method statement for office container and equipment mobilization
Post on 23-Dec-2015
907 Views
Preview:
TRANSCRIPT
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
1 of 12
TABLE OF CONTENTS
1. GENERAL 2
2. PURPOSE 2
3. SCOPE 2
4. TERMS & DEFINITIONS 2
5. REFERENCES 2
6. RESPONSIBILITIES 3
7. ORGANIZATION CHART 7
8. MOBILIZATION OF PLANT, EQUIPMENT, TOOLS & MANPOWER 7
9. PERSONNEL QUALIFICATION 810.
METHODOLOGY- PREPARATORY WORK, WORK EXECUTION METHOD 8
11. HEALTH SAFETY ENVIRONMENT 1112.
ATTACHMENTS 12
1. GENERAL
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
2 of 12
This document covers the sequence activities for the Office Containers & Equipment Mobilization
and Demobilization, General lifting operation of construction materials / equipments at The laying
of gas transmission pipelines from meranti view to banyan avenue in jurong island project.
2. PURPOSE
The purpose of this document is to follow proper methodology and to carry out the activities in
sequence for the Office Containers & Equipment Mobilization and demobilization, General loading,
unloading and lifting operation of construction materials / equipments at The laying of gas
transmission pipelines from meranti view to banyan avenue in jurong island project.
3. SCOPE
The scope of the work method statement is to outline the procedure and work sequence for the
Office Containers & Equipment Mobilization and Demobilization, general unloading and lifting
operation of construction materials / equipments at The laying of gas transmission pipelines from
meranti view to banyan avenue in jurong island project. This Works Method details the followings,
The requirements and procedures in mobilization of office container & equipment.
Responsibilities.
Organisation chart.
Manpower & Equipment used.
Lifting plan.
Lifting sequence.
Roof installation sequence.
Site Location.
Proposed location for WEC site office.
Roof Structure.
Single Line Diagram.
Risk Assessment.
4. TERMS & DEFINITIONS
HSE – Health safety & Environment.
RA – Risk Assesment.
LM – Lifting Machine.
LG – Lifting Gear.
5. REFERENCE
Work Place Safety And Health Act
Work Place Safety And Health(General Provisions) Regulations
Work Place Safety And Health(Construction) Regulations 2007
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
3 of 12
WSH(Operations Of Cranes) Regulations 2011
Code of Practice on Safe Lifting Operations in the Work Places
SS536: Code of practice for the safe use of mobile cranes
SS528: specification for personal fall arrest system
SS537 code of practice for safe use of machinery
Code of practice for working safely at heights.
6. RESPONSIBILITY
6.1 Project Manager
Undergone Project Manager's Safety Course and possess valid certificate.
Familiarize himself with the Company's environmental, health and safety management
system and ensure its effective application.
Take prompt corrective actions to remove any unsafe or unhealthy work conditions and to
maintain effectively such corrections made.
Ensure good housekeeping is practiced on site.
Ensure that environmental, health and safety is planned into all operations.
Review all working methods and process, both new and existing to see that all
environmental, health and safety are met.
Act as Chairman to the site safety, health and environment committee and conduct monthly
site committee inspection and meeting.
Participate in all incident investigation and dangerous occurrences incidents.
6.2 Project Engineers
Familiar himself with the Company's environmental, health and safety management system.
Review any new or changes in processes, equipment and materials to ensure that safety,
health and environment are not disregarded.
Establish and maintain a programme for the identification and assessment of hazards.
Assist in the investigation of every serious or fatal accident and dangerous occurrence and
recommend preventive measures.
Ensure that method statements, hazard analysis and safe work procedures for hazardous
operations must be submitted by the sub-contractors prior to commencement of work on site.
6.3 WSH Coordinator
Undergone Building Construction Safety Supervisor Course and WSH Co-coordinator
Course possess valid Certificate.
Ensure that all rules and regulations as stipulated in the WSHA (Construction) Regulations
are met.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
4 of 12
Inspect and rectifying any unsafe place of work and unsafe practices.
