResidentialDisplacement

40-50 50-60 45-55 30-40 80-90 100-110 85-95 110-120

 

Moredisplaced

Fewer displaced

Business

Displacement 20-30 45-55 10-20 25-35 50-60 65-75 65-75 65-75

Historic Impacts

Moredisplaced

Fewer displaced

More adverseimpacts

Fewer adverseimpacts

3 3 None None 3 4 4 4

Impacts to Low-incomeCommunity

16 None None None None 16 16 32

Riparian Habitat

Moredisplaced

Fewer displaced

More impact Less impactImpacts

0.9 acre6.5

acres7.6

acres8.6

acres9.5

acres16.0acres

16.0acres

14.3acres

Noise Receptor Impacts

11 26 36 22 33 62 54 61

More noise Less noise

 

Cost $148million $388million $501million $306million

$451million $692million $687million $708million

 

More uses* Fewer uses*

 

* Assumes concurrence on de minimis findings and temporaryoccupancy 4* 4 * None None 4 * 4* 4 * 4 *

¹ From the Draft EIS

DEIS Topic Areas with Similar Total Impact

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 41/49

DEIS Topic Areas with Similar Total ImpactAcross Build Alternatives

We did not find substantial total impact differences

Land Use Invasive Species

Visual Resources  Air Quality

Threatened & Geology

n angereSpecies Hazardous Materials

41

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 42/49

Starting to Narrow Alternatives

2A 2B 4C3 4A 4B 4D 4ENo

Bld

? ? ? ? ?

?

42

?

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 43/49

Prepare for Next Meeting

Between now and July, you should:

Talk to your group/constituents to learn howthey feel about the alternatives

Review the executive summary to learn aboutdifferences between alternatives

  Write down your thoughts! This will help thediscussion in July.

Review public comments

  ar o narrow own a erna ves

43

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 44/49

Questions?

44

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 45/49

Statements from the Public

45

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 46/49

Statements from the public

We will not be accepting comments on the

Draft EIS tonight.

Comments on the document can be submitted inwriting or at the public hearing dates (May 8 and17).

  e w accep commen s a ou e process or questions for the OT/TF team to consider 

.

46

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 47/49

Next Ste s/Remainin Questions

47

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 48/49

Next Steps

Public Hearings/Open House

Tuesday, May 8 (4-7 pm)

Thursday, May 17 (3-7 pm)

Next Meetings

= , ,

TF = Tuesday, July 24 or Thursday, July 26

, ,

JOINT = Tuesday, August 16 or Thursday, August 18

  , ,

48

8/2/2019 Salem River Crossing: Oversight Team and Task Force Meeting

http://slidepdf.com/reader/full/salem-river-crossing-oversight-team-and-task-force-meeting 49/49

Questions?

49