DANNENBAUM – PROGRAM MANAGER
1 05/21/2014
PMC/GEC STATUS REPORT 05/21/2014
HCRMA Board of Directors
Dennis Burleson, Chairman
Josue Reyes, Vice-Chairman
Ricardo Perez, Secretary/Treasurer
Michael Cano, Director
R. David Guerra, Director
Forrest Runnels, Director
Alonzo Cantu, Director
HCRMA Staff
Pilar Rodriguez, P.E., Executive Director
Jerry Dale, CPA / CGFO, CFO
Flor E. Koll, Program Administrator
Program Management Consultant
DANNENBAUM ENGINEERING CORP
DANNENBAUM – PROGRAM MANAGER
2
Overview
1. Workshop: Aesthetics Design Recommendations [Gus Lopez]
2. Review: PMC Invoice [Louis Jones]
3. Status: Systemwide Tasks [Eric Davila]
4. Status: SH 365 Project [Gus/Eric/Jaime]
5. Status: IBTC Project [Gus/Eric/Jaime]
6. Status: OW/OS Corridor [George Ramon]
7. Status: Constr. Cost Trends [Eric Davila]
05/21/2014
DANNENBAUM – PROGRAM MANAGER
3
Aesthetics Design Recommendations
05/21/2014
ORIGINAL SIMPLE COLUMN DESIGN
DANNENBAUM – PROGRAM MANAGER
4
Aesthetics Design Recommendations
05/21/2014
ORIGINAL INVERTED-T BENT DESIGN
DANNENBAUM – PROGRAM MANAGER
5
Aesthetics Design Recommendations
05/21/2014
NEW PROPOSED SIMPLE COMBINATION COLUMN-BENT DESIGN
PROPOSED SIMPLE COMBINATION COLUMN-BENT DESIGN (BY PMC)
DANNENBAUM – PROGRAM MANAGER
6
Aesthetics Design Recommendations
05/21/2014
UTILIZE ORIGINAL PROPOSED RETAINING WALL DESIGN
DANNENBAUM – PROGRAM MANAGER
7
Aesthetics Design Recommendations
05/21/2014
PROPOSED BACK-LIT HCRMA LOGO ADDED TO RETAINING WALL DESIGN (BY PMC)
DANNENBAUM – PROGRAM MANAGER
8
Aesthetics Design Recommendations
05/21/2014
PROPOSED NIGHT ILLUMINATION OF TRAFFIC BARRIER WALL (BY PMC)
DANNENBAUM – PROGRAM MANAGER
9
Aesthetics Design Recommendations
05/21/2014
PROPOSED NIGHT ILLUMINATION UNDER BRIDGE (BY PMC)
DANNENBAUM – PROGRAM MANAGER
10
PMC Invoice Overview (Active WA’s: 05/2014 Invoice)
05/21/2014
Util. Exposures Mgt. of Strat. Pln IBTC ROW Map IBTC Low Flight TRZ2 Input RTA Inv. Grd. T&R TIGER Grant All Active WA's
SA5 to WA 6
1/1/13 - 08/31/14
WA 9
3/1/14 - 6/30/18
WA 10
3/25/14-5/31/14
WA 11
3/25/14-5/31/15
WA 12
3/25/14-10/31/14
WA 13
3/25/14-6/30/14
WA 14
3/25/14-9/30/14
WA 15
3/25/14-4/25/14
WA6 - WA15
11/1/11 - 6/30/18
Program Management Consultant 288$ 291,027$ -$ -$ -$ -$ -$ -$ 291,315$
Project & Systemwide Mgt 288$ 291,027$ -$ -$ -$ -$ -$ -$ 291,315$
Construction Mgt -$ -$ -$ -$ -$ -$ -$ -$ -$
General Engineering Consultant
(Tasks on Behalf of the Agency)3,224$ -$ 42,921$ 30,500$ 51,213$ 21,352$ 56,449$ 80,256$ 285,915$
Analyzing Documentation -$ -$ -$ -$ -$ -$ -$ -$ -$
Building Agency -$ -$ -$ -$ 51,213$ -$ -$ -$ 51,213$
Strategic Planning -$ -$ -$ -$ -$ -$ 56,449$ 80,256$ 136,705$
Public Outreach -$ -$ -$ -$ -$ -$ -$ -$ -$
Advance Planning 3,224$ -$ 42,921$ 30,500$ -$ 21,352$ -$ -$ 97,997$
Total for All Tasks: 3,512$ 291,027$ 42,921$ 30,500$ 51,213$ 21,352$ 56,449$ 80,256$ 577,230$
Firm (Current Billing)SA5 to WA 6
1/1/13 - 08/31/14
WA 9
3/1/14 - 6/30/18
WA 10
3/25/14-5/31/14