Checking sub-contractors work to ensure compliance with the WSHA (Construction)
Regulations.
Liaison with sub-contractors with respect to environmental, health and safety works
undertaken by them.
Assist the Safety Manager, Workplace Safety and Health Officer and Environmental Control
Officer in all safety, health & environment matters.
Carry out site safety, health and environment programmes and procedures.
Assist in organizing safety, health and environment awareness activities such as toolbox
meetings, safety, health and environment orientation, safety, health and environment
promotional activities, etc.
Ensure that issuance of personal protective equipment are properly recorded and
documented.
Coordinates and assures compliance with the Risk Assessment Program
6.4 Foremen/ Supervisor
Responsible for the safety, health & welfare of all workers either assigned or not assigned to
him but may be working temporary in his area.
Ensure that workers know safety, health and environment rules and regulations, follow safe
job procedures and be aware of all major hazards associated with their work and work areas.
Maintain satisfactory standards of housekeeping in his assigned area.
Investigate all incidents to worker(s) and/or equipment in his area and assist Workplace
Safety and Health Officer to put up accurate incident report on all such investigation.
Ensure that all workers working in his area use the appropriate personal protective
equipment.
6.5 Lifting Supervisors
Undergone Lifting Supervisor Safety Course and possess valid certificate
Possess relevant experience in lifting operations for a period of not less than one year before
the appointment as a lifting supervisor.
Co-ordinate all lifting activities.
Supervise all lifting operation by a mobile crane or tower crane in accordance with the
lifting plan.
Ensure that only registered crane operators, appointed riggers and appointed signalmen
participate in any lifting operation involving the use of a mobile crane or a tower crane.
Ensure that the ground conditions are safe for any lifting operation to be performed by any
mobile crane.
Brief all crane operators, riggers and signalmen on the lifting plan
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
5 of 12
If any unsatisfactory or unsafe conditions are reported to him by any crane operator or
rigger, take such measures to rectify the unsatisfactory or unsafe condition or otherwise
ensure that any lifting operation is carried out safely.
6.6 Crane Operators
Undergone Crane Operator's Training Course and possess valid certificate.
Before the start of every work shift, to carry out operational tests on all limiting and
indicating devices under no load conditions before any lifting operation is carried out and
shall enter the results of such tests in a log book or log-sheet.
To ascertain whether the ground conditions, in particular the ground surface on which a
mobile crane is to be operated, are safe for travel or any lifting operation; and if he is of the
opinion that it is not safe for travel or any lifting operation, he shall report this to the lifting
supervisor.
To ensure that any outrigger when it is required is fully extended and secured.
Not to carry out any lifting operation unless he has been briefed by the lifting supervisor on
the lifting plan.
Not to hoist any object if he is unable to ascertain the weight of the load.
Not to hoist any load unless he has received a clear signal from a signalman.
Not to engage in any act or manoeuvre which is not in accordance with safe and sound
practice.
Not to hoist any load if there is any obstruction in the path of manoeuvre and if there is any
such obstruction, he shall report this immediately to the lifting supervisor.
Not to manoeuvre or hold any suspended load over any public road or public area unless that
road or area has been cordoned off
Not to operate a mobile crane or a tower crane within 3 metres of any live overhead power
line.
Not to use the crane for any operation for which it is not intended, including pulling or
dragging a load
To ensure that any stationary truck mounted or wheel mounted crane is adequately and
securely blocked while it is on a slope.
To report any failure or malfunction of the crane to the lifting supervisor and to make an
appropriate entry of the failure or malfunction in the log book or log-sheet of the crane.
6.7 Riggers
Appoint a rigger in a workplace unless the person has successfully completed rigger training
course acceptable to the Commissioner.
Check the slings to be used for slinging the loads to ensure that the slings are of good
construction, sound and suitable material, and adequate strength and free from patent defect.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
6 of 12
Ensure that an adequate number of legs of the sling are used and that the slinging angle is
correct so as to prevent the sling from being overloaded during the hoisting.
