NewbuildupdateSeptember2016

ThenewschoolbuildTheviewfromthesportshalltowardsthegroundfloor

SEN

Englishclassrooms

Staircase

Reception

Mainoffice

LookingfromtheCopsewoodRoad/SkillsCentrecorner

Sciencerooms

Englishrooms

Photographyrooms

Staircase/entrance

TheNewBuild– updateMainsteelframe:• Qtr 1&Qtr 2– CopsewoodRoadtoDimondRoadfulllengthofbuildinginplace.HalfdepthtowardsOaktreeRoadcomplete

• Qtr 3&Qtr 4– tobecompletedbyendofSeptember.• Floorbeamstotheground,firstandsecondfloorsonQtr 1ongoing

Ongoing/whatishappeningnext• Steelworkandfloors• Externalwalls/envelopeofthebuilding• Roof• Drainageandservices• Groundwork/framefortheactivitystudios

ThesportshallblockThesportshallbuildinghasnowbeenhandedback:• 2xlargermainchangingroomstoreplacethemainschoolchangingroomblock.

• 2xnewsmallerchangingrooms.• Newmale/femaletoiletblockseparatefromthechangingrooms.

• Revamp/newlocationsforPEoffices.

Logistics:• AllPElessonsstudentchangingtothesportshall.• Dancelessonchangingonlytothemainblockchangingrooms.• TemporaryentrancebehindMFLhutstobeusedbystudents.• 2xMFLclassroomsbacktoclassrooms.