WA 11
3/25/14-5/31/15
WA 12
3/25/14-10/31/14
WA 13
3/25/14-6/30/14
WA 14
3/25/14-9/30/14
WA 15
3/25/14-4/25/14
WA6 - WA15
11/1/11 - 6/30/18
Dannenbaum Eng Corp. 288$ 184,957$ -$ -$ -$ -$ -$ -$ 185,245$
Direct Labor: Pathfinder -$ 15,000$ -$ -$ -$ -$ -$ -$ 15,000$
Direct Labor: Orchard Data -$ -$ -$ -$ -$ -$ -$ -$ -$
Direct Labor: Jose Correa -$ -$ -$ -$ -$ -$ -$ -$ -$
Direct Labor: George Ramon -$ 15,600$ -$ -$ -$ -$ -$ -$ 15,600$
Direct Labor: Tony Aguirre -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: Aranda and Assoc. (DBE) -$ 46,670$ 42,921$ -$ 51,213$ -$ -$ -$ 140,804$
Sub: Blanton & Assoc. (DBE) -$ 28,800$ -$ -$ -$ -$ -$ -$ 28,800$
Sub: Barrera Torres Infra. (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: Guzman & Muñoz (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: HDR Engineering -$ -$ -$ -$ -$ -$ -$ 80,256$ 80,256$
Sub: C&M Associates (DBE) -$ -$ -$ -$ -$ 21,352$ 56,449$ -$ 77,801$
Sub: RODS SUE (DBE) 3,224$ -$ -$ -$ -$ -$ -$ -$ 3,224$
Sub: ADS (DBE) -$ -$ -$ 30,500$ -$ -$ -$ -$ 30,500$
Sub: UNINTECH (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Total for All Firms: 3,512$ 291,027$ 42,921$ 30,500$ 51,213$ 21,352$ 56,449$ 80,256$ 577,230$
Task (Current Billing)
DANNENBAUM – PROGRAM MANAGER
11
PMC Invoice Overview (Active WA’s: Earned to Date)
05/21/2014
Util. Exposures Mgt. of Strat. Pln IBTC ROW Map IBTC Low Flight TRZ2 Input RTA Inv. Grd. T&R TIGER Grant All Active WA's
SA5 to WA 6
1/1/13 - 08/31/14
WA 9
3/1/14 - 6/30/18
WA 10
3/25/14-5/31/14
WA 11
3/25/14-5/31/15
WA 12
3/25/14-10/31/14
WA 13
3/25/14-6/30/14
WA 14
3/25/14-9/30/14
WA 15
3/25/14-4/25/14
WA6 - WA15
11/1/11 - 6/30/18
Program Management Consultant 2,689$ 547,977$ -$ -$ -$ -$ -$ -$ 550,666$
Project & Systemwide Mgt 2,689$ 547,977$ -$ -$ -$ -$ -$ -$ 550,666$
Construction Mgt -$ -$ -$ -$ -$ -$ -$ -$ -$
General Engineering Consultant
(Tasks on Behalf of the Agency)30,086$ -$ 85,842$ 49,034$ 94,426$ 21,352$ 56,449$ 80,256$ 417,445$
Analyzing Documentation -$ -$ -$ -$ -$ -$ -$ -$ -$
Building Agency -$ -$ -$ -$ 94,426$ -$ -$ -$ 94,426$
Strategic Planning -$ -$ -$ -$ -$ -$ 56,449$ 80,256$ 136,705$
Public Outreach -$ -$ -$ -$ -$ -$ -$ -$ -$
Advance Planning 30,086$ -$ 85,842$ 49,034$ -$ 21,352$ -$ -$ 186,315$
Total for All Tasks: 32,775$ 547,977$ 85,842$ 49,034$ 94,426$ 21,352$ 56,449$ 80,256$ 968,111$
Firm (Earned to Date)SA5 to WA 6
1/1/13 - 08/31/14
WA 9
3/1/14 - 6/30/18
WA 10
3/25/14-5/31/14
WA 11
3/25/14-5/31/15
WA 12
3/25/14-10/31/14
WA 13
3/25/14-6/30/14
WA 14
3/25/14-9/30/14
WA 15
3/25/14-4/25/14
WA6 - WA15
11/1/11 - 6/30/18
Dannenbaum Eng Corp. 2,689$ 335,837$ -$ -$ -$ -$ -$ -$ 338,526$
Direct Labor: Pathfinder -$ 30,000$ -$ -$ -$ -$ -$ -$ 30,000$
Direct Labor: Orchard Data -$ -$ -$ -$ -$ -$ -$ -$ -$
Direct Labor: Jose Correa -$ -$ -$ -$ -$ -$ -$ -$ -$
Direct Labor: George Ramon -$ 31,200$ -$ -$ -$ -$ -$ -$ 31,200$