Determine the weight of the load which is to be lifted and inform the crane operator of the
weight of the load;
Ensure that only proper lifting gears are used in conjunction with the sling.
Ensure that the load to be lifted is secure, stable and balanced.
Ensure that any loose load (which includes any stone, brick or tile) is placed in a receptacle
to prevent the load or part thereof from falling during the lifting operation.
Place adequate padding at the edges of the load which come in contact with the sling so as to
prevent the sling from being damaged; and
Report any defect in the lifting gear to the lifting supervisor.
6.8 Signalmen
Undergone Signalman's Training Course and possess valid certificate.
Ensure or verify with the rigger that the load is properly rigged up before he gives a clear
signal to the crane operator to lift the load.
Give correct and clear signals to guide the crane operator in the maneuver of the load safely
to its destination.
6.9 Banksmen
He will be in-house trained, with a whistle and hi-visibility vest.
Assist in assessing the ground conditions prior to the entry of equipment/ machinery/
vehicle.
Use standard signals to guide the movements of machinery/equipment/vehicle at/to the
location of works to be carried out.
Communicate to the drivers/operators during the movements of the
machinery/equipment/Vehicle.
Station full time on site assisting in guiding all vehicular movements on site.
Report any incidents/accidents to his immediate supervisor, sembcorp site/safety personnel
The movements of machinery/equipment/vehicle will be stopped during the absence of the
banksman to prevent any incidents on site.
The operator/driver must be able to see the banksman during the communication process.
The banksman must be stationed in such a way not to be in the line of fire (front, behind or
in-between) of the equipment movement
6.10 Workers
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
7 of 12
Accepting individual responsibility for their own safe behavior as well as sharing
responsibility with their fellow workers and line supervision to look out for their own as
well as their co-workers.
Work in a safe manner at all times.
Complying with HSE requirements which apply to an individual’s work activities.
Keeping the work area in an orderly condition.
Wear PPE provided to them and inspect it daily.
Comply with work instructions and permits.
Attend daily tool box/pre-task meetings
Inspect all tools before use and on a daily basis.
7. ORGANIZATION CHART
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
8 of 12
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
9 of 12
8. MOBILIZATION OF PLANT, EQUIPMENT, TOOLS AND RESOURCES
8.1 Equipments
8.1.1 Mobile Crane.
8.1.2 Lorry Crane.
8.1.3 Crowler Crane.
8.1.4 Excavator.
8.1.5 Trailer
8.1.6 Transportation Trucks
8.1.7 Welding machines
8.1.8 Vibrating machines
8.1.9 Road Roller
8.1.10 Personal Protective Equipments
8.1.11 Electrical Generators
8.1.12 Roofing Frame
8.1.13 Roofing Sheet
8.2 Tools
8.2.1 Measuring and Leveling Tools
8.2.2 Clamping Tools
8.2.3 Hand held Tools- Spanner, screw driver, plumb etc.
8.2.4 Lifting Tools- Belts, Sling, Chain Block, Hoist, Shackle, Ropes etc.
8.2.5 Portable power Tools like Grinding machine, Drilling Machine etc.
8.2.6 Stepladder & Extension ladder
8.2.7 Nails for the metal roofing
8.2.8 Heavy duty hammer & half a pound 2” sized roofing nails
8.2.9 Hand Saw
8.2.10 Scaffolding pipe.
8.2.11 GI wire.
8.2.12 Welding Torch.
8.2.13 Portable power Tools like Grinding machine, Drilling Machine etc.
8.2.14 Power & Welding cables
8.2.15 Fire blanket.
8.3 Man Power
8.3.1 Project Engineer 1 person
8.3.2 Safety Co ordinator 1 person
8.3.3 Lifting supervisor 1 person
8.3.4 Crane operator 1 person
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
10 of 12
8.3.5 Rigger man 2 persons
8.3.6 Banks man 1 person
8.3.7 signal man 1 person
8.3.8 General worker 2 persons
9. PERSONNEL QUALIFICATION
All personnel delegated to the work would have undergone the relevant mandatory and project specific in-house training
All personnel would be competent for the tasks that they will be carrying out,
Supervisory personnel will act as “vehicle commanders” by following and guiding the vehicle into and around the plant
Please refer the attachment for the competency personnel certificates.
