PROJECTS GROUP INTRODUCTION
RICHARD STARK
APACHE NORTH SEA
PROJECTS SERVICES MANAGER
SUBSEA UK
NW ENGLAND CONFERENCE
27TH NOV 2014
Apache North Sea
The Projects Group
Projects
Procurement
Summary
ITINERARY
2
APACHE NORTH SEA
3
Bought 2003
$6Bn – drilling
$3Bn – facilities
3 / 4D seismic
Power ring main
Delta V
Pipelines replaced
Deep gas Lift
Bacchus 2012
FASP 2012
4
Bought 2012
Platform rig upgrades
3D Seismic
Semi-sub programme
Access shut in production
Subsea integrity works
APACHE NORTH SEA
Company Improvement Notices Prohibition Notices
Maersk (all sections) 13 3
Talisman 10 1
Shell U.K. Limited 8 6
CNR 8 1
Marathon 7 0
Petrofac Facilities Management 5 0
Total E&P 4 0
Chevron 4 0
Taqa 3 0
Nexen 3 0
BP 2 0
Premier Oil 2 0
Apache 2 0
Sources: OGUK Benchmarking 2013 Data and HSE http://www.hse.gov.uk/notices/notices
SAFETY PERFORMANCE
PRODUCTION – HISTORICAL / CURRENT
6
Forties
Beryl Area
Nelson Scott
Nevis S Telford Buckland Ness Maclure Bacchus
0
500
1,000
1,500
2,000
2,500
3,000
MBOE/D
0
20
40
60
80
100
120
140
Gas
Oil
Mill
ion
s o
f b
bls
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
2013 PRODUCTION EFFICIENCY
7
1
3
5
7
9
11
13
15
17
19
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Op
erat
or
Ran
kin
g
Source: OGUK Production Efficiency Task Force Data Pack
FortiesAcquisit
ion2003 2004 2005 2006 2007 2008 2009 2010 2011
MNSLAcquisit
ion2012 2013
Running Costs 130 180 186 226 226 236 198 208 253 365 428
Other Capital 683 9 19 35 22 26 23 24 48 33 1250 64 84
ITS Capital 28 158 214 176 253 226 156 202 263 271 323
Drilling Capital 23 185 240 133 260 210 198 367 527 553 476
Cum. Spend ($ million) 683 873 1415 2091 2647 3412 4106 4681 5507 6583 7833 9086 10397
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
0
200
400
600
800
1,000
1,200
1,400
Cu
mu
lati
ve S
pen
d $
mill
ion
An
nu
al S
pen
d $
mill
ion
EXPENDITURE AND REVENUE
8
2003 2004 2005 2006 2007 2008 2009 2010 2011MNSL
Acquisition
2012 2013
Oil & Gas Revenue 273 472 1275 1355 1399 2103 1369 1605 2185 2771 2728
Total Spend -873 -542 -675 -557 -765 -694 -576 -826 -1076 -1250 -1254 -1311
Current Tax Liability -41 35 -310 -504 -439 -1091 -360 -599 -1235 -1097 -880
Cumulative Rev less Spend less Tax Liability -641 -677 -388 -94 102 419 853 1034 908 -342 78 616
-2,000
-1,500
-1,000
-500
-
500
1,000
1,500
2,000
2,500
3,000
$
mill
ion
THE PROJECTS GROUP
9
The mission of the Projects Group is to provide Apache North Sea with safe, world class project delivery in order to maximize the return
on investment for the Corporation. The Projects Group will, as a minimum, provide the following services: Brownfield project and modifications management to the CNS (Forties and
Bacchus), NNS (Beryl and SAGE) Management of the execution of all topsides and subsea projects Concept development of all greenfield and major brownfield projects Management of all projects from concept definition through to completion and
close out Support to worldwide projects as requested Education, advice and training to; the management team, partners, operations
and support services in Apache North Sea in project management and project implementation
THE MISSION
Pace, Innovation and Excellence Unity of effort, focus and momentum whilst
empowering individuals to use their own discretion and initiative within the implementation process
THE CULTURE
PROJECTS
12
FORTIES ALPHA SATELLITE PLATFORM (FASP)
Mobilised UK yard Largest Tyneside platform 75% UK content Target cost contracting 30% cheaper than benchmark
BACCHUS
14
Manufactured @ Isleburn, Invergordon
Transported to Wester via Wick (above)
6.7 KM
Subsea 7 - Wester
Installed by Subsea 7
Manufactured by RBG
Petrofac Aberdeen
Vetco Gray - Montrose
AVIAT
15
FC FB
FD FE FA
NELSON
FORTIES
AVIAT
BACCHUS
Forties Field TAR 14 days completed 1 day early 37,000 manhours
FPS 36” SSIV installation IRM CNS and NNS campaigns
4 weeks 12 projects
SAGE nitrogen injection facility Civils work complete
SAGE 30” pipeline isolation upgrade Aviat
Fabrication commenced Commence detailed design
2014 SUBSEA PROGRAMME
36” SSIV
IRM – 3 x BB caisson stabilisers
Replacement of 30” SAGE valves
THE FUTURE MORE WITH LESS
Reduced costs
Value
