Rushern L. Baker, IIICounty Executive
Haitham A. HijaziDirector
Beltsville Academy May 17, 2012
Project Information Meeting
Agenda• Exhibit Review• Welcome• Presentation• Q/A
Sunnyside Avenue Bridge Replacement
Existing Roadway
Sunnyside Avenue Bridge Replacement
Existing BridgeBridge History
- Type: single span, steel multi-beam bridge with a concrete deck- Length: 37 feet- Clear Width: 22 feet- Built: 1946- Frequent flooding- Structurally Deficient
Sunnyside Avenue Bridge Replacement
Existing Bridge
Extensive Deterioration
Sunnyside Avenue Bridge Replacement
Existing Bridge
Extensive Deterioration
Sunnyside Avenue Bridge Replacement
Proposed Bridge
Sunnyside Avenue Bridge Replacement
Planned Improvements• Mitigate flooding• Create a “Green / Complete Street” that
includes shoulders, bike paths, sidewalks and street lights
• Create additional environmental features, including additional wetland beneath the bridge, Storm Water Management facilities
Sunnyside Avenue Bridge Replacement
Proposed Roadway
Sunnyside Avenue Bridge Replacement
• Mitigate flooding• Create Green / Complete Street• Create additional wetland beneath the bridge• Create Storm Water Management facilities
Right-of-Way and Environmental ImpactsBeltsville Agricultural Research Center (BARC)
2.67 Acres
Sunnyside Avenue Bridge Replacement
Fee Simple Right-of-Way•2.67 acresTemporary Construction Easement•0.34 acrePermanent Section 4(f) Use•3.01 acres (2.67 acres + 0.34 acre)
0.34 Acres
0.21 Acre
0.11 Acre
Sunnyside Avenue Bridge Replacement
Fee Simple Right-of-Way• 0.21 acre
Temporary Construction Easement• 0.11 acre
Right-of-Way and Environmental ImpactsWashington Metro Area Transit Authority (WMATA)
Proposed Bridge
Sunnyside Avenue Bridge Replacement
South Side
Construction Stage I
• Maintain traffic on existing bridge• Construct south portion of new bridge• Construct south portion of approach roadway• Relocate Utilities
Sunnyside Avenue Bridge Replacement
North Side
South Side
Stage II• Shift traffic to the new bridge• Remove the existing bridge• Construct the north portion of new bridge• Construct the north portion of approach roadway
ConstructionSunnyside Avenue Bridge Replacement
North Side South Side
Stage III
• Reset the temporary barrier and shift traffic to the final lanes of new bridge• Construct the sidewalk on the south portion of new bridge
Construction
Sunnyside Avenue Bridge Replacement
• Complete Final Design Spring 2013• Right-of-Way Acquisition Fall 2013• Advertise for Construction Fall 2013• Begin Construction Spring 2014• Total Construction Duration 18 Months
Next StepsSunnyside Avenue Bridge Replacement
QUESTIONS?
Prince George’s County DPW&T Project Website:WWW.PRINCEGEORGESCOUNTYMD.GOV/DPWT