10. METHODOLOGY
10.1 Preparatory Work
Ensure that the document received bear the stamp “Issued for Construction” and are of
latest revision.
The documents submitted/referred with this method statement shall be considered as
an integral part of this method statement and shall be read in conjunction with the
same.
LG & LM certificate to be submitted.
All vehicles & equipment to be used in the work should be initially checked and approved by the authorized personnel.
Survey and measurement should be taken and marked.
Cable detection must be carried out.
Lifting Supervisor & crane operator will check & plan the travel routes prior to mobilization. Ensure travel routes & access to the jobsite is in good condition and free from obstruction.
Check and confirm crane set-up positioning.
Soil combaction must be carried out to set adequate ground condition for container and lifting work.
Concreting and steel reinforcement works must be finished and checked before lifting the container.
Container must be placed at least 300mm above from the ground level.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
11 of 12
Working area shall be barricaded with proper devices & warning signs to display.
Unauthorized person are not allowed in the area barricaded off
Workers shall wear appropriate PPE for the task.
Safety Coordinator & Lifting supervisor shall be present at all time during lifting activity.
10.2 Work Execution Method
9.2.1 Lifting Work:
All lifting tools, equipments and ropes used for lifting shall be inspected and certified by WSH regulations. Activities shall be done according to the proper method statement for lifting and mobilization.
Submit method statement and RA for review and approval by authorised person before commencing the mentioned work.
Lifting plan (as per attachment) shall be filled up and attached with load chart and LM certificate shall be submitted during application for permit.
Apply the lifting permit before work commence. Lifting supervisor will conduct tool box and brief the safe lifting operation before work start.
Prior to Lifting Works, it must have an approved Lifting permit and Lifting Plan. Which indicate the type of cranes & lifting gears accessories indicated. The lifting plan must be attached with the lifting permit and display in the lifting area.
Before starting the lifting work, the assigned people must wear proper PPE and adequate safety procedure must be implemented.
All employee and worker involved in the work should first undergo training or safety induction with Sembcorp
WEC shall employ an experienced, competent and responsible Lifting supervisor to plan and execute lifting operations.
Barricade the marked location scheduled for unloading and lifting operation with safety signages.
To Provide safe work during mobilization and demobilization of office containers, there are consideration which take according to weight of the container.
The site supervisor should prepare the site area to be clean and clear from obstruction.
Positioned the Crane near the designated storage area and steel plate should be place over the landed of the crane out-rigger.
Attached the four hooks lifting gear with tag line to the hook attached to the tip of lifting boom.
Attached the four hooks to the four lifting slot corners of steel plates, container and ensure that the hooks were locked.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
12 of 12
Lift one steel plate / sheet pile and container at a time and unload at the nearby designated storage area.
The load shall be controlled by means of tag lines to prevent the load from turning or swinging.
Repeat the process until all materials were unloaded.
Safety equipment must always present and ready for immediate use.
9.2.2 Fencing Work
Manual and Machinery excavation work must be carried out safely for every 3m once as shown in the dwg.
The maximum depth of the excavation is 300mm.
Pre fabricated poles should be placed in the excavation and refilled again.
Hoarding sheet (860x600) must be installed using self tapping screw.
9.2.3 Roofing Work
Determine the roofing material required.
Cut the timber to the precise length.
Fix the scaffolding pipe using clamp in the container vane edge.
Use stepladder to reach the top of container & hang up the hook to scaffold pipes to prevent falling.
Lift up timber one by one and fixed using GI wire to scaffolding pipe.
When the roof structure is finish, put the roofing sheet using 2” nails.
Finally do proper house keeping.
9.2.4 Installation of lightining protection.
Bolt one No. of Air terminal in each corners of the top layer of the container.
Connect the four air terminal each other with the use of aluminium tape.
