Club House-Column casting up to
plinth beam work in Progress.
Club House-Column casting up to
plinth beam work in Progress.
Building-2-(Parking-2) 1 Slab shuttering
work in Progress.
Building-3-Column work up to
typical floor slab completed.
Building-4-4th floor Mivan slab pour-1 casted.
Pour-2 work in progress.
Building-5-4th floor shuttering in progress.
Overall view
Overall view
Building-6-Parking–Columns up to typical slab
completed & typical slab work in progress.
Building-7-Parking-2 floor 1st slab pour-1 casted.
Pour-2 work in progress.
Overall view
Overall view
Building-8-1st typical 1st floor Mivan slab
Pour-1 casted & pour-2 shuttering work in progress.
Building-9-1st typical floor mivan shuttering
shifting and fixing work in progress.