Lessons Learned from a Rocky Situation: The Story of the

North Topsail Beach Phase 5 Project

Ken Willson

NCBIWA Fall Conference 2015

A World of Solutions

1

• Geologic Setting

• Marine Sand Search / Characterization of the Beach

• Additional Context

• Construction Sequence

• Lessons Learned

Presentation Outline

2 A World of Solutions

Geologic Setting

Town of North Topsail Beach, Onslow County, North Carolina

Project Area

High

Low

3 A World of Solutions

Geologic Setting

Project Area

High

Low

Coastal Change Along the Shore of Northeastern South Carolina:

The South Carolina Coastal Erosion Study

W. A. Barnhardt (Editor)

4 A World of Solutions

Geologic Setting

Rock

Outcrops

Thin Veneer

of Sand Over

Rock

Town of North Topsail Beach, Onslow County, North Carolina

Thin Veneer

of Sand Over

Rock

5 A World of Solutions

2005 and 2006 Offshore Sand Search

– Geophysical Surveys

– Vibracore Surveys

– Cultural Resource Surveys

Sand Search Investigation

Fathometer Magnetometer CHIRP

Seismic Fish

Survey Vessel

Sidescan Sonar Fish

6 A World of Solutions

Final Borrow Area Design

Sand Search Investigation

7 A World of Solutions

Sand Search Investigation

8 A World of Solutions

Sand Search Investigation

Vibracore Investigations

Rock Rock

9 A World of Solutions

Characterization of the Beach

Native Beach: 3,421 Clasts > 3 inches in Diameter in 50,000 ft2 area

10 A World of Solutions

Project 100% LOCALLY FUNDED (No Federal, State, or County* Funds)

USDA Rural Development Loan

Local Government Commission (LGC) approval required

Bidding – Who’s responsible for “unsuitable material”

Permits only allow dredging up to April 30 (Environmental Windows)

Negotiations with low bidder / Decreased mob/demob cost contingent on Town agreeing not to require return the following dredge season (no guaranteed minimum volume)

Additional Context

* County ended up contributing funds after the construction

11 A World of Solutions

Project Overview

Contingency Portion

Of Project

Project Start:

December 18, 2014

No Dredge

Area

Pipeline

A World of Solutions

12

December 18, 2014 at 7:00 P.M. pumping begins.

Construction

A World of Solutions

13

Construction

Early AM December 19, 2014 rocks are first observed in the fill.

Contractor adjusts cutterhead elevation and is able to avoid rock.

Dredging continued with minimal rock until 6:00 AM December 23, 2014 (Christmas Break)

14 A World of Solutions

During Break: Review of vibracore data, geophysical data, extensive coordination with contractor, identify suggested dredge areas, begin discussions regarding methods to handle rock

December 28 – 29, 2014: Dredging resumes, dredge moved to a different location, material has much less rock in it

December 30 – 31, 2014: State and CPE-NC discuss rock concentrations on beach. Conduct an official rock survey

Construction

15 A World of Solutions

Construction

View Looking North At Sta. 750+00

View Looking South At Sta. 748+50

16 A World of Solutions

Construction Continued from Dec. 28th – Jan. 16th with minimal rock contained in the fill.

– Multiple Site Visits by DCM and USACE Representatives

– Coordination regarding rock removal (Town, Engineer, Contractor, NC DCM, and USACE)

January 15, 2015: Town executed a change order with contractor to remove rock (Rock Picker).

January 16, 2015: Higher concentration of rock observed at the discharge.

January 16 – February 6, 2015: Intermittent periods of higher rock discharged. Coordination with DCM and USACE.

February 6, 2015 - Execution of Change Order to Install Rock Boxes.

Construction

17 A World of Solutions

Construction

Rock Picker

18 A World of Solutions

Rock Boxes: Installed

February 12, 2015

Construction

19 A World of Solutions

Mid-February: Rock Picker working, Rock Boxes Installed

Mid-February – Mid-March: Continued monitoring of the beach fill shows intermittent areas with higher concentrations of rock.

March 17, 2015: Multi-Agency Site Visit Conducted to evaluate rock situation

Construction

20 A World of Solutions

Following March 17, 2015 Inter-Agency Site Visit:

Implement Post Hole Digger Monitoring.

Implement Bulk Gravel Analysis.

Hire 3rd Party Contractor (Tigerhole Landscaping) to remediate upper 36 inches of fill

Reduce mesh size of Rock Boxes to 1.5 inches.

Modify Rock Box opperations (No Overflow / Stockpile Proximity).

Officially requested to maintain Rock Box log.

Construction

21 A World of Solutions

Construction

Post Hole Digger – Rock Analysis

22 A World of Solutions

Construction

Bulk Gravel Analysis

23 A World of Solutions

Construction

Remediation of Upper 36” of berm

24 A World of Solutions

Construction

Reduced Mesh Size on Rock Boxes

25 A World of Solutions

April 2, 2015 – USACE orders project to shut down unless a cutterhead screen is installed (USFWS recommendation)

– USFWS agrees to allow work to continue for the evening and then shut down for weather

April 3 – 4, 2015: Contractor Installs cutterhead screen

April 5, 2015: Dredging Resumes w/ Cutterhead screen

Construction

26 A World of Solutions

April 7, 2015 Inter-Agency Site Visit:

Inspect Rock Box Mesh

Inspect Bulk Gravel Analysis.

Inspect 3rd Party Contractor (Tigerhole Landscaping) remediation of upper 36 inches of fill

Inspect Rock Box Emptying /Disposal Operations .

Results of Inter-Agency Site Visit:

Methods being used are resulting in an acceptable beach

Cutterhead Screen can be removed

Continue monitoring

Construction

A World of Solutions

27

Construction

April 7, 2015

USACE Permit Modification

USFWS Formal Consultation

NMFS Informal Consultation

NC DCM Permit Modification

28 A World of Solutions

AGENCIES ARE NOT YOUR ENEMIES!!

Use best available science

Sediment Criteria may require modifications:

– 3 inch clast threshold

– Threshold for Rock in the Borrow Area – Screens

Have contingency plans in place a head of time

Methodology for successfully screening rock

Methodology for monitoring bulk gravel / buried rock

Lessons Learned

29 A World of Solutions

Offshore borrow areas with rock can be used if necessary

Lessons Learned

30 A World of Solutions

Lessons Learned

Offshore borrow areas with rock can be used if necessary

31 A World of Solutions

Lessons Learned

Offshore borrow areas with rock can be used if necessary

A World of Solutions

32

Jan. 1 – March 31

April 1 – June 20

Lessons Learned

Dredge Window Expansion (With Conservation Measures)

A World of Solutions

33

Turtle Monitoring

Benthic Monitoring

Bird Monitoring

Light Survey

2 Nests: Project during construction

2 Nests: Along pipeline during construction

3 Nests: Project after construction (1 Green)

Lessons Learned

Dredge Window Expansion (With Conservation Measures)

34 A World of Solutions

Project Completion

Cooperative Approach to Resolution of Issues (Town, Contractor, Agencies)

Completed Project Within Budget

Constructed a Successful Project (Provide Storm Damage Reduction to homes and infrastructure and a beach environment conducive to natural ecology)

A World of Solutions

35

Comparison of Pre- and Post-Construction Conditions

Project Completion

A World of Solutions

36