Connect the air terminal with copper rod in underground using aluminium tape.
Finally do proper house keeping.
9.2.5 Generator Installation.
D……………………………….
9.2.6 Apron work.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
13 of 12
Setting out alignment and elevation
Power saw existing flexible pavement
Licensed operator will use an hydraulic excavator SK 100 with breaker attachment to break up existing flexible pavement
During the breaking / excavation, a bench men will be appointed to assist and guide the operator
After breaking the existing pavement, proceed to excavate to the sub grade level
The excavated material will be disposed off.
9.2.7 Erection of car park.
The sub grade will be leveled and compacted by the 6 ton road roller machine
300mm thick of graded aggregate will be laid in two layer and compact by the 6 ton road roller machine
Expansion point will be provided at every 25m interval.
The car park erection and installation should be according to LTA/RD/SD99/PAV/6
Longitudinal joint will be provided at every lane though out (LTA/RD/SD99/PAV/6).
Formwork to be erected at site if necessary
225mm thick Grade 40 concrete will be laid with a layer of reinforcement B8 BRC, leveled, trowelled and roughen with broom finish to the proposed design level
9.2.2 Welding work.
Welding shall be carried out in the 2G position (flat) wherever possible.
Prior to welding, the surfaces shall be cleaned free from rust, oil, paint, and moisture and other contaminants detrimental to welding.
Piping components to be welded shall be aligned in such a manner as not to result in developing residual stress.
The internal lining shall be cut back a minimum of 50mm to eliminate any blistering, prior to fit up.
Either grinding or gas cutting shall be applied in removing bridges etc.
In gas cutting, the toe of the weld shall be cut and finished to the base metal surface by grinding.
Welders carrying out welding, including tack welding shall be qualified in accordance with ASME Section IX or API 1104 as approved by the Client.
Welding consumables shall conform to the requirements of ASME Section II, Part C and shall be controlled in accordance with Control of Consumables Procedure.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
14 of 12
9.2.2 Electrical work.
11. HEALTH, SAFETY AND ENVIRONMENT
WEC HSE Manager shall ensure that the work is performed accordance to the approved
Construction Safety Manual and precautions specified in the work permit. He shall
ensure that barricades, warning tapes, warning signs, firefighting equipments and first
aid kits are readily available at the working area.
Tool box talk shall be conducted on a daily basis to inform the workers of the recent
safety issues and incidents and to get feedback of any unreported unsafe acts. Feedback
will then be processed and resolved.
11.1 Safety Procedures
11.1.1 Area shall be barricaded adequately with warning barriers prior to any lift.
11.1.2 All Equipment shall be checked for good conditions before commencing the work.
11.1.3 Unauthorized persons shall be excluded from the area.
11.1.4 Lifting equipment capacity and correct load slinging will be verified.
11.1.5 When lifting, the personnel shall not remain in the lifting equipment work area.
11.1.6 Adequate standards shall be adopted for the construction of stages, planks, scaffolds,
etc.
11.1.7 Adequate caution boards and warning signs shall be provided.
11.1.8 All lifting equipment shall have valid certificates.
11.1.9 Only trained and authorized personnel shall operate the vehicles / Machinaries.
11.1.10 All lifting gears and shackles used shall be approved type with valid certificates.
11.1.11 Electrical installations and equipment shall conform to standards.
11.1.12 Do not stand under suspended loads.
METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF
OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.
Project:
LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND
Project No.:
P4262
Rev:
00
Date:
16/02/2015
Page:
15 of 12
11.1.13 On completion of job, the area shall be cleared of any materials and keep clean and tidy.
11.1.14 Hazard analysis for hazardous operation shall be carried out prior to commencing the
works.
12. ATTACHMENT
1. Proposed location for site plan.2. Proposed site office and worker rest area.3. Roof structure.4. Single line drawing for site office container.5. Certificates.6. Lifting Plan.7. Plot Plan8. LM, LG & callibration certificates.9. Appointment letter.10. Training matrix.
top related