Direct Labor: Tony Aguirre -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: Aranda and Assoc. (DBE) -$ 93,340$ 85,842$ 18,534$ 94,426$ -$ -$ -$ 292,142$
Sub: Blanton & Assoc. (DBE) -$ 57,600$ -$ -$ -$ -$ -$ -$ 57,600$
Sub: Barrera Torres Infra. (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: Guzman & Muñoz (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Sub: HDR Engineering -$ -$ -$ -$ -$ -$ -$ 80,256$ 80,256$
Sub: C&M Associates (DBE) -$ -$ -$ -$ -$ 21,352$ 56,449$ -$ 77,801$
Sub: RODS SUE (DBE) 30,086$ -$ -$ -$ -$ -$ -$ -$ 30,086$
Sub: ADS (DBE) -$ -$ -$ 30,500$ -$ -$ -$ -$ 30,500$
Sub: UNINTECH (DBE) -$ -$ -$ -$ -$ -$ -$ -$ -$
Total for All Firms: 32,775$ 547,977$ 85,842$ 49,034$ 94,426$ 21,352$ 56,449$ 80,256$ 968,111$
Task (Earned to Date)
DANNENBAUM – PROGRAM MANAGER
12
Systemwide Tasks
05/21/2014
Investment grade study for the HCRMA is underway by C&M and managed by the PMC. – Currently updating origin/destination at border areas as well
conducting a “special generators” study for local traffic (e.g. new cold storage facilities, new attraction centers, etc.) that influence local/global traffic patterns that feed into traffic models.
ProjectWise implementation completed: – All active users have accounts created that limit the access and
edit of documents to the scope of work they need to conduct for the agency
PMC is developing project dashboards that will be used to inform Board / stakeholders of project progress (budget / cost / schedule).
DANNENBAUM – PROGRAM MANAGER
13
Project Overview for SH 365
05/21/2014
Seg. 3 (US 281 Overpass/BSIF Connector)
ROW purchased by: 6/30/14 Construction bid phase start: 9/1/14 Construction period: 1/1/15 – 6/30/16 (18
months)
Segs. 1 & 2 (FM 396/Anzalduas Hwy to US 281)
ROW purchased by: 6/15/15 Construction bid phase start: 9/1/15 Construction period: 1/1/16 – 6/30/18 (30
months)
Purchase ROW Start
Environmental Clearance
PS&E Complete
ROW Purchase Complete
Bid Phase
Construction Begins
Toll Operations Begin
01/2
01
4
01
/201
5
01
/201
6
01
/201
7
01
/201
8
DANNENBAUM – PROGRAM MANAGER
14
Project Schedule for SH 365
05/21/2014
DANNENBAUM – PROGRAM MANAGER
15
Progress on SH 365 Project
05/21/2014
Design / Utilities – PMC reviewing 30% PS&E on all segments.
– Engineers will start to incorporate utility exposure info into plans.
– Utility conflicts will be identified and meetings to be set with impacted utilities.
Environmental – PMC and Atkins have incorporated final comments to Draft EA. Submittal
will be made as soon as some ROW calculations (based primarily on changes from TxDOT comments) are updated within document.
– An updated archaeological survey report has been submitted to TxDOT ENV, then THC, for final review and guidance. THC will dictate the options for mitigation that they will accept for the archaeological sites.
– Once Daft EA and Archeological Reports are accepted then process will move onto FHWA.
– PMC and Atkins will start to document the ROW process using TxDOT Early ROW Acquisition Guidance.
