Project Update | June 2016
Bid Results and Revised ScheduleThe Highway 4 through St. James project was successfully rebid in May and is ready to move forward with construction. S M Hentges & Sons, Inc. of Jordan was awarded the contract with a bid of $15,685,646, about $3.2 million less than the lowest bid in February. A couple of factors figured into the lower bids. There were more bidders, staging options were offered and the risk with the hazardous material removal was reduced.The contractor has submitted a preliminary schedule of construction activities that includes work beginning on 8th Avenue N in July 2016. Most work on Highway 4 will begin in 2017 and be completed in 2018. The detour route and construction sequencing maps provide scheduling and traffic routing for each stage of construction. Information is subject to change, sign-up for project updates on the city’s website.
Sue JensenMnDOT Project Liaisonsusan.jensen@state.mn.us(507) 317-6149
Joe McCabeSt. James City Managerjoe.mccabe@ci.stjames.mn.us(507) 375-5090
Chris ChromyBolton & Menk, Inc., Project Managerchrisch@bolton-menk.com507-625-4171 ext. 2428
Project Contacts
Project Schedule:Nov 2013 – Sept 2015 . . . . . . . . . . . . . . . . . . . .Project DesignOct 2015 – Jan 2016 . . . . . . . . . . . . . . . . . . Agency ApprovalsFeb – Jun 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . Project BiddingAug – Oct 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Initial WorkMay – Oct 2017. . . . . . . . . . . . . . . . . . . . . . Major ConstructionMay – Sept 2018. . . . . . . . . . . . . . . . . . . . . Major ConstructionMay – Mid-June 2019 . . . . . . . . . . . . . . . . . . . . .Finishing Work
Project Website: www.mndot.gov/stjames
¿Preferiría que el boletín es en espanol?
Habla con Joe McCabe a City Hall por email a joe.mccabe@ci.state.mn.us o por teléfono al
(507) 375-5090.
Project elements include: • Reconstruct Highway 4 from approximately
10th Avenue South to 11th Avenue North • Realign 7th Avenue South to increase safety • Construct mini-roundabouts at the two existing signals
on 1st Avenue South • Provide back-in angle parking on 1st Avenue South • Replace and install new sidewalks • Bring all pedestrian accommodations up to Americans
with Disability Act (ADA) standards • Improve roadway aesthetics and safety • Upgrade storm sewer throughout the corridor • Update lighting standards and fixtures
PROOF
6
4
5
3
1
14
13
12
8
2
910
11
To/From Sleepy Eye
To/From Hwy 60
NorthsideElementary
School
Armour Eckrich Meats
Nelson Furniture
LibraryCounty Courthouse
St. Paul’s Lutheran School
Armstrong Preschool/Community Education
CountyFair Grounds
National GuardTraining &
Community Center
St. JamesSecondary
School
Quick Facts:
• Three year construction schedule: Aug – Oct 2016, May – Oct 2017, and May – Sept 2018
• A detour route will be provided with proper signage for drivers (See Detour Route Map)
• There will be three separate phases: º Stage 4A: 2016 construction º Stage 1, 2 & 3: – 2017 construction º Stage 4B: 2018 construction
• Phases take into account school and county fair schedules
Detour Route
3
1
14
13
8
2
10
11
To/From Sleepy Eye
To/From Hwy 60To/From Hwy 60/Hwy 4
3333333333
1
13
8
2NorthsideElementary
School
Smith�eld Foods
Nelson Furniture
Library
County Courthouse
St. Paul’s Lutheran School
Armstrong Preschool/Community Education
CountyFair Grounds
National GuardTraining &
Community Center
St. JamesSecondary
School
St. JamesLake
Stage 4B- Full Roadway/Sidewalk ReconstructionTimeline: May – August 2018: Complete by School Opening
National Guard
Stage 4B- Full Roadway/Sidewalk ReconstructionTimelineMay – August 2018
Stage 2- Tra�c Signal Removal- Two Mini-Roundabouts- Back-In Angle Parking- Full Roadway/Sidewalk ReconstructionTimelineApril – August 2017
Stage 4A- Utility Replacement/Associated
Roadway ImprovementsTimelineJuly – October 2016
unty Courthouse
Stage 3- 7th St S Roadway Closure- Full Roadway/Sidewalk ReconstructionTimelineMay – September 2017
/n
Stage 3- 7th Ave S Roadway Realignment- Full Roadway/Sidewalk ReconstructionTimelineMay – September 2017
Stage 1- Sidewalk Construction East of Hwy 4- Full Roadway ReconstructionTimelineJuly – October 2017: Completed After Watonwan County Fair
Partial Tra�c Mobility Maintained Throughout
Construction
Construction Sequencing
Draft - Subject to Change
One or more cross streets open in each phase for cross town travel PROOF