israel energy & business convention · 2018. 11. 25. · ensco ds-7 lorelay. a safe, reliable,...

Post on 17-Oct-2020

2 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Energizing the World,Bettering People’s Lives ®

Leviathan Field DevelopmentA Safe, Reliable, Environmentally Responsible Gas Supply

Israel Energy & Business Convention

November 2018

A Safe, Reliable, Environmentally Responsible Gas Supply

Leviathan Progress Highlights

✓ Project is on schedule at 68% complete.

✓ Completed Jacket Roll-Up.

✓ Completed installation of the first Crane Pedestal.

✓ Completed installation of Chemical Injection Skid.

✓ Completed load-out and sail-away of MEG Reclamation Unit (MRU) to Fabrication Yard.

✓ Completed Umbilicals System Integration Test (SIT).

✓ Commenced Jumper Pipe fabrication.

✓ Installed the final Subsea Tree on Leviathan #7 Well.

✓ Completed 6” pipe bundle pulling for Horizonal Directional Drilling (HDD) #3.

✓ Completed Leviathan #3 Well and mobilized rig to Leviathan #5 Well.

2

A Safe, Reliable, Environmentally Responsible Gas Supply

Platform Construction

Platform Deck Construction

3

DSM Main Deck Lift

MRU Sailaway

Platform Cranes

A Safe, Reliable, Environmentally Responsible Gas Supply

Jacket Fabrication

4

Jacket Roll-up (In-Progress) Jacket Roll-up (Completed)

Jacket Fabrication

A Safe, Reliable, Environmentally Responsible Gas Supply

Subsea

5

Umbilical SIT

SSIV Manifold Piping Main Umbilical 1A LoadoutManifold Fabrication

Manifold Pile Loadout

A Safe, Reliable, Environmentally Responsible Gas Supply

Onshore

6

Condensate Metering Skid

Pipeline ConstructionDor Valve Station (DVS) Construction

Pipeline Stringing & Welding HDD

A Safe, Reliable, Environmentally Responsible Gas Supply

Subsea Installation – Current Progress

7

A Safe, Reliable, Environmentally Responsible Gas Supply

Current Work Areas - Offshore

8

ENSCO DS-7

Lorelay

A Safe, Reliable, Environmentally Responsible Gas Supply

Current Work Areas - Onshore

9

CVS &

Sections 12-

13

DVS

Sections 10 - 11

Sections 7 - 9

A Safe, Reliable, Environmentally Responsible Gas Supply

2019 Timeline

10

Dec 19Nov 19Oct 19Sep 19Aug 19Jul 19Jun 19May 19Apr 19Mar 19Feb 19Jan 19

First Gas

Jacket Installation Topsides Sailaway Topsides InstallationTopsides Commissioning

Jacket Transit

Subsea

Installation

Subsea

Commissioning

Hagit

Construction

Onshore Pipeline

Construction/

Commissioning

Subsea Host Onshore

A Safe, Reliable, Environmentally Responsible Gas Supply

Thank You

11

top related