pingp unit 1 & unit 2 mur 2010 lessons learned
Post on 03-Feb-2016
42 Views
Preview:
DESCRIPTION
TRANSCRIPT
PINGPUnit 1 & Unit 2 MUR 2010
Lessons Learned
Martin CabiroFeedwater System 02/24/2011
MUR Uprate Specifications
MUR Power Uprate from current licensed core power of 1650 MWt to 1677 MWt.
Expected increase of 9 MWe on Unit 1 and Unit 2.
RCS and Safety Related Systems were not impacted by the Uprate due to only ½ Degree F change in Th and Tc values.
MUR impact solely on BOP systems only.
MUR- BOP System Impacts
Installation of Cameron Leading Edge Flow Meter (LEFM) on Unit 1 (1R25) and Unit 2 (2R25) with a power measurement uncertainty of .36%
Parameter 1650 MWTh Unit 1 1677 MWth
Unit 2 1677 MWth
MS Flow 7.12e6 lbm/hr 7.32e6 lbm/hr 7.33e6 lbm/hr
FW Flow 7.18e6 lbm/hr 7.34e6 lbm/hr 7.33e6 lbm/hr
MWe 571/570 MWe 581 MWe 580 MWe
Turbine First Stage Pressure
513/514 psig 526 psig 527 psig
MUR- Power Ascension Monitoring Plan
Pre and Post Monitoring put in place due to industry OE of changes in MS, FW,HD, and Extraction Steam system flow induced vibrations.
PINGP System Engineering Team (15 Engineers) generated to perform Pre and Post Monitoring.
MUR- Pre Monitoring Walk-down
Visual walk-downs performed in Turbine Building and Aux Building.
Target of walk-downs:– Identify existing pre Uprate system vibrations,
oscillations in FW heaters, unusual piping configurations, audible and visual indications of flashing in pipes or tanks, and support or hanger positions.
MUR- Pre Monitoring Walk-down Findings
Examples of Pre Walk-down findings:
MUR- Pre Monitoring Walk-down Findings (cont.)