Resource constraints
Alternative locations
Fit for purpose
Standardised engineering
Re-use of engineering
Aligned contracting
Unity of effort
Source: McKinsey’s Energy Insight Offshore Operations Benchmarking Database
Drilling CNS 2015
3 x Forties platform crews 1 x FASP Jack up
NNS 2015 2 x Beryl platform crews
2015 – 2018 2 x semi sub rig shares – Existing fields / E & A / P & A
Developments Tie backs to existing hubs Tie backs to 3rd parties Stand alone developments New Challenges
HP / HT Heavy Oil
FUTURE PLANS
18
Routine contract 3 year + 2 x 1 year extension Non-exclusive
WoodGroup Kenny – Detailed Design 2012 – 2015
Harkand – Diving 2014 – 2017
EMAS – Heavy lift / pipelay 2014 – 2017
Fugro – Inspection ROV 2014 – 2017
Subsea Project Management Support TBA 2014 – 2017
Petrofac – Topsides Scopes 2012 - 2015
EXISTING TIER 1 SUBSEA CONTRACTS
19
SUBSEA ONGOING / PLANS
20
4
3
4 New Distribution Unit
New Controls Umbilical –
8km
New WI & GL line OR New Production Line –
8km
BKA Ness Nevis Pig Receiver works at SAGE Maersk Leadon decommissioning
Aviat – detailed design FA – Slot recovery Bacchus Well 4 Bacchus Well 1 water conversion
New Power/ Sig Cable –
2km
Replace 3 slot Distribution Unit
with 8 slot Distribution Unit
New Production Line – 9.2km
New Distribution Unit
PROCUREMENT
21
Projects, Subsea Driling, Well Svs Operations, Maintenance
Kevin Forbes
Anthony Yule Bruce Alexander John Boyle
Contracts & Purchasing
Supervisor
Senior Contracts Engineer Contracts Engineer Senior Contracts Engineer
Roger Brimmer
Supply Chain Manager
SUPPLY CHAIN -CONTRACTS & PURCHASING
First Point Assessment Ltd (FPAL)
Apache uses FPAL as it’s only ‘vendor database’ to identify potential suppliers.
Registration with FPAL is a prerequisite for doing business with Apache.
Contract Philosophy:
Preference for longer term agreements, typically 3 years with extension options.
Consolidation of workscopes into single agreements combining multiple asset requirements.
Supply Chain -Key Contacts
Contractor Selection:
Competitive pricing and ability to deliver value
Technical Capability including Innovation, Enterprise and proven Expertise
Evidence of Safety, Health, & Environment culture, focus and performance
Alignment with Apache Business Conduct standards and Ethics
Financial Stability & Integrity
aberdeen.contracts@apachecorp.com
10 years of investment in Forties Do the same at Beryl
The future Control costs
Maintain production
Develop new opportunities
Apache’s vendors Shared interest
Pace, innovation and excellence
SUMMARY
23
ADDITIONAL SLIDES
24
MAINT & INTEGRITY –CONTRACT REQUIREMENTS
• Maintenance Tenders to be conducted in 2014/2015 – • Q1 - 2015 : Offshore Module & TR Doors - Supply, Maint & Repair – £3.5M • Q2 - 2015 : Fixed Lifting Equipment - Inspection & Certification - £1.5M • Q2 - 2015 : Hydraulic Services – Flushing, testing and repair – £0.6 M
Specialised Maintenance Support Requirements :- • Production and Deep Gas Lift Gas Compressors - Maintenance, overhaul
Engineering and Technical labour • Equipment LSA Decontamination – Onshore UK • Electrical Motor – Supply and repairs • Valves – Provision of new and or repaired Control, choke and block valves • Diesel Systems - Audit, Managing and testing
• Integrity Tenders to be conducted in 2014/2015 – • Q4 - 2014 : Pipe, Fittings and Flanges (incl studbolts, gaskets) • Q1 - 2015 : Pipeline & Process Services
TOPSIDES PROJECTS – ONGOING / UPCOMING
Forties
Flowlines for drill wells
Alpha modifications for Aviat
Alpha slot recovery
Bravo & Delta lifeboat, davit and winch upgrades
Bravo Switchboard upgrade
Bravo & Delta 110V distribution upgrades
Charlie PA/GA upgrade
New Delta switchroom for future ESPs
Delta sandwash package
Beryl
Flowlines for drill wells
New Alpha switchroom for future ESPs
Prep for Alpha 2016 major shutdown
Alpha gas export metering upgrades
Alpha crude transfer piping upgrade
Bravo Delta V control system upgrade
Bravo Crane upgrades
SAGE
New Liquid nitrogen storage and distribution facilities
Atlantic and Cromarty prep for demolition
Note that some of the above scopes will be managed through Petrofac Facilities Management - Apache’s EPC Contractor.