nimes landslide stabilization presentation

Post on 25-May-2015

1.900 Views

Category:

Design

3 Downloads

Preview:

Click to see full reader

DESCRIPTION

Nimes Landslide Stabilization Presentation

TRANSCRIPT

Landslide Stabilization905 Nimes Place

Bel Air

Drill Rigs Overlooking Wilshire Skyline.

These large drill rigs drill 36” holes to 100’ in roughly one hour.

Drill Rigs and 125’ Cranes

Pumping Concrete in Inclinometer Pile # 8-20

There are close to 220 piles being installed to stabilize the landslides, 8 of which will have Slope Inclinometers

attached to monitor future movement. The Slope Inclinometer Piles pictured are ready to install.

Pumping Concrete @ 3500psi into Slope Inclinometer Pile # 8-5

Slope Inclinometer Fastened to Pile

Moving 90’ Slope Inclinometer Pile Into Place

Slope Inclinometer Pile Being Lowered into Boring Hole

Cranes with Pile, and 6” Concrete Pumping Hose Apparatus

Aligning Slope Inclinometer Pile into Bore Hole

Lowering Inclinometer Pile into Bore Hole

Installing New Inclinometer Pile While Drilling New Boring in Background

Pile Row with Shotcrete Wall. Inclinometer Pile Installation is in the Background

Pumping Concrete @ 3500psi with Inclinometer Pile # 6-60 at Elevation

Installed Inclinometer Pile # 8-5

Pile Row with Shotcrete Wall. Excavation and removal of the landslide is now being performed. Some

areas of the pile wall will have a 70’ vertical exposure before the material is replaced and re-compacted.

Top of Pile with Slope Inclinometer DataMate

Installed Inclinometer Pile

top related