Leviathan Field DevelopmentA Safe, Reliable, Environmentally Responsible Gas Supply
Israel Energy & Business Convention
November 2018
A Safe, Reliable, Environmentally Responsible Gas Supply
Leviathan Progress Highlights
✓ Project is on schedule at 68% complete.
✓ Completed Jacket Roll-Up.
✓ Completed installation of the first Crane Pedestal.
✓ Completed installation of Chemical Injection Skid.
✓ Completed load-out and sail-away of MEG Reclamation Unit (MRU) to Fabrication Yard.
✓ Completed Umbilicals System Integration Test (SIT).
✓ Commenced Jumper Pipe fabrication.
✓ Installed the final Subsea Tree on Leviathan #7 Well.
✓ Completed 6” pipe bundle pulling for Horizonal Directional Drilling (HDD) #3.
✓ Completed Leviathan #3 Well and mobilized rig to Leviathan #5 Well.
2
A Safe, Reliable, Environmentally Responsible Gas Supply
Platform Construction
Platform Deck Construction
3
DSM Main Deck Lift
MRU Sailaway
Platform Cranes
A Safe, Reliable, Environmentally Responsible Gas Supply
Jacket Fabrication
4
Jacket Roll-up (In-Progress) Jacket Roll-up (Completed)
Jacket Fabrication
A Safe, Reliable, Environmentally Responsible Gas Supply
Subsea
5
Umbilical SIT
SSIV Manifold Piping Main Umbilical 1A LoadoutManifold Fabrication
Manifold Pile Loadout
A Safe, Reliable, Environmentally Responsible Gas Supply
Onshore
6
Condensate Metering Skid
Pipeline ConstructionDor Valve Station (DVS) Construction
Pipeline Stringing & Welding HDD
A Safe, Reliable, Environmentally Responsible Gas Supply
Subsea Installation – Current Progress
7
A Safe, Reliable, Environmentally Responsible Gas Supply
Current Work Areas - Offshore
8
ENSCO DS-7
Lorelay
A Safe, Reliable, Environmentally Responsible Gas Supply
Current Work Areas - Onshore
9
CVS &
Sections 12-
13
DVS
Sections 10 - 11
Sections 7 - 9
A Safe, Reliable, Environmentally Responsible Gas Supply
2019 Timeline
10
Dec 19Nov 19Oct 19Sep 19Aug 19Jul 19Jun 19May 19Apr 19Mar 19Feb 19Jan 19
First Gas
Jacket Installation Topsides Sailaway Topsides InstallationTopsides Commissioning
Jacket Transit
Subsea
Installation
Subsea
Commissioning
Hagit
Construction
Onshore Pipeline
Construction/
Commissioning
Subsea Host Onshore
A Safe, Reliable, Environmentally Responsible Gas Supply