DANNENBAUM – PROGRAM MANAGER
16
Progress on SH 365 Project
05/21/2014
ROW Mapping / Acquisition – Segment 3
Stripmap 100% complete / Parcel plats 100% complete
Distribution of those plats have been made to appraiser and agent
– SH 365 Segments 1 and Segments 2/4 Stripmaps are nearing completion
Surveyors are preparing survey parcel plats for ROW acquisition
DANNENBAUM – PROGRAM MANAGER
17
Project Overview for IBTC
05/21/2014
Segs. 1 - 3 (Interchange w/ SH 365 to I-2 and to FM 493)
ROW purchased by: 7/31/15 Construction bid phase start: 9/1/15 Construction period: 1/1/16 – 6/30/18
(30 months)
Purchase ROW Start
PS&E Complete
Environmental Clearance
ROW Purchase Complete
Bid Phase
Construction Begins
Toll Operations Begin
01/2
01
4
01
/201
5
01
/201
6
01
/201
7
01
/201
8
DANNENBAUM – PROGRAM MANAGER
18
Project Schedule for IBTC
05/21/2014
DANNENBAUM – PROGRAM MANAGER
19
Progress on IBTC Project
Design / Utilities – PMC 95% schematic submitted to TxDOT Pharr District for comment on 3/17/2014,
comments received 5/19/2014. PMC putting together 100% package for TxDOT Austin review.
– The 100% schematic will address TxDOT comments and utilize updated topo/aerial (obtained in WA 11) to finalize the ROW lines.
– PS&E Kickoff held with Engineers (Halff, TEDSI, and S&B) and ProjectWise users issued and teams are actively working on this project.
– Meetings with various utilities along stretch from north of the Donna Lakes to I-2 have been initiated.
Environmental – Requested scoping meeting with TxDOT and are pending a date to document the
approach whereby technical reports are submitted for concurrent review with TxDOT ENV and Pharr District. All work is ongoing from a technical standpoint.
– Atkins and their sub have been mobilized and are working on updating the work necessary for federal clearance.
– Regional Toll Analysis (WA 13) is underway with initial buy-in from HCMPO and TxDOT Pharr District. Working closely with both reviewers/stakeholders to analyze all tollroad projects.
05/21/2014
DANNENBAUM – PROGRAM MANAGER
20
Progress on IBTC Project
ROW Mapping – Strip map is near completion and will be ready first week in June for
distribution to the survey pool to proceed in the preparation of the survey plats for ROW acquisition.
– Once strip map is complete, the PMC and Atkins will document the ROW process using TxDOT Early ROW Acquisition Guidance.
ROW Acquisition – Stakeholder coordination meetings are taking place between
HCRMA, City of Donna, and Residents of the impacted communities north of the Donna Lake.
– Emphasis of those meetings was to provide clarity on which areas will need to be acquired and the timeframe for relocations.
– Quiet Village is being inspected by the Appraiser.
05/21/2014
DANNENBAUM – PROGRAM MANAGER
21
Project Overview for Overweight/Oversize Corridor Permits
05/21/2014
Establish online permitting system
Approve scale owner(s) in MX
Evaluate TxDOT's Pave- ment Condition Study
Coordinate with stakeholders
Issuing Permits
02/2
01
4
03/2
01
4
04
/201
4
DANNENBAUM – PROGRAM MANAGER
22
Progress on OW/OS Corridor Permits
05/21/2014
PMC is obtaining status on readiness from Grupo Jugas, the who are constructing a scale for facilitating the sale of permits in Reynosa, Mexico.
Grupo Jugas is 85% complete toward opening for operations. Pending certification from PROFECO.
Other PROFECO scales are available throughout the interior of Mexico and PMC is working toward obtaining a list for use on the HCRMA Permit website.
DANNENBAUM – PROGRAM MANAGER
23
Progress on OW/OS Corridor Permits
05/21/2014
DANNENBAUM – PROGRAM MANAGER
24
Construction Cost Index
05/21/2014
Source: McGraw Hill Construction ENR
1.8%
2.6% 2.6%
3.0%
2.7%
3.1%
4.3%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%
4.0%
4.5%
5.0%
2008 2009 2010 2011 2012 2013 2014
CC
I (Y
ear
ly A
ve)
YEAR
Construction Cost Index (2008-2014) (as of May 2014)
CCI (Year-Over-Year Change)
Costs Increased +1.8% from 2013-2014 and 2.9%
from May a Year Ago
DANNENBAUM – PROGRAM MANAGER
25
Construction Cost Trends: Asphalt Paving Prices
1. The 20-city average price for liquid asphalt has changed in 2014:
a. +0.0% Jan
b. +0.1% Feb
c. +0.1% Mar
d. +0.3% Apr
e. -0.3% May
2. Asphalt paving prices are up 2.0% from a year ago.
05/21/2014
Source: McGraw Hill